CN206971760U - A kind of full steel structure assembled climbs material platform - Google Patents
A kind of full steel structure assembled climbs material platform Download PDFInfo
- Publication number
- CN206971760U CN206971760U CN201720574402.1U CN201720574402U CN206971760U CN 206971760 U CN206971760 U CN 206971760U CN 201720574402 U CN201720574402 U CN 201720574402U CN 206971760 U CN206971760 U CN 206971760U
- Authority
- CN
- China
- Prior art keywords
- platform
- windrow
- guide rail
- wall
- material platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
It the utility model is related to technical field of building construction, there is provided a kind of full steel structure assembled climbs material platform, including guide rail, windrow platform, operating platform, the lifting hanging seat on external wall;Guide rail is arranged on external wall by wall-attaching equipment, and windrow platform, operating platform are each attached on guide rail;Operating platform is located at the lower section of windrow platform;Steel wire rope upper end is mounted on the suspension ring of lifting hanging seat, and lower end is connected through the pulley on operating platform with the guide chain of electric block lower end;Electric block is arranged at the bottom of windrow platform.The beneficial effects of the utility model are:Material platform is easy for installation, and ground once assembles, and the mode of relatively conventional every layer of installation of material platform is saved manually, the operation dangerous matter sources that high-altitude peace is torn open are reduced, climb operation is simple, has falling proof device safe and reliable, it can return to and be used in turn, there is good Social benefit and economic benefit.
Description
Technical field
Technical field of building construction is the utility model is related to, more particularly to a kind of full steel structure assembled material that climbs is put down
Platform.
Background technology
In Tall Reinforced Concrete Buildings construction, exterior wall discharging platform uses steel wood mixed form more.But current institute
Some shortcomings all be present in the discharge platform device used:Due to using steel wood mixed form, connection is not firm, and piece is not rigorous,
Expect platform platform bad sealing;Off-load is fixed in material platform platform closing piece, and material platform platform is directly shelved on the inside of balcony or window opening
On floor, safety coefficient is low;Material platform platform has from function of climbing, and every layer of construction completion needs tower crane to coordinate to be lifted into upper strata and build
Build and reinstall, labor intensity is big.
Utility model content
The purpose of this utility model is exactly overcome the deficiencies in the prior art, there is provided a kind of full steel structure assembled climbs thing
Expect platform, can all be connected by screw bolts, disposably be set up on ground, realize discharging platform certainly by electric block after lifting
Climb function, windrow platform floor and protection network create the high work of a safety coefficient all using full steel structure to worker
Environment.
A kind of full steel structure assembled of the utility model climbs material platform, including guide rail, windrow platform, operating platform,
Lifting hanging seat on external wall;
The guide rail is arranged on external wall by wall-attaching equipment, and the windrow platform, operating platform are each attached to institute
State on guide rail;The operating platform is located at the lower section of the windrow platform;
Steel wire rope upper end is mounted on the suspension ring of the lifting hanging seat, and lower end passes through pulley and electricity on the operating platform
The guide chain connection of dynamic cucurbit lower end;The electric block is arranged at the bottom of the windrow platform.
Further, the guide rail is 2, and 2 guide rails are connected as one by connection framework;The windrow is put down
Platform, operating platform are each attached on 2 guide rails.
Further, the windrow platform is firmly connected by sub-truss with guide rail;Described sub-truss one end and institute
Guide rail connection is stated, the other end is connected with the windrow mesa base;The windrow platform, guide rail, sub-truss collectively form three
Angular rock-steady structure.
Further, the wall-attaching equipment is fixed on external wall by through-wall bolt.
Further, the material platform also includes closing piece, and the guide rail can be locked by fastening the bolt on the closing piece
In the wall-attaching equipment.
Further, the windrow platform periphery is provided with guardrail board.
Further, the wall-attaching equipment is 3, is respectively arranged on 3 layers of adjacent external wall.
