CN206942785U - A kind of supporting for being used to support Super-large-section tunnel - Google Patents
A kind of supporting for being used to support Super-large-section tunnel Download PDFInfo
- Publication number
- CN206942785U CN206942785U CN201720648725.0U CN201720648725U CN206942785U CN 206942785 U CN206942785 U CN 206942785U CN 201720648725 U CN201720648725 U CN 201720648725U CN 206942785 U CN206942785 U CN 206942785U
- Authority
- CN
- China
- Prior art keywords
- support
- rod
- section
- supporting
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
本专利申请属于用混凝土现场浇注;为此所用的模板或其他设备,具体涉及一种用于支撑特大断面隧道的支护;包括位于断面内的底座,底座内设有第一液压缸,第一液压缸的输出轴上连接有顶杆,底座上固定有底板,底板的两侧分别铰接有斜杆,其中一个斜杆开有供另一个斜杆穿过的滑腔;斜杆的表面均匀设有若干凸块,凸块上设有滑槽,滑槽中滑动连接有可与断面接触的支撑杆,支撑杆上顶部设有球状支撑头,凸块底部和支撑杆之间焊接有弹簧,支撑杆伸入滑槽的端部设有可防止支撑杆滑出滑槽的挡板。本专利申请可适配不同形式断面,对断面施加多个支撑,增强支撑效果,加快工程进度。
This patent application belongs to the field pouring of concrete; the formwork or other equipment used for this purpose specifically relates to a support for supporting a super-large section tunnel; it includes a base located in the section, and a first hydraulic cylinder is arranged in the base. The output shaft of the hydraulic cylinder is connected with a push rod, the base is fixed with a base plate, and the two sides of the base plate are respectively hinged with oblique rods, one of which has a sliding cavity for the other oblique rod to pass through; the surface of the oblique rod is evenly designed There are several bumps, and there are slide grooves on the bumps, and the support rods that can contact with the section are slidably connected in the slide grooves. The top of the support rods is provided with a spherical support head, and a spring is welded between the bottom of the bumps and the support rods. The end of the rod extending into the chute is provided with a baffle that can prevent the support rod from slipping out of the chute. This patent application can be adapted to different types of sections, and multiple supports can be applied to the sections to enhance the supporting effect and speed up the progress of the project.
Description
技术领域technical field
本发明属于用混凝土现场浇注;为此所用的模板或其他设备,具体涉及一种用于支撑特大断面隧道的支护。The invention belongs to on-site pouring of concrete; formwork or other equipment used for this purpose, in particular to a support for supporting a super-large section tunnel.
背景技术Background technique
近年来,随着我国经济建设的发展,城市化进程的不断加速,对基础设施,尤其是交通设施建设的需求在不断增加,大量出现大断面、多断面隧道工程现象,且规模越来越大,其中开挖断面面积大于140平方米的断面称为特大断面。对大断面、多断面隧道施工方案,不仅需要能很好地满足特殊地质及地形条件、线桥隧衔接方式、总体路线线型的特殊要求,而且还需要考虑是否有利于公路整体线型规划和线型优化,能否取得良好的技术经济效果等因素。In recent years, with the development of my country's economic construction and the continuous acceleration of urbanization, the demand for infrastructure, especially the construction of transportation facilities, has been increasing, and a large number of large-section and multi-section tunnel projects have appeared, and the scale is getting larger and larger , and the section with an excavated section area greater than 140 square meters is called a super-large section. For large-section and multi-section tunnel construction schemes, it is not only necessary to meet the special requirements of special geological and topographical conditions, line-bridge-tunnel connection methods, and overall route alignment, but also to consider whether it is conducive to the overall alignment planning and construction of the highway. Linear optimization, whether good technical and economic effects can be achieved and other factors.
目前,对大断面、多断面隧道工程的衬砌施工,多采用不同的断面全液压衬砌台车进行施工,对不同断面进行施工时,换用新的符合需要的衬砌台车,即同一隧道包括多少种形式的断面,即需换用多少台衬砌台车,多台衬砌台车需分别组拼安装,这必然造成大量人力、物力、财力的浪费,并直接影响整个工程进度。而且支撑点单一,支撑效果不好。At present, for the lining construction of large-section and multi-section tunnel projects, full-hydraulic lining trolleys with different sections are mostly used for construction. There are different types of sections, that is, how many lining trolleys need to be replaced, and multiple lining trolleys need to be assembled and installed separately, which will inevitably cause a lot of waste of manpower, material resources, and financial resources, and directly affect the progress of the entire project. And the support point is single, and the support effect is not good.
发明内容Contents of the invention
本发明的目的在于提供一种用于支撑特大断面隧道的支护,可适配不同形式断面,对断面施加多个支撑,增强支撑效果,加快工程进度。The object of the present invention is to provide a support for supporting a super-large section tunnel, which can adapt to different types of sections, apply multiple supports to the section, enhance the supporting effect, and speed up the progress of the project.
为达到上述目的,本发明的基础方案如下:In order to achieve the above object, the basic scheme of the present invention is as follows:
一种用于支撑特大断面隧道的支护,包括位于断面内的底座,所述底座内设有第一液压缸,所述第一液压缸的输出轴上连接有顶杆,所述底座上固定有底板,所述底板的两侧分别铰接有斜杆,其中一个斜杆开有供另一个斜杆穿过的滑腔;所述斜杆的表面均匀设有若干凸块,所述凸块上设有滑槽,所述滑槽中滑动连接有可与断面接触的支撑杆,所述支撑杆上顶部设有球状支撑头,所述凸块底部和支撑杆之间焊接有弹簧,所述支撑杆伸入滑槽的端部设有可防止支撑杆滑出滑槽的挡板。A support for supporting a super-large section tunnel, including a base located in the section, a first hydraulic cylinder is arranged in the base, and a push rod is connected to the output shaft of the first hydraulic cylinder, and the base is fixed on the There is a bottom plate, and the two sides of the bottom plate are respectively hinged with oblique rods, one of which has a sliding chamber for the other oblique rod to pass through; the surface of the oblique rod is evenly provided with several bumps, and on the bumps A chute is provided, and a support rod that can be in contact with the section is slidably connected in the chute, a spherical support head is provided on the top of the support rod, a spring is welded between the bottom of the protrusion and the support rod, and the support The end of the rod extending into the chute is provided with a baffle that can prevent the support rod from slipping out of the chute.
本方案一种用于支撑特大断面隧道的支护的原理和有益效果在于:The principle and beneficial effects of this scheme for supporting the support of a super-large section tunnel are:
底座位于断面内的地面,底座内设有第一液压缸,第一液压缸的输出轴上连接有顶杆,顶杆在输出轴的作用下可向上移动。底座上固定有底板,底板的两侧分别铰接有斜杆,其中一个斜杆开有供另一个斜杆穿过的滑腔,顶杆向上移动到与斜杆接触后,会继续向上移动进而推动斜杆绕其与底板的铰接点转动,在斜板转动的同时,斜杆的表面均匀设有的凸块会逐渐靠近断面,凸块中滑槽中滑动连接有可与断面接触的支撑杆,支撑杆上顶部设有球状支撑头,凸块底部和支撑杆之间焊接有弹簧,凸块随斜板逐渐靠近断面内壁,凸块中的的支撑杆在与断面接触之后,在凸块的移动过程中,逐渐挤压弹簧,当斜板在顶杆的作用下转动到位后,顶杆停止上行,并保持固定,此时斜板上的若干支撑杆均会与断面内壁接触并对其进行支撑,斜板上有多个支撑杆,这些支撑杆会分别对断面的内壁的弧面的各个点进行支撑,增强支撑效果。凸块底部和支撑杆之间焊接有弹簧,当遇到不同大小的断面的时候,弹簧的压缩程度的不同,但是同样能够使得支撑杆对断面进行支撑或者支护。The base is located on the ground in the section, and a first hydraulic cylinder is arranged in the base, and a push rod is connected to the output shaft of the first hydraulic cylinder, and the push rod can move upward under the action of the output shaft. The bottom plate is fixed on the base, and the two sides of the bottom plate are respectively hinged with inclined rods. One of the inclined rods has a sliding cavity for the other oblique rod to pass through. The inclined bar rotates around its hinge point with the bottom plate. When the inclined bar rotates, the bumps uniformly provided on the surface of the inclined bar will gradually approach the section. The chute in the bump is slidably connected with a support rod that can contact the section. There is a spherical support head on the top of the support rod, and a spring is welded between the bottom of the bump and the support rod. The bump gradually approaches the inner wall of the section with the inclined plate. During the process, the spring is gradually squeezed, and when the swash plate rotates to the position under the action of the ejector rod, the ejector rod stops moving up and remains fixed. At this time, several support rods on the swash plate will contact and support the inner wall of the section. , There are multiple support rods on the inclined plate, and these support rods will respectively support each point of the arc surface of the inner wall of the section to enhance the support effect. A spring is welded between the bottom of the bump and the support rod. When encountering sections of different sizes, the compression degree of the spring is different, but the support rod can also support or support the section.
优选方案一:作为对基础方案的进一步优化,顶杆上的顶部设有万向轮,减少摩擦,保护设备。Preferred option 1: As a further optimization of the basic solution, a universal wheel is provided on the top of the ejector rod to reduce friction and protect the equipment.
优选方案二:作为对基础方案的进一步优化,斜杆的端部设有缓冲垫,所述缓冲垫为橡胶缓冲垫,防止斜杆的顶端戳坏断面。The second preferred solution: As a further optimization of the basic solution, a buffer pad is provided at the end of the slanting rod, and the buffer pad is a rubber buffer pad to prevent the top of the slanting rod from poking the section.
优选方案三:作为对基础方案的进一步优化,底板上沿中线对称设有第二液压缸,所述第二液压缸的输出端设有连杆,所述连杆底部设有滑轮,第二液压缸可将滑轮推动下行,使得滑轮接触地面,使得整个设备可在地面运输或者移动。The third preferred option: As a further optimization of the basic solution, a second hydraulic cylinder is arranged symmetrically along the center line on the bottom plate, a connecting rod is arranged at the output end of the second hydraulic cylinder, and a pulley is arranged at the bottom of the connecting rod. The cylinder can push the pulley down, so that the pulley touches the ground, so that the whole device can be transported or moved on the ground.
优选方案四:作为对基础方案的进一步优化,支撑头的表面均匀分布有凸起,增大摩擦,防止支撑头在支撑点上滑动。The fourth preferred solution: As a further optimization of the basic solution, the surface of the support head is evenly distributed with protrusions to increase friction and prevent the support head from sliding on the support point.
附图说明Description of drawings
图1是本发明一种用于支撑特大断面隧道的支护实施例的结构示意图。Fig. 1 is a structural schematic diagram of an embodiment of a support for supporting a super-large section tunnel according to the present invention.
具体实施方式detailed description
下面通过具体实施方式对本发明作进一步详细的说明:The present invention will be described in further detail below by means of specific embodiments:
说明书附图中的附图标记包括:断面1、底座2、第一液压缸3、第二液压缸4、底板5、顶杆6、斜杆7、凸块8、支撑杆9、支撑头10、万向球11、缓冲垫12、弹簧13。The reference signs in the drawings of the description include: section 1, base 2, first hydraulic cylinder 3, second hydraulic cylinder 4, bottom plate 5, ejector rod 6, inclined rod 7, bump 8, support rod 9, support head 10 , universal ball 11, buffer pad 12, spring 13.
实施例基本如图1所示:The embodiment is basically as shown in Figure 1:
本实施例的一种用于支撑特大断面隧道的支护,包括位于断面1内的底座2,底座2内设有第一液压缸3,第一液压缸3的输出轴上连接有顶杆6,顶杆6上的顶部设有万向轮;底座2上固定有底板5,底板5的两端分别铰接有斜杆7,斜杆7的端部设有缓冲垫12,其中左端的斜杆7开有供右端的斜杆7穿过的滑腔;斜杆7的表面均匀设有若干凸块8。每个凸块8上开有滑槽,滑槽中滑动连接有可与断面1接触的支撑杆9,支撑杆9上顶部设有球状的支撑头10,凸块8底部和支撑杆9之间焊接有弹簧13,支撑杆9伸入滑槽的端部设有可防止支撑杆9滑出滑槽的挡板。底板5上沿中线对称安装有第二液压缸4,第二液压缸4的输出端设有连杆,连杆底部设置有可滑动的滑轮。A support for supporting a super-large section tunnel in this embodiment includes a base 2 located in the section 1, a first hydraulic cylinder 3 is arranged in the base 2, and a push rod 6 is connected to the output shaft of the first hydraulic cylinder 3 , the top on the push rod 6 is provided with a universal wheel; the base 2 is fixed with a base plate 5, and the two ends of the base plate 5 are respectively hinged with oblique rods 7, and the ends of the oblique rods 7 are provided with buffer pads 12, wherein the oblique rod at the left end 7 has a sliding chamber for the oblique rod 7 at the right end to pass through; the surface of the oblique rod 7 is evenly provided with several projections 8 . There is a chute on each bump 8, and a support rod 9 that can be in contact with the section 1 is slidably connected in the chute. The top of the support rod 9 is provided with a spherical support head 10. Welded with spring 13, the end that support rod 9 stretches into chute is provided with the baffle plate that can prevent support rod 9 from slipping out of chute. A second hydraulic cylinder 4 is installed symmetrically along the center line on the bottom plate 5 , a connecting rod is arranged at the output end of the second hydraulic cylinder 4 , and a slidable pulley is arranged at the bottom of the connecting rod.
本实施例放氧化一种用于支撑特大断面1隧道的支护的具体工作过程为:In this embodiment, a kind of specific working process for supporting the support of the ultra-large section 1 tunnel is as follows:
利用第二液压缸4,将滑轮推动到与地面接触,此时推动本装置在地面移动到需要支护的断面1的合适位置,底座2上固定有底板5,底板5的两端分别铰接有斜杆7,其中一个斜杆7开有供另一个斜杆7穿过的滑腔,顶杆6向上移动到与斜杆7接触后,会继续向上移动进而推动斜杆7绕其与底板5的铰接点转动,在斜板转动的同时,斜杆7的表面均匀设有的凸块8会逐渐靠近断面1,凸块8中滑槽中滑动连接有可与断面1接触的支撑杆9,支撑杆9上顶部设有球状支撑头10,支撑头10的表面均匀分布有凸起,增大摩擦,防止支撑头10在支撑点上滑动。凸块8底部和支撑杆9之间焊接有弹簧13,凸块8随斜板逐渐靠近断面1内壁,凸块8中的的支撑杆9在与断面1接触之后,在凸块8的移动过程中,逐渐挤压弹簧13,当斜板在顶杆6的作用下转动到位后,顶杆6停止上行,并保持固定,此时斜板上的若干支撑杆9均会与断面1内壁接触并对其进行支撑,斜板上有多个支撑杆9,这些支撑杆9会分别对断面1的内壁的弧面的各个点进行支撑,增强支撑效果。斜杆7的端部设有缓冲垫12,缓冲垫12为橡胶缓冲垫12,防止斜杆7的顶端戳坏断面1。凸块8底部和支撑杆9之间焊接有弹簧13,当遇到不同大小的断面1的时候,弹簧13的压缩程度的不同,但是同样能够使得支撑杆9对断面1进行支撑或者支护。Use the second hydraulic cylinder 4 to push the pulley into contact with the ground. At this time, the device is pushed to move on the ground to the appropriate position of the section 1 that needs to be supported. The base 2 is fixed with a base plate 5, and the two ends of the base plate 5 are respectively hinged. Slant rods 7, one of which has a sliding chamber for the other slant rod 7 to pass through, and the push rod 6 moves upwards to contact with the slanted rod 7, then it will continue to move upwards and push the slanted rod 7 around it and the bottom plate 5 When the swash plate rotates, the bump 8 uniformly provided on the surface of the slant rod 7 will gradually approach the section 1, and the chute in the bump 8 is slidably connected with the support rod 9 that can contact the section 1. The upper top of the support rod 9 is provided with a spherical support head 10, and the surface of the support head 10 is evenly distributed with protrusions to increase friction and prevent the support head 10 from sliding on the support point. A spring 13 is welded between the bottom of the bump 8 and the support rod 9. The bump 8 gradually approaches the inner wall of the section 1 along with the slant plate. During the process, the spring 13 is gradually squeezed, and when the swash plate rotates to the position under the action of the push rod 6, the push rod 6 stops moving up and remains fixed. To support it, there are a plurality of support rods 9 on the slant plate, and these support rods 9 will respectively support each point of the arc surface of the inner wall of the section 1 to enhance the support effect. The end of the inclined rod 7 is provided with a buffer pad 12, and the buffer pad 12 is a rubber buffer pad 12 to prevent the top of the inclined rod 7 from poking the section 1. A spring 13 is welded between the bottom of the bump 8 and the support rod 9. When encountering sections 1 of different sizes, the compression degree of the spring 13 is different, but it can also enable the support rod 9 to support or support the section 1.
以上所述的仅是本发明的实施例,方案中公知的具体结构及特性等常识在此未作过多描述。应当指出,对于本领域的技术人员来说,在不脱离本发明结构的前提下,还可以作出若干变形和改进,这些也应该视为本发明的保护范围,这些都不会影响本发明实施的效果和专利的实用性。本申请要求的保护范围应当以其权利要求的内容为准,说明书中的具体实施方式等记载可以用于解释权利要求的内容。What is described above is only an embodiment of the present invention, and common knowledge such as specific structures and characteristics known in the scheme are not described here too much. It should be pointed out that for those skilled in the art, under the premise of not departing from the structure of the present invention, several modifications and improvements can also be made, and these should also be regarded as the protection scope of the present invention, and these will not affect the implementation of the present invention. Effects and utility of patents. The scope of protection required by this application shall be based on the content of the claims, and the specific implementation methods and other records in the specification may be used to interpret the content of the claims.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720648725.0U CN206942785U (en) | 2017-06-06 | 2017-06-06 | A kind of supporting for being used to support Super-large-section tunnel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720648725.0U CN206942785U (en) | 2017-06-06 | 2017-06-06 | A kind of supporting for being used to support Super-large-section tunnel |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206942785U true CN206942785U (en) | 2018-01-30 |
Family
ID=61363747
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720648725.0U Expired - Fee Related CN206942785U (en) | 2017-06-06 | 2017-06-06 | A kind of supporting for being used to support Super-large-section tunnel |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206942785U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109826659A (en) * | 2019-02-28 | 2019-05-31 | 中建七局第四建筑有限公司 | A kind of constructing tunnel tunnel arched door support device |
-
2017
- 2017-06-06 CN CN201720648725.0U patent/CN206942785U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109826659A (en) * | 2019-02-28 | 2019-05-31 | 中建七局第四建筑有限公司 | A kind of constructing tunnel tunnel arched door support device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206600175U (en) | A kind of all-hydraulic walking side wall trolley | |
| CN107815974A (en) | A kind of road and bridge construction Multifunctional protection device for power | |
| CN206290286U (en) | A kind of subway pipe-line system construction support frame | |
| CN207348882U (en) | Exploit excavation supporting mechanism in a kind of tunnel | |
| CN204646284U (en) | A kind of roadway support equipment of gob side entry retaining | |
| CN202125299U (en) | Walking type shield translation station-passing system | |
| CN207773924U (en) | A kind of geotechnical engineering soil sample save set easy to remove | |
| CN207469304U (en) | Mould trolley in a kind of piping lane | |
| CN213538587U (en) | Environment-friendly travel ecological road and rural highway pavement structure | |
| CN201661308U (en) | Basic support for filling and supporting | |
| CN108593441A (en) | Linear motion type accelerating and loading test instrument | |
| CN210194392U (en) | A road leveling device for municipal engineering construction | |
| CN204900659U (en) | Section of jurisdiction is vibration isolation platform for production line | |
| CN203889433U (en) | Garbage lifting device for garbage can | |
| CN209621355U (en) | A kind of filling coal mining support apparatus | |
| CN209211247U (en) | A translation device for moving an inverted arch trestle | |
| CN207564681U (en) | A kind of prefabricated three-dimensional mobile formwork of cantilever beam section long line method | |
| CN213265634U (en) | A quick hoisting device for road bridge tunnel construction | |
| CN209323329U (en) | A kind of lava area subgrade construction care device | |
| CN209724379U (en) | A kind of underground coal mine roof fall deliverance apparatus | |
| CN204608525U (en) | A kind of thrustor for dismantling solid concrete roabed | |
| CN108554601A (en) | A kind of heavy-duty crusher of good damping effect | |
| CN209277911U (en) | A kind of subway work suspension device | |
| CN209798498U (en) | A new structure sampling hole asphalt concrete backfill compaction device | |
| CN220953223U (en) | River course bank protection laying device for hydraulic engineering |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20241112 Address after: No. 210 Jinkai Avenue West Section, Dazhulin Street, Yubei District, Chongqing 401120, 3rd Floor, Attachment No. 22-02-002929 (Cluster Registration) Patentee after: Chongqing Huailing Technology Co.,Ltd. Country or region after: China Address before: 402260 No. 1 North and South Avenue, Binjiang new town, Jiangjin District, Chongqing. Patentee before: CHONGQING VOCATIONAL INSTITUTE OF ENGINEERING Country or region before: China |
|
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180130 |