CN206707122U - A kind of concrete filled steel tube component of the steel tube confinement of sandwich - Google Patents

A kind of concrete filled steel tube component of the steel tube confinement of sandwich Download PDF

Info

Publication number
CN206707122U
CN206707122U CN201720235020.6U CN201720235020U CN206707122U CN 206707122 U CN206707122 U CN 206707122U CN 201720235020 U CN201720235020 U CN 201720235020U CN 206707122 U CN206707122 U CN 206707122U
Authority
CN
China
Prior art keywords
component
concrete
steel tube
core
outer layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720235020.6U
Other languages
Chinese (zh)
Inventor
张素梅
周绪红
郭兰慧
陈杰
王玉银
石宇
杨华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Graduate School Harbin Institute of Technology
Original Assignee
Shenzhen Graduate School Harbin Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Graduate School Harbin Institute of Technology filed Critical Shenzhen Graduate School Harbin Institute of Technology
Priority to CN201720235020.6U priority Critical patent/CN206707122U/en
Application granted granted Critical
Publication of CN206707122U publication Critical patent/CN206707122U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of concrete filled steel tube component of the steel tube confinement of sandwich, the concrete filled steel tube new type of component of the steel tube confinement of wherein described sandwich is made up of outer layer pipe, sandwich material and core concrete filled steel tubular member, and the outer layer pipe and sandwich material only provide core concrete filled steel tube sidewise restraint effect;The outer layer pipe and core concrete filled steel tubular member are circle;Wherein outer layer pipe is not attached along the elongated arrangement in core concrete filled steel tubular member surface and with the end of core component and bean column node, the utility model can strengthen the cooperation performance between core component steel pipe and core concrete, improve the bearing capacity and ductility of component, improve the failure mode of component, strengthen the antidetonation of component, corrosion-resistant and fire resistance;The utility model principle is clear, excellent in mechanical performance, engineering cost are relatively low.

Description

A kind of concrete filled steel tube component of the steel tube confinement of sandwich
Technical field
The utility model belongs to building structural element field, more particularly to a kind of round steel pipe of the steel tube confinement of sandwich is mixed Coagulate native component.
Background technology
The combined member that concrete filled steel tube refers to the fill concrete in steel pipe and formed.Concrete filled steel tubular member is in stress mistake Cheng Zhong, steel pipe makes concrete be in the stress state of three dimension stress to the effect of contraction of concrete, so that core is mixed in steel pipe The intensity for coagulating soil is improved, and ductility significantly improves;Meanwhile the presence of core concrete can avoid or delay steel pipe Local buckling, so as to ensure that its material property is not fully exerted.Compared with reinforced concrete structure, in concrete-filled steel tube construction During, steel pipe can save formwork cost, accelerating construction progress as the template for pouring its core concrete;With steel knot Structure is compared, and the presence of core concrete makes the fire resistance of component more preferable, saves fireproof coating, reduces construction costs.By steel pipe Concrete filled steel tube is combined into coagulation local soil type, by the interaction of steel pipe and core concrete, can not only make up two kinds of materials The shortcomings that respective, and the advantages of the two can be given full play to, make concrete filled steel tube that there are a series of superior mechanical properties. In recent years, concrete filled steel tube is favored by engineering circles because of its superior mechanical property, in skyscraper and long-span bridge More and more extensive application has been obtained in beam.
But concrete filled steel tube applied in Practical Project in there is also weak point, specifically include:
(1)Steel core concrete column is under xial feed effect, and steel pipe undertakes longitudinal load simultaneously with core concrete, therefore Steel pipe fails to be not fully exerted to the binding effect of core concrete, especially for steel pipe high strength concrete column reinforcing, steel pipe pair The binding effect of core concrete is not notable, and core high-strength concrete is also easy to produce shearing conquassation in loading process and destroyed;
(2)For concrete filled steel tubular member under xial feed effect, steel pipe is typically in the stress of the horizontal tension of longitudinal direction compression State, this makes longitudinal yield strength of steel pipe be less than the unidirectional tensile yield strength of steel pipe;With the increase of deformation, steel pipe is to core The lateral confinement effect gradually enhancing of concrete, particularly after steel pipe is surrendered, the longitudinal stress of steel pipe is with its lateral stress Increase and gradually reduce, be i.e. contribution of the steel pipe to component longitudinal load-bearing power also weakens therewith;
(3)Concrete filled steel tubular member meet with equivalent to this area seismic fortification intensity set up defences earthquake effect when, component It may be damaged, its steel pipe is likely to be breached surrender or produces flexing, and component, which need to carry out repairing and reinforcement, can just be continuing with;
(4)Concrete filled steel tubular member is under xial feed effect, and at the initial stage of loading, steel pipe is in bullet with core concrete Sexual stage, because the Poisson's ratio of steel pipe is more than core concrete, the transversely deforming of steel pipe is bigger than the transversely deforming of core concrete, This, which causes to produce between steel pipe and core concrete, disengages phenomenon, especially for thin-wall steel tube high-strength concrete component, high-strength core Heart concrete is small in loading transversely deforming at initial stage, and thin-wall steel tube and core concrete disengagement phenomenon are more notable;In addition, actual work In journey due to the pouring of core concrete, maintenance method is improper or core concrete produce shrink, creeping can lead with temperature deformation Cause to produce phenomenon of coming to nothing between steel pipe and core concrete, above phenomenon can influence the phase interaction of steel pipe and core concrete With making steel pipe to produce larger initial stress initial stage in loading, so as to influence the mechanical property of component;
(5)In actual concrete filled steel tubular member, steel pipe because its poor corrosion resistance need to periodically carry out strict preservative treatment, Otherwise corrosion easily occurs, influences the durability and mechanical property of component, limits such component in some particular surroundings Use, such as Ultra-Long Spans CFST Arch Bridge is because the rotproofness difference of outer layer pipe causes it in development of coastal area and answers With being restricted;
(6)The steel pipe of concrete filled steel tubular member is in outermost layer, and steel pipe need to undertake longitudinal load, under fire effect, The intensity and modulus of elasticity of steel pipe strongly reduce, and so as to reduce the bearing capacity of concrete filled steel tubular member, therefore in Practical Project, are The fire resistance of concrete filled steel tubular member is improved, is still needed in outer surface of steel tube sprayed fire proofing protective layer, so as to increase construction costs.
For this reason, it is necessary to design a kind of new concrete filled steel tube component, component steel pipe can be strengthened core is mixed The effect of contraction of soil is coagulated, improves the bearing capacity and ductility of component, improves the failure mode of component, strengthens antidetonation, the corrosion resistant of component Erosion and fire resistance.
Utility model content
The purpose of this utility model is to provide a kind of concrete filled steel tube component of the steel tube confinement of sandwich, it is intended to solves The deficiency of certainly existing concrete filled steel tubular member technology, to strengthen the cooperation between core component steel pipe and core concrete Performance, the bearing capacity and ductility of component are improved, improve the failure mode of component, strengthen the antidetonation of component, corrosion-resistant and fire resistance Energy.