The beneficial effects of the utility model are:Material platform is easy for installation, and ground once assembles, relatively conventional every layer of material platform
The mode of installation is saved and manually, reduces the operation dangerous matter sources that high-altitude peace is torn open, and climb operation is simple, and there is falling proof device safely may be used
Lean on, can return to and be used in turn, there is good Social benefit and economic benefit.
Brief description of the drawings
Fig. 1 show a kind of full steel structure assembled of the utility model embodiment and climbed material platform structural representation.
Fig. 2 show the wall-attaching equipment and lifting hanging seat mounting structure schematic diagram of the utility model embodiment.
Fig. 3 show the through-wall bolt installation and windrow platform turnover panel schematic diagram of the utility model embodiment.
Fig. 4 show the electric block schematic view of the mounting position of the utility model embodiment.
Fig. 5 show after the utility model climbs in place schematic diagram under working condition.
Wherein:1- guide rails, 2- connection frameworks, 3- wall-attaching equipments, 4- liftings hanging seat, 5- electric blocks, 6- closing pieces, 7- supports
Truss, 8- guardrail boards, 9- windrows platform, 10- operating platforms, 11- external walls, 12- through-wall bolts, 13- steel wire ropes, 14-
Turnover panel.
Embodiment
The utility model specific embodiment is described in detail below in conjunction with specific accompanying drawing.It should be noted that following implementations
Example described in technical characteristic or technical characteristic combination be not construed as it is isolated, they can be mutually combined from
And reach superior technique effect.In the accompanying drawing of following embodiments, the identical label that each accompanying drawing occurs represents identical spy
Sign or part, can be applied in different embodiments.
As Figure 1-5, a kind of full steel structure assembled of the utility model embodiment climbs material platform, including guide rail 1,
Windrow platform 9, operating platform 10, installed in external wall(Building structure)Lifting hanging seat 4 on 11;
The guide rail 1 is arranged on external wall by wall-attaching equipment 3(Building structure)On 11, the windrow platform 9, operation
Platform 10 is each attached on the guide rail 1;The operating platform 10 is located at the lower section of the windrow platform 9;
The upper end of steel wire rope 13 is mounted on the suspension ring of the lifting hanging seat 4, and lower end passes through the cunning on the operating platform 10
Wheel is connected with the guide chain of the lower end of electric block 5;The electric block 5 is arranged at the bottom of the windrow platform 9.
The guide rail 1 is 2 or multiple(Determined according to material platform size), pass through between 2 or multiple guide rails 1
Connection framework 2 connects as one;The windrow platform 9, operating platform 10 are each attached on 2 or multiple guide rails 1.
Preferably, the windrow platform 9 is firmly connected by sub-truss 7 with guide rail 1;Described one end of sub-truss 7 with
The guide rail 1 is connected, and the other end is connected with the bottom of windrow platform 9;The windrow platform 9, guide rail 1, sub-truss 7 are common
Triangle rock-steady structure.
The wall-attaching equipment 3 is fixed on external wall by through-wall bolt 12(Building structure)On 11.
Preferably, the material platform also includes closing piece 6, and the guide rail 1 can be locked by fastening the bolt on the closing piece 6
In the wall-attaching equipment 3.
The periphery of windrow platform 9 is provided with guardrail board 8, to ensure safety.
In actual use is installed, on ground by guide rail 1, connection framework 2, wall-attaching equipment 3, closing piece 6, sub-truss 7, anti-
Guardrail board 8, windrow platform 9, operating platform 10 connect integral.
As shown in Fig. 2 external wall can be lifted into by building site tower crane(Building structure)11 extensions, adjust wall-attaching equipment 3
With the relative position of guide rail 1, wall-attaching equipment 3 is fixed to external wall using through-wall bolt 12(Building structure)On 11, and will
Bolt fastening on closing piece 6, external wall is locked to by this device(Building structure)On 11, as Fig. 4 passes through through-wall bolt 12
3 wall-attaching equipments 3 are installed.
As shown in figure 4, the upper end of boom hoist cable 13 is mounted on the suspension ring of lifting hanging seat 4, lower end passes through operating platform 10
On pulley be connected with the lower end guide chain of electric block 5, after installing, do site tests, meet operation of being climbed after requiring.
When climbing, all items in windrow platform 9 are removed totally, starts electric block 5 and shrinks guide chain, drive whole body
After 10cm climbs upwards along wall-attaching equipment 3 in system, closing piece 6 is removed, then proceedes to climb, is installed after being raised to superstructure plate face height
Whole system is locked in superstructure structural edge by closing piece 6, and electric block 5 is loosened and pulled down, and is had enough to meet the need to superstructure, is such as schemed
5 remove lifting hanging seat 4 and through-wall bolt 12, are installed to superstructure structure.Treat to repeat above-mentioned stream after the completion of superstructure discharging
Journey, it is repeatedly lifted up.
Top building construction discharging is completed, and hanging method, which hangs whole system, when passing through installation tears open to ground, is disintegrated,
Encapsulation storage.
The beneficial effects of the utility model are:Material platform is easy for installation, and ground once assembles, relatively conventional every layer of material platform
The mode of installation is saved and manually, reduces the operation dangerous matter sources that high-altitude peace is torn open, and climb operation is simple, and there is falling proof device safely may be used
Lean on, can return to and be used in turn, there is good Social benefit and economic benefit.
Although having been presented for several embodiments of the present utility model herein, those skilled in the art should manage
Solution, in the case where not departing from the utility model spirit, can be changed to the embodiments herein.Above-described embodiment simply shows
Example property, restriction that should not using the embodiments herein as the utility model interest field.
Claims (7)
- The material platform 1. a kind of full steel structure assembled climbs, it is characterised in that including guide rail, windrow platform, operating platform, peace Lifting hanging seat on external wall;The guide rail is arranged on external wall by wall-attaching equipment, and the windrow platform, operating platform are each attached to described lead On rail;The operating platform is located at the lower section of the windrow platform;Steel wire rope upper end is mounted on the suspension ring of the lifting hanging seat, and lower end passes through pulley and electronic calabash on the operating platform The guide chain connection of reed lower end;The electric block is arranged at the bottom of the windrow platform.
- 2. material platform as claimed in claim 1, it is characterised in that the guide rail is 2, and 2 guide rails pass through connection Framework connects as one;The windrow platform, operating platform are each attached on 2 guide rails.
- 3. material platform as claimed in claim 1, it is characterised in that the windrow platform is firm with guide rail by sub-truss Connection;Described sub-truss one end is connected with the guide rail, and the other end is connected with the windrow mesa base;The windrow is put down Platform, guide rail, sub-truss collectively form triangle rock-steady structure.
- 4. material platform as claimed in claim 1, it is characterised in that the wall-attaching equipment is fixed on building by through-wall bolt On exterior wall.
- 5. the material platform as described in claim any one of 1-4, it is characterised in that the material platform also includes closing piece, tightly Gu the guide rail can be locked in the wall-attaching equipment by the bolt on the closing piece.
- 6. the material platform as described in claim any one of 1-4, it is characterised in that the windrow platform periphery is provided with protection Breast board.
- 7. the material platform as described in claim any one of 1-4, it is characterised in that the wall-attaching equipment is 3, is installed respectively In on 3 layers of adjacent external wall.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720574402.1U CN206971760U (en) | 2017-05-22 | 2017-05-22 | A kind of full steel structure assembled climbs material platform |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720574402.1U CN206971760U (en) | 2017-05-22 | 2017-05-22 | A kind of full steel structure assembled climbs material platform |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206971760U true CN206971760U (en) | 2018-02-06 |
Family
ID=61409695
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720574402.1U Expired - Fee Related CN206971760U (en) | 2017-05-22 | 2017-05-22 | A kind of full steel structure assembled climbs material platform |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206971760U (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109113353A (en) * | 2018-07-24 | 2019-01-01 | 北京天恒建设集团有限公司 | A kind of construction material feeding plateform system with enhanced feature |
| CN110512869A (en) * | 2018-05-21 | 2019-11-29 | 王四兵 | It is novel and multifunctional to cut wall drill hole fluting and material lift all-in-one machine |
| CN111439687A (en) * | 2020-04-16 | 2020-07-24 | 中建四局第一建筑工程有限公司 | Bottom protection and operation platform of a super high-rise building climbing boom tower crane |
| CN113089990A (en) * | 2021-05-12 | 2021-07-09 | 江西致邦住宅工业集团有限公司 | High-rise steel structure construction platform |
| CN117552650A (en) * | 2023-10-24 | 2024-02-13 | 中国一冶集团有限公司 | A semi-automatic hanging climbing unloading platform and its use method |
-
2017
- 2017-05-22 CN CN201720574402.1U patent/CN206971760U/en not_active Expired - Fee Related
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110512869A (en) * | 2018-05-21 | 2019-11-29 | 王四兵 | It is novel and multifunctional to cut wall drill hole fluting and material lift all-in-one machine |
| CN109113353A (en) * | 2018-07-24 | 2019-01-01 | 北京天恒建设集团有限公司 | A kind of construction material feeding plateform system with enhanced feature |
| CN109113353B (en) * | 2018-07-24 | 2020-12-04 | 北京天恒建设集团有限公司 | A building construction material receiving platform system with lifting function |
| CN111439687A (en) * | 2020-04-16 | 2020-07-24 | 中建四局第一建筑工程有限公司 | Bottom protection and operation platform of a super high-rise building climbing boom tower crane |
| CN113089990A (en) * | 2021-05-12 | 2021-07-09 | 江西致邦住宅工业集团有限公司 | High-rise steel structure construction platform |
| CN113089990B (en) * | 2021-05-12 | 2022-07-15 | 致邦住宅工业集团有限公司 | High-rise steel structure construction platform |
| CN117552650A (en) * | 2023-10-24 | 2024-02-13 | 中国一冶集团有限公司 | A semi-automatic hanging climbing unloading platform and its use method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206971760U (en) | A kind of full steel structure assembled climbs material platform | |
| CN205077885U (en) | Hydraulic intelligent climbing protection platform for core tube of building | |
| CN109779244A (en) | A kind of self-elevating type elevator hoistway exterior wall creeping formwork operating platform construction | |
| KR101923924B1 (en) | Rope type elevator of high speed and heavy road and mast structure for constructing high-rise building | |
| CN214269987U (en) | Hoisting device applied to high-rise building roof elevator shaft | |
| CN204529038U (en) | Construction elevator floor passageway integral type turns over a door system | |
| CN204418629U (en) | Integrated form climbs frame | |
| CN202214974U (en) | 5.8 m ultrahigh external climbing frame | |
| CN211923476U (en) | Electric hoist lifting system attached to lifting scaffold | |
| CN205743040U (en) | A kind of integrated form material hoisting platform | |
| CN111851980A (en) | Lifting protection platform attached to elevator shaft and application method thereof | |
| CN205000656U (en) | From over -and -under type material cycling platform | |
| CN204626930U (en) | Integrated lifting frame operating platform | |
| CN202441045U (en) | Rail-type electric attached lifting scaffold | |
| CN201460186U (en) | Adhesive lifting scaffold | |
| CN209482687U (en) | A kind of Super High exterior frame column construction operation platform | |
| CN107288361B (en) | High-rise falling-prevention backward anchoring self-hanging double-layer horizontal safety net device and construction method thereof | |
| CN205370860U (en) | A tower section of thick bamboo for wind generating set | |
| CN217871986U (en) | High-rise building demolishs building machine | |
| CN103225390B (en) | Hollow facade pulley guide attached-type lifting scaffold | |
| CN206487129U (en) | Safety hanging cradle for industrial premises Construction of Steel Structure | |
| CN216105498U (en) | Elevator shaft with special hanging basket | |
| CN212154622U (en) | Outer wall plate mounting ladder stand for steel structure factory building | |
| CN204873616U (en) | Climb frame basis in tower crane | |
| CN105781610A (en) | Safety cabin for manual hole digging operation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180206 |