CN206646493U - A kind of bored concrete pile suitable for solution cavity geology - Google Patents

A kind of bored concrete pile suitable for solution cavity geology Download PDF

Info

Publication number
CN206646493U
CN206646493U CN201720093496.0U CN201720093496U CN206646493U CN 206646493 U CN206646493 U CN 206646493U CN 201720093496 U CN201720093496 U CN 201720093496U CN 206646493 U CN206646493 U CN 206646493U
Authority
CN
China
Prior art keywords
mould bag
bind
reinforcement cage
steel reinforcement
solution cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720093496.0U
Other languages
Chinese (zh)
Inventor
段能超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Positive Basic Construction Engineering Co Ltd
Original Assignee
Shenzhen Positive Basic Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Positive Basic Construction Engineering Co Ltd filed Critical Shenzhen Positive Basic Construction Engineering Co Ltd
Priority to CN201720093496.0U priority Critical patent/CN206646493U/en
Application granted granted Critical
Publication of CN206646493U publication Critical patent/CN206646493U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of bored concrete pile suitable for solution cavity geology, the retaining wall body for being adapted including steel reinforcement cage, with steel reinforcement cage and being scattered for limiting concrete, and it is filled in the concrete-pile formed in retaining wall body by concrete setting, the retaining wall body is the mould bag with sack, the mould bag, which is located at sack, is provided with bind rope, the bind rope bind is in steel reinforcement cage, the utility model is rational in infrastructure, predominantly staff can use mould bag bind on steel reinforcement cage, because bind process spends the time shorter, so project progress can be lifted.

Description

A kind of bored concrete pile suitable for solution cavity geology
Technical field
It the utility model is related to architecture foundation pile engineering field, more particularly to a kind of bored concrete pile suitable for solution cavity geology.
Background technology
Solution cavity geology refers to that the soluble rock stratum such as dolomite, limestone produces ditch after the chemistry and mechanism of water Groove, crack or earth's surface cratering caused by cavity.
Drill in solution cavity geology, connected due to drilling with solution cavity, during concrete perfusion, the stream shape body such as concrete Easily scattered from drilling into solution cavity, first the inner space of solution cavity can be filled up, can just reach the top of drilling afterwards, during which Fullness coefficient is high, causes a large amount of wastes of concrete.For this problem, a kind of existing construction method is after piercing, to incite somebody to action Under steel pile casting made of 10 ~ 20mm of thickness steel plate into drilling, sleeve pipe is similar to until being formed at the top of drilling in foot of hole Retaining wall body, then place steel reinforcement cage and concrete perfusion, retaining wall body is steel pile casting, under the restriction effect of steel pile casting, coagulation Soil is not easy to scatter into solution cavity, and this construction method effect is preferable, but steel pile casting is made of sheet metal welding, works as pile When longer, the quantity of required sheet metal is bigger, therefore weld interval is longer, increases construction work amount.
Utility model content
The purpose of this utility model is to provide a kind of bored concrete pile suitable for solution cavity geology, using mould bag bind in steel reinforcement cage On, bind process spends the time shorter, lifts project progress.
Above-mentioned technical purpose of the present utility model technical scheme is that:
A kind of bored concrete pile suitable for solution cavity geology, including steel reinforcement cage, be adapted with steel reinforcement cage and for limiting concrete Wandering retaining wall body, and the concrete-pile formed in retaining wall body by concrete setting is filled in, the retaining wall body is with bag The mould bag of mouth, the mould bag, which is located at sack, is provided with bind rope, and the bind rope bind is in steel reinforcement cage.
By using above-mentioned technical proposal, mould bag is first put into steel reinforcement cage by staff, then by tying up on sack Then splicing bind moves the bottom of mould bag to the tail end of steel reinforcement cage in the head end of steel reinforcement cage, then by lifting means by steel Muscle cage is put into the drilling of solution cavity;Because bind process spends the time shorter, so spending the time relative to some steel of welding The time that piece is spent is more of short duration, so project progress can be lifted.
Preferably, the mould bag is arranged at the inside of steel reinforcement cage.
By using above-mentioned technical proposal, mould bag is arranged on the inside of steel reinforcement cage, its can by the spacing of steel reinforcement cage, After its inside penetration concrete, mould bag is not easy to be squeezed into the inner space of solution cavity;Steel is arranged on relative to by mould bag The outside of muscle cage, this is easy for causing concrete that its part is squeezed into the inner space of solution cavity, and it is mixed also to increase a part Coagulate the dosage of soil.
Preferably, the mould bag bottom also is provided with bind rope, and the bind rope bind positioned at the mould bag bottom is in steel The bottom of muscle cage.
By using above-mentioned technical proposal, because mould bag only has certain weight, and location of gathering Xia Shui be present in drilling Phenomenon, mould bag bottom is fixed on to the bottom of steel reinforcement cage, foot of hole can be immersed into steel reinforcement cage, so it is just It will not be suspended in underground water, therefore also be not easy to hinder the operation for stretching into perfusion conduit into drilling.
Preferably, the mould bag is in sleeve-shaped, is provided with some reinforcing rings, the reinforcement along centerline direction inside it Ring is knitted to mould bag inwall.
By using above-mentioned technical proposal, in the concrete perfusion into mould bag, mould bag side is easily formed down necking, And reinforcing ring is woven in mould bag inwall, mould bag can be strutted, and then mould bag is not easy necking, deformed upon.
Preferably, by steel wire bind between the reinforcing ring and mould bag inwall of the mould bag bottom, close to institute State between the reinforcing ring of mould bag sack and mould bag inwall by terylene rope bind.
By using above-mentioned technical proposal, when originating the penetration concrete into mould bag, the necking trend below mould bag is relative It is larger, it is higher to the attachment structure intensity requirement between reinforcing ring and mould bag inside, so using steel wire bind, irrigate at leisure Man Hou, it is desirable to it is relatively low, terylene rope sewing braiding can now need to be only used, is operated relatively simple.
Preferably, it is woven with reinforcing strip between the mould bag inner bottom part edge and mould bag side wall.
By using above-mentioned technical proposal, similarly, in the concrete perfusion into mould bag, shape between mould bag bottom and inside Change trend is larger, it is therefore necessary to set the structural strength of reinforcing strip reinforcement herein, reaches the effect for being not easy deformation.
Preferably, the mould bag is arranged at the outside of steel reinforcement cage.
By using above-mentioned technical proposal, this scheme is arranged at the inside of steel reinforcement cage relative to mould bag, and being arranged on outside makes It can be bonded together when obtaining concrete curing with steel reinforcement cage, and then improve the structural strength of bored concrete pile.
In summary, the utility model has the advantages that:Using mould bag bind on steel reinforcement cage, coagulation is being avoided Under conditions of soil is wandering, its bind process spends the time shorter, lifts project progress;Simultaneously in the reinforcement of reinforcing ring and reinforcing strip Under effect, the structural strength of mould bag is improved, it is more not easy to be damaged.
Brief description of the drawings
Fig. 1 is the structural representation of embodiment 1;
Fig. 2 is the structural representation inside embodiment 1.
Reference:1st, steel reinforcement cage;2nd, mould bag;21st, sack;3rd, bind rope;4th, reinforcing ring;5th, steel wire;6th, terylene rope;7、 Reinforcing strip.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.Wherein identical parts identical accompanying drawing Mark represents.It should be noted that the word "front", "rear", "left", "right", the "up" and "down" that are used below in description refer to It is the direction in accompanying drawing, word " bottom surface " and " top surface ", " interior " and " outer " are referred respectively to towards or away from particular elements geometry The direction at center.
Embodiment 1:Referring to Fig. 1, a kind of bored concrete pile suitable for solution cavity geology, including steel reinforcement cage 1, steel reinforcement cage 1 is interior to be set There is retaining wall body, retaining wall body is the cylindric mould bag 2 being adapted with steel reinforcement cage 1, and mould bag 2 has circular sack 21, while in sack Its edge is provided with some bind ropes 3 at 21, the bottom of mould bag 2 is enclosed construction, and the outer ledge in bottom is equally set There are some bind ropes 3.Mould bag 2 is first put into steel reinforcement cage 1 by staff, and then the bind of bind rope 3 on sack 21 exists The upper end of steel reinforcement cage 1 to, then the bottom of mould bag 2 is moved to the tail end of steel reinforcement cage 1, by the bind of bind rope 3 of bottom in steel reinforcement cage 1 Lower end steel ring on, now mould bag 2 be bonded steel reinforcement cage 1.
Referring to Fig. 1 and Fig. 2, centerline direction is also provided with some reinforcing bar reinforcing rings 4 in the inside of mould bag 2, lower section Steel wire 5 is provided between reinforcing ring 4 and bag body, steel wire 5 through mould bag 2 and around reinforcing ring 4 and then is wound clot, and then Realize that reinforcing ring 4 is fixedly connected on inside mould bag 2, reach the purpose for strutting mould bag 2;Then between top reinforcing ring 4 and mould bag 2 Sewing braiding is carried out by terylene rope 6, it is right around reinforcing ring 4 similarly then to penetrate mould bag 2 by large-scale syringe needle connection terylene rope 6 After pass mould bag 2 carry out bind, reach the purpose that reinforcing ring 4 is fixedly connected with mould bag 2.In order to strengthen the inside portion of mould bag 2 with Structural strength between the bottom of mould bag 2, the present embodiment are sewed also between both and are woven with the reinforcing strip of linen material 7。
Concrete operations mode is:In sewing processing factory, reinforcing ring 4 is first passed through into terylene rope 6 or steel wire 5 by above-mentioned requirements Bind is sewed between the bottom of mould bag 2 and inside portion in mould bag 2, while by reinforcing strip 7, and staff elder generation side mould bag 2 Be put into steel reinforcement cage 1, then by the bind of bind rope 3 on sack 21 steel reinforcement cage 1 head end, then by the bottom of mould bag 2 Move the tail end of steel reinforcement cage 1 to, by the bind of bind rope 3 of the bottom of mould bag 2 in the bottom of steel reinforcement cage 1, then passing through lifting means will Steel reinforcement cage 1 is put into the drilling of solution cavity;Because bind process spends the time shorter, so spending the time some relative to welding The time that steel disc is spent is more of short duration, so project progress can be lifted.
Embodiment 2:A kind of bored concrete pile suitable for solution cavity geology, it is with the difference of embodiment 1, the mould bag of setting 2 are slightly larger than the size of steel reinforcement cage 1, are then woven with bind rope 3 at same sack 21 and at bottom outside, and the mould bag 2 is used to cover The outside of steel reinforcement cage 1 is connected on, then again by the bind of bind rope 3 on steel reinforcement cage 1, because concrete and rebar cage 1 directly contacts, So it is higher to obtain filling pile structure intensity.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but As long as all protected in right of the present utility model by Patent Law.

Claims (7)

1. a kind of bored concrete pile suitable for solution cavity geology, including steel reinforcement cage(1)With steel reinforcement cage(1)It is adapted and mixed for limiting The wandering retaining wall body of solidifying soil, and it is filled in the concrete-pile formed in retaining wall body by concrete setting, it is characterised in that it is described Retaining wall body is with sack(21)Mould bag(2), the mould bag(2)Positioned at sack(21)Place is provided with bind rope(3), the bind Rope(3)Bind is in steel reinforcement cage(1).
A kind of 2. bored concrete pile suitable for solution cavity geology according to claim 1, it is characterised in that the mould bag(2)If It is placed in steel reinforcement cage(1)Inside.
A kind of 3. bored concrete pile suitable for solution cavity geology according to claim 2, it is characterised in that the mould bag(2)Bottom Portion also is provided with bind rope(3), positioned at the mould bag(2)The bind rope of bottom(3)Bind is in steel reinforcement cage(1)Bottom.
A kind of 4. bored concrete pile suitable for solution cavity geology according to claim 3, it is characterised in that the mould bag(2)It is in Sleeve-shaped, some reinforcing rings are provided with along centerline direction inside it(4), the reinforcing ring(4)It is knitted to mould bag(2)Inwall.
5. a kind of bored concrete pile suitable for solution cavity geology according to claim 4, it is characterised in that close to the mould bag (2)The reinforcing ring of bottom(4)With mould bag(2)Pass through steel wire between inwall(5)Bind, close to the mould bag(2)Sack(21)'s Reinforcing ring(4)With mould bag(2)Pass through terylene rope between inwall(6)Bind.
A kind of 6. bored concrete pile suitable for solution cavity geology according to claim 5, it is characterised in that the mould bag(2)It is interior Bottom margin and mould bag(2)Reinforcing strip is woven between side wall(7).
A kind of 7. bored concrete pile suitable for solution cavity geology according to claim 6, it is characterised in that the mould bag(2)If It is placed in steel reinforcement cage(1)Outside.
CN201720093496.0U 2017-01-22 2017-01-22 A kind of bored concrete pile suitable for solution cavity geology Expired - Fee Related CN206646493U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720093496.0U CN206646493U (en) 2017-01-22 2017-01-22 A kind of bored concrete pile suitable for solution cavity geology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720093496.0U CN206646493U (en) 2017-01-22 2017-01-22 A kind of bored concrete pile suitable for solution cavity geology

Publications (1)

Publication Number Publication Date
CN206646493U true CN206646493U (en) 2017-11-17

Family

ID=60284062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720093496.0U Expired - Fee Related CN206646493U (en) 2017-01-22 2017-01-22 A kind of bored concrete pile suitable for solution cavity geology

Country Status (1)

Country Link
CN (1) CN206646493U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360505A (en) * 2018-02-11 2018-08-03 湖北工业大学 A kind of filling pile structure and its construction method passing through solution cavity
CN108589718A (en) * 2018-03-30 2018-09-28 中交路桥北方工程有限公司 Piles in Karst Region base construction method
CN111042124A (en) * 2019-12-09 2020-04-21 江苏省地质矿产局第三地质大队 Multifunctional pile casing suitable for sludge bottom layer and construction method adopting pile casing
CN115679955A (en) * 2022-10-09 2023-02-03 重庆大学 Construction device and construction method for pile foundation in solution cavity

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360505A (en) * 2018-02-11 2018-08-03 湖北工业大学 A kind of filling pile structure and its construction method passing through solution cavity
CN108589718A (en) * 2018-03-30 2018-09-28 中交路桥北方工程有限公司 Piles in Karst Region base construction method
CN111042124A (en) * 2019-12-09 2020-04-21 江苏省地质矿产局第三地质大队 Multifunctional pile casing suitable for sludge bottom layer and construction method adopting pile casing
CN115679955A (en) * 2022-10-09 2023-02-03 重庆大学 Construction device and construction method for pile foundation in solution cavity
CN115679955B (en) * 2022-10-09 2024-06-04 重庆大学 Construction device and construction method for pile foundation in solution cavity

Similar Documents

Publication Publication Date Title
CN206646493U (en) A kind of bored concrete pile suitable for solution cavity geology
CN208167713U (en) A kind of film bag grouting and reinforcing type filling pile structure
CN202557970U (en) Multi-room mine goaf filling string bag
CN201358456Y (en) Plastic sleeve concrete pile
CN108411918A (en) Pore-creating filling pile pile crown abolishes device and its construction method
CN208472708U (en) A kind of grouting behind shaft or drift lining filling pile structure
CN106193032A (en) A kind of anti-float anchor rod construction method
CN208136909U (en) A kind of anti-levitating device of filling concrete pile cages fluking type
CN105672250B (en) A kind of diaphram wall and underwater concrete tongue and groove bindiny mechanism and construction method
CN104564091A (en) Method and device for removing anchor rods from shield crossing area
CN207331673U (en) Sleeve valve pipe horizontal grouting construction device
CN113699981A (en) Construction method for preventing necking of rotary-digging cast-in-place pile in high-fill field
CN105064352A (en) Building expanding head anchor rod pile construction technology and anchor rod pile adopting technology
CN106480876A (en) A kind of inclined hole steel pipe piles set into rock construction
CN211973505U (en) A grouting system for different filling types of karst caves
CN108643202A (en) Massif prosthetic appliance
CN208105272U (en) One kind preventing superfilled device
CN204282360U (en) Covering layer prestressed anchoring structure
CN109403328B (en) Perforated pipe grouting assembly and construction method
CN206635722U (en) Side slope geotechnical fabric bag slope protection device
CN206971210U (en) A kind of long casing in pile foundation construction
CN109930602A (en) A kind of Water Cutting vibration immersed tube pile pulling device
CN208456595U (en) A ductile wellbore structure under high pressure and high energy impact surrounding rock
CN109898505A (en) With the compound tubular pole of reinforced structure in soft stratum
CN108360524A (en) One kind preventing superfilled device and its application method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171117

Termination date: 20210122

CF01 Termination of patent right due to non-payment of annual fee