The utility model is achieved in that a kind of concrete filled steel tube component of the steel tube confinement of sandwich, by hollow The outer layer assembly nested groups of the core component of column structure and hollow cylinder structure are into the outer layer assembly and the core component Between be filled with sandwich material;Inner layer material, the core component and the outer layer assembly are filled with inside the core component Cross section figure be centrosymmetric image;The symmetrical centre weight of the cross section of the core component and the outer layer assembly Close;The inwall width of the outer layer assembly is more than the outer wall width of the core component and both do not contact with each other;The outer layer The length of component is less than the core component;The sandwich material length is identical with the outer layer assembly;The inner layer material length Degree is identical with the core component;The core component is hollow cylindrical structure.By the length of core component will be longer than institute Outer layer assembly and sandwich material are stated, and the bean column node of Practical Project China and foreign countries layer assembly and sandwich material not with core component connects Connect, so this programme China and foreign countries layer assembly and sandwich material are substantially what is do not stressed, simply core component and concrete are provided The effect of lateral confinement.
This is very different with common double-layer nested steel pipe tool in the prior art, though double-layer pipe of the prior art So from the cross-sectional structure in the middle part of component for this programme be the same, but because the length of its layer structure is in internal layer Structure is identical, so being to bear longitudinal force effect simultaneously both during stress;Make constraint of the layer structure steel pipe to endothecium structure With can not give full play to.
It is of the present utility model further technical scheme be:The outer layer assembly is hollow cylindrical structure.Hollow cylinder knot Structure can provide the effect of identical lateral confinement in all directions, make so as to strengthen constraint of the core component to inner layer material With.
It is of the present utility model further technical scheme be:The manufacture material of the core component and the outer layer assembly is carbon One kind in plain steel, stainless steel and high-strength steel.These materials are readily available, and cost is cheap.
It is of the present utility model further technical scheme be:The inner layer material prepares material as high performance concrete, height One or more in reinforced concrete, normal concrete and regeneration concrete;The material for preparing of the sandwich material is cement base Grouting material, fiber reinforcement grouting material, structure glue, high performance concrete, high-strength concrete, normal concrete or regeneration coagulation One or more in soil.These materials are readily available, and cost is cheap.
The beneficial effects of the utility model are:Compared with prior art, the utility model has the advantages that:
(1)Outer layer round steel sleeve pipe does not undertake longitudinal load, and the steel pipe and core of core circular steel tube concrete component are mixed Solidifying soil plays effect of contraction, and compared with conventional steel concrete component, the binding effect that core concrete is subject to is stronger, and its ductility can It is further improved, reduces the phenomenon that core concrete produces failure by shear, while outer layer round steel sleeve pipe is circular to core The steel pipe of concrete filled steel tubular member(Internal layer round steel pipe)Producing effect of contraction can effectively prevent or delay inner layer steel pipe generation office Portion's flexing, and outer layer round steel sleeve pipe does not undertake longitudinal load, equally avoids the buckling problem of steel pipe, therefore the utility model structure Part will be effectively improved the failure mode of conventional steel concrete component;
(2)Outer layer round steel sleeve pipe plays effect of contraction, core to the steel pipe and core concrete of core circular steel tube concrete post The binding effect enhancing that heart concrete is subject to, its bearing capacity can obtain further raising;The horizontal tension effect of inner layer steel pipe will Weakened, its longitudinal stress then accordingly improves, and the contribution to element bearing capacity is bigger, with conventional steel concrete component phase Than the mechanical property of the utility model core concrete and steel pipe is more effectively played, and stress is clearly reasonable, and bearing capacity can It is significantly improved;
(3)Outer layer round steel sleeve pipe does not undertake longitudinal load, avoids the buckling problem of steel pipe, while can more effectively constrain core Heart concrete, alleviate the phenomenon of core concrete destruction;When component is set up defences by equivalent to this area seismic fortification intensity During earthquake effect, it may occur however that damage, carry out local route repair reinforcing to component using the utility model mode, component can be continued Use, therefore the utility model also adds while conventional steel concrete component shock resistance is improved to be repaired after the shake of component Admittedly provide approach;
(4)Outer layer round steel sleeve pipe does not undertake longitudinal load, can weaken between loading inner layer steel pipe at initial stage and core concrete Disengagement phenomenon, inner layer steel pipe is produced effect of contraction initial stage in loading to core concrete, strengthen the mechanical property of component; The utility model can also effectively overcome core concrete to pour, maintenance method is improper or core concrete produces and shrinks, creeps, be warm The problem of inner layer steel pipe is with core concrete adhesion strength deficiency caused by degree deformation, so as to improve inner layer steel pipe and concrete two Service behaviour between person;
(5)When the outer layer round steel sleeve pipe of component uses stainless steel tube, outer layer stainless steel tube will significantly improve component Decay resistance, preservative treatment process is reduced, conventional steel concrete component can be extended to the spies such as moist, Korrosionsmedium is strong Used in different environment;
(6)The utility model has outsourced a layer interlayer material on the outside of original core circular steel tube concrete component, folder The specific heat capacity of the specific heat ratio inner layer steel pipe of layer material is big, can effectively delay the heat transfer of fire, while outer layer round steel sleeve pipe Longitudinal load is not undertaken under fire effect, the above can improve the fire endurance of core circular steel tube concrete component.
Brief description of the drawings
, below will be to embodiment or existing in order to illustrate more clearly of the embodiment of the present application or technical scheme of the prior art There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments described in application, for those of ordinary skill in the art, on the premise of not paying creative work, Other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is that the structure of the concrete filled steel tube component of the steel tube confinement for the sandwich that the utility model embodiment provides is shown It is intended to.
Fig. 2 is the concrete filled steel tube element cross-section of the steel tube confinement for the sandwich that the utility model embodiment provides Schematic diagram.
Fig. 3 is the concrete filled steel tube component preparation process of the steel tube confinement for the sandwich that the utility model embodiment provides In schematic diagram.
Fig. 4 is the concrete filled steel tube member processing method of the steel tube confinement for the sandwich that the utility model embodiment provides The schematic diagram of middle fixture.
Reference:1- inner layer materials;2- core components;The outer layer assemblies of 3-;4- sandwich materials;5- fixtures.
Embodiment
The explanation of following embodiment is with reference to additional schema, and the specific of implementation is can be used to illustrate the utility model Embodiment.The direction term that the utility model is previously mentioned, for example, " on ", " under ", "front", "rear", "left", "right", " interior ", " Outside ", " side " etc., only it is the direction with reference to annexed drawings.Therefore, the direction term used is to illustrate and understand this practicality It is new, and be not used to limit the utility model.
Fig. 1 is that the structure of the concrete filled steel tube component of the steel tube confinement for the sandwich that the utility model embodiment provides is shown It is intended to.As can be seen from Figure 1 the outward appearance of the concrete filled steel tube component of the steel tube confinement for the sandwich that this programme provides.It is a kind of The concrete filled steel tube component of the steel tube confinement of sandwich, by the core component 2 and hollow cylinder structure of hollow cylinder structure The outer nested composition of layer assembly 3, is filled with sandwich material 4 between the outer layer assembly and the core component;The core component Inside is filled with inner layer material 1, and the cross section figure of the core component and the outer layer assembly is centrosymmetric image;Institute The symmetrical centre for stating the cross section of core component and the outer layer assembly overlaps;The inwall width of the outer layer assembly is more than described The outer wall width of core component and both do not contact with each other;The length of the outer layer assembly is less than the core component;The folder Layer material length is identical with the outer layer assembly;The inner layer material length is identical with the core component.
Fig. 2 is the concrete filled steel tube element cross-section of the steel tube confinement for the sandwich that the utility model embodiment provides Schematic diagram.Figure it is seen that specific in the present embodiment, core component uses circular configuration, and outer layer assembly is also using circle Shape structure.
Because the length of core component will be longer than the outer layer assembly, thus this programme China and foreign countries layer assembly be substantially not by Power, the effect of lateral confinement is simply provided core component and concrete.Compared to traditional concrete filled steel tubular member, this reality With the new cooperation performance strengthened between steel pipe and core concrete, the bearing capacity and ductility of component are improved, improves structure The failure mode of part, strengthen the antidetonation of component, corrosion-resistant and fire resistance.
This is very different with common double-layer nested steel pipe tool in the prior art, though double-layer pipe of the prior art So from the cross-sectional structure in the middle part of component for this programme be the same, but because the length of its layer structure is in internal layer Structure is identical, so being to bear longitudinal force effect simultaneously both during stress, makees constraint of the layer structure steel pipe to endothecium structure With can not give full play to.
In this programme, it can be achieved when the both ends of core component are than outer layer pipe and each longer sandwich material both ends outer Layer assembly is not completely by longitudinal load, in Practical Project, the outer layer assembly along the elongated arrangement of the core component, but not with Any form is connected with the end of the core component and node.
Further, the manufacture material of the core component and the outer layer assembly is carbon steel, stainless steel and high-strength steel In one kind, to adapt to different requirement of engineering, particularly when outer layer assembly uses stainless steel tube, integrated member can be improved Decay resistance and aesthetic.
Further, the inner layer material prepare material for high performance concrete, high-strength concrete, normal concrete and One or more in regeneration concrete, to adapt to the needs of different engineerings, when component be used for high-rise, high-rise building or greatly across To spend in arch bridge structure, high performance concrete and high-strength concrete can play bigger advantage and benefit, and when core concrete is adopted During with regeneration concrete, can solve natural aggregate resources problem in short supply, the ecological environment in the protection aggregate place of production, and can solves city The problems such as stacking, occupation of land and environmental pollution of discarded object, there is significant society, economical and environmentally friendly benefit.
The sandwich material prepares material as cement-based grouting material, fiber reinforcement grouting material, structure glue, high-performance One or more in concrete, high-strength concrete, normal concrete or regeneration concrete.These materials are readily available, cost It is cheap.
The preparation method of the concrete filled steel tube component of the steel tube confinement of sandwich in this programme, this method bag is described below Include following steps:
Step A:Positioning step, the positioning step system are positioned core component and outer layer assembly by design;It is described Core component system cylindrical structure.
Wherein, the step A include it is following step by step:
Step A1:Making component step, the making component step system is by design length interception rectangular core component and outside Layer assembly, or choose sheet material curling welding by design requirement and form circular skin component and core component;
Step A2:Component fixing step, fixture 5, Fig. 3 is inserted in the end of the core component and the outer layer assembly Be the utility model embodiment provide sandwich steel tube confinement concrete filled steel tube component preparation process in schematic diagram. As can be seen from Figure 3 the installation site of the fixture.The fixture system annular steel plate, Fig. 4 are the utility model realities The schematic diagram of fixture in the concrete filled steel tube member processing method of the steel tube confinement of the sandwich of example offer is provided.From Fig. 4 It can be seen that being provided with circular hollow out among the fixture, the hollow out shape is identical with the outer surface of the core component, The external diameter of the fixture is identical with the external diameter of the outer layer assembly, and the fixture is connected with the outer layer assembly spot welding.It is logical The position crossed between fixture guarantee core component and outer layer assembly, it is ensured that both can be concentric.
Step B:Pour step, it is described pour step system and irrigate inner layer material enter the core component, by interlayer material Material perfusion enters between the outer layer assembly and core component;
The step B include it is following step by step:
Step B1:Inner layer material pours step, and the inner layer material pours step system by concrete according to design proportioning system Standby inner layer material, the surface laying polyethylene film of pair fixture 5 contacted with sandwich material 4 simultaneously smear machine oil;Then by institute State inner layer material to irrigate to the core component, and fully vibrate and reach closely knit to the inner layer material;
Step B2:Sandwich material pours step, and the sandwich material pours step system and prepares interlayer material according to design proportioning Material, the inner layer material is irrigated between the core component and the outer layer assembly, and fully vibrated to the internal layer material Material reaches closely knit.
Step C:Curing step, the curing step system conserve to the step B products obtained.
Specifically, the step C include it is following step by step:
Step C1:The test specimen for pouring completion is conserved;
Step C2:Remove the fixture used in step A2.
Compared with prior art, the utility model has the advantages that:
(1)Outer layer round steel sleeve pipe does not undertake longitudinal load, and the steel pipe and core of core circular steel tube concrete component are mixed Solidifying soil plays effect of contraction, and compared with conventional steel concrete component, the binding effect that core concrete is subject to is stronger, and its ductility can It is further improved, reduces the phenomenon that core concrete produces failure by shear, while outer layer round steel sleeve pipe is circular to core The steel pipe of concrete filled steel tubular member(Internal layer round steel pipe)Producing effect of contraction can effectively prevent or delay inner layer steel pipe generation office Portion's flexing, and outer layer round steel sleeve pipe does not undertake longitudinal load, equally avoids the buckling problem of steel pipe, therefore the utility model structure Part will be effectively improved the failure mode of conventional steel concrete component;
(2)Outer layer round steel sleeve pipe plays effect of contraction, core to the steel pipe and core concrete of core circular steel tube concrete post The binding effect enhancing that heart concrete is subject to, its bearing capacity can obtain further raising;The horizontal tension effect of inner layer steel pipe will Weakened, its longitudinal stress then accordingly improves, and the contribution to element bearing capacity is bigger, with conventional steel concrete component phase Than the mechanical property of the utility model core concrete and steel pipe is more effectively played, and stress is clearly reasonable, and bearing capacity can It is significantly improved;
(3)Outer layer round steel sleeve pipe does not undertake longitudinal load, avoids the buckling problem of steel pipe, while can more effectively constrain core Heart concrete, alleviate the phenomenon of core concrete destruction;When component is set up defences by equivalent to this area seismic fortification intensity During earthquake effect, it may occur however that damage, carry out local route repair reinforcing to component using the utility model mode, component can be continued Use, therefore the utility model also adds while conventional steel concrete component shock resistance is improved to be repaired after the shake of component Admittedly provide approach;
(4)Outer layer round steel sleeve pipe does not undertake longitudinal load, can weaken between loading inner layer steel pipe at initial stage and core concrete Disengagement phenomenon, inner layer steel pipe is produced effect of contraction initial stage in loading to core concrete, strengthen the mechanical property of component; The utility model can also effectively overcome core concrete to pour, maintenance method is improper or core concrete produces and shrinks, creeps, be warm The problem of inner layer steel pipe is with core concrete adhesion strength deficiency caused by degree deformation, so as to improve inner layer steel pipe and concrete two Service behaviour between person;
(5)When the outer layer round steel sleeve pipe of component uses stainless steel tube, outer layer stainless steel tube will significantly improve component Decay resistance, preservative treatment process is reduced, conventional steel concrete component can be extended to the spies such as moist, Korrosionsmedium is strong Used in different environment;
(6)The utility model has outsourced a layer interlayer material on the outside of original core circular steel tube concrete component, folder The specific heat capacity of the specific heat ratio inner layer steel pipe of layer material is big, can effectively delay the heat transfer of fire, while outer layer round steel sleeve pipe Longitudinal load is not undertaken under fire effect, the above can improve the fire endurance of core circular steel tube concrete component.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (5)

  1. A kind of 1. concrete filled steel tube component of the steel tube confinement of sandwich, it is characterised in that:By the core of hollow cylinder structure The outer layer assembly nested groups of component and hollow cylinder structure are into being filled with interlayer between the outer layer assembly and the core component Material;Inner layer material is filled with inside the core component;The cross section figure of the core component and the outer layer assembly is equal Centered on symmetric figure;The symmetrical centre of the cross section of the core component and the outer layer assembly overlaps;The outer layer assembly Inwall width be more than the core component outer wall width and both do not contact with each other;The length of the outer layer assembly is less than institute State core component;The sandwich material length is identical with the outer layer assembly;The inner layer material length and the core component It is identical;The core component is hollow cylindrical structure.
  2. 2. the concrete filled steel tube component of the steel tube confinement of sandwich according to claim 1, it is characterised in that:It is described outer Layer assembly is hollow cylindrical structure.
  3. 3. according to the concrete filled steel tube component of the steel tube confinement of any described sandwich in claim 1-2, its feature exists In:The sandwich material prepares material as cement-based grouting material, fiber reinforcement grouting material, structure glue, high-performance coagulation One or more in soil, high-strength concrete, normal concrete or regeneration concrete.
  4. 4. according to the concrete filled steel tube component of the steel tube confinement of any described sandwich in claim 1-2, its feature exists In:The manufacture material of the core component and the outer layer assembly is one kind in carbon steel, stainless steel and high-strength steel.
  5. 5. according to the concrete filled steel tube component of the steel tube confinement of any described sandwich in claim 1-2, its feature exists In:The inner layer material prepares material as in high performance concrete, high-strength concrete, normal concrete and regeneration concrete It is one or more.
CN201720235020.6U 2017-03-10 2017-03-10 A kind of concrete filled steel tube component of the steel tube confinement of sandwich Active CN206707122U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720235020.6U CN206707122U (en) 2017-03-10 2017-03-10 A kind of concrete filled steel tube component of the steel tube confinement of sandwich

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720235020.6U CN206707122U (en) 2017-03-10 2017-03-10 A kind of concrete filled steel tube component of the steel tube confinement of sandwich

Publications (1)

Publication Number Publication Date
CN206707122U true CN206707122U (en) 2017-12-05

Family

ID=60469768

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720235020.6U Active CN206707122U (en) 2017-03-10 2017-03-10 A kind of concrete filled steel tube component of the steel tube confinement of sandwich

Country Status (1)

Country Link
CN (1) CN206707122U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106906951A (en) * 2017-03-10 2017-06-30 哈尔滨工业大学深圳研究生院 The concrete filled steel tube component and its processing method of a kind of steel tube confinement of sandwich
CN108842965A (en) * 2018-07-04 2018-11-20 什邡泰锐钢结构工程有限公司 Shake lower three-dimensional multistage yielding in pole stops building not reversed structure
CN108930542A (en) * 2018-09-05 2018-12-04 山东科技大学 A kind of compound CFRP restrained concrete arch of light-duty high-strength and construction method
CN111456241A (en) * 2020-04-14 2020-07-28 太原理工大学 Stainless steel composite pipe-concrete-carbon steel member
CN112726959A (en) * 2021-01-06 2021-04-30 华南理工大学 High-strength concrete composite column with high-strength steel pipes and internally-arranged FRP pipes
CN114427280A (en) * 2022-02-21 2022-05-03 南京林业大学 Novel bamboo-steel-construction waste combined component and manufacturing method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106906951A (en) * 2017-03-10 2017-06-30 哈尔滨工业大学深圳研究生院 The concrete filled steel tube component and its processing method of a kind of steel tube confinement of sandwich
CN108842965A (en) * 2018-07-04 2018-11-20 什邡泰锐钢结构工程有限公司 Shake lower three-dimensional multistage yielding in pole stops building not reversed structure
CN108842965B (en) * 2018-07-04 2020-04-14 什邡泰锐钢结构工程有限公司 Three-dimensional multi-order yielding blocking building non-falling structure under extreme earthquake
CN108930542A (en) * 2018-09-05 2018-12-04 山东科技大学 A kind of compound CFRP restrained concrete arch of light-duty high-strength and construction method
CN108930542B (en) * 2018-09-05 2023-06-02 山东科技大学 Light high-strength composite carbon fiber confined concrete arch frame and construction method
CN111456241A (en) * 2020-04-14 2020-07-28 太原理工大学 Stainless steel composite pipe-concrete-carbon steel member
CN112726959A (en) * 2021-01-06 2021-04-30 华南理工大学 High-strength concrete composite column with high-strength steel pipes and internally-arranged FRP pipes
CN114427280A (en) * 2022-02-21 2022-05-03 南京林业大学 Novel bamboo-steel-construction waste combined component and manufacturing method thereof

Similar Documents

Publication Publication Date Title
CN206707122U (en) A kind of concrete filled steel tube component of the steel tube confinement of sandwich
CN106906951A (en) The concrete filled steel tube component and its processing method of a kind of steel tube confinement of sandwich
CN106917470A (en) The steel tube confinement concrete-filled rectangular steel tube component and its processing method of a kind of sandwich
CN106481090B (en) A kind of Shockproof reinforcing method of existing reinforced concrete concrete frame joint
CN206308801U (en) Steel tube binding type steel regeneration concrete post and reinforced beam end plate connecting node
CN105239726B (en) The prefabricated combined special-shaped power consumption post of steel reinforced concrete
CN106760215A (en) A kind of fiber-bamboo wood composite pipe concrete composite structure
CN206512590U (en) A kind of assembled hollow steel pipe constrains reinforced column squat pier
CN208533868U (en) A kind of novel arrangement of reinforcement hollow steel pipe high-strength concrete column
CN105507497A (en) Bamboo-wound pipe and cast concrete integrated column for buildings and preparation method of bamboo-wound pipe and cast concrete integrated column for buildings
CN106760211A (en) A kind of bamboo wood-steel pipe concrete combined structure
CN102535749A (en) Double-function multi-cavity steel tube concrete column provided with soft steel sleeve at bottom, and manufacturing method thereof
CN207332114U (en) A kind of steel tube confinement concrete-filled rectangular steel tube component of sandwich
CN206681263U (en) A kind of concrete filled steel tube new type of component of steel tube confinement
CN105970803A (en) Shearing resisting energy consumption device and construction method of prefabricated pier
CN108060718A (en) A kind of detachable assembling type column and basic ductility joint connection mode
CN107034793A (en) A kind of ruggedized construction of arch bridge spandrel arch circle
CN206752848U (en) A kind of L-type coupled column
CN108590035A (en) High-strength recycled concrete superposed column and preparation method thereof
CN208136920U (en) A kind of triangle prestressing force foundation pit supporting pile and its connection structure
CN107083822A (en) The concrete filled steel tube new type of component and its processing method of a kind of steel tube confinement
CN203701292U (en) Steel tube and concrete reinforced tubular joint with local hollow interlayers
CN206408838U (en) A kind of fiber bamboo wood multiple tube concrete combination column
CN206245845U (en) High intensity thinner tube centrifuge concrete filled steel tubular substation framework post
CN203008234U (en) SCS (steel concrete structure) square concrete-filled steel tube column based on CFRP (carbon fiber reinforced plastic) fabric reinforcement

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant