CN206708556U - Side wall seismatic method for pipeline finished product suspension and support - Google Patents
Side wall seismatic method for pipeline finished product suspension and support Download PDFInfo
- Publication number
- CN206708556U CN206708556U CN201720324574.3U CN201720324574U CN206708556U CN 206708556 U CN206708556 U CN 206708556U CN 201720324574 U CN201720324574 U CN 201720324574U CN 206708556 U CN206708556 U CN 206708556U
- Authority
- CN
- China
- Prior art keywords
- hoop
- hinge seat
- connecting rod
- fluororubber layer
- crossbeam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title description 2
- 239000000725 suspension Substances 0.000 title 1
- 229920001973 fluoroelastomer Polymers 0.000 claims abstract description 18
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 13
- 210000005069 ears Anatomy 0.000 claims description 5
- 239000006096 absorbing agent Substances 0.000 claims description 3
- 230000035939 shock Effects 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 4
- 230000002265 prevention Effects 0.000 abstract description 2
- 238000004870 electrical engineering Methods 0.000 description 4
- 238000011089 mechanical engineering Methods 0.000 description 4
- YCKRFDGAMUMZLT-UHFFFAOYSA-N Fluorine atom Chemical compound [F] YCKRFDGAMUMZLT-UHFFFAOYSA-N 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 229920001971 elastomer Polymers 0.000 description 3
- 229910052731 fluorine Inorganic materials 0.000 description 3
- 239000011737 fluorine Substances 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 3
- 238000013016 damping Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 241000282414 Homo sapiens Species 0.000 description 1
- 206010044565 Tremor Diseases 0.000 description 1
- 238000004378 air conditioning Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000001066 destructive effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
本实用新型公开了一种侧墙用管道抗震成品支吊架,包括横梁和位于横梁下方的抱箍,二者通过连接梁固定连接,所述横梁一端设有一竖板,所述竖板中部与横梁连接,上、下部各设有一水平的锚固件,所述横梁上方设有一第一铰座,第一铰座中铰接一连杆,连杆顶部连接一第二铰座,抱箍包括上半箍和下半箍,二者通过长螺栓与横梁固定,二者内壁贴合固定连接一氟橡胶层,所述氟橡胶层宽度和厚度均大于抱箍的宽度和厚度,氟橡胶层朝向圆心的一面设有数条加强筋,所述加强筋沿抱箍圆周方向设置。本实用新型适用于侧墙等数值墙面,具有很强的承载力,以及稳定的支撑性能,具有防火、耐热的效果,尤其适用于蒸汽管道,热水管道等高温管道。
The utility model discloses a pipeline anti-seismic finished support and hanger for side walls, which comprises a beam and a hoop located below the beam. The two are fixedly connected through a connecting beam. The beam is connected, and the upper and lower parts are respectively provided with a horizontal anchor piece. A first hinge seat is provided above the beam, a connecting rod is hinged in the first hinge seat, and a second hinge seat is connected to the top of the connecting rod. The hoop includes the upper half The hoop and the lower half hoop are fixed to the crossbeam by long bolts, and the inner walls of the two are fitted and fixedly connected to a fluororubber layer. The width and thickness of the fluororubber layer are greater than that of the hoop, and the fluororubber layer faces the Several reinforcing ribs are arranged on one side, and the reinforcing ribs are arranged along the circumferential direction of the hoop. The utility model is suitable for numerical wall surfaces such as side walls, has strong bearing capacity, stable support performance, fire prevention and heat resistance, and is especially suitable for high temperature pipelines such as steam pipelines and hot water pipelines.
Description
技术领域technical field
本实用新型涉及一种成品支吊架,尤其涉及一种侧墙用管道抗震成品支吊架。The utility model relates to a finished support and hanger, in particular to a pipeline anti-seismic finished support and hanger for side walls.
背景技术Background technique
近年来,地质灾害频发,地震是人类几乎不可抗拒的自然灾害。其中大的破坏性地震给人们造成生命财产 损失几乎不可估计。地震波造成所波及到的所有物体发生震颤,尤其建筑内具有支撑、悬 挂、吊装状态的物体。建筑机电工程抗震设计规范》中规定抗震设防烈度为6度及6度以上地区的建筑 机电工程必须进行抗震设计,旨在减轻地震对机电工程设施的破坏。机电工程设施主要包 括电梯,照明系统和应急电源,通信设备,管道系统,供暖和空气调节系统,火灾报警和消防 系统等。所以,如何提高支吊架的抗震性能,是需要解决的问题。In recent years, geological disasters have occurred frequently, and earthquakes are almost irresistible natural disasters for human beings. Among them, the large destructive earthquakes caused almost immeasurable loss of life and property to people. Seismic waves cause tremors to all objects affected, especially objects in a building that are supported, suspended, and hoisted. The Code for Seismic Design of Building Mechanical and Electrical Engineering stipulates that the building's mechanical and electrical engineering in areas with a seismic fortification intensity of 6 degrees and above must carry out seismic design in order to reduce the damage to the mechanical and electrical engineering facilities caused by earthquakes. Mechanical and electrical engineering facilities mainly include elevators, lighting systems and emergency power supplies, communication equipment, piping systems, heating and air conditioning systems, fire alarm and fire fighting systems, etc. Therefore, how to improve the seismic performance of the support and hanger is a problem that needs to be solved.
另外,由于安装环境的不同,有些位置只能侧装,但侧装必然存在不稳定性,而且,现在的支架一般不具有耐热、耐高温的功能,在对于蒸汽管道、热水管道这种支架,很容易高温腐蚀。In addition, due to the different installation environments, some positions can only be installed on the side, but the side installation is bound to be unstable. Moreover, the current brackets generally do not have the function of heat resistance and high temperature resistance. The bracket is easy to corrode at high temperature.
发明内容Contents of the invention
本实用新型的目的就在于提供一种解决上述问题,抗震效果好,且耐高温的侧墙用管道抗震成品支吊架。The purpose of this utility model is to provide an anti-seismic finished product support and hanger for pipes for side walls, which solves the above problems and has good anti-seismic effect and high temperature resistance.
为了实现上述目的,本实用新型采用的技术方案是这样的:一种侧墙用管道抗震成品支吊架,包括横梁和位于横梁下方的抱箍,二者通过连接梁固定连接,所述横梁一端设有一竖板,所述竖板中部与横梁连接,上、下部各设有一水平的锚固件,所述横梁上方设有一第一铰座,第一铰座中铰接一连杆,所述连杆底部能绕第一铰座在横梁所在的竖直面内旋转,连杆顶部连接一第二铰座,所述第二铰座能绕连杆在横梁所在的竖直面内旋转,第二铰座底部垂直连接一锚固件;In order to achieve the above purpose, the technical solution adopted by the utility model is as follows: a pipe anti-seismic finished support and hanger for side walls, including a beam and a hoop located below the beam, the two are fixedly connected by a connecting beam, and one end of the beam is A vertical plate is provided, the middle part of the vertical plate is connected with the crossbeam, and a horizontal anchor piece is provided on the upper and lower parts respectively, and a first hinge seat is provided above the crossbeam, and a connecting rod is hinged in the first hinge seat, and the connecting rod The bottom can rotate around the first hinge seat in the vertical plane where the crossbeam is located, and the top of the connecting rod is connected with a second hinge seat, and the second hinge seat can rotate around the connecting rod in the vertical plane where the crossbeam is located. An anchor is vertically connected to the bottom of the seat;
所述抱箍包括上半箍和下半箍,二者两端设有水平的安装耳,抱箍两侧分别设有一长螺栓,一端穿过安装耳将上半箍和下半箍固定,另一端与横梁下表面固定连接,所述长螺栓和连接梁与横梁的连接处,设有减震垫;The hoop includes an upper half hoop and a lower half hoop, both ends of which are provided with horizontal mounting ears, and a long bolt is respectively provided on both sides of the hoop, one end passes through the mounting ear to fix the upper half hoop and the lower half hoop, and the other One end is fixedly connected to the lower surface of the crossbeam, and the connection between the long bolt and the connecting beam and the crossbeam is provided with a shock absorber;
所述上半箍和下半箍内壁贴合固定连接一氟橡胶层,所述氟橡胶层宽度和厚度均大于抱箍的宽度和厚度,氟橡胶层朝向圆心的一面设有数条加强筋,所述加强筋沿抱箍圆周方向设置。The inner walls of the upper half hoop and the lower half hoop are fitted and fixedly connected with a fluororubber layer, the width and thickness of the fluororubber layer are larger than the width and thickness of the hoop, and the side of the fluororubber layer facing the center of the circle is provided with several reinforcing ribs. The reinforcing ribs are arranged along the circumferential direction of the hoop.
作为优选:所述横梁上也设有沿其长度方向设置的加强条。As a preference: the beam is also provided with reinforcement strips arranged along its length direction.
作为优选:所述抱箍和横梁表面,均设有镀锌层。As a preference: the surfaces of the hoop and the beam are all provided with a galvanized layer.
