CN206736743U - Lay the easy structure of mountable steel bridge - Google Patents

Lay the easy structure of mountable steel bridge Download PDF

Info

Publication number
CN206736743U
CN206736743U CN201720546946.7U CN201720546946U CN206736743U CN 206736743 U CN206736743 U CN 206736743U CN 201720546946 U CN201720546946 U CN 201720546946U CN 206736743 U CN206736743 U CN 206736743U
Authority
CN
China
Prior art keywords
steel bridge
vertical rod
cross bar
mountable steel
montant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720546946.7U
Other languages
Chinese (zh)
Inventor
张青宇
张世殊
冉从彦
曲海珠
杨寿成
原先凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201720546946.7U priority Critical patent/CN206736743U/en
Application granted granted Critical
Publication of CN206736743U publication Critical patent/CN206736743U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of easy structure for laying mountable steel bridge, it is related to engineering construction field, solves the problems, such as to be to provide a kind of easy structure for only relying on scaffold and can manually completing mountable steel bridge erection construction.The technical solution adopted in the utility model is:Lay the easy structure of mountable steel bridge, including the abutment positioned at river two sides, being set up between two abutments has scaffold, and scaffold includes the vertical rod being vertically arranged, and horizontally disposed cross bar and montant, center line direction arrangement at least two row of the vertical rod along two abutments, same column vertical rod restocking is provided with bridging, and cross bar is connected between same column vertical rod, montant is connected between cross bar, cross bar and montant form top layer platform and underlying platform on the top of vertical rod, and mountable steel bridge is laid on top layer platform.The utility model is using the scaffold being easily obtained and can manually complete mountable steel bridge erection construction, overcomes construction difficult problem during without special erection equipment, and can reduce construction costs.

Description

Lay the easy structure of mountable steel bridge
Technical field
Engineering construction field is the utility model is related to, specifically one kind can lay assembled when lacking large lifting equipment The easy structure of steel bridge.
Background technology
Mountable steel bridge was invented in 1938 by Britain engineer Donald Xi Beilei.Mountable steel bridge is by high-strength steel The compositions such as light standardization truss element component and horizontal stroke, longeron, floorings, bridge chair and connector are made in material, have structure Simply, lightly, quickly, economic, widely used, strong applicability, unit(-)construction system are good, interchangeability is strong and easily assembling etc. it is excellent Point, and different across footpaths and type can be selected according to requirement of engineering, played in fields such as road transport, rescue and relief work, water conservancy constructions Important function.
The erection method of mountable steel bridge has that cantilever releases method, tailstock releases method, erecting by floating into position, whole hole lift-on/lift-off system, just Ground assembly method (i.e. bridge on bridge).Under normal conditions, mountable steel bridge releases the laying of method progress steel bridge using cantilever, and this is just needed Configure a set of special erection equipment.But lack spanning equipment in engineering site sometimes, or spanning equipment is difficult to Position, the erection of steel bridge how is carried out using simple engineering resource just turns into the problem of facing.
Utility model content
Technical problem to be solved in the utility model is to provide one kind and only relies on scaffold and artificial can completion dress Easy structure with formula steel bridge erection construction.
Technical scheme is used by the utility model solves its technical problem:The easy structure of mountable steel bridge is laid, Being set up including the abutment positioned at river two sides, between two abutments has scaffold, and scaffold includes the vertical rod being vertically arranged, and Horizontally disposed cross bar and montant, center line direction arrangement at least two row of the vertical rod along two abutments, same column vertical rod restocking are provided with Bridging, the cross bar is connected between same column vertical rod, the length direction of cross bar is consistent with the center line direction of two abutments, cross bar it Between connect montant, the length direction of montant is vertical with the center line direction of two abutments;Cross bar and montant are formed on the top of vertical rod Two platforms, it is divided into top layer platform and underlying platform, mountable steel bridge is laid on top layer platform.
It is further:There is collapse rock-fall between two abutments, the top of the collapse rock-fall of exposure sets levelling Concrete, the cross bar and montant are placed on the top or levelling concrete of collapse rock-fall;Or the bottom of vertical rod is placed in and collapsed On slump stone.
It is further:The width of the abutment is consistent with the width of mountable steel bridge, and the vertical rod is two row, and two row are vertical Horizontal range of the bar apart from the edge of homonymy mountable steel bridge is 1m.
It is further:Hound is also set up on the outside of the scaffold, the spacing of adjacent hound is 2m.
It is further:The spacing of adjacent two vertical rods of same column is 0.5m, and the spacing of adjacent two montants is 0.5m.
The beneficial effects of the utility model are:The easy structure of laying mountable steel bridge using the scaffold that is easily obtained and Mountable steel bridge erection construction can be manually completed, makes full use of readily available resources, is overcome without special erection equipment When construction difficult problem, and low engineering cost.According to measuring and calculating, if the construction process of the mountable steel bridge according to routine, is about needed 6~70,000 yuan are wanted, but lays the easy structure of mountable steel bridge, it is only necessary to which 30,000 yuan can just complete construction, can save more than half Engineering funds, it is shown that great superiority.
Brief description of the drawings
Fig. 1 is the easy structure schematic top plan view of the utility model laying mountable steel bridge.
Fig. 2 is the easy structure schematic side view of the utility model laying mountable steel bridge.
Parts, position and numbering in figure:Abutment 1, vertical rod 2, cross bar 3, montant 4, bridging 5, mountable steel bridge 6, collapse Slump stone 7, concrete eight, hound 9.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
As depicted in figs. 1 and 2, the easy structure of the utility model laying mountable steel bridge, including positioned at river two sides Abutment 1, setting up between two abutments 1 has scaffold, and scaffold includes the vertical rod 2 being vertically arranged, and horizontally disposed horizontal stroke Bar 3 and montant 4, vertical rod 2 are vertically inserted into riverbed, center line direction arrangement at least two row of the vertical rod 2 along two abutments 1, and two Row vertical rod 2 is parallel to each other, and the center line side of the cross bar 3, the length direction of cross bar 3 and two abutments 1 is connected between same column vertical rod 2 To consistent, montant 4 is connected between cross bar 3, the length direction of montant 4 is vertical with the center line direction of two abutments 1.Each row vertical rod 2 restockings are provided with bridging 5, ensure the rigidity and intensity of scaffold.Cross bar 3 and montant 4 are two layers, and cross bar 3 and montant 4 are in vertical rod Two platforms are formed at 2 top, are divided into top layer platform and underlying platform, mountable steel bridge 6 is laid on top layer platform.Bridging 5 In vertical rod 2 between top layer platform and underlying platform.
The width of abutment 1 is consistent with the width of mountable steel bridge 6, and two row vertical rods 2 are apart from the edge of homonymy mountable steel bridge 6 Horizontal range be 1m, i.e. width big 2m of the distance of two row vertical rod 2 compared with mountable steel bridge 6.Hound is also set up on the outside of scaffold 9, the spacing of adjacent hound 9 is 2m.Vertical rod 2 is two row, and the spacing of adjacent two vertical rods 2 of each column is 0.5m, on underlying platform The spacing of adjacent two montants 4 is 1m, and the spacing of adjacent two montants 4 is 0.5m on top layer platform.
Such as Fig. 2, there is collapse rock-fall 7 between two abutments 1, if the overhead height of collapse rock-fall 7 and underlying platform height Unanimously, the top of the collapse rock-fall 7 of exposure sets levelling concrete eight, and vertical rod 2, cross bar 3 and montant 4 are located at collapse rock-fall 7 On top or levelling concrete eight.If for the overhead height of collapse rock-fall 7 less than underlying platform height, the bottom of vertical rod 2 is located at avalanche On falling rocks 7.Collapse rock-fall 7 is often larger, and the stability on riverbed is preferable, can bear larger pressure.
Certain power station is located on the tributary of Yunnan Province Huize County, and river valley two sides form is more symmetrical, the wide 30~45m of river, river Depth of water 3m or so, bed material are ovum containing mud (broken) sand gravel layer (alQ4) and bulk collapse rock-fall, ovum (broken) sand gravel material Composition is mainly dolomitic limestone, limestone, basalt, quartzy sandstone, and more in time corner angle~secondary round shape, a small amount of gravel is in perfectly round Shape.Wherein, ovum (broken) general 60mm~100mm of stone particle diameter, accounts for 20%~25%;Grain size of gravel based on 30mm~50mm, Secondary is 2mm~10mm, accounts for 50%~60%;20%~25% is accounted for for the sand filling containing shale, sand between coarse granule, its Structure is more closely knit, and bearing capacity average value is 0.74MPa.Bulk collapse rock-fall is mainly dolomitic limestone, limestone, and scale is in 2m3 ~4m3
In order to engineering material requested transport, it is necessary in one individual layer mountable steel bridge of tributary restocking, design steel bridge 13 saves, Long 3m is often saved, bridge floor is from water surface 3m or so.But locality does not set up the special erection equipment of this kind of steel bridge, by this practicality The easy structure of new laying mountable steel bridge carries out setting up concretely comprising the following steps for work:
A. surveying setting-out, the abutment 1 for river both sides of constructing;Every section steel bridge is assembled simultaneously, and according to the suitable of assembling Sequence is arranged in order standby.
B. the line centered on the center line of two abutments 1, scaffold building is carried out, the distance of two row vertical rod 22 is than abutment 1 wide two Rice, wherein both sides are each wide one meter.To improve efficiency of construction, scaffold is set up to installation among river respectively from two abutments 1, is wrapped It is 1m to include and set up vertical rod 2, cross bar 3 and montant 4, the spacing of each column vertical rod 2, and the spacing of montant 4 is also 1m.Vertical rod 2, should be anti-when setting up It is multiple to insert several times more, make one of vertical rod 2 to enter the certain depth in riverbed, ensure its bearing capacity.Cross bar 3 and montant 4 are two layers, bottom Layer platform is located above the water surface, and top layer platform is located at the position more slightly higher than abutment 1.Vertical rod between top layer platform and underlying platform Bridging 5 is continuously set on 2, hounds 9 are set every two meters in vertical rod 2.
C. scaffold is reinforced and encrypted, vertical rod 2 and the spacing of montant 4 is changed into 0.5m;To on top layer platform Montant 4 is encrypted, in order to which people walks.Scaffold construction, which can rely on manually will often save scaffold and carry on scaffold, is pacified Dress.
D. steel bridge will be often saved to carry on top layer platform and carry out fabricated construction.
Finally, after steel bridge assembling construction, scaffold is removed.In stepb, if run into when setting up vertical rod 2 big The collapse rock-fall 7 of type, levelling with concrete eight, based on it.Because large-scale collapse rock-fall 7 is larger, on riverbed Stability it is preferable, larger pressure can be born.
The easy structure for laying mountable steel bridge only meets construction requirement by scaffold and artificial just reach, and solves and applies Work problem, takes full advantage of existing resource.According to measuring and calculating, if the construction process of the mountable steel bridge according to routine, is about needed 6~70,000 yuan are wanted, but is constructed with this method, it is only necessary to which 30,000 yuan just complete construction, have saved the fund of more than half.

Claims (5)

1. lay the easy structure of mountable steel bridge, including the abutment (1) positioned at river two sides, set up between two abutments (1) There is scaffold, scaffold includes the vertical rod (2) being vertically arranged, and horizontally disposed cross bar (3) and montant (4), vertical rod (2) Along the row of center line direction arrangement at least two of two abutments (1), same column vertical rod (2) restocking is provided with bridging (5), same column vertical rod (2) Between connect the cross bar (3), the length direction of cross bar (3) is consistent with the center line direction of two abutments (1), between cross bar (3) Montant (4) is connected, the length direction of montant (4) is vertical with the center line direction of two abutments (1);Cross bar (3) and montant (4) are vertical Two platforms are formed at the top of bar (2), are divided into top layer platform and underlying platform, mountable steel bridge (6) is laid on top layer platform.
2. the easy structure of laying mountable steel bridge as claimed in claim 1, it is characterised in that:Two abutments (1) it Between have a collapse rock-fall (7), the top of the collapse rock-fall (7) of exposure sets levelling concrete (8), the cross bar (3) and montant (4) it is placed on the top or levelling concrete (8) of collapse rock-fall (7);Or the bottom of vertical rod (2) is placed in collapse rock-fall (7) On.
3. the easy structure of laying mountable steel bridge as claimed in claim 1, it is characterised in that:The width of the abutment (1) Consistent with the width of mountable steel bridge (6), the vertical rod (2) is two row, and two row vertical rods (2) are apart from homonymy mountable steel bridge (6) The horizontal range at edge be 1m.
4. the easy structure of laying mountable steel bridge as claimed in claim 1, it is characterised in that:Also taken on the outside of the scaffold If hound (9), the spacing of adjacent hound (9) is 2m.
5. the easy structure of laying mountable steel bridge as claimed in claim 1, it is characterised in that:Adjacent two vertical rods of same column (2) spacing is 0.5m, and the spacing of adjacent two montants (4) is 0.5m.
CN201720546946.7U 2017-05-17 2017-05-17 Lay the easy structure of mountable steel bridge Active CN206736743U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720546946.7U CN206736743U (en) 2017-05-17 2017-05-17 Lay the easy structure of mountable steel bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720546946.7U CN206736743U (en) 2017-05-17 2017-05-17 Lay the easy structure of mountable steel bridge

Publications (1)

Publication Number Publication Date
CN206736743U true CN206736743U (en) 2017-12-12

Family

ID=60566013

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720546946.7U Active CN206736743U (en) 2017-05-17 2017-05-17 Lay the easy structure of mountable steel bridge

Country Status (1)

Country Link
CN (1) CN206736743U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113430950A (en) * 2021-08-11 2021-09-24 中铁六局集团有限公司 Construction method of large-span Bailey bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113430950A (en) * 2021-08-11 2021-09-24 中铁六局集团有限公司 Construction method of large-span Bailey bridge

Similar Documents

Publication Publication Date Title
CN205205635U (en) Stride footpath bailey frame steel suspension bridge structure greatly
CN102425082A (en) Subgrade strengthening structure for highly karstified station turnout zone on high-speed railway
CN203320535U (en) Rock slope green protection structure
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN202148907U (en) Non-isoparametric initial-stage supporting structure of four-lane large-span tunnel
CN206736743U (en) Lay the easy structure of mountable steel bridge
CN206204986U (en) A kind of civil construction retaining wall structure
CN104005431B (en) Oblique orthogonal makes template for group's pile-pile cap-superstructure scale model
CN103981799B (en) A kind of concrete filled steel tube opens string stiff beam and construction method thereof
CN204000885U (en) Metro Deep Excavation concrete support hangs mould mould
CN203334301U (en) Cave slope strengthening protection structure
CN105369823A (en) Box-type retaining wall
CN201671103U (en) Integral construction forming platform of underwater pier cap drilled pile
CN202139603U (en) Storage-type tower crane foundation
CN107938724A (en) A kind of friction-type bored concrete pile and its Model Calculating Method for karst region
CN209323553U (en) A kind of steady type house foundation
CN207904938U (en) A kind of stable type highway subgrade ecological revetment
CN110439092A (en) Mortar flag stone drains ditch construction method and groove slope trimming measurement and positioning tool
CN209508954U (en) A kind of Construction of Civil Engineering small pile
CN203429557U (en) Anchor pole back beam applied to underpass bridge jacking construction
CN205242267U (en) Hollow thin wall rectangle dun dun pushes up construction structures
CN205100242U (en) Three laminar cantilever operation platform systems
CN206143727U (en) Concrete pile board dam
CN205243069U (en) Simply connect bridge
CN205259212U (en) Box -type retaining wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant