CN206581636U - A kind of support frame for being applied to pour build floor - Google Patents
A kind of support frame for being applied to pour build floor Download PDFInfo
- Publication number
- CN206581636U CN206581636U CN201621432616.7U CN201621432616U CN206581636U CN 206581636 U CN206581636 U CN 206581636U CN 201621432616 U CN201621432616 U CN 201621432616U CN 206581636 U CN206581636 U CN 206581636U
- Authority
- CN
- China
- Prior art keywords
- support beam
- column
- support
- build floor
- side wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000003351 stiffener Substances 0.000 claims description 4
- 238000005728 strengthening Methods 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 21
- 229910000831 Steel Inorganic materials 0.000 abstract description 15
- 239000010959 steel Substances 0.000 abstract description 15
- 230000033228 biological regulation Effects 0.000 description 4
- 238000009415 formwork Methods 0.000 description 4
- 230000006641 stabilisation Effects 0.000 description 3
- 238000011105 stabilization Methods 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002708 enhancing effect Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000004540 pour-on Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model disclose it is a kind of be applied to pour the support frame of build floor, including column and some are connected to the column top, the template of pouring build floor for treating forms the support beam of stable support.When in pouring construction, workmen fixes the bottom of column on the ground, by each support beam and the template contacts of build floor to be poured that are connected to column top, and forms stable support, then starts pouring construction.A large amount of steel pipes or log are needed in build floor to pouring the mode that build floor is supported compared to existing pour, the utility model carries out stable support using each support beam for being connected to column top to pouring build floor, a root post only need to be set up between the template of build floor to be poured and ground, without using support members such as substantial amounts of steel pipes, the usage quantity of support member is so greatly reduced, big quantity space is vacated, improve space availability ratio simultaneously, and then other work post operations can be carried out in the space, improve construction efficiency.
Description
Technical field
The utility model is related to technical field of building construction, more particularly to a kind of support frame for being applied to pour build floor.
Background technology
With growth of the national economic, urbanization is developed rapidly, and city is constantly extended, and increasing building is used for carrying
Development of Urbanization demand.
At present, all kinds of buildings are built using concreting, generally comprise that post is poured, beam slab is poured and building
Ladder is poured.Wherein, in building concrete floor slab placement Concrete, use is as template branch with steel pipe or log
Support, it is necessary to which a large amount of steel pipes or log are supported to formwork for placing in concrete floor slab placement work progress, and due to single steel pipe
Or log Area of bearing is smaller, when the area for pouring build floor is larger, it is necessary to which intensive arrangement steel pipe or log are to formwork for placing
It is supported, may now takes the space entirely constructed, because construction space is occupied full, can not also implements in the space other
The work of work post, so that the duration is extended, and if the floor height of each floor plate is different, then these intensive steel pipes or log can not
Enough it is recycled, it is necessary to more steel pipes or log are supported to formwork for placing, not only increases building cost, and due to
The a large amount of steel pipes of needs or log are supported to formwork for placing, increase is built the time, namely increase construction period.
Therefore, how on the basis of stable support build floor template to be poured is ensured so that occupancy when support frame is used
Area is reduced, and is improved space availability ratio, is those skilled in the art's technical problem urgently to be resolved hurrily.
Utility model content
The purpose of this utility model is to provide a kind of support frame for being applied to pour build floor, can be treated ensureing stable support
Pour on the basis of slab form, area occupied when support frame is used is greatly reduced, improve space availability ratio, do not influence other
The construction speed of work post, improves construction efficiency.
In order to solve the above technical problems, the utility model provides a kind of support frame for being applied to pour build floor, including column
The template for be connected to the column top with some, pouring build floor for treating forms the support beam of stable support;
Also include be telescopically arranged in each support beam, the support contact area for adjusting each support beam
Retractable support beam.
Preferably, on the side wall of the retractable support beam be provided with the side wall of the support beam several mutually it is relative
The first positioning hole answered, and each first positioning hole sets along the retractable support beam telescopic direction;Also include being used for institute
State the first fastening screw that the first positioning hole on the side wall of support beam and retractable support beam in correspondence with each other is fixed on predeterminated position.
Preferably, in addition to it is telescopically arranged on the column, treats for adjusting the support beam and pour build floor
The telescopic column of the bearing height of template.
Preferably, with being provided with several on the side wall of the telescopic column in correspondence with each other on the side wall of the column
Second positioning hole, and telescopic direction setting of each second positioning hole along the telescopic column;Also include being used to described to stand
The second positioning hole on the side wall of post and telescopic column in correspondence with each other is fixed on the second fastening screw of predeterminated position.
Preferably, one end of the support beam rotates with the telescopic column and is connected;Also include one end and the support beam
Bottom be connected, the side wall of the other end and the telescopic column rotates connection, for adjusting between the support beam and telescopic column
The angle adjusting mechanism of angle.
Preferably, the angle adjusting mechanism specifically includes hound and rotating screw sleeve pipe, the rotating screw sleeve pipe
One end be rotatably arranged on the side wall of the telescopic column, the hound is telescopically disposed in the rotating screw
In sleeve pipe, and the end of the hound is fixed on the bottom of the support beam.
Preferably, in addition to be arranged at the column bottom, for increase with the bottom plate of contact area of ground, and set
Between the side wall and the bottom plate of the column, the stiffener plate for strengthening stability.
A kind of support frame for being applied to pour build floor provided by the utility model, mainly includes column and some supports
Beam.Wherein, each support beam is both connected to column top, and is mainly used in treating the template for pouring build floor and being formed stablizing support, and
The bottom of column is contacted with ground, is mainly used in each support beam formation stable support structure that will be all connected with its top.When suitable
When applying for pouring the support frame of build floor in pouring construction, workmen fixes the bottom of column on the ground, by even
Each support beam of column top and the template contacts of build floor to be poured are connected on, and forms stable support, then starts pouring construction.
A large amount of steel pipes or log are needed in build floor to pouring the mode that build floor is supported, the utility model profit compared to existing pour
Carry out stable support to pouring build floor with each support beam of column top is connected to, only need to build floor to be poured template and ground
A root post is set up between face, without using support members such as substantial amounts of steel pipes, the use of support member is so greatly reduced
Quantity, has vacated big quantity space, while improving space availability ratio, and then other work post operations can be carried out in the space, carried
High building efficiency of construction.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art
Or the accompanying drawing used required in description of the prior art is briefly described, it should be apparent that, drawings in the following description are only
It is embodiment of the present utility model, for those of ordinary skill in the art, on the premise of not paying creative work, also
Other accompanying drawings can be obtained according to the accompanying drawing of offer.
Fig. 1 is a kind of overall structure diagram of embodiment provided by the utility model.
Wherein, in Fig. 1:
Bottom plate -1, stiffener plate -2, column -3, telescopic column -4, the first positioning hole -5, the second positioning hole -51,
Alignment pin -63 of first alignment pin -6, the second alignment pin -61, the, three alignment pin -62, the four, support beam -7, retractable support
Beam -8, hound -9, rotating screw sleeve pipe -10.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belongs to the scope of the utility model protection.
Fig. 1 is refer to, Fig. 1 is a kind of overall structure diagram of embodiment provided by the utility model.
In a kind of embodiment provided by the utility model, the support frame that should be applied to pour build floor is mainly wrapped
Include column 3 and some support beams 7.
Generally, support beam 7 may be designed as 4, that is, 4 be arranged in a mutually vertical manner piece support beam 7.And each support beam 7
Column top is both connected to, is mainly used in treating the template for pouring build floor and being formed stablizing support, and the bottom of column 3 connects with ground
Touch, be mainly used in each support beam 7 being all connected with its top forming stable support structure.Certainly, support beam can also be 6
Root or 8 etc., its certain quantity are not limited only to above-mentioned situation, can be adjusted according to actual conditions.
Specifically, when being applied suitable for pouring the support frame of build floor pouring construction, workmen is by the bottom of column 3
End is fixed on the ground, by each support beam 7 and the template contacts of build floor to be poured that are connected to the top of column 3, and forms stabilization
Support, then starts pouring construction.A large amount of steel pipes or log is needed to be carried out to pouring build floor in build floor compared to existing pour
The mode of support, the utility model pours build floor using 7 pairs of each support beam for being connected to the top of column 3 and carries out stable support,
A root post 3 only need to be set up between the template of build floor to be poured and ground, without using support members such as substantial amounts of steel pipes,
The usage quantity of support member is so greatly reduced, big quantity space has been vacated, while space availability ratio is improved, and then can be at this
Other work post operations are carried out in space, construction efficiency is improved.
So that the quantity of support beam 7 is 4 as an example, support frame provided by the utility model is mainly using being connected to column 3
7 pairs of 4 support beams on top pour build floor and carry out stable support, only need to set up one between the template of build floor to be poured and ground
Root post 3 completes support operation, namely by increasing the Area of bearing for the support beam 7 being connected with the top of column 3, and then realize
Treat the construction operation for the template formation support for pouring build floor.
Based on this, in order to further increase the Area of bearing of support beam, retractable support beam can be set in each support beam 7
8, the retractable support beam 8 is mainly used in adjusting Area of bearing on the support contact surface of support beam 7, especially by retractable support beam
8 collapsing length realizes the function of adjustment Area of bearing.
In a kind of preferred embodiment being telescopically disposed on retractable support beam 8 in support beam 7, it can stretch
With being provided with several the first positioning holes 5 in correspondence with each other on the side wall of support beam 7 on the side wall of contracting support beam 8.Also, should
First positioning hole 5 can be placed equidistant along the telescopic direction of retractable support beam 8, such as can be set per 100mm spacing.Certainly, each
Set-up mode of one positioning hole 5 on the side wall of retractable support beam 8 and on the side wall of support beam 7 is not limited only to above-mentioned equidistantly set
Put, naturally it is also possible to not spaced set, and being adjusted according to practice of construction requirement.
General, the relative position on retractable support beam 8 and support beam 7 is determined, it is necessary to will using the first fastening screw 6
Retractable support beam 8 is fixed on the predetermined position in support beam 7, i.e. the first fastening screw 6 and is plugged on the side wall of retractable support beam 8
In corresponding first positioning hole 5, meanwhile, the first fastening screw 6 is also plugged on the first positioning hole of correspondence 5 on the side wall of support beam 7
In.In this way, the relative position for completing retractable support beam 8 and support beam 7 by the first fastening screw 6 determines to operate, that is, determine
Extension elongation of the retractable support beam 8 in support beam 7, the extension elongation is that correspond to treat the supporting surface for pouring slab form
Product.It is of course also possible to use the mode of self-locking sliding-rail, can equally realize retractable support beam 8 being fixed on the pre- of support beam 7
If at position.
If entered during in view of the different situation of the floor height of each floor plate, it is necessary to treat and pour the bearing height of slab form
Row adjustment, therefore, telescopic telescopic column 4 can be set on column 3.The telescopic column 4 is by adjustment from column 3
On flexible height, and then adjust and treat the bearing height that pours slab form.Now, the top of telescopic column 4 and each support
Beam 7 is connected.
In a kind of preferred embodiment on telescopic column 4, can by the side wall of telescopic column 4 with column 3
Several the second positioning holes 51 in correspondence with each other, and flexible side of second positioning hole 51 along telescopic column 4 are provided with the wall of side
It is usually to be set per 50mm spacing to being placed equidistant.Certainly, above-mentioned spacing is not limited only to set, can not also spaced set,
And can be adjusted according to practice of construction requirement.
At this time, it may be necessary to telescopic column 4 is fixed on to the predetermined position on column 3 using the second fastening screw 61, i.e.,
Two fastening screws 61 are plugged on the side wall of telescopic column 4 in corresponding second positioning hole 51, meanwhile, the second fastening screw 61 is also inserted
Be connected in the second positioning hole of correspondence 51 on the side wall of column 3, in this way, by the second fastening screw 61 complete by telescopic column 4 with
The relative position of column 3 determines operation, that is, determines extension elongation of the telescopic column 4 on column 3, and the extension elongation is correspondence
And treat the bearing height for pouring slab form.
It may need to pour the structure for building up certain angle of inclination in view of top floor, it is therefore desirable to by build floor mould to be poured
Plate shape is supported into the stabilization with certain angle of inclination.Based on this, the present embodiment is set up between support beam 7 and telescopic column 4
Angle adjusting mechanism, at this time, it may be necessary to which support beam 7 is rotatably connected on into the top of telescopic column 4, can specifically be inserted using the 4th positioning
Support beam 7 is rotatably arranged on the top of telescopic column 4 by pin 63.One end of the angle adjusting mechanism is connected with the bottom of support beam 7,
And the other end is rotated with the side wall of telescopic column 4 and is connected, and specifically can realize angle adjusting mechanism using the 3rd fastening screw 62
Rotation between telescopic column 4 is connected.The angle adjusting mechanism is mainly used in adjusting the folder between support beam 7 and telescopic column 4
Angle, and then treat and pour the angle of inclination of slab form and be adjusted.
, can be by the first positioning hole 5 and the second positioning in order to which the support frame for being applied to pour build floor is easy to processing and manufacturing
Hole 51 is designed as identical dimensional structure.Further, can also be by the first alignment pin 6, the second alignment pin 61, the 3rd alignment pin 62
Identical dimensional structure is both designed as with the 4th alignment pin 63.
It is connected it is of course also possible to which the other end of angle adjusting mechanism is rotated with the side wall of column 3.
In a kind of preferred embodiment on angle adjusting mechanism, hound 9 and rotation spiral shell can be designed to
The combining structure of rotation set pipe 10.Specifically, one end of rotating screw sleeve pipe 10 can be rotatably arranged in the side of telescopic column 4
On wall, hound 9 is telescopically disposed in rotating screw sleeve pipe 10, and the end of hound 9 is fixed on the bottom of support beam 7
Portion.In this way, by changing the length that hound 9 stretches out from rotating screw sleeve pipe 10, you can support beam 7 is surrounded telescopic column
4 top is circumferentially rotated, and then changes the angle between support beam 7 and telescopic column 4, and building slab is poured so as to realize and treat
The regulation at the angle of inclination of plate.It is of course also possible to which angle adjustment mechanism is designed as into two hounds 9 and rotating screw sleeve pipe
10 combining structure.Specifically, one end of wherein one hound 9 and the side wall of telescopic column 4 are rotatedly connected, another diagonal brace
One end of bar 9 is connected with the lower rotation of support beam 7, and two hounds 9 the other end respectively with 10 liang of rotating screw sleeve pipe
End correspondence is connected, i.e., the other ends of two hounds 9 is both provided with external screw thread, and with the internal thread of the inwall of rotating screw sleeve pipe 10
It is engaged, only rotating screw sleeve pipe 10 need to be rotated by external force, you can changes what hound 9 stretched out from rotating screw sleeve pipe 10
Length, in this way, realizing that support beam 7 is circumferentially rotated around the top of telescopic column 4, and then changes support beam 7 and telescopic vertical
Angle between post 4, namely treat the regulation at the angle of inclination for pouring slab form.
It is of course also possible to use the angle between hydraulic cylinder regulation support beam 7 and telescopic column 4, now needs hydraulic stem
End be connected with support beam 7, the side wall of hydraulic cylinder and telescopic column 4, which is rotated, be connected, in this way, by adjusting stretching for hydraulic stem
Length, you can realize the regulation of the angle between support beam 7 and telescopic column 4.
Under normal circumstances, the support frame that should be applied to pour build floor bears larger pressure in use, in order to carry
The resistance to overturning of high carriage, can set up bottom plate 1 in the bottom of column 3.The surface area of the bottom plate 1 add column 3 with
Contact area between ground, so that pressure of the column 3 to bottom surface is reduced, while also enhancing the resistance to overturning of support frame.
Further, stiffener plate 2 can also be set up between the side wall and bottom plate 1 of column 3 in the present embodiment.The reinforcement
Gusset 2 can share support pressure, so as to improve the overall stability in use of support frame.
In summary, a kind of support frame for being applied to pour build floor provided by the utility model mainly includes the He of column 3
Some support beams 7.Wherein, each support beam 7 is both connected to column top, and is mainly used in treating the template for pouring build floor and is formed
Stable support, and the bottom of column 3 is contacted with ground, is mainly used in each support beam 7 being all connected with its top forming stabilization
Supporting construction.When being applied suitable for pouring the support frame of build floor pouring construction, workmen fixes the bottom of column 3
On the ground, by each support beam 7 and the template contacts of build floor to be poured that are connected to the top of column 3, and stable support is formed, so
After start pouring construction.A large amount of steel pipes or log are needed in build floor to pouring the side that build floor is supported compared to existing pour
Formula, the utility model pours build floor using 7 pairs of each support beam for being connected to the top of column 3 and carries out stable support, need to only treat
Pour and a root post 3 is set up between the template of build floor and ground, without using support members such as substantial amounts of steel pipes, so significantly
The usage quantity of support member is reduced, big quantity space has been vacated, while improving space availability ratio, and then can be entered in the space
Other work post operations of row, improve construction efficiency.And should be applied to pour the support frame of build floor can also adjust bearing height
And support angle, with suitable for many pouring construction environment.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or new using this practicality
Type.A variety of modifications to these embodiments will be apparent for those skilled in the art, determine herein
The General Principle of justice can in other embodiments be realized in the case where not departing from spirit or scope of the present utility model.Cause
This, the utility model is not intended to be limited to the embodiments shown herein, and is to fit to and principles disclosed herein
The most wide scope consistent with features of novelty.
Claims (7)
1. a kind of support frame for being applied to pour build floor, it is characterised in that be connected to the column including column (3) and some
(3) top, the template for pouring for treating build floor form the support beam (7) of stable support;
Also include be telescopically arranged on each support beam (7), the support contact surface for adjusting each support beam (7)
Long-pending retractable support beam (8).
2. the support frame according to claim 1 for being applied to pour build floor, it is characterised in that the retractable support beam (8)
Side wall on being provided with several the first positioning holes (5) in correspondence with each other on the side wall of the support beam (7), it is and each described
First positioning hole (5) is set along retractable support beam (8) telescopic direction;Also include being used for the support beam (7) and stretching
The first positioning hole (5) on the side wall of support beam (8) in correspondence with each other is fixed on the first fastening screw (6) of predeterminated position.
3. the support frame according to claim 1 for being applied to pour build floor, it is characterised in that also including telescopically setting
In the telescopic column (4) that the bearing height for pouring slab form is treated on the column (3), for adjusting the support beam (7).
4. the support frame according to claim 3 for being applied to pour build floor, it is characterised in that the side wall of the column (3)
It is provided with several the second positioning holes (51) in correspondence with each other on the upper side wall with the telescopic column (4), and each described the
Telescopic direction of two positioning holes (51) along the telescopic column (4) is set;Also include being used for the column (3) and telescopic column
(4) the second positioning hole (51) on side wall in correspondence with each other is fixed on the second fastening screw (61) of predeterminated position.
5. the support frame according to claim 3 for being applied to pour build floor, it is characterised in that the one of the support beam (7)
End rotates with the telescopic column (4) and is connected;Also be connected including one end with the bottom of the support beam (7), the other end with it is described
The side wall of telescopic column (4) rotates connection, the angular adjustment for adjusting angle between the support beam (7) and telescopic column (4)
Mechanism.
6. the support frame according to claim 5 for being applied to pour build floor, it is characterised in that the angle adjusting mechanism tool
Body includes hound (9) and rotating screw sleeve pipe (10), and one end of the rotating screw sleeve pipe (10) is rotatably arranged in institute
On the side wall for stating telescopic column (4), the hound (9) is telescopically disposed in the rotating screw sleeve pipe (10), and institute
The end for stating hound (9) is fixed on the bottom of the support beam (7).
7. being applied to according to claim 1-6 any one pours the support frame of build floor, it is characterised in that also including setting
It is placed in the column (3) bottom, for increase and the bottom plate (1) of contact area of ground, and is arranged at the side of the column (3)
Stiffener plate (2) between wall and the bottom plate (1), for strengthening stability.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621432616.7U CN206581636U (en) | 2016-12-23 | 2016-12-23 | A kind of support frame for being applied to pour build floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621432616.7U CN206581636U (en) | 2016-12-23 | 2016-12-23 | A kind of support frame for being applied to pour build floor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206581636U true CN206581636U (en) | 2017-10-24 |
Family
ID=60108968
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621432616.7U Expired - Fee Related CN206581636U (en) | 2016-12-23 | 2016-12-23 | A kind of support frame for being applied to pour build floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206581636U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106522582A (en) * | 2016-12-23 | 2017-03-22 | 雅克设计有限公司 | Supporting frame applicable to poured floor |
CN110486061A (en) * | 2019-08-20 | 2019-11-22 | 辽宁有色基础工程公司 | The controllable support top system of cavern's Dangerous Rock Body and its application method |
CN111535196A (en) * | 2020-05-19 | 2020-08-14 | 刘赞 | Bridge building templates link for civil engineering |
CN113216399A (en) * | 2021-05-25 | 2021-08-06 | 中国建筑第二工程局有限公司 | Large-span steel reinforced concrete structure and construction method thereof |
CN114922423A (en) * | 2022-04-22 | 2022-08-19 | 山东省水利工程局有限公司 | Can have enough to meet need and use cast in situ concrete template strutting arrangement |
-
2016
- 2016-12-23 CN CN201621432616.7U patent/CN206581636U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106522582A (en) * | 2016-12-23 | 2017-03-22 | 雅克设计有限公司 | Supporting frame applicable to poured floor |
CN110486061A (en) * | 2019-08-20 | 2019-11-22 | 辽宁有色基础工程公司 | The controllable support top system of cavern's Dangerous Rock Body and its application method |
CN111535196A (en) * | 2020-05-19 | 2020-08-14 | 刘赞 | Bridge building templates link for civil engineering |
CN111535196B (en) * | 2020-05-19 | 2021-08-03 | 嘉兴德基机械设计有限公司 | Bridge building templates link for civil engineering |
CN113216399A (en) * | 2021-05-25 | 2021-08-06 | 中国建筑第二工程局有限公司 | Large-span steel reinforced concrete structure and construction method thereof |
CN114922423A (en) * | 2022-04-22 | 2022-08-19 | 山东省水利工程局有限公司 | Can have enough to meet need and use cast in situ concrete template strutting arrangement |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106522582A (en) | Supporting frame applicable to poured floor | |
CN206581636U (en) | A kind of support frame for being applied to pour build floor | |
CN207794608U (en) | A kind of adjustable support for shuttering of movement for groove construction column | |
CN207122129U (en) | A kind of early removing system built for provided with floor slab with beam, harden structure | |
CN106760574A (en) | Rectangle steel tubing string construction plumbing device and vertical adjustment method in inverse method one-column one-pile | |
CN207144475U (en) | One kind building Curved beam formwork | |
CN114059765A (en) | Batter post template and template support bracket at adjustable inclination | |
CN204040450U (en) | A kind of for angle connector in tools type section steel builder's jack | |
CN201891174U (en) | Stiff connecting node for ring girder and ring-shaped bracket column | |
CN206707128U (en) | Reuse adjustable frame trestle reinforcing bar spacer ferrule | |
CN207392053U (en) | A kind of alignment control device suitable for steel construction abnormity tower | |
CN206418523U (en) | A kind of liftable post-cast strip template structure and system | |
CN206458110U (en) | Rectangle steel tubing string construction plumbing device in inverse method one-column one-pile | |
CN108661334A (en) | A kind of steel column hoop support device preventing the outer unstability of cast-in-situ reinforced concrete oblique circular cylinder plane | |
CN107816209A (en) | The large-scale Roof Truss construction technology of installation is lifted across outer both sides | |
CN210152313U (en) | Civil engineering frame roof beam reinforcing apparatus | |
CN204609265U (en) | For the steel platform of granulation tower Superstructure Construction | |
CN207686147U (en) | Floor and double steel bar protective layer thickness control device | |
CN103195079B (en) | Installing type template, installing type template group and complete installing type plate device | |
CN205857710U (en) | Air-conditioning formwork support structure | |
CN215670536U (en) | Reinforcing steel bar structure of ladder way pier stud | |
CN206015700U (en) | A kind of raft foundation steelframe support | |
CN206971725U (en) | Hang the erecting device of mould | |
CN106193600A (en) | A kind of steel pipe scaffold early tears component open | |
CN210369898U (en) | Self-adjusting support frame for civil engineering building construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171024 |