CN206827922U - A kind of slip rope guy device on crane arm - Google Patents

A kind of slip rope guy device on crane arm Download PDF

Info

Publication number
CN206827922U
CN206827922U CN201720684236.0U CN201720684236U CN206827922U CN 206827922 U CN206827922 U CN 206827922U CN 201720684236 U CN201720684236 U CN 201720684236U CN 206827922 U CN206827922 U CN 206827922U
Authority
CN
China
Prior art keywords
rope
tripod
cable wind
arm
main chord
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720684236.0U
Other languages
Chinese (zh)
Inventor
张耀
项建强
苏豫东
周厚亚
张跃辉
潘晓炜
曹宝勇
丁园园
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Original Assignee
JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd filed Critical JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Priority to CN201720684236.0U priority Critical patent/CN206827922U/en
Application granted granted Critical
Publication of CN206827922U publication Critical patent/CN206827922U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is a kind of slip rope guy device on crane arm,Crossbeam including being arranged on arm bottom,Crossbeam is fixedly mounted on a left side for arm bottom by anchor ear I,It is vertically arranged on right main chord and with main chord,On the left side on arm top,Right side is mounted on tripod,Tripod outer end is connected by cable wind rope I with the beam-end of phase the same side,On the left side on tripod top,Anchor ear II symmetrically is housed on right main chord,The outer end of tripod is connected by drag-line with the anchor ear II of phase the same side,Crane lifting lifting rope bottom is connected with hoisting sling,A left side for hoisting sling,Right side is slidably connected by cable wind rope II and becket bridle and the cable wind rope I of phase the same side respectively,Becket bridle is slidably located on cable wind rope I,One end of cable wind rope II is connected with hoisting sling,The other end is connected with becket bridle,Form slip rope structure,Hoisting sling and a hanging object are constrained during lifting,Reduce amplitude of fluctuation,It is easy to lift operating efficiency and security performance.

Description

A kind of slip rope guy device on crane arm
Technical field
It the utility model is related to the guy equipment of crane, more particularly to a kind of slip rope guy on crane arm Device.
Background technology
Traditional crane plays hanging object and has different degrees of swing, then swing more aggravate to the wind during lift heavy thing Strong, very dangerous, in addition, when crane needs to carry out the aerial lifting effect of machinery, amplitude of fluctuation is uncontrolled, makees lifting Industry is difficult, delays job scheduling.
The content of the invention
Technical problem to be solved in the utility model is in view of the shortcomings of the prior art, there is provided one kind can effectively reduce The slip rope guy device being used on crane arm of hanging object swing is played during craning weight of same.
Technical problem to be solved in the utility model is realized by following technical scheme.The utility model is A kind of slip rope guy device on crane arm, it is characterized in:Crossbeam including being arranged on arm bottom, the crossbeam It is fixedly mounted on the left and right main chord of arm bottom by two anchor ears I and is vertically arranged with main chord, on arm top Left and right side is mounted on tripod, and plane where tripod is vertical with arm, and the outer end of tripod passes through cable wind rope I Connected with the beam-end of phase the same side, it is symmetrical on the left and right main chord on tripod top that anchor ear II be housed, tripod outside End is connected by drag-line with the anchor ear II on the main chord of phase the same side, and crane lifting lifting rope bottom is connected with hoisting hook Tool, the left and right side of the hoisting sling are slidably connected by cable wind rope II and becket bridle and the cable wind rope I of phase the same side respectively, The becket bridle is slidably located on cable wind rope I, and one end of cable wind rope II is connected with hoisting sling, and the other end is connected with becket bridle, shape Into slip rope structure.
Technical problem to be solved in the utility model can also further be realized by following technical scheme.With In a kind of upper described slip rope guy device on crane arm:The tripod is fixed on by anchor ear II and hung On the left and right main chord on arm top.
Technical problem to be solved in the utility model can also further be realized by following technical scheme.With In a kind of upper described slip rope guy device on crane arm:The both ends of cable wind rope I are connected to horizontal stroke by cover of wedge On beam and tripod, and cable wind rope I is exceptionally straight state.
Technical problem to be solved in the utility model can also further be realized by following technical scheme.With In a kind of upper described slip rope guy device on crane arm:The drag-line both ends are connected to tripod by cover of wedge On the anchor ear II on tripod top, and drag-line is exceptionally straight state.
Technical problem to be solved in the utility model can also further be realized by following technical scheme.With In a kind of upper described slip rope guy device on crane arm:Filled out between the anchor ear I, anchor ear II and main chord Fill and be provided with nylon back plate.
Crossbeam is stably fixed on the main chord of crane arm bottom by the utility model by using anchor ear I, is utilized Beam sides are connected by cable wind rope I with the tripod outer end on arm top, using cable wind rope II and becket bridle by hoisting sling with Cable wind rope I connects, and realizes and hoisting sling and a hanging object are constrained during lifting, reduced hanging object amplitude of fluctuation, just The efficiency and safety loading coefficient of lifting effect and aerial lifting operation are carried out in lift crane;Three pin are lifted by using drag-line Frame outer end, ensure that tripod is in stable state, cable wind rope I is kept exceptionally straight state, whole cable wind system is kept stable. The utility model has simple in construction and the advantages of beneficial to lift crane operating efficiency and safety coefficient.
Brief description of the drawings
Fig. 1 is a kind of structural representation of the present utility model;
Fig. 2 is a kind of structural representation of crossbeam and anchor ear I.
Embodiment
Concrete technical scheme of the present utility model described further below, in order to those skilled in the art further The utility model is understood, without forming the limitation to its right.
Reference picture 1-2, a kind of slip rope guy device on crane arm, including it is arranged on the horizontal stroke of the bottom of arm 1 Beam 2, the crossbeam 2 are fixedly mounted on the left and right main chord 4 of the bottom of arm 1 and vertical with main chord 4 by two anchor ears I 3 Set, be connected between anchor ear I 3 and main chord 4 using high-strength bolt nut assembly, ensure that crossbeam 2 is stably fixed at arm 1 Bottom, tripod 7 is mounted in the left and right side on the top of arm 1, and the place plane of tripod 7 is vertical with arm 1, three pin The outer end of frame 7 is connected by cable wind rope I 5 with the end of crossbeam 2 of phase the same side, the left and right main chord 4 on the top of tripod 7 Upper that anchor ear II 12 is symmetrically housed, the outer end of tripod 7 passes through drag-line 6 and the anchor ear II 12 on the main chord 4 of phase the same side connects Connect, the bottom of crane lifting lifting rope 11 is connected with hoisting sling 10, and the left and right side of the hoisting sling 10 passes through cable respectively Wind rope II 8 and becket bridle 9 and the cable wind rope I 5 of phase the same side are slidably connected, and the becket bridle 9 is slidably located on cable wind rope I 5, guy Restrict II 8 one end is connected with hoisting sling 10, and the other end is connected with becket bridle 9, forms slip rope structure, it is right during lifting to realize Hoisting sling 10 and a hanging object are constrained, and have been reduced hanging object amplitude of fluctuation, have been easy to lift crane to carry out lifting effect and sky The efficiency and security performance of middle lifting operation;
The tripod 7 is fixed on by anchor ear II 12 on the left and right main chord 4 on the top of arm 1;
The both ends of cable wind rope I 5 are connected on crossbeam 2 and tripod 7 by cover of wedge, and cable wind rope I 5 is exceptionally straight state;
The both ends of drag-line 6 are connected on tripod 7 and the anchor ear II 12 on the top of tripod 7 by cover of wedge, and drag-line 6 is Exceptionally straight state, drag-line 6 play lifting effect to tripod 7, ensure that tripod 7 is in stable state, cable wind rope I 5 is kept taut Straight state, whole cable wind system is set to keep stable;
Nylon back plate has been filled between the anchor ear I 3, anchor ear II 12 and main chord 4, protection has been played and damping is made With.

Claims (5)

  1. A kind of 1. slip rope guy device on crane arm, it is characterised in that:Crossbeam including being arranged on arm bottom, The crossbeam is fixedly mounted on the left and right main chord of arm bottom by two anchor ears I and is vertically arranged with main chord, is being hung The left and right side on arm top is mounted on tripod, and plane where tripod is vertical with arm, and the outer end of tripod passes through Cable wind rope I connects with the beam-end of phase the same side, symmetrical on the left and right main chord on tripod top that anchor ear II is housed, and three The outer end of foot stool is connected by drag-line with the anchor ear II on the main chord of phase the same side, and the connection of crane lifting lifting rope bottom is set There is hoisting sling, the left and right side of the hoisting sling is slided by cable wind rope II and becket bridle and the cable wind rope I of phase the same side respectively Dynamic connection, the becket bridle are slidably located on cable wind rope I, and one end of cable wind rope II is connected with hoisting sling, the other end and becket bridle Connection.
  2. A kind of 2. slip rope guy device on crane arm according to claim 1, it is characterised in that:Described three Foot stool is fixed on the left and right main chord on arm top by anchor ear II.
  3. A kind of 3. slip rope guy device on crane arm according to claim 1, it is characterised in that:The cable The both ends of wind rope I are connected on crossbeam and tripod by cover of wedge, and cable wind rope I is exceptionally straight state.
  4. A kind of 4. slip rope guy device on crane arm according to claim 1, it is characterised in that:The drawing Rope both ends are connected on tripod and the anchor ear II on tripod top by cover of wedge, and drag-line is exceptionally straight state.
  5. A kind of 5. slip rope guy device on crane arm according to claim 1, it is characterised in that:Described armful Nylon back plate has been filled between hoop I, anchor ear II and main chord.
CN201720684236.0U 2017-06-13 2017-06-13 A kind of slip rope guy device on crane arm Active CN206827922U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720684236.0U CN206827922U (en) 2017-06-13 2017-06-13 A kind of slip rope guy device on crane arm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720684236.0U CN206827922U (en) 2017-06-13 2017-06-13 A kind of slip rope guy device on crane arm

Publications (1)

Publication Number Publication Date
CN206827922U true CN206827922U (en) 2018-01-02

Family

ID=60775695

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720684236.0U Active CN206827922U (en) 2017-06-13 2017-06-13 A kind of slip rope guy device on crane arm

Country Status (1)

Country Link
CN (1) CN206827922U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109809303A (en) * 2019-03-19 2019-05-28 徐工集团工程机械股份有限公司建设机械分公司 Crane hanging component system
CN110342409A (en) * 2018-04-02 2019-10-18 中国核工业第五建设有限公司 A kind of no hanging beam Lift-on/Lift-off System and decoupling device method is lifted without hanging beam

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110342409A (en) * 2018-04-02 2019-10-18 中国核工业第五建设有限公司 A kind of no hanging beam Lift-on/Lift-off System and decoupling device method is lifted without hanging beam
CN110342409B (en) * 2018-04-02 2022-02-08 中国核工业第五建设有限公司 Lifting system without lifting beam and lifting unhooking method without lifting beam
CN109809303A (en) * 2019-03-19 2019-05-28 徐工集团工程机械股份有限公司建设机械分公司 Crane hanging component system

Similar Documents

Publication Publication Date Title
CN204342250U (en) A kind of multi-state hoisting balance beam
CN201809036U (en) Hanging hopper with detachable chassis
CN101649682A (en) Method for assembling tower by post-assembly rocker arm holding pole technology
CN206345591U (en) A kind of building tower crane with safety hanging cradle
CN206827922U (en) A kind of slip rope guy device on crane arm
CN103437298A (en) Hoisting method and hoisting device for concrete prefabricated box beam
CN100567129C (en) A kind of hoisting device for loop wheel machine
CN207001991U (en) A kind of hanging apparatus of high ferro prefabricated case beam
CN201809034U (en) Lifting appliance applied to adjusting posture of large member in air
CN104276514B (en) Mounting method of flooring self-balance wrapping rod
CN102351129B (en) Super-lifting device for improving lifting performance of crane and crane
CN204342257U (en) A kind of large-scale component turning device
CN203667798U (en) Light-weight high-strength cross beam lifting appliance
CN204702437U (en) A kind of build-up type power pontoon combination mast crane device
CN202988609U (en) Diagonal bracing type derrick crane
CN203781677U (en) Trial mass device of crane
CN203653080U (en) Mooring rope hanging mechanism capable of meeting motion of portal crane
CN202625662U (en) Self-balancing amplitude modulation hold pole
CN205170159U (en) Can hang hoist that hangs in overhead traveling crane
CN202449743U (en) Lifting regulation device
CN103738852A (en) Weight testing device of crane
CN209038856U (en) A kind of overhead traveling crane steel plate special suspender
CN207608243U (en) A kind of building tower crane of stable safety
CN103321202B (en) An arm method of boom hoisting, dynamic compaction machinery and dynamic compaction machinery
CN201236098Y (en) Combined pressure bar sling

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant