CN206736963U - Ditch millet section high water level district lid tunnel stagnant water structure - Google Patents
Ditch millet section high water level district lid tunnel stagnant water structure Download PDFInfo
- Publication number
- CN206736963U CN206736963U CN201720459706.3U CN201720459706U CN206736963U CN 206736963 U CN206736963 U CN 206736963U CN 201720459706 U CN201720459706 U CN 201720459706U CN 206736963 U CN206736963 U CN 206736963U
- Authority
- CN
- China
- Prior art keywords
- cement
- tunnel
- soil mixing
- cover
- mixing pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 32
- 235000002748 Paspalum commersonii Nutrition 0.000 title 1
- 240000004928 Paspalum scrobiculatum Species 0.000 title 1
- 239000002689 soil Substances 0.000 claims abstract description 82
- 238000002156 mixing Methods 0.000 claims abstract description 78
- 239000004568 cement Substances 0.000 claims abstract description 34
- 239000002002 slurry Substances 0.000 claims abstract description 30
- 238000009412 basement excavation Methods 0.000 claims description 17
- 239000010426 asphalt Substances 0.000 claims description 3
- 238000000465 moulding Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 27
- 239000011435 rock Substances 0.000 abstract description 9
- 239000003673 groundwater Substances 0.000 abstract description 6
- 238000003756 stirring Methods 0.000 description 14
- 238000013461 design Methods 0.000 description 13
- 238000005553 drilling Methods 0.000 description 6
- 238000000034 method Methods 0.000 description 6
- 239000003795 chemical substances by application Substances 0.000 description 3
- 239000011440 grout Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 239000010881 fly ash Substances 0.000 description 2
- 238000011065 in-situ storage Methods 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 230000035699 permeability Effects 0.000 description 2
- 238000005507 spraying Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000011083 cement mortar Substances 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 230000008595 infiltration Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000003823 mortar mixing Methods 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 239000002352 surface water Substances 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
一种沟谷段高水位区盖挖隧道止水结构,包括盖拱拱脚下的水泥土搅拌桩墙、隧道底面下的水泥浆止水帷幕和盖拱拱顶防水装置。水泥土搅拌桩墙、隧道底面下水泥浆止水帷幕与盖拱拱顶防水装置一起形成一个完整的止水结构,以降低沟谷段高水位区盖挖隧道施工时地下水带来的风险,还能增强盖拱拱脚处地基承载力,改善隧道围岩的工程性质。
A waterproof structure for a covered tunnel in a high water level area in a valley section includes a cement-soil mixing pile wall under the foot of a cover arch, a cement slurry waterproof curtain under the bottom of the tunnel, and a waterproof device for the top of the cover arch. The cement-soil mixing pile wall, the cement slurry waterproof curtain under the bottom of the tunnel, and the waterproof device for the top of the cover arch together form a complete waterproof structure to reduce the risk of groundwater during the construction of a covered tunnel in a high water level area in the valley section, and can also enhance the bearing capacity of the foundation at the foot of the cover arch and improve the engineering properties of the tunnel surrounding rock.
Description
技术领域technical field
本实用新型涉及一种沟谷段高水位区盖挖隧道止水结构,属于隧道工程防水施工技术领域。The utility model relates to a cover-excavation tunnel water-stop structure in a high water level area of a valley section, belonging to the technical field of tunnel engineering waterproof construction.
背景技术Background technique
随着我国西部基础交通设施的快速发展,各处涌现了大量的隧道工程。我国的西部地区山岭纵横,必将会出现大量的隧道穿越山岭沟谷段,这将不可避免形成沟谷段超浅埋隧道,而盖挖法施工能够保证在超浅埋段施工支护安全的前提下减少对周围环境的影响,且在短期内能恢复地面交通,盖挖施工方法在隧道超浅埋段中有着其他施工方法没有的优越性,现已经开始被推广应于山区隧道施工,所以在未来山岭超浅埋隧道施工中盖挖法施工会越来越多。但一般来说,山岭冲沟常年受到雨水的侵蚀,地质环境一般较差,隧道围岩强度低、稳定性差、岩体松散破碎,还伴有一定程度的地表渗水等情况,经常发生隧道坍塌,甚至山体失稳滑坡,给盖挖隧道支护施工及以后的正常运营使用带来了困难和风险。With the rapid development of basic transportation facilities in western my country, a large number of tunnel projects have sprung up everywhere. In the western region of our country, there are many mountains and ridges, and there will inevitably be a large number of tunnels passing through the valley sections of the mountains, which will inevitably form ultra-shallow tunnels in the valley sections, and the cover-excavation method can ensure the safety of construction support in the ultra-shallow sections. Reduce the impact on the surrounding environment and restore ground traffic in a short period of time. The cover-and-excavation construction method has advantages that other construction methods do not have in ultra-shallow sections of tunnels. There will be more and more cover-excavation constructions in the construction of ultra-shallow buried tunnels in mountains. But generally speaking, mountain gullies are eroded by rainwater all year round, and the geological environment is generally poor. The surrounding rock of the tunnel has low strength, poor stability, loose and broken rock mass, and is accompanied by a certain degree of surface water seepage, etc. Tunnel collapse often occurs. Even mountain instability and landslides have brought difficulties and risks to the support construction of cover-excavation tunnels and subsequent normal operation and use.
实用新型内容Utility model content
本实用新型解决现有技术的不足而提供一种能降低沟谷段高水位区的地下水在盖挖隧道施工时带来的风险,避免由于地下水的作用使得隧道产生大变形失稳灾害的沟谷段高水位区盖挖隧道止水结构。The utility model solves the deficiencies of the prior art and provides a method that can reduce the risks brought by the groundwater in the high water level area of the valley section during the construction of the tunnel cover and excavation, and avoid the large deformation and instability of the tunnel due to the action of the groundwater. Cover and dig tunnel water-stop structures in the water level area.
本实用新型提出了一种沟谷段高水位区盖挖隧道止水结构,在隧道的两侧设置有垂直布设的至少一排水泥土搅拌桩墙,所述水泥土搅拌桩墙的底部在土体中的深度大于隧道底部的深度,所述水泥土搅拌桩墙的沿隧道延伸方向延伸覆盖整个隧道盖挖段区域的两侧,所述水泥土搅拌桩墙与盖拱接触面上设有凸出水泥土搅拌桩墙的止水件,所述止水件作为连接件将盖拱连接在两块水泥土搅拌桩墙之间。通过水泥土搅拌桩墙防止水从隧道的两侧渗入隧道,通过与盖拱连接的止水件,防止水从盖拱下方沿盖拱与水泥土搅拌桩墙之间的间隙流入隧道内,能有效地控制盖挖隧道施工时洞内渗水,而且同时还提高了盖拱的稳定性,通过垂直布设的水泥土搅拌桩墙,大大提高了盖拱的稳定性,也可以提高沟谷段区域坡体的稳定性,减少施工灾害,改善了隧道围岩的工程性质,加强沟谷段破碎围岩的整体性,还能节省工程造价,降低了地下水对盖挖隧道施工时所带来的困难和风险。The utility model proposes a cover-dug tunnel water-stop structure in the high water level area of the valley section, at least one row of cement-soil mixing pile walls vertically arranged on both sides of the tunnel, the bottom of the cement-soil mixing pile wall is in the soil The depth of the cement-soil mixing pile wall is greater than the depth of the bottom of the tunnel. The cement-soil mixing pile wall extends along the extension direction of the tunnel to cover both sides of the entire tunnel cover excavation area. The water stop piece of the mixing pile wall is used as a connecting piece to connect the cover arch between two cement-soil mixing pile walls. Prevent water from seeping into the tunnel from both sides of the tunnel through the cement-soil mixing pile wall, and prevent water from flowing into the tunnel from the bottom of the cover arch along the gap between the cover arch and the cement-soil mixing pile wall through the water stop connected to the cover arch. It effectively controls the water seepage in the tunnel during the construction of the cover-excavation tunnel, and at the same time improves the stability of the cover arch. Through the vertically arranged cement-soil mixing pile wall, the stability of the cover arch is greatly improved, and the slope body in the valley section can also be improved. The stability of the tunnel can reduce construction disasters, improve the engineering properties of the tunnel surrounding rock, strengthen the integrity of the broken surrounding rock in the valley section, save the engineering cost, and reduce the difficulties and risks caused by groundwater to cover and excavate the tunnel construction.
所述隧道下方的土体中还设有通过注浆成型的、且沿水平方向布设的水泥浆止水帷幕,所述水泥浆止水帷幕沿隧道延伸方向延伸设置在整个隧道盖挖段区域的下方,所述水泥浆止水帷幕设置在两块水泥土搅拌桩墙之间且与分别与两块水泥土搅拌桩墙连接。通过隧道底面设置的水泥浆止水帷幕,防止了水泥土搅拌桩墙外的水从水泥土搅拌桩墙底部倒灌入隧道内,从而更好地控制盖挖隧道施工时洞内涌水的现象。The soil below the tunnel is also provided with a cement slurry water-stop curtain formed by grouting and arranged in the horizontal direction. Below, the cement slurry water-stop curtain is arranged between two cement-soil mixing pile walls and connected with the two cement-soil mixing pile walls respectively. The cement slurry water-stop curtain installed on the bottom of the tunnel prevents the water outside the cement-soil mixing pile wall from pouring back into the tunnel from the bottom of the cement-soil mixing pile wall, so as to better control the phenomenon of water gushing in the tunnel during tunnel construction.
优选地,所述水泥浆止水帷幕分为两段分别靠近两侧水泥土搅拌桩墙设置。Preferably, the cement slurry water-stop curtain is divided into two sections and arranged close to the cement-soil mixing pile walls on both sides.
优选地,所述水泥土搅拌桩墙设置有多排水泥土搅拌桩,相邻每排水泥土搅拌桩之间间隔500mm。Preferably, the cement-soil mixing pile wall is provided with multiple rows of cement-soil mixing piles, and the distance between each adjacent row of cement-soil mixing piles is 500mm.
优选地,所述止水件为防水板,所述防水板沿水泥土搅拌桩墙中线布设,所述防水板与水泥土搅拌桩墙之间的缝隙通过沥青密封,所述防水板露出水泥土搅拌桩墙的部分与盖拱的拱脚现浇为一整体。Preferably, the water stopper is a waterproof board, the waterproof board is arranged along the centerline of the cement-soil mixing pile wall, the gap between the waterproof board and the cement-soil mixing pile wall is sealed by asphalt, and the waterproof board exposes the cement-soil The part of the mixing pile wall is integrated with the arch foot of the covered arch.
优选地,所述水泥土搅拌桩墙由垂直布设的多根水泥土搅拌桩沿隧道延伸方向排列构成,相邻所述水泥土搅拌桩相互搭接。Preferably, the cement-soil mixing pile wall is composed of a plurality of cement-soil mixing piles vertically arranged along the extension direction of the tunnel, and the adjacent cement-soil mixing piles overlap each other.
优选地,所述水泥土搅拌桩的直径为600mm,相邻水泥土搅拌桩搭接宽度为100mm。Preferably, the diameter of the cement-soil mixing pile is 600 mm, and the overlapping width of adjacent cement-soil mixing piles is 100 mm.
优选地,所述盖拱的拱顶上铺设防水层,然后回填土施工完毕后铺设有胶泥防渗层,胶泥防渗层与边坡脚位置的截水沟相连。Preferably, a waterproof layer is laid on the vault of the cover arch, and then a cement anti-seepage layer is laid after the backfilling is completed, and the cement anti-seepage layer is connected to the intercepting ditch at the foot of the slope.
综上所述,本实用新型设计合理,施工方便,能有效地控制盖挖隧道施工时洞内渗水、隧道底面涌水,提高了盖拱拱脚处的地基承载力以及提高沟谷段区域坡体的稳定性,减少施工灾害,改善了隧道围岩的工程性质,加强沟谷段破碎围岩的整体性,还能节省工程造价,降低了地下水对盖挖隧道施工时所带来的困难和风险。To sum up, the utility model has reasonable design and convenient construction. It can effectively control the water seepage in the tunnel and the water gushing at the bottom of the tunnel during the construction of the cover-excavation tunnel. Stability, reducing construction disasters, improving the engineering properties of the tunnel surrounding rock, strengthening the integrity of the broken surrounding rock in the valley section, saving engineering costs, and reducing the difficulties and risks brought about by groundwater during tunnel construction.
附图说明Description of drawings
图1为本实用新型布设在隧道周围的结构示意图。Fig. 1 is a schematic diagram of the structure of the utility model arranged around the tunnel.
图2为本实用新型水泥土搅拌桩墙的结构示意图。Fig. 2 is the structural representation of the cement-soil mixing pile wall of the utility model.
图3为水泥土搅拌桩墙顶部与防水板连接后的结构示意图。Fig. 3 is a schematic diagram of the structure after the top of the cement-soil mixing pile wall is connected with the waterproof board.
附图中:1.水泥土搅拌桩、2.防水板、3.盖拱、4.砂石垫层、5.注浆管、6.水泥浆止水帷幕、7.二衬、8.胶泥防渗层、9.回填土、10.截水沟、11.防水层。In the attached drawings: 1. Cement-soil mixing pile, 2. Waterproof board, 3. Cover arch, 4. Sand and gravel cushion, 5. Grouting pipe, 6. Cement slurry water-stop curtain, 7. Secondary lining, 8. Clay Anti-seepage layer, 9. Backfill soil, 10. Intercepting ditch, 11. Waterproof layer.
具体实施方式detailed description
下面通过附图对本实用新型的技术方案做进一步详细描述。The technical scheme of the utility model is described in further detail below by means of the accompanying drawings.
实施例,Example,
一种沟谷段高水位区盖挖隧道止水结构,包括盖拱拱脚下的水泥土搅拌桩墙、隧道底面下的水泥浆止水帷幕和盖拱拱顶防水装置。水泥土搅拌桩墙由单轴水泥土搅拌桩搭接而成,打入土体中以形成止水帷幕,在水泥土搅拌桩墙完成后在桩顶过圆心开出一道深20cm的凹槽,放置事先焊接好的高50cm的防水板2,再使用沥青处理密封缝,最后露出一截防水板与盖拱3拱脚现浇为一整体,可以避免水从盖拱与搅拌桩墙交接缝中渗入;水泥浆止水帷幕6为在隧道内轮廓开挖以后,在隧道拱脚处用小型钻机钻孔,边钻孔边打入护壁套管,放入注浆管直至预定的灌浆深度,使用水泥浆泵机灌注以一定比例混合的水泥浆与粉煤灰,并辅以早强剂以增加早期强度,形成连接水泥土搅拌桩墙的水泥浆止水帷幕。盖拱3拱顶的防水装置为在盖拱强度到达设计值后,在盖拱上铺设一层防水层11,然后开始洞顶回填,回填土9施工完毕后,然后再铺设50cm厚的胶泥防渗层8,胶泥防渗层8与边坡脚连接处位置设置截水沟10。水泥土搅拌桩墙、隧道底面下水泥浆止水帷幕与盖拱拱顶防水装置一起形成一个完整的止水结构,以降低富水区盖挖隧道施工时地下水带来的风险,还能增强盖拱拱底地基承载力,改善隧道围岩的工程性质,组合止水结构立面图可见图1。A cover-excavated tunnel water-stop structure in a high water level area of a valley section, comprising a cement-soil mixing pile wall at the foot of a cover arch, a cement slurry water-stop curtain under the tunnel bottom surface, and a cover-arch vault top waterproof device. The cement-soil mixing pile wall is formed by overlapping single-axis cement-soil mixing piles, which are driven into the soil to form a water-stop curtain. After the cement-soil mixing pile wall is completed, a 20cm deep groove is opened at the top of the pile to cross the center of the circle. Place the pre-welded waterproof board 2 with a height of 50cm, and then use asphalt to seal the joints, and finally expose a section of the waterproof board and the arch foot of the arch 3 as a whole, which can prevent water from flowing from the joint between the arch and the mixing pile wall infiltration; the cement slurry water-stop curtain 6 is after excavating the inner contour of the tunnel, using a small drilling rig to drill holes at the arch foot of the tunnel, inserting the wall casing while drilling, and putting the grouting pipe until the predetermined grouting depth, Use the cement slurry pump to pour the cement slurry and fly ash mixed in a certain proportion, and add early strength agent to increase the early strength to form a cement slurry water-stop curtain connecting the cement-soil mixing pile wall. The waterproof device for the roof of the arch 3 is to lay a waterproof layer 11 on the arch after the strength of the arch reaches the design value, and then start backfilling the top of the cave. An intercepting ditch 10 is provided at the joint between the seepage layer 8 and the cement anti-seepage layer 8 and the slope toe. The cement-soil mixing pile wall, the cement slurry water-stop curtain under the tunnel bottom and the waterproof device of the arch vault form a complete water-stop structure to reduce the risk of groundwater during tunnel construction in water-rich areas and strengthen the arch The bearing capacity of the foundation of the arch bottom can be improved, and the engineering properties of the surrounding rock of the tunnel can be improved. The elevation of the combined water-stop structure can be seen in Figure 1.
具体施工步骤如下:The specific construction steps are as follows:
如图1至3所示,在盖拱3两侧拱脚位置设置水泥土搅拌桩墙,具体是在拱脚位置沿隧道延伸方向连续排布多根直径为600mm的水泥土搅拌桩1形成水泥土搅拌桩墙,相邻水泥土搅拌桩1相互搭接,且搭接宽度为100mm,本例中,每侧水泥土搅拌桩墙设置两排水泥土搅拌桩,每排水泥土搅拌桩之间桩心距为500mm。本例中,水泥土搅拌桩的水泥掺入量为16%,外加早强剂以提高成桩质量,搅拌轴速度60rad/min,水灰比控制为0.5∶1,施工过程中注意要搅拌均匀,提升速度与喷浆速度之间要协调,以保障沿桩身全长喷浆均匀,水泥土搅拌桩平面布置情况和立面图见附图2和附图3。As shown in Figures 1 to 3, cement-soil mixing pile walls are installed at the arch feet on both sides of the cover arch 3. Specifically, a plurality of cement-soil mixing piles 1 with a diameter of 600mm are continuously arranged at the arch feet along the extension direction of the tunnel to form cement For the soil mixing pile wall, adjacent cement-soil mixing piles 1 are overlapped with each other, and the overlap width is 100mm. In this example, two rows of cement-soil mixing piles are arranged on each side of the cement-soil mixing pile wall, and the pile center between each row of cement-soil mixing piles The distance is 500mm. In this example, the cement content of the cement-soil mixing pile is 16%, plus an early strength agent to improve the quality of the pile, the speed of the stirring shaft is 60rad/min, and the water-cement ratio is controlled at 0.5:1. During the construction process, pay attention to stirring evenly , The lifting speed and the spraying speed should be coordinated to ensure uniform spraying along the entire length of the pile body. See attached drawings 2 and 3 for the plane layout and elevation of the cement-soil mixing pile.
水泥土搅拌桩墙具体施工步骤:Concrete construction steps of cement-soil mixing pile wall:
(1)测量放点。用经纬仪进行区域边线及桩位的测定;对于标定的基准点及桩位要做好明显的标志和编号,并做好保护工作;做好测量放线记录,以便复核。(1) Measure the release point. Use theodolite to measure the borderline and pile position of the area; clearly mark and number the calibrated reference point and pile position, and do a good job of protection; make a record of the measurement and setting out for review.
(2)桩机就位。桩机就位、移动前,看清上、下、左、右各方情况,发现有阻及时排除,移动结束后检查定位情况,并及时纠正;采用水平尺校正基座并保持基座水平,保证桩机做到平稳、周正;动力头、搅拌头、桩位三点中心位于同一垂直线上;桩位定位偏差不大于40mm,桩身垂直度偏差小于20mm。(2) The pile driver is in place. Before the pile driver is in place and moving, see the upper, lower, left and right sides clearly, find any obstructions and eliminate them in time, check the positioning situation after the movement, and correct it in time; use a spirit level to correct the base and keep the base level, Ensure that the pile driver is stable and upright; the center of the three points of the power head, the mixing head and the pile position are located on the same vertical line; the positioning deviation of the pile position is not more than 40mm, and the verticality deviation of the pile body is less than 20mm.
(3)预搅下沉。严格控制下沉速度,密切观察动力头电机工作负荷,其电流指数不大于70A,以防烧毁电机;如遇较硬地层下沉速度过慢时,可以通过中心管压入少量稀浆,以利润湿土体,加快下沉;严格控制桩底标高,搅拌头必须下沉到设计桩底标高。(3) Pre-stir and sink. Strictly control the sinking speed, and closely observe the working load of the motor of the power head. The current index is not greater than 70A to prevent the motor from being burned; Wet soil will accelerate the sinking; strictly control the pile bottom elevation, the mixing head must sink to the design pile bottom elevation.
(4)灰浆制备。在搅拌头预搅下沉同时,严格按设计配合比制作灰浆,水灰比应严格按照设计要求的0.5∶1,灰浆搅拌时间不得小于2分钟,以使浆液充分拌合;将外掺剂按比例溶解于水中,然后定量加入拌制浆液中一起搅拌;(4) Mortar preparation. While the mixing head is pre-stirring and sinking, make mortar strictly according to the design mix ratio. The water-cement ratio should be strictly in accordance with the design requirements of 0.5:1, and the mortar mixing time should not be less than 2 minutes to fully mix the slurry; The ratio is dissolved in water, and then quantitatively added to the mixing slurry and stirred together;
(5)第一次注浆提升搅拌。搅拌头至桩底设计标高后,即刻上提20cm并开启压浆泵(40L/min)送浆,搅拌头在桩底原位搅拌20~30秒后,以0.5m/min左右提升速度边搅拌边提升,直至设计桩顶标高,并检查注浆量。(5) The first grouting is lifted and stirred. After the stirring head reaches the design elevation of the pile bottom, lift it up 20cm immediately and turn on the grouting pump (40L/min) to deliver the slurry. After the stirring head stirs at the bottom of the pile for 20-30 seconds, it will be stirred at a lifting speed of about 0.5m/min. While lifting, until the design pile top elevation, and check the amount of grouting.
(6)第二次搅拌下沉。注浆搅拌提升至设计桩顶标高后,停浆,即刻搅拌下沉至设计桩底标高,并控制好下沉速度,一般为0.5m/min左右。(6) The second stirring sinks. After the grouting stirring is raised to the design pile top elevation, the grouting is stopped, and the stirring immediately sinks to the design pile bottom elevation, and the sinking speed is well controlled, generally about 0.5m/min.
(7)第二次注浆搅拌提升。搅拌至设计桩底标高后,送浆,原位送浆搅拌20~30秒后,以0.5m/min左右提升速度注浆提升搅拌,注浆提升离设计桩顶标高1m段内,减慢提升速度,且在桩顶原位注浆搅拌15~30秒,以确保桩顶质量。(7) The second grouting stirring is lifted. After stirring to the design pile bottom elevation, send the slurry. After the slurry is sent in situ and stirred for 20-30 seconds, the grouting is lifted at a lifting speed of about 0.5m/min. Speed, and in-situ grouting at the top of the pile and stirring for 15 to 30 seconds to ensure the quality of the top of the pile.
(8)第三次下沉、提升、搅拌。(8) Sinking, lifting and stirring for the third time.
(9)成桩结束后,清冼钻杆及管道,桩架移至下一桩位。(9) After the pile is completed, the drill pipe and pipeline are cleaned, and the pile frame is moved to the next pile position.
水泥土搅拌桩搭接完成后,在水泥土搅拌桩墙桩顶过圆心开出一道深20cm的凹槽,放置事先焊接好的50cm高的防水板2,再使用沥青处理密封缝,最后露出一截防水板与盖拱3拱脚现浇为一整体,可以避免水从盖拱与搅拌桩墙交接缝中渗入。水泥土搅拌桩墙平面布置情况和单个水泥土搅拌桩立面图见附图2和附图3。After the lapping of the cement-soil mixing pile is completed, a groove with a depth of 20 cm is made on the top of the wall pile of the cement-soil mixing pile, and a 50 cm high waterproof board 2 welded in advance is placed. The cut-off waterproof board and the 3 arch feet of the cover arch are cast-in-place as a whole, which can prevent water from infiltrating from the joint between the cover arch and the mixing pile wall. The plane layout of the cement-soil mixing pile wall and the elevation of a single cement-soil mixing pile are shown in attached drawings 2 and 3.
等水泥土搅拌桩墙施工完毕养护28天后,在盖拱拱脚处设置10cm砂石垫层4。施工完毕垫层后,立即安装盖拱钢拱架,浇筑盖拱,浇筑盖拱时将水泥土搅拌桩墙凸出的防水板2与盖拱现浇在一起。待盖拱施工养护完毕达到设计强度后,开始施工盖拱拱顶防水装置。After the cement-soil mixing pile wall is constructed and maintained for 28 days, a 10cm sandstone cushion 4 is set at the foot of the arch arch. After the cushion layer has been constructed, immediately install the cover arch steel arch, and pour the cover arch. When pouring the cover arch, the waterproof board 2 protruding from the cement-soil mixing pile wall is cast together with the cover arch. After the construction and maintenance of the arch cover reaches the design strength, the construction of the waterproof device for the arch cover arch begins.
盖拱拱顶的防水装置具体为:在盖拱强度到达设计值后,在盖拱上铺设防水层11,然后开始洞顶回填,回填土分层夯实后,然后再铺设50cm厚的胶泥防渗层8,最后在与边坡脚连接处设置截水沟10。截水沟能够将降雨时从边坡上流下的水流排出。The waterproof device of the arch vault is as follows: after the strength of the arch reaches the design value, a waterproof layer 11 is laid on the arch, and then the top of the cave is backfilled. After the backfill is compacted in layers, a 50cm-thick cement is laid to prevent seepage Layer 8, and finally set the intercepting ditch 10 at the connection with the slope toe. Intercepting ditches are used to divert water that runs down the slope during rainfall.
盖拱顶防水装置施工完毕后,开始隧道暗挖施工,开挖一定进尺深度后在隧道拱脚处开始水泥浆止水帷幕6施工,具体施工过程如下:After the construction of the waterproofing device for the vault roof is completed, the tunnel excavation construction starts. After a certain depth of excavation, the construction of the cement slurry water-stop curtain 6 is started at the arch foot of the tunnel. The specific construction process is as follows:
水泥浆止水帷幕6的工艺流程为:钻孔→下注浆管5、套管→边注浆边拔套管→封孔。注浆前,应通过灌浆压力、灌浆孔距等有关技术参数的确定;通过现场灌浆试验确定灌浆孔距,即根据岩石和土的裂隙、松散情况、渗透性以及灌浆设备能力等条件选定。在沟谷段高水位地区,本次水泥浆止水帷幕6设置厚度为0.8m;灌浆压力是指灌浆段所受的全压力,即孔口处压力表上指示的压力,所用压力大小视钻孔深度、土的渗透性以及水泥浆的稠度等而定,一般为0.2~0.6Mpa。灌浆孔距根据具体的地质条件和现场灌浆实验确定,但必须保证搭接合理无裂缝存在。The technological process of the cement slurry water-stop curtain 6 is: drilling → lowering the grouting pipe 5, casing → pulling out the casing while grouting → sealing the hole. Before grouting, relevant technical parameters such as grouting pressure and grouting hole spacing should be determined; the grouting hole spacing should be determined through on-site grouting tests, that is, selected according to conditions such as rock and soil cracks, looseness, permeability, and grouting equipment capabilities. In the high water level area of the valley section, the thickness of the cement slurry water-stop curtain 6 is set to 0.8m; the grouting pressure refers to the total pressure on the grouting section, that is, the pressure indicated on the pressure gauge at the orifice, and the pressure used depends on the borehole It depends on the depth, the permeability of the soil and the consistency of the cement slurry, etc., generally 0.2-0.6Mpa. The grouting hole spacing is determined according to the specific geological conditions and on-site grouting experiments, but it must be ensured that the overlap is reasonable and there are no cracks.
在隧道拱脚处用小型钻机钻孔,钻孔至要求的深度并探测地质情况,边钻孔边打入护壁套管,然后在套管内插入的注浆管,注浆管的下部与底部管壁上钻有注浆孔,隧道打孔表面空隙用水泥砂浆填塞,使用水泥浆泵机灌注以一定比例混合的水泥浆与粉煤灰,并辅以早强剂以增加早期强度,接着拔出套管,用压浆泵将水泥浆压入注浆管而透入土层孔隙中,水泥浆应连续一次压入,不得中断。灌浆先从稀浆开始,逐渐加浓。灌浆次序一般把注浆管一次沉入整个深度后,自下而上分段连续进行,分段拔注浆管直至设计高程为止,灌浆宜间隙进行,第1组孔灌浆结束后,再灌第2组、第3组,直至形成搭接好的水泥浆止水帷幕,每一侧的水泥浆止水帷幕6的水平长度为隧道跨径的三分之一左右。Use a small drilling rig to drill holes at the arch foot of the tunnel, drill to the required depth and detect the geological conditions, drill into the wall casing while drilling, and then insert the grouting pipe in the casing, the lower part of the grouting pipe and the bottom pipe Grouting holes are drilled on the wall, and the gaps on the surface of the tunnel drilling are filled with cement mortar. The cement slurry and fly ash mixed in a certain proportion are poured with a cement slurry pump, and an early strength agent is added to increase the early strength, and then pulled out For the casing, use a grouting pump to press the grout into the grouting pipe and penetrate into the pores of the soil layer. The grout should be pressed in one time continuously without interruption. Grouting starts with thin grout and gradually thickens. The grouting sequence generally sinks the grouting pipe to the entire depth at one time, and proceeds continuously in sections from bottom to top. Pull out the grouting pipe in sections until the design elevation. The grouting should be carried out in intervals. Group 2 and Group 3 until the lapped cement slurry waterstop curtain is formed, and the horizontal length of the cement slurry waterstop curtain 6 on each side is about one-third of the span of the tunnel.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720459706.3U CN206736963U (en) | 2017-04-28 | 2017-04-28 | Ditch millet section high water level district lid tunnel stagnant water structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720459706.3U CN206736963U (en) | 2017-04-28 | 2017-04-28 | Ditch millet section high water level district lid tunnel stagnant water structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206736963U true CN206736963U (en) | 2017-12-12 |
Family
ID=60562516
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720459706.3U Expired - Fee Related CN206736963U (en) | 2017-04-28 | 2017-04-28 | Ditch millet section high water level district lid tunnel stagnant water structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206736963U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108019211A (en) * | 2018-01-23 | 2018-05-11 | 中国铁路设计集团有限公司 | Waterproof of man and its construction method in a kind of pilot tunnel of rich water sand-pebble layer |
CN109915150A (en) * | 2019-04-26 | 2019-06-21 | 重庆交通大学 | A kind of pile foundation pre-reinforced supporting structure for controlling tunnel settlement and its construction method |
CN110748358A (en) * | 2019-08-27 | 2020-02-04 | 西南交通大学 | Cold region tunnel entrance to a cave two-sided heat preservation system |
-
2017
- 2017-04-28 CN CN201720459706.3U patent/CN206736963U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108019211A (en) * | 2018-01-23 | 2018-05-11 | 中国铁路设计集团有限公司 | Waterproof of man and its construction method in a kind of pilot tunnel of rich water sand-pebble layer |
CN108019211B (en) * | 2018-01-23 | 2023-09-12 | 中国铁路设计集团有限公司 | Water-intercepting curtain in pilot tunnel of water-rich sandy pebble stratum and construction method thereof |
CN109915150A (en) * | 2019-04-26 | 2019-06-21 | 重庆交通大学 | A kind of pile foundation pre-reinforced supporting structure for controlling tunnel settlement and its construction method |
CN110748358A (en) * | 2019-08-27 | 2020-02-04 | 西南交通大学 | Cold region tunnel entrance to a cave two-sided heat preservation system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103590425B (en) | A kind of Peaty soft soil stratum subway station construction technology | |
CN108842819B (en) | Urban rail transit cable line tunnel construction method | |
CN107503257A (en) | One kind is close to mountain high-filled subgrade stabilization and Deformation control structure and construction method | |
CN108560541A (en) | A kind of full casing follow-up scar drilling construction method of churning driven | |
CN107542108A (en) | A kind of reverse construction method of building basement structure | |
CN110017149A (en) | A kind of underground structure and construction method of underground excavation and construction of arch cover | |
CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
CN113174958A (en) | Construction method for foundation pit of adjacent road under poor ground condition | |
CN110080248A (en) | Nearly depth of water foundation pit supporting construction | |
CN105464685A (en) | Cave-pile method bored tunnel waterproof curtain and construction method thereof | |
CN112144559B (en) | Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well | |
CN108571000A (en) | The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river | |
CN206736963U (en) | Ditch millet section high water level district lid tunnel stagnant water structure | |
CN103572764A (en) | Ultra-deep manual hole digging pile dado water stop structure and construction method thereof | |
CN110055973A (en) | Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time | |
CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
CN102235007B (en) | Method for supporting deep foundation with upper nail-lower pile combination | |
CN112761166A (en) | Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method | |
CN110344394A (en) | A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method | |
CN109898556A (en) | A kind of underground pipe gallery structure and sunk type construction method | |
CN103821140B (en) | A kind of construction method of reinforcing soft foundation | |
CN113668564A (en) | Construction method for supporting and reinforcing open-cut underground passage adjacent to subway station | |
CN105484270B (en) | Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit | |
CN112523272B (en) | Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof | |
CN212225255U (en) | Large-scale filling type karst cave geological tunnel foundation reinforcing structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171212 Termination date: 20210428 |
|
CF01 | Termination of patent right due to non-payment of annual fee |