CN206881492U CN201720779071.5U CN201720779071U CN206881492U CN 206881492 U CN206881492 U CN 206881492U CN 201720779071 U CN201720779071 U CN 201720779071U CN 206881492 U CN206881492 U CN 206881492U
Authority
CN
China
Prior art keywords
discharge
discharging
slurries
charging aperture
warehouse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720779071.5U
Other languages
Chinese (zh)
Inventor
刘玉新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Datang Environment Industry Group Co Ltd
Original Assignee
Datang Environment Industry Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Datang Environment Industry Group Co Ltd filed Critical Datang Environment Industry Group Co Ltd
Priority to CN201720779071.5U priority Critical patent/CN206881492U/en
Application granted granted Critical
Publication of CN206881492U publication Critical patent/CN206881492U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of lime stone slurry discharging discharger is the utility model is related to, including:Agstone warehouse, it includes the cylinder warehouse and circular cone warehouse of connection;Two discharge buckets, it is arranged on circular cone warehouse bottom and communicated with circular cone warehouse bottom;Two discharge pipes, its charging aperture are connected with two discharge bucket discharging openings, and discharging opening is connected with two discharging machine inlets, and two discharging machine inlets are connected with two slurry tank charging apertures;Two slurries discharge tubes, its charging aperture are connected with two slurry tank discharging openings, and two slurries discharge tube discharging openings are connected to absorption tower.The beneficial effects of the utility model:Two groups of dischargers are standby each other, ensure that desulfurizing agent is run steadily in the long term, while be easy to on-bne repair.

Description

A kind of lime stone slurry discharging discharger
Technical field
It the utility model is related to a kind of lime stone slurry discharging discharger.
Background technology
Desulfurization method of limestone-gypsum is the domestic most common sulfur removal technology used.The technique is using lime stone as de- Sulphur agent is configured to lime stone slurry by adding process water, and lime stone slurry reacts with the sulfur dioxide in flue gas and generates stone Cream is to reach the purpose of desulfurization.Only a discharge bucket and a slurries emptying pump for conventional limestone slurries discharging discharger Device, trouble point is more in operation, when often result in stoppage in transit, scene wastes a large amount of maintenance times, is often unsatisfactory for desulfurization and continuously runs It is required that it also can not guarantee desulphurization system stable operation on time.
Utility model content
Weak point present in regarding to the issue above, the utility model provide a kind of lime stone slurry discharging discharge dress Put, two groups of dischargers are standby each other, ensure that desulfurizing agent is run steadily in the long term, while be easy to on-bne repair.
To achieve the above object, the utility model provides a kind of lime stone slurry discharging discharger, including:
Agstone warehouse, it includes the cylinder warehouse and circular cone warehouse of connection;
First discharge bucket, it is arranged on the circular cone warehouse bottom and communicated with the circular cone warehouse bottom;
Second discharge bucket, it is arranged on the circular cone warehouse bottom and communicated with the circular cone warehouse bottom;
First discharge pipe, its charging aperture are connected with the first discharge bucket discharging opening, the first discharge pipe discharging Mouth is connected with the first discharging machine inlet, and the first discharging machine inlet is connected with the first slurry tank charging aperture;
Second discharge pipe, its charging aperture are connected with the second discharge bucket discharging opening, the second discharge pipe discharging Mouth is connected with the second discharging machine inlet, and the second discharging machine inlet is connected with the second slurry tank charging aperture;
First slurries discharge tube, its charging aperture are connected with the first slurry tank discharging opening, the first slurries discharge Pipeline discharging opening is connected to absorption tower;
Second slurries discharge tube, its charging aperture are connected with the second slurry tank discharging opening, the second slurries discharge Pipeline discharging opening is connected to the absorption tower.
Further improved as the utility model, first discharge bucket and second discharge bucket are symmetrically installed.
Further improved as the utility model, the angle a between first discharge bucket and second discharge bucket is 55 °~60 °.
Further improved as the utility model, the first meter is installed on first discharge pipe, described second Second meter is installed on discharge pipe.
Further improved as the utility model, the first meter and the first controller electrical connection, described second Meter is electrically connected with second controller.
Further improved as the utility model, first unloader is electrically connected with first controller, described Second unloader is electrically connected with the second controller.
Further improved as the utility model, the first slurries emptying pump be installed on the first slurries discharge tube, Second slurries emptying pump is installed on the second slurries discharge tube.
The beneficial effects of the utility model are:
1st, by setting two discharge buckets, the angle between two discharge buckets is 55~60 °, and the angle can cause lime stone Powder will not glue grey headwall, and the load of two discharge buckets is identical, and standby each other, ensure that desulphurization system will not be because of a discharging Mouth blocks and stops desulfurization, ensures that desulfurizing agent is run steadily in the long term, while is easy to another discharging opening of on-bne repair, and discharge oral sex For using the service life for also extending device, there is good stability;
2nd, by setting two slurries emptying pumps, the load of two slurries emptying pumps is identical, and standby each other, ensures de- Sulphur system will not stop desulfurization because a slurries emptying pump blocks, and ensure that desulfurizing agent is run steadily in the long term, while be easy to Line overhauls another slurries discharge pump installation, and slurries discharge pump installation is used alternatingly the service life for also extending device, had Good stability;
3rd, by meter, the agstone amount of output can be estimated, all agstones is exported, avoided out Existing blowing is not thorough, causes dust accumulation in storehouse, meanwhile, control discharging output quantity can be measured according to demand, will not cause to waste.
Brief description of the drawings
Fig. 1 is a kind of structural representation of lime stone slurry discharging discharger of the utility model.
In figure:
1st, cylinder warehouse;2nd, circular cone warehouse;3-1, the first discharge bucket;3-2, the second discharge bucket;4-1, the first discharge pipe; 4-2, the second discharge pipe;5-1, the first meter;5-2, the second meter;6-1, the first controller;6-2, second controller; 7-1, the first unloader;7-2, the second unloader;8-1, the first slurry tank;8-2, the second slurry tank;9-1, the discharge of the first slurries Pipeline;9-2, the second slurries discharge tube;10-1, the first slurries emptying pump;10-2, the second slurries emptying pump;11st, absorption tower.
Embodiment
As shown in figure 1, a kind of lime stone slurry discharging discharger of the utility model embodiment, including limestone powder bin Body, agstone warehouse include the cylinder warehouse 1 and circular cone warehouse 2 of connection.
The utility model set two discharge buckets, the first discharge bucket 3-1 be arranged on the bottom of circular cone warehouse 2 and with circular cone warehouse 2 bottoms communicate, and the second discharge bucket 3-2 is arranged on the bottom of circular cone warehouse 2 and communicated with the bottom of circular cone warehouse 2.Further, first Discharge bucket 3-1 and the second discharge bucket 3-2 are symmetrically installed.Preferably, the folder between the first discharge bucket 3-1 and the second discharge bucket 3-2 Angle a is 55 °~60 °, and the angle can cause agstone not glue discharging headwall.
First discharge pipe 4-1 charging apertures are connected with the first discharge bucket 3-1 discharging openings, the first discharge pipe 4-1 discharging openings It is connected with the first unloader 7-1 charging apertures, the first unloader 7-1 charging apertures are connected with the first slurry tank 8-1 charging apertures.Second unloads Pipe material 4-2 charging apertures are connected with the second discharge bucket 3-2 discharging openings, the second discharge pipe 4-2 discharging openings and the second unloader 7-2 Charging aperture is connected, and the second unloader 7-2 charging apertures are connected with the second slurry tank 8-2 charging apertures.Further, the first discharge pipe It is provided with 4-1 on the first meter 5-1, the second discharge pipe 4-2 and the second meter 5-2 is installed.First meter 5-1 with First controller 6-1 is electrically connected, and the second meter 5-2 and second controller 6-2 is electrically connected.First unloader 7-1 and One controller 6-1 is electrically connected, and the second unloader 7-2 and second controller 6-2 is electrically connected.Unloader measures according to meter Lime stone output quantity control output agstone or stop output agstone, when needing from limestone powder bin to outside defeated When sending agstone, opening unloader can be transported to agstone outside storehouse, and agstone can be blocked by closing unloader It is transported to outside storehouse.Need, from during discharging over there, unloader correspondingly to be opened by controller.
First slurries discharge tube 9-1 charging apertures are connected with the first slurry tank 8-1 discharging openings, the first slurries discharge tube 9- 1 discharging opening is connected to absorption tower 11.Second slurries discharge tube 9-2 charging apertures are connected with the second slurry tank 8-2 discharging openings, and second Slurries discharge tube 9-2 discharging openings are connected to absorption tower 11.The first slurries emptying pump is installed on first slurries discharge tube 9-1 The second slurries emptying pump 10-2 is installed on 10-1, the second slurries discharge tube 9-2.
By setting two slurries emptying pumps, the load of two slurries emptying pumps is identical, and standby each other, ensures desulfurization System will not stop desulfurization because a slurries emptying pump blocks, and ensure that desulfurizing agent is run steadily in the long term, while be easy to online Another slurries discharge pump installation is overhauled, slurries discharge pump installation is used alternatingly the service life for also extending device, had very Good stability.
When specifically used, when the first discharge bucket 3-1 is blocked, the second discharge duct is opened by the way that second controller 6-2 is corresponding The startup of the second unloader 7-2 on road 4-2, the agstone in the second discharge bucket 3-2 is drawn off, meanwhile, open the second slurry Liquid discharge tube 9-2 the second slurries emptying pump 10-2 excludes slurries to absorption tower 11.Similarly, when the second discharge bucket 3-2 is blocked up During plug, by the corresponding startups for opening the first unloader 7-1 on the first discharge pipe 4-1 of the first controller 6-1, first is gone out Agstone in hopper 3-1 is drawn off, meanwhile, opening the first slurries discharge tube 9-1 the first slurries emptying pump 10-1 will starch Liquid is excluded to absorption tower 11.
Preferred embodiment of the present utility model is the foregoing is only, is not limited to the utility model, for this For the technical staff in field, the utility model can have various modifications and variations.It is all in the spirit and principles of the utility model Within, any modification, equivalent substitution and improvements made etc., it should be included within the scope of protection of the utility model.

Claims (7)

  1. A kind of 1. lime stone slurry discharging discharger, it is characterised in that including:
    Agstone warehouse, it includes the cylinder warehouse (1) and circular cone warehouse (2) of connection;
    First discharge bucket (3-1), it is arranged on circular cone warehouse (2) bottom and communicated with circular cone warehouse (2) bottom;
    Second discharge bucket (3-2), it is arranged on circular cone warehouse (2) bottom and communicated with circular cone warehouse (2) bottom;
    First discharge pipe (4-1), its charging aperture are connected with the first discharge bucket (3-1) discharging opening, first discharge duct Road (4-1) discharging opening is connected with the first unloader (7-1) charging aperture, the first unloader (7-1) charging aperture and the first slurries Case (8-1) charging aperture connects;
    Second discharge pipe (4-2), its charging aperture are connected with the second discharge bucket (3-2) discharging opening, second discharge duct Road (4-2) discharging opening is connected with the second unloader (7-2) charging aperture, the second unloader (7-2) charging aperture and the second slurries Case (8-2) charging aperture connects;
    First slurries discharge tube (9-1), its charging aperture are connected with the first slurry tank (8-1) discharging opening, first slurry Liquid discharge tube (9-1) discharging opening is connected to absorption tower (11);
    Second slurries discharge tube (9-2), its charging aperture are connected with the second slurry tank (8-2) discharging opening, second slurry Liquid discharge tube (9-2) discharging opening is connected to the absorption tower (11).
  2. 2. lime stone slurry discharging discharger according to claim 1, it is characterised in that the first discharge bucket (3- 1) it is symmetrically installed with second discharge bucket (3-2).
  3. 3. lime stone slurry discharging discharger according to claim 2, it is characterised in that the first discharge bucket (3- 1) the angle a between second discharge bucket (3-2) is 55 °~60 °.
  4. 4. lime stone slurry discharging discharger according to claim 1, it is characterised in that first discharge pipe First meter (5-1) is installed on (4-1), the second meter (5-2) is installed on second discharge pipe (4-2).
  5. 5. lime stone slurry discharging discharger according to claim 4, it is characterised in that the first meter (5- 1) it is electrically connected with the first controller (6-1), second meter (5-2) is electrically connected with second controller (6-2).
  6. 6. lime stone slurry discharging discharger according to claim 5, it is characterised in that the first unloader (7- 1) it is electrically connected with first controller (6-1), second unloader (7-2) is electric with the second controller (6-2) Connection.
  7. 7. lime stone slurry discharging discharger according to claim 1, it is characterised in that the first slurries delivery pipe First slurries emptying pump (10-1) is installed on road (9-1), the second slurries are installed on the second slurries discharge tube (9-2) Emptying pump (10-2).
CN201720779071.5U 2017-06-30 2017-06-30 A kind of lime stone slurry discharging discharger Active CN206881492U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720779071.5U CN206881492U (en) 2017-06-30 2017-06-30 A kind of lime stone slurry discharging discharger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720779071.5U CN206881492U (en) 2017-06-30 2017-06-30 A kind of lime stone slurry discharging discharger

Publications (1)

Publication Number Publication Date
CN206881492U true CN206881492U (en) 2018-01-16

Family

ID=61297821

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720779071.5U Active CN206881492U (en) 2017-06-30 2017-06-30 A kind of lime stone slurry discharging discharger

Country Status (1)

Country Link
CN (1) CN206881492U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109795068A (en) * 2019-01-22 2019-05-24 安徽中科都菱商用电器股份有限公司 Foaming machine is used in commercial refrigerator production

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109795068A (en) * 2019-01-22 2019-05-24 安徽中科都菱商用电器股份有限公司 Foaming machine is used in commercial refrigerator production

Similar Documents

Publication Publication Date Title
CN201495126U (en) Lime cream preparing and adding device
CN206881492U (en) A kind of lime stone slurry discharging discharger
CN204197705U (en) A kind of aluminum paste feedway
CN104888599B (en) Spray drying desulfurizer used for cement plant and process method
CN107140333A (en) A kind of limestone powder bin
CN206881493U (en) A kind of slurrying tapping equipment
CN206538821U (en) A kind of double water sending devices of aluminium powder stirring
CN206885860U (en) A kind of limestone powder bin
CN204746080U (en) A spray drying desulphurization unit for cement plant
CN208980594U (en) A kind of lime device with Pneumatic power back-blowing equipment
CN208878363U (en) Activated carbon powder automatic feeding device and system
CN204093300U (en) Coal-burning boiler carbide slag desulphurization plant
CN201200863Y (en) Dispensing device suitable for concentrated pulp of gypsum
CN204297684U (en) The thin ash of a kind of converter dry method dust two-tube pair of storehouse pump static pressure concentrated phase segmentation assisted air-transport system
CN206886256U (en) A kind of agstone device for discharging
CN202705854U (en) Asphalt material supply system
CN203695244U (en) Novel coal ash sorting device
CN206950973U (en) A kind of slurries tapping equipment
CN204297683U (en) A kind of preventing is corroded and the sticky sintering machine head dust removing static pressure concentrated phase segmentation assisted air-transport system sticking plugging
CN207546169U (en) A kind of desulfurization tower bottom dust stratification broken arch transport system
CN109079995A (en) A kind of the cement can system and method for modifying of multistage recycling cement dust
CN107096370A (en) A kind of slurrying tapping equipment
CN101943517B (en) Discharge gas distribution device for harrow drying equipment
CN208275302U (en) Water process lime slurry automatic preparation system
CN208394358U (en) A kind of positive pressure transfer pot

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant