CN206767419U - Wind electricity blade web lifting device - Google Patents

Wind electricity blade web lifting device Download PDF

Info

Publication number
CN206767419U
CN206767419U CN201720604938.3U CN201720604938U CN206767419U CN 206767419 U CN206767419 U CN 206767419U CN 201720604938 U CN201720604938 U CN 201720604938U CN 206767419 U CN206767419 U CN 206767419U
Authority
CN
China
Prior art keywords
web
sides
hanging beam
overall
integral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720604938.3U
Other languages
Chinese (zh)
Inventor
马寅虎
杜兴洲
刘普亮
刘华
许秀强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baiyin Sino Wind Energy Co ltd
Hunan Zhongke Yu Neng Technology Co ltd
Original Assignee
BAIYIN SINO-WIND ENERGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BAIYIN SINO-WIND ENERGY Co Ltd filed Critical BAIYIN SINO-WIND ENERGY Co Ltd
Priority to CN201720604938.3U priority Critical patent/CN206767419U/en
Application granted granted Critical
Publication of CN206767419U publication Critical patent/CN206767419U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

A kind of wind electricity blade web lifting device is the utility model is related to, by the overall hanging beam on top(1)With the suspender of bottom(8)Composition, overall hanging beam(1)By multiple hanging beams(3)Pass through flange(2)Connection composition, overall hanging beam(1)Both sides are arranged with suspension rod(6), suspension rod(6)Top is provided with upper hanger(7), upper hanger(7)Both sides pass through steel wire rope(5)With overall hanging beam(1)Connection;Overall hanging beam(1)Two bottom sides are arranged with suspension hook(9), suspension hook(9)With suspender(8)Connection, web(10)It is placed in suspender(8)In.Overall hanging beam segmentation connection, makes, transports, be easy to use.Lifted by crane by collecting web, clamping tool, coordinate web entirety hanging beam integral lifting, it is easy to operate, securely and reliably.

Description

风电叶片腹板吊装工具Wind power blade web lifting tool

技术领域technical field

本实用新型属于风电叶片制作领域,具体涉及一种风电叶片腹板吊装工具。The utility model belongs to the field of wind power blade production, in particular to a wind power blade web hoisting tool.

背景技术Background technique

风电叶片制作过程因为腹板长度较大,经组装后使用分段吊梁吊装过程容易造成扭曲变形,进而造成叶片结构变形。Due to the large web length in the manufacturing process of wind power blades, the hoisting process of the segmented lifting beams after assembly is likely to cause distortion and deformation, which in turn causes deformation of the blade structure.

发明内容Contents of the invention

本实用新型的目的是提供一种风电叶片腹板吊装工具,以解决现有技术中吊装过程造成组装腹板扭曲变形等问题,为制作精度提供保障。The purpose of the utility model is to provide a wind power blade web hoisting tool to solve the problems in the prior art such as the twisting and deformation of the assembly web caused by the hoisting process, and to provide guarantee for the manufacturing accuracy.

为实现上述目的,采取的技术方案是:一种风电叶片腹板吊装工具,其特征在于:由上部的整体吊梁(1)和下部的吊具(8)组成,整体吊梁(1)由多个支吊梁(3)通过法兰(2)连接组成,整体吊梁(1)两侧对称设有吊杆(6),吊杆(6)顶部设有上吊耳(7),上吊耳(7)两侧通过钢丝绳(5)与整体吊梁(1)连接,保证起吊平衡;整体吊梁(1)底部两侧对称设有吊钩(9),吊钩(9)与吊具(8)连接,腹板(10)置于吊具(8)中。In order to achieve the above purpose, the technical solution adopted is: a wind power blade web hoisting tool, which is characterized in that it consists of an upper integral lifting beam (1) and a lower lifting tool (8), and the integral lifting beam (1) consists of A plurality of supporting beams (3) are connected by flanges (2). The overall hanging beam (1) is symmetrically provided with suspenders (6) on both sides. The top of the suspenders (6) is provided with upper lugs (7). (7) The two sides are connected to the overall hanging beam (1) through the steel wire rope (5) to ensure the lifting balance; the bottom of the integral hanging beam (1) is symmetrically provided with hooks (9) on both sides, and the hooks (9) and the lifting gear ( 8) Connection, the web (10) is placed in the spreader (8).

所述吊杆(6)距整体吊梁(1)端头的距离为整体吊梁(1)长度的三分之一。The distance between the suspension rod (6) and the end of the integral suspension beam (1) is one-third of the length of the integral suspension beam (1).

所述吊具(8)为:丝杠(84)通过手轮(83)固定在吊具(8)的横梁中间,该横梁上部两侧设有下吊耳(82),下部两则设有定位杆(81),丝杠(84)底端设有吊座(85),腹板(9)置于吊座(85)上。The spreader (8) is as follows: the lead screw (84) is fixed in the middle of the beam of the spreader (8) through the hand wheel (83), the upper two sides of the beam are provided with lower lugs (82), and the lower two are provided with Positioning bar (81), leading screw (84) bottom is provided with suspender (85), and web (9) is placed on the suspender (85).

所述整体吊梁(1)为焊接制作,焊缝位置采用钢板(4)焊接加固。The overall hanging beam (1) is manufactured by welding, and the weld seam position is reinforced by welding of steel plates (4).

本实用新型的有益效果是:整体吊梁分段连接,制作、运输、使用方便。通过集腹板起吊、夹紧工装,配合腹板整体吊梁整体起吊,操作方便,安全可靠。解决了腹板起吊过程中使用分段吊梁所造成的扭曲变形或使用棘齿皮带捆绑吊装时所造成的腹板晃动、变形等问题。The beneficial effects of the utility model are: the whole hanging beam is connected in sections, and the manufacture, transportation and use are convenient. It is easy to operate, safe and reliable by lifting and clamping the tooling by collecting the web, and cooperating with the integral lifting beam of the web. It solves the problems of twisting and deformation caused by segmented lifting beams during web hoisting or web shaking and deformation caused by ratchet belt binding and hoisting.

附图说明Description of drawings

图1为本实用新型主视图;Fig. 1 is a front view of the utility model;

图2为本实用新型吊具示意图;Fig. 2 is the utility model spreader schematic diagram;

图中:1-整体吊梁,2-法兰,3-支吊梁,4-加固钢板,5-钢丝绳,6-吊杆,7-上吊耳,8-吊具,9-吊钩,10-腹板, 81-定位杆,82-下吊耳,83-手轮,84-丝杠,85-吊座。In the figure: 1-integral hanging beam, 2-flange, 3-hanging beam, 4-reinforced steel plate, 5-wire rope, 6-hanging rod, 7-hanging lug, 8-sling, 9-hook, 10 -web plate, 81-location bar, 82-lower lifting lug, 83-hand wheel, 84-leading screw, 85-hanging seat.

具体实施方式detailed description

以下结合附图对本实用新型的原理和特征进行描述,所举实例只用于解释本实用新型,并非用于限定本实用新型的范围。The principles and features of the present utility model are described below in conjunction with the accompanying drawings, and the examples given are only used to explain the utility model, and are not used to limit the scope of the utility model.

实施例1:如图1-2所示,一种风电叶片腹板吊装工具,由上部的整体吊梁1和下部的吊具8组成,整体吊梁1由多个支吊梁3通过法兰2连接组成,整体吊梁1两侧对称设有吊杆6,吊杆6顶部设有上吊耳7,上吊耳7两侧通过钢丝绳5与整体吊梁1连接,保证起吊平衡;整体吊梁1底部两侧对称设有吊钩9,吊钩9与吊具8连接。吊杆6距整体吊梁1端头的距离为整体吊梁1长度的三分之一。Embodiment 1: As shown in Figure 1-2, a wind power blade web hoisting tool is composed of an upper integral lifting beam 1 and a lower lifting tool 8, and the integral lifting beam 1 is composed of multiple supporting beams 3 passing through the flange 2 connection composition, the two sides of the overall suspension beam 1 are symmetrically provided with suspension rods 6, and the top of the suspension rod 6 is provided with upper lifting lugs 7, and the two sides of the upper lifting lugs 7 are connected with the overall suspension beam 1 through steel wire ropes 5 to ensure the lifting balance; the overall suspension beam 1 Bottom two sides are symmetrically provided with suspension hook 9, and suspension hook 9 is connected with hanger 8. The distance between suspension rod 6 and the end of integral suspension beam 1 is 1/3rd of the length of integral suspension beam 1 .

所述吊具8为:丝杠84通过手轮83固定在吊具8的横梁中间,该横梁上部两侧设有下吊耳82,下部两则设有定位杆81,丝杠84底端设有吊座85,腹板10置于吊座85上。The spreader 8 is as follows: a lead screw 84 is fixed in the middle of the crossbeam of the spreader 8 through a hand wheel 83, the upper two sides of the crossbeam are provided with lower lugs 82, the lower two are provided with positioning rods 81, and the bottom of the lead screw 84 is provided with There is a hanger 85 on which the web 10 is placed.

支吊梁3长度为6米,支吊梁3之间使用法兰固定连接,根据使The length of the supporting and hanging beams 3 is 6 meters, and the supporting and hanging beams 3 are fixedly connected by flanges.

用需要自由调整长度。采用方管结构型焊接,结构性能稳定。焊缝位置采用钢板4焊接加固。I adjust the length freely as needed. Square tube structural welding is adopted, and the structural performance is stable. The weld position is reinforced by steel plate 4 welding.

吊装过程:先将吊具8安装在腹板10上,定位杆81将腹板10固定,旋转手轮83带动丝杠84使吊座85与腹板10夹紧,整体吊梁1通过上吊耳7用天车吊起,开至吊装位置,将吊钩9与下吊耳82相连,整体起吊。Hoisting process: first install the spreader 8 on the web 10, the positioning rod 81 fixes the web 10, rotate the handwheel 83 to drive the screw 84 to clamp the hanger 85 and the web 10, and the overall hanging beam 1 passes the upper lug 7. Hoist with a crane, open to the hoisting position, connect the suspension hook 9 with the lower lug 82, and hoist as a whole.

以上所述仅为本实用新型的较佳实施例,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present utility model shall be included in this utility model. within the scope of protection of utility models.

Claims (4)

1.一种风电叶片腹板吊装工具,其特征在于:由上部的整体吊梁(1)和下部的吊具(8)组成,整体吊梁(1)由多个支吊梁(3)通过法兰(2)连接组成,整体吊梁(1)两侧对称设有吊杆(6),吊杆(6)顶部设有上吊耳(7),上吊耳(7)两侧通过钢丝绳(5)与整体吊梁(1)连接;整体吊梁(1)底部两侧对称设有吊钩(9),吊钩(9)与吊具(8)连接,腹板(10)置于吊具(8)中。1. A wind power blade web hoisting tool, characterized in that: it consists of an upper integral lifting beam (1) and a lower lifting tool (8), and the integral lifting beam (1) is passed by a plurality of supporting beams (3) Flanges (2) are connected, the overall suspension beam (1) is symmetrically provided with suspenders (6) on both sides, the top of the suspenders (6) is provided with upper lugs (7), and the two sides of the upper lugs (7) pass through the wire ropes (5 ) is connected with the overall suspension beam (1); the bottom of the overall suspension beam (1) is symmetrically provided with hooks (9) on both sides, the hooks (9) are connected with the spreader (8), and the web (10) is placed on the spreader (8). 2.如权利要求1所述的风电叶片腹板吊装工具,其特征在于:所述吊杆(6)距整体吊梁(1)端头的距离为整体吊梁(1)长度的三分之一。2. The wind power blade web hoisting tool according to claim 1, characterized in that: the distance between the boom (6) and the end of the integral suspension beam (1) is 1/3 of the length of the integral suspension beam (1) one. 3.如权利要求1所述的风电叶片腹板吊装工具,其特征在于所述吊具(8)为:丝杠(84)通过手轮(83)固定在吊具(8)的横梁中间,该横梁上部两侧设有下吊耳(82),下部两则设有定位杆(81),丝杠(84)底端设有吊座(85),腹板(10)置于吊座(85)上。3. The wind power blade web hoisting tool according to claim 1, characterized in that the hanger (8) is: the lead screw (84) is fixed in the middle of the beam of the hanger (8) through the handwheel (83), The two sides of the upper part of the beam are provided with lower lugs (82), the lower two are provided with positioning rods (81), the bottom of the screw (84) is provided with a hanger (85), and the web (10) is placed on the hanger ( 85) on. 4.如权利要求1所述的风电叶片腹板吊装工具,其特征在于:所述整体吊梁(1)为焊接制作,焊缝位置采用钢板(4)焊接加固。4. The wind power blade web hoisting tool according to claim 1, characterized in that: the integral hoisting beam (1) is made by welding, and the weld seam position is reinforced by welding of steel plates (4).
CN201720604938.3U 2017-05-27 2017-05-27 Wind electricity blade web lifting device Expired - Fee Related CN206767419U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720604938.3U CN206767419U (en) 2017-05-27 2017-05-27 Wind electricity blade web lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720604938.3U CN206767419U (en) 2017-05-27 2017-05-27 Wind electricity blade web lifting device

Publications (1)

Publication Number Publication Date
CN206767419U true CN206767419U (en) 2017-12-19

Family

ID=60639300

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720604938.3U Expired - Fee Related CN206767419U (en) 2017-05-27 2017-05-27 Wind electricity blade web lifting device

Country Status (1)

Country Link
CN (1) CN206767419U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108439183A (en) * 2018-04-05 2018-08-24 南京高传机电自动控制设备有限公司 A kind of leaf blade hanging structure
CN115092806A (en) * 2022-07-29 2022-09-23 中交一公局第七工程有限公司 Lifting beam device for lifting steel net rack and design method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108439183A (en) * 2018-04-05 2018-08-24 南京高传机电自动控制设备有限公司 A kind of leaf blade hanging structure
CN115092806A (en) * 2022-07-29 2022-09-23 中交一公局第七工程有限公司 Lifting beam device for lifting steel net rack and design method

Similar Documents

Publication Publication Date Title
CN205011284U (en) A simple and easy hoisting apparatus for rack high altitude is in bulk
CN204265213U (en) A kind of light-weight precast slab overhead hoist
CN206767419U (en) Wind electricity blade web lifting device
CN103303787B (en) Clamping device for lifting assembled shear web plates in wind turbine blade
CN203006738U (en) Section bar lifting tool
CN210710342U (en) A hanger device for hoisting and transporting twisted king blocks
CN204265218U (en) A kind of power station unit internal head cover special hanger
CN205034944U (en) Web hoisting accessory
CN203781677U (en) Trial mass device of crane
CN201330124Y (en) Deviation rectification and turning device for sling of crane
CN204454225U (en) A kind of welded structure of solid drawn pipe is without moment of flexure support beam
CN205346692U (en) Swing arm tower machine of supporting multiple mounting means becomes width of cloth pulley yoke
CN211898916U (en) Fixing structure of steel beam and connecting lug plate
CN204400427U (en) The detachable shearing resistance hanger of a kind of truss lifting
CN203428725U (en) Resin sand model hoisting tool
CN203295025U (en) Clamping tool for hoisting single H beam
CN204265221U (en) A kind of super large-scale hoisting steel plate instrument
CN211817874U (en) Ride non-standardized hanging flower basket mounting structure of beam formula
CN209601929U (en) A kind of suspender for wind power flange and tower welding group pair
CN206599390U (en) A kind of crane receives hook mechanism automatically
CN202003830U (en) Lifting appliance of rolled iron core device body
CN205328438U (en) Handling is from lift -type cylindric spud leg hanging beam
CN202575681U (en) Steel coil lifting device
CN207597852U (en) Lower suspension centre structure
CN104355225B (en) A kind of power station unit internal head cover hanging method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180802

Address after: 413000 401 Industrial Park, East New District, Yiyang hi tech Development Zone, Hunan

Co-patentee after: BAIYIN SINO-WIND ENERGY Co.,Ltd.

Patentee after: Hunan Zhongke Yu Neng Technology Co.,Ltd.

Address before: 730900 Baiyin high tech Zone, Baiyin, Gansu

Patentee before: BAIYIN SINO-WIND ENERGY Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171219