与现有技术相比,本实用新型的优点在于:横梁通过竖板上的锚固件,可以与竖直墙面进行固定,而通过第一铰座、第二铰座、连杆的设置及旋转方式,施工人员可以调整第二铰座与竖直墙面接触,并也通过锚固件与墙面固定,由于连杆两端铰接的灵活性,可以适用于不平整的墙面,而抱箍内设有氟橡胶层,而所述氟橡胶层宽度和厚度均大于抱箍的宽度和厚度,氟橡胶层朝向圆心的一面设有数条加强筋,具有很强的承载力,以及稳定的支撑性能,具有防火、耐热的效果,尤其适用于蒸汽管道,热水管道等高温管道。Compared with the prior art, the utility model has the advantage that the beam can be fixed to the vertical wall through the anchor piece on the vertical plate, and can be fixed through the setting and rotation of the first hinge seat, the second hinge seat, and the connecting rod. In this way, the construction personnel can adjust the second hinge seat to be in contact with the vertical wall, and also fix it with the wall through the anchor piece. Due to the flexibility of the hinge at both ends of the connecting rod, it can be applied to uneven walls, and the inside of the hoop A fluororubber layer is provided, and the width and thickness of the fluororubber layer are larger than the width and thickness of the hoop. The side of the fluororubber layer facing the center of the circle is provided with several reinforcing ribs, which have strong bearing capacity and stable support performance. It has the effect of fire prevention and heat resistance, especially suitable for high temperature pipes such as steam pipes and hot water pipes.
上半箍和下半箍通过穿过安装耳的长螺栓固定,并通过长螺栓与横梁下表面固定连接,避免因震动导致抱箍坏掉后,管道掉落。长螺栓和连接梁与横梁的连接处,设有减震垫,使本实用新型整体抗震性能好。The upper half hoop and the lower half hoop are fixed by long bolts passing through the mounting ears, and are fixedly connected to the lower surface of the beam through long bolts to prevent the pipe from falling when the hoop is broken due to vibration. The joints of the long bolts and the connecting beam and the crossbeam are provided with damping pads, so that the overall seismic performance of the utility model is good.
附图说明Description of drawings
图1为本实用新型结构示意图;Fig. 1 is the structural representation of the utility model;
图2为图1中下半箍的结构示意图。Fig. 2 is a schematic structural diagram of the lower half hoop in Fig. 1 .
图中:1、横梁;2、竖板;3、锚固件;4、第一铰座;5、连杆;6、第二铰座;7、下半箍;8、上半箍;9、氟橡胶层;10、长螺栓;11、加强条;12、安装耳;13、加强筋。In the figure: 1. beam; 2. vertical plate; 3. anchor; 4. first hinge seat; 5. connecting rod; 6. second hinge seat; 7. lower half hoop; 8. upper half hoop; 9. Fluorine rubber layer; 10, long bolts; 11, reinforcing strips; 12, mounting ears; 13, reinforcing ribs.
具体实施方式detailed description
下面将结合附图对本实用新型作进一步说明。The utility model will be further described below in conjunction with accompanying drawing.
实施例1:参见图1和图2,一种侧墙用管道抗震成品支吊架,包括横梁1和位于横梁1下方的抱箍,二者通过连接梁固定连接,所述横梁1一端设有一竖板2,所述竖板2中部与横梁1连接,上、下部各设有一水平的锚固件3,所述横梁1上方设有一第一铰座4,第一铰座4中铰接一连杆5,所述连杆5底部能绕第一铰座4在横梁1所在的竖直面内旋转,连杆5顶部连接一第二铰座6,所述第二铰座6能绕连杆5在横梁1所在的竖直面内旋转,第二铰座6底部垂直连接一锚固件3;Embodiment 1: Referring to Fig. 1 and Fig. 2 , a pipeline anti-seismic finished support and hanger for side walls includes a crossbeam 1 and a hoop located below the crossbeam 1, the two are fixedly connected by a connecting beam, and one end of the crossbeam 1 is provided with a Riser 2, the middle part of the riser 2 is connected to the crossbeam 1, a horizontal anchor 3 is provided on the upper and lower parts, a first hinge seat 4 is arranged above the crossbeam 1, and a connecting rod is hinged in the first hinge seat 4 5. The bottom of the connecting rod 5 can rotate around the first hinge seat 4 in the vertical plane where the beam 1 is located, and the top of the connecting rod 5 is connected to a second hinge seat 6, and the second hinge seat 6 can rotate around the connecting rod 5 Rotating in the vertical plane where the beam 1 is located, the bottom of the second hinge seat 6 is vertically connected to an anchor 3;
所述抱箍包括上半箍8和下半箍7,二者两端设有水平的安装耳12,抱箍两侧分别设有一长螺栓10,一端穿过安装耳12将上半箍8和下半箍7固定,另一端与横梁1下表面固定连接,所述长螺栓10和连接梁与横梁1的连接处,设有减震垫;The hoop includes an upper half hoop 8 and a lower half hoop 7, both ends of which are provided with horizontal mounting ears 12, and a long bolt 10 is respectively provided on both sides of the hoop, and one end passes through the mounting ear 12 to connect the upper half hoop 8 and the The lower half hoop 7 is fixed, and the other end is fixedly connected to the lower surface of the crossbeam 1, and the connection between the long bolt 10 and the connecting beam and the crossbeam 1 is provided with a shock absorber;
所述上半箍8和下半箍7内壁贴合固定连接一氟橡胶层9,所述氟橡胶层9宽度和厚度均大于抱箍的宽度和厚度,氟橡胶层9朝向圆心的一面设有数条加强筋13,所述加强筋13沿抱箍圆周方向设置。The inner walls of the upper half hoop 8 and the lower half hoop 7 are fit and fixedly connected with a fluororubber layer 9, the width and thickness of the fluororubber layer 9 are greater than the width and thickness of the hoop, and the side of the fluororubber layer 9 facing the center of the circle is provided with several A reinforcing rib 13 is arranged along the circumferential direction of the hoop.
本实施例中,所述横梁1上也设有沿其长度方向设置的加强条11,所述抱箍和横梁1表面,均设有镀锌层。In this embodiment, the crossbeam 1 is also provided with reinforcing strips 11 arranged along its length direction, and the hoop and the surface of the crossbeam 1 are all provided with a galvanized layer.
安装时,将横梁1一端靠在竖直墙面上,调整第一铰座4、第二铰座6、连杆5的位置,使第二铰座6底部与竖直墙面贴合,再分别通过两根锚固件3固定竖板2,通过一根锚固件3固定第二铰座6。When installing, put one end of the beam 1 against the vertical wall, adjust the positions of the first hinge seat 4, the second hinge seat 6, and the connecting rod 5, so that the bottom of the second hinge seat 6 fits the vertical wall surface, and then The riser 2 is fixed by two anchors 3 and the second hinge seat 6 is fixed by one anchor 3 respectively.
根据管道尺寸选择合适的抱箍,抱箍内设有氟橡胶层9,而所述氟橡胶层9宽度和厚度均大于抱箍的宽度和厚度,氟橡胶层9朝向圆心的一面设有数条加强筋13,管道位于氟橡胶层9中,氟橡胶具有很好的耐高温,耐热效果,尤其适用于蒸汽管道,热水管道等高温管道,而加强筋13的设计,使抱箍具有很强的承载力。Choose the appropriate hoop according to the size of the pipe. There is a fluororubber layer 9 inside the hoop, and the width and thickness of the fluororubber layer 9 are larger than the width and thickness of the hoop. The side of the fluororubber layer 9 facing the center of the circle is provided with several reinforcements. Rib 13, the pipe is located in the fluorine rubber layer 9, fluorine rubber has good high temperature resistance and heat resistance effect, especially suitable for high temperature pipes such as steam pipes and hot water pipes, and the design of the reinforcement rib 13 makes the hoop have a strong carrying capacity.
为了避免因震动导致抱箍坏掉后,管道掉落的情况,通过一长螺栓10将上半箍8和下半箍7固定在一起,且长螺栓10与横梁1下表面固定连接,并在长螺栓10和连接梁与横梁1的连接处,设有减震垫。使本实用新型整体抗震性能好。In order to avoid the situation that the pipe falls after the hoop is broken due to vibration, the upper half hoop 8 and the lower half hoop 7 are fixed together by a long bolt 10, and the long bolt 10 is fixedly connected to the lower surface of the beam 1, and the The connection between the long bolt 10 and the connecting beam and the crossbeam 1 is provided with a damping pad. The overall anti-seismic performance of the utility model is improved.
横梁1上也设有沿其长度方向设置的加强条11,有效加强横梁1的强度,避免因管道太多太重,造成的拉扯变形,抱箍和横梁1表面,均设有镀锌层,具有优秀的耐热性能,使本实用新型不易受高温腐蚀。The crossbeam 1 is also provided with reinforcing strips 11 along its length direction, which can effectively strengthen the strength of the crossbeam 1 and avoid pulling deformation caused by too many and heavy pipes. The hoop and the surface of the crossbeam 1 are all provided with galvanized layers. With excellent heat resistance, the utility model is not easily corroded by high temperature.
本实用新型结构简单,尤其适合用于支撑蒸汽管道,热水管道等高温管道。The utility model has a simple structure, and is especially suitable for supporting high-temperature pipelines such as steam pipelines and hot water pipelines.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720324574.3U CN206708556U (en) | 2017-03-30 | 2017-03-30 | Side wall seismatic method for pipeline finished product suspension and support |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720324574.3U CN206708556U (en) | 2017-03-30 | 2017-03-30 | Side wall seismatic method for pipeline finished product suspension and support |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206708556U true CN206708556U (en) | 2017-12-05 |
Family
ID=60468191
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720324574.3U Expired - Fee Related CN206708556U (en) | 2017-03-30 | 2017-03-30 | Side wall seismatic method for pipeline finished product suspension and support |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206708556U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108248596A (en) * | 2018-02-08 | 2018-07-06 | 安徽华菱汽车有限公司 | A kind of vehicle and its more gas receiver mounting structures |
| CN109357084A (en) * | 2018-08-15 | 2019-02-19 | 深圳市君盈建筑科技有限公司 | A kind of building anti-seismic support and hanger and its on-line monitoring method of anti-seismic performance |
| CN111895183A (en) * | 2020-08-13 | 2020-11-06 | 徐静刚 | Engineering support and hanger system |
| CN113513156A (en) * | 2021-04-27 | 2021-10-19 | 山东恒信建业集团有限公司 | Beam-penetrating sleeve structure and mounting method |
-
2017
- 2017-03-30 CN CN201720324574.3U patent/CN206708556U/en not_active Expired - Fee Related
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108248596A (en) * | 2018-02-08 | 2018-07-06 | 安徽华菱汽车有限公司 | A kind of vehicle and its more gas receiver mounting structures |
| CN109357084A (en) * | 2018-08-15 | 2019-02-19 | 深圳市君盈建筑科技有限公司 | A kind of building anti-seismic support and hanger and its on-line monitoring method of anti-seismic performance |
| CN109357084B (en) * | 2018-08-15 | 2020-04-07 | 广东博智林机器人有限公司 | Building anti-seismic support and hanger and anti-seismic performance online monitoring method thereof |
| CN111895183A (en) * | 2020-08-13 | 2020-11-06 | 徐静刚 | Engineering support and hanger system |
| CN111895183B (en) * | 2020-08-13 | 2021-12-14 | 四川宏景阳城市建设开发有限公司 | Engineering support and hanger system |
| CN113513156A (en) * | 2021-04-27 | 2021-10-19 | 山东恒信建业集团有限公司 | Beam-penetrating sleeve structure and mounting method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206708556U (en) | Side wall seismatic method for pipeline finished product suspension and support | |
| CN204901062U (en) | A three -dimensional antidetonation gallows | |
| CN106051314B (en) | A kind of antidetonation suspension and support | |
| CN207406698U (en) | A kind of combined earthquake-resistant stent | |
| CN110005899A (en) | Drag-line composite damping Self-resetting energy consumption pipeline para-seismic support | |
| CN206708696U (en) | Shear the antidetonation finished product suspension and support of structure | |
| CN108533834B (en) | Vibration reduction type anti-seismic support and hanger with adjustable supporting rigidity | |
| CN206458900U (en) | A kind of para-seismic support for pipes | |
| CN207525886U (en) | A kind of steel building assembles damping device | |
| CN103510463B (en) | Horizontally rotate hinged-support | |
| CN103866876B (en) | Building water damping damping device | |
| CN104314193B (en) | The fire prevention of a kind of shock insulation rubber bearing and wind resistance combination unit | |
| CN211289185U (en) | A pipeline checkpost structure for antidetonation support | |
| CN209370602U (en) | Pipeline of nuclear power plant damper mount connection structure | |
| CN207671541U (en) | A kind of vibration damping suspension rope and hanger | |
| CN209925856U (en) | Sleeve friction type adjustable damping energy dissipation and shock absorption support | |
| CN210860116U (en) | Wall-through air duct | |
| CN218510334U (en) | Bridge lateral anti-seismic support hanger | |
| CN214744121U (en) | Fire control combination pipeline formula antidetonation supports gallows | |
| CN209781873U (en) | Anti-seismic support | |
| CN211401597U (en) | Anti-seismic support and hanger loading device | |
| CN209469880U (en) | Multi-pipe co-frame lateral seismic support and hanger structure | |
| CN108105476A (en) | Siphon drainage pipe is across the pre- anti-rock fixing means of grid structure | |
| CN209856514U (en) | Pipeline antidetonation assembled supporting equipment | |
| CN221323574U (en) | Metal pressure pipeline connecting structure penetrating through shock insulation ditch |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171205 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |