CN206477497U - A kind of trussing for exempting to support steel form - Google Patents

A kind of trussing for exempting to support steel form Download PDF

Info

Publication number
CN206477497U
CN206477497U CN201621362079.3U CN201621362079U CN206477497U CN 206477497 U CN206477497 U CN 206477497U CN 201621362079 U CN201621362079 U CN 201621362079U CN 206477497 U CN206477497 U CN 206477497U
Authority
CN
China
Prior art keywords
steel
support
steel form
trussing
steel formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621362079.3U
Other languages
Chinese (zh)
Inventor
赵楠
李天宇
薛韧
李志聪
李永锋
王嘉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science And Industry Co ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201621362079.3U priority Critical patent/CN206477497U/en
Application granted granted Critical
Publication of CN206477497U publication Critical patent/CN206477497U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

本实用新型实施例属于建筑结构技术领域,提供了一种免支撑钢模板的桁架系统。该桁架系统包括安装在钢梁上的钢筋桁架、安装在钢筋桁架上的钢模板,以及钩头连接件,钢模板的下表面焊接分布有若干背杠,钩头连接件的一端挂设在钢筋桁架上,其另一端与钢模板可拆卸连接。将背杠焊接分布在钢模板上,能够增强钢模板的整体刚度,使得钢筋桁架在较大跨度范围搭设时,无需采用大量脚手架进行支撑即能保证钢模板的稳定性,并且在浇筑混凝土完成后拆除钢模板周转使用时,可通过对背杠施力对钢模板拆除,防止对钢模板造成损害,延长钢模板的使用寿命。

The embodiment of the utility model belongs to the technical field of building structures, and provides a truss system of a support-free steel formwork. The truss system includes a steel bar truss installed on the steel beam, a steel formwork installed on the steel bar truss, and hook connectors. The lower surface of the steel formwork is welded with several back bars, and one end of the hook connector is hung on the steel bar. On the truss, the other end is detachably connected with the steel formwork. Distributing the welding of the back bar on the steel formwork can enhance the overall rigidity of the steel formwork, so that when the steel truss is erected in a large span range, the stability of the steel formwork can be guaranteed without using a large number of scaffolding for support, and after the concrete is poured When the steel formwork is removed for turnover, the steel formwork can be removed by applying force to the back bar to prevent damage to the steel formwork and prolong the service life of the steel formwork.

Description

一种免支撑钢模板的桁架系统A truss system for free-support steel formwork

技术领域technical field

本实用新型属于建筑结构技术领域,尤其涉及一种免支撑钢模板的桁架系统。The utility model belongs to the technical field of building structures, in particular to a truss system of a support-free steel formwork.

背景技术Background technique

常用的桁架系统有钢桁架、钢筋混凝土桁架、预应力混凝土桁架、木桁架、钢与木组合桁架、钢与混凝土组合桁架。桁架按外形分有三角形桁架、梯形桁架、多边形桁架、平行弦桁架,及空腹桁架。在选择桁架形式时,应综合考虑桁架的用途、材料、支承方式和施工条件,在满足使用要求的前提下,力求制造和安装所用的材料和劳动量为最小。Commonly used truss systems include steel trusses, reinforced concrete trusses, prestressed concrete trusses, wooden trusses, steel and wood composite trusses, and steel and concrete composite trusses. According to the shape, the trusses are divided into triangular trusses, trapezoidal trusses, polygonal trusses, parallel chord trusses, and vierendeel trusses. When choosing the truss form, the use, material, support method and construction conditions of the truss should be considered comprehensively. Under the premise of meeting the use requirements, the materials and labor used for manufacturing and installation should be minimized.

目前,钢筋混凝土桁架中,由于钢模板的整体刚度不强,当钢模板在跨度范围较大的情况下搭设时,需要利用大量脚手架进行反向支撑工作,施工工作量大;待混凝土保护层浇筑完成后,钢模板不拆卸,但需要在进行吊顶遮盖,增加成本;而有的钢模板在进行拆卸时,需要使用撬棍拆除,然而撬棍用力过大容易损坏钢模板,减少了钢模板的使用寿命。At present, in reinforced concrete trusses, due to the overall rigidity of the steel formwork is not strong, when the steel formwork is erected in the case of a large span range, it is necessary to use a large number of scaffolding for reverse support work, and the construction workload is large; After the completion, the steel formwork will not be disassembled, but the ceiling needs to be covered, which increases the cost; and some steel formwork needs to be removed with a crowbar when dismantling, but the crowbar is too strong to easily damage the steel formwork, which reduces the steel formwork service life.

实用新型内容Utility model content

本实用新型实施例所要解决的技术问题在于提供一种免支撑钢模板的桁架系统,旨在解决现有技术的桁架系统在较大跨度范围下搭设时,需要用大量脚手架进行支撑所存在的施工量大以及在拆卸钢模板时容易损坏钢模板的问题。The technical problem to be solved by the embodiment of the utility model is to provide a truss system without supporting steel formwork, which aims to solve the construction problem that a large number of scaffolds need to be used for support when the truss system of the prior art is erected in a large span range. The large amount and the problem that the steel formwork is easily damaged when the steel formwork is disassembled.

本实用新型实施例是这样实现的,一种免支撑钢模板的桁架系统,包括安装在钢梁上的钢筋桁架和安装在所述钢筋桁架上的钢模板,所述桁架系统还包括钩头连接件,所述钢模板的下表面焊接分布有若干背杠,所述钩头连接件的一端挂设在所述钢筋桁架上,其另一端与所述钢模板可拆卸连接。The embodiment of the utility model is achieved in this way. A truss system without supporting steel formwork includes a steel bar truss installed on a steel beam and a steel formwork installed on the steel bar truss. The truss system also includes a hook connection The lower surface of the steel formwork is welded with several back bars, one end of the hook connector is hung on the steel truss, and the other end is detachably connected to the steel formwork.

进一步地,所述的若干背杠相互平行,并且其长度方向沿所述钢筋桁架的长度方向设置。Further, the plurality of back bars are parallel to each other, and their length direction is arranged along the length direction of the steel bar truss.

进一步地,所述的若干背杠均匀地分布在所述钢模板的下表面。Further, the plurality of back bars are evenly distributed on the lower surface of the steel formwork.

进一步地,所述背杠为C型钢或方钢管。Further, the back bar is C-shaped steel or square steel pipe.

进一步地,所述钢筋桁架的两端焊接在钢梁上,所述钩头连接件包括挂件和螺栓,所述挂件挂设在所述钢筋桁架上,所述螺栓的尾端依次穿过所述背杠与钢模板之后,与所述挂件螺纹连接,所述螺栓的头端抵靠在所述背杠上。Further, the two ends of the steel bar truss are welded on the steel beam, the hook connector includes a hanger and a bolt, the hanger is hung on the steel bar truss, and the tail ends of the bolts pass through the After the back bar and the steel template, it is threadedly connected with the hanger, and the head end of the bolt leans against the back bar.

进一步地,所述钢筋桁架包括连为一体的相互垂直的横梁与立梁,所述立梁位于所述横梁的两端,所述挂件挂设在所述横梁上,所述立梁焊接在钢梁上。Further, the steel bar truss includes mutually perpendicular beams and vertical beams connected as a whole, the vertical beams are located at both ends of the horizontal beams, the hangers are hung on the horizontal beams, and the vertical beams are welded on steel on the beam.

进一步地,所述横梁上安装有用于支撑所述钢模板的若干支撑件。Further, several supports for supporting the steel formwork are installed on the beam.

进一步地,所述支撑件包括连为一体的支脚和支架,所述支脚上的一边沿支撑所述钢模板,所述支架可转动地卡接在所述横梁上。Further, the supporting member includes a foot and a bracket connected as a whole, one edge of the foot supports the steel formwork, and the bracket is rotatably clamped on the beam.

进一步地,所述的若干支撑件沿所述横梁的长度方向均匀分布。Further, the plurality of support members are evenly distributed along the length direction of the beam.

进一步地,所述支撑件由塑料制成。Further, the support member is made of plastic.

本实用新型实施例与现有技术相比,有益效果在于:本实用新型中的钢模板下表面焊接分布有若干背杠,钩头连接件的一端挂设在钢筋桁架上,另一端与钢模板可拆卸连接,从而将钢模板悬吊;通过背杠的焊接增强钢模板的整体刚度,使得钢筋桁架在较大跨度范围搭设时,无需采用大量脚手架进行支撑即能保证钢模板的稳定性,并且在浇筑混凝土完成后拆除钢模板周转使用时,可通过对背杠施力对钢模板拆除,防止对钢模板造成损害,延长钢模板的使用寿命。Compared with the prior art, the embodiment of the utility model has the beneficial effect that: the lower surface of the steel formwork in the utility model is welded with several back bars, one end of the hook connector is hung on the steel bar truss, and the other end is connected with the steel formwork. The steel formwork can be suspended by detachable connection; the overall rigidity of the steel formwork is enhanced through the welding of the back bar, so that when the steel truss is erected in a large span range, the stability of the steel formwork can be guaranteed without using a large number of scaffolding for support, and When the steel formwork is dismantled after the pouring of concrete is completed, the steel formwork can be removed by applying force to the back bar to prevent damage to the steel formwork and prolong the service life of the steel formwork.

另外,在钢模板拆卸后周转运输时,利用背杠嵌合堆放钢模板,防止钢模板在运输的过程中滑落,提高运输堆放的安全性。In addition, when the steel formwork is disassembled and transported, use the back bar to stack the steel formwork to prevent the steel formwork from slipping during transportation and improve the safety of transportation and stacking.

附图说明Description of drawings

图1是本实用新型实施例提供的免支撑钢模板的桁架系统的整体结构示意图;Fig. 1 is the overall structural schematic diagram of the truss system of the free-support steel formwork provided by the embodiment of the utility model;

图2是图1所示的免支撑钢模板的桁架系统安装在钢梁上的结构示意图;Fig. 2 is a structural schematic diagram of the truss system of the free-support steel formwork shown in Fig. 1 installed on the steel beam;

图3是图1中的钩头连接件示意图;Fig. 3 is a schematic diagram of the hook connector in Fig. 1;

图4是本实用新型实施例一提供的支撑件结构示意图;Fig. 4 is a schematic structural diagram of a support provided by Embodiment 1 of the present invention;

图5是本实用新型实施例二提供的支撑件结构示意图;Fig. 5 is a schematic structural diagram of the support provided by the second embodiment of the utility model;

图6是图1中的钢模板堆放状态的示意图。Fig. 6 is a schematic diagram of the stacked state of the steel formwork in Fig. 1 .

具体实施方式detailed description

为了使本实用新型的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本实用新型进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本实用新型,并不用于限定本实用新型。In order to make the purpose, technical solution and advantages of the utility model clearer, the utility model will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model, and are not intended to limit the utility model.

如图1与图2所示,是本实用新型实施例提供的免支撑钢模板的桁架系统一较佳实施例,该桁架系统包括安装在钢梁1上的钢筋桁架2、安装在钢筋桁架2上的钢模板3以及钩头连接件4。钢筋桁架2的两端焊接在钢梁1上,钢模板3的下表面焊接有若干背杠5,该若干背杠5均匀地分布在钢模板3的下表面,钩头连接件4的上端挂设在钢筋桁架2上,其下端与钢模板3可拆卸连接,从而可将钢膜板3悬吊在钢筋桁架2上或从钢筋桁架2上拆除。上述的若干背杠5相互平行,并且其长度方向沿钢筋桁架2的长度方向设置,保证钢模板3的整体刚度。As shown in Figure 1 and Figure 2, it is a preferred embodiment of the truss system of the free-support steel formwork provided by the embodiment of the present invention. The truss system includes a steel truss 2 installed on the steel beam 1, a The steel formwork 3 and the hook connector 4 on it. The two ends of the steel truss 2 are welded on the steel beam 1, and the lower surface of the steel formwork 3 is welded with a number of back bars 5, which are evenly distributed on the lower surface of the steel formwork 3, and the upper end of the hook connector 4 is hung It is arranged on the steel bar truss 2, and its lower end is detachably connected with the steel formwork 3, so that the steel membrane plate 3 can be suspended on the steel bar truss 2 or removed from the steel bar truss 2. The above-mentioned back bars 5 are parallel to each other, and their length direction is arranged along the length direction of the steel bar truss 2 to ensure the overall rigidity of the steel formwork 3 .

上述实施例中,背杠5为C型钢或方钢管。在本实施方式中,背杠5为C型钢,将两个相邻的C型钢背对设置形成一组双拼背杠5,若干组双拼背杠5均匀地分布在钢模板3的下表面,使钢模板的整体刚度达到最佳效果。请参阅图6所示,拆卸钢模板3后,利用焊接在钢模板3上的背杠5相互错位嵌合堆放,背杠5对钢模板3起到限位作用,防止钢模板3滑落,保证在运输堆放过程中的稳定性和安全性。In the above-mentioned embodiment, the back bar 5 is a C-shaped steel or a square steel pipe. In this embodiment, the back bar 5 is a C-shaped steel, and two adjacent C-shaped steels are set up against each other to form a group of double back bars 5, and several groups of double back bars 5 are evenly distributed on the lower surface of the steel formwork 3 , so that the overall rigidity of the steel formwork can achieve the best effect. Please refer to Fig. 6, after the steel formwork 3 is disassembled, the back bars 5 welded on the steel formwork 3 are stacked in dislocation, and the back bars 5 play a limiting role on the steel formwork 3 to prevent the steel formwork 3 from slipping, ensuring Stability and safety during transportation and stacking.

请一同参阅图3所示,钩头连接件4包括挂件41和螺栓42。挂件41上具有钩口410,在将钢模板3安装使用时,通过钩口410将挂件41挂设在钢筋桁架2上,螺栓42的尾端依次穿过背杠5与钢模板3之后,与挂件41螺纹连接,螺栓42的头端抵靠在背杠5上。为了增强螺栓42与背杠5的连接效果,在螺栓42的头端与背杠5之间设置有垫片43,螺栓42穿设该垫片43之后再穿设背杠5。Please refer to FIG. 3 together, the hook connector 4 includes a hanger 41 and a bolt 42 . There is a hook mouth 410 on the hanger 41. When the steel formwork 3 is installed and used, the hanger 41 is hung on the steel bar truss 2 through the hook mouth 410. The hanger 41 is threaded, and the head end of the bolt 42 leans against the back bar 5 . In order to enhance the connection effect between the bolt 42 and the back bar 5 , a gasket 43 is arranged between the head end of the bolt 42 and the back bar 5 , and the bolt 42 passes through the gasket 43 before passing through the back bar 5 .

上述的钢筋桁架2包括连为一体的相互垂直的横梁21与立梁22。立梁22位于横梁21的两端,挂件41挂设在横梁21上,立梁22焊接在钢梁1上。在本实施方式中,设置有相互平行的两根横梁21,挂件41的上端两侧均具有钩口410,挂件位于两根横梁21之间,并且通过其两侧的钩口410分别挂设在两根横梁21上,保证挂件41挂设的稳定性。通过螺栓42与挂件41的螺纹旋合长度,可将钢模板3的高度调整至与钢梁1的上端面持平;待浇筑混凝土保护层(图中未示出)完成后,将螺栓42从挂件41上卸下,并从混凝土保护层中旋出,从而可将钢模板3从钢筋桁架2上拆卸,拆装方便,便于钢模板3的周转使用,节省了施工材料,降低了施工成本。The above-mentioned steel bar truss 2 includes vertical beams 21 and vertical beams 22 which are connected as a whole. The upright beam 22 is located at both ends of the crossbeam 21 , the pendant 41 is hung on the crossbeam 21 , and the upright beam 22 is welded on the steel beam 1 . In this embodiment, two beams 21 parallel to each other are provided, and both sides of the upper end of the pendant 41 have hook openings 410. The pendant is located between the two beams 21, and is respectively hung on the On the two beams 21, the stability of hanging the pendant 41 is guaranteed. The height of the steel formwork 3 can be adjusted to be equal to the upper end surface of the steel beam 1 by the threaded length of the bolt 42 and the hanger 41; 41, and unscrewed from the concrete cover, so that the steel formwork 3 can be disassembled from the steel bar truss 2, which is convenient for disassembly and assembly, convenient for the turnover of the steel formwork 3, saving construction materials and reducing construction costs.

请一同参阅图4所示,在横梁21上安装有用于支撑钢模板3的若干由塑料制成的支撑件6,该若干支撑件6沿横梁21的长度方向均匀分布。横梁21与钢模板3之间的空间用于浇筑混泥土保护层。支撑件6的大小依据混凝土工程规范定制,在螺栓42与挂件41旋紧的过程中,支撑件6可将钢模板3抵顶住,保证钢模板3的稳定性,并能保证钢模板3与横梁21之间具备所需的厚度来浇筑混泥土保护层。本实用新型实施例的支撑件6的一种实施方式为,支撑件6包括连为一体的支脚61和支架62,支脚61上的一边沿支撑钢模板3,这样,在浇筑混凝土保护层完成后,支撑件6上的支脚61底端几乎不外露,可以忽略,省去补浆或腻子的工序,降低施工成本。支架62可转动地卡接在横梁21上,其能够调整支架62的角度,以支撑钢模板3的上表面。请参阅图5所示,本实用新型实施例的另一种方式为,支撑件6’由水泥预制而成,该支撑件6’的上端包覆于横梁21上,并且其下表面水平,这样,在浇筑混凝土保护层完成后也无需进行补浆或腻子的工序。Please also refer to FIG. 4 , on the beam 21 are installed a number of supports 6 made of plastic for supporting the steel template 3 , and the supports 6 are evenly distributed along the length direction of the beam 21 . The space between the beam 21 and the steel formwork 3 is used for pouring the concrete protection layer. The size of the support member 6 is customized according to the concrete engineering specification. During the tightening process of the bolt 42 and the hanger 41, the support member 6 can support the steel formwork 3 to ensure the stability of the steel formwork 3 and ensure that the steel formwork 3 and the The required thickness is provided between the beams 21 to pour the concrete protection layer. One embodiment of the support 6 in the embodiment of the utility model is that the support 6 includes a leg 61 and a bracket 62 connected together, and one edge on the leg 61 supports the steel formwork 3, so that after the pouring of the concrete protective layer is completed , the bottom end of the support foot 61 on the support member 6 is hardly exposed, which can be ignored, and the process of grouting or putty is omitted, and the construction cost is reduced. The bracket 62 is rotatably clamped on the beam 21 , which can adjust the angle of the bracket 62 to support the upper surface of the steel formwork 3 . Please refer to Fig. 5, another form of the embodiment of the present utility model is that the support 6' is prefabricated by cement, the upper end of the support 6' is covered on the beam 21, and its lower surface is horizontal, so , After pouring the concrete protective layer, there is no need to carry out the process of grouting or putty.

综上所述,本实用新型实施例的免支撑钢模板的桁架系统具有如下优点:To sum up, the truss system of the free-support steel formwork in the embodiment of the utility model has the following advantages:

(1)便于钢模板3拆卸周转使用,减少对钢模板3的损坏,延长钢模板3的使用上命。(2)拆卸钢模板3的过程中无需拆除背杠5,提升了钢模板3的拆卸及周转安装速度,加快施工进度。(3)减少支撑件6上的支脚61在浇筑混凝土之后外露面积,从而省去补浆或腻子的工序,降低施工成本。(4)钢筋桁架2在较大跨度范围搭设时,无需采用大量脚手架进行支撑钢模板3,节省施工的工作量,安装方便。(5)焊接在钢模板3上的背杠5能够防止钢模板3在运输的过程中滑落,提高运输堆放的稳定性和安全性。(1) It is convenient for the steel formwork 3 to be disassembled and turned over for use, reducing damage to the steel formwork 3 and prolonging the service life of the steel formwork 3 . (2) There is no need to dismantle the back bar 5 during the dismantling of the steel formwork 3, which improves the disassembly and turnaround installation speed of the steel formwork 3, and speeds up the construction progress. (3) Reduce the exposed area of the feet 61 on the support member 6 after pouring concrete, thereby eliminating the process of grouting or putty, and reducing construction costs. (4) When the steel bar truss 2 is erected in a relatively large span, there is no need to use a large number of scaffolds to support the steel formwork 3, which saves construction workload and facilitates installation. (5) The back bar 5 welded on the steel formwork 3 can prevent the steel formwork 3 from slipping during transportation, and improve the stability and safety of transportation and stacking.

以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present utility model shall be included in this utility model. within the scope of protection of utility models.

Claims (10)

1. a kind of trussing for exempting to support steel form, including steel bar girder on girder steel and installed in the reinforcing bar purlin Steel form on frame, it is characterised in that the trussing also includes gib head connector, the lower surface welding point of the steel form Some back of the body thick sticks are furnished with, one end of the gib head connector is hung on the steel bar girder, its other end can with the steel form Dismounting connection.
2. the trussing as claimed in claim 1 for exempting to support steel form, it is characterised in that described some back of the body thick sticks are mutually put down OK, and length direction of its length direction along the steel bar girder is set.
3. the trussing as claimed in claim 2 for exempting to support steel form, it is characterised in that described some back of the body thick sticks are equably It is distributed in the lower surface of the steel form.
4. the trussing as claimed in claim 1 for exempting to support steel form, it is characterised in that the back of the body thick stick is C-type steel or side Steel pipe.
5. exempting from as described in any one in Claims 1-4 supports the trussing of steel form, it is characterised in that the steel The two ends of muscle truss are welded on girder steel, and the gib head connector includes suspension member and bolt, and the suspension member is hung on the reinforcing bar On truss, the tail end of the bolt sequentially passes through the back of the body thick stick with after steel form, being threadedly coupled with the suspension member, the bolt Head end be resisted against it is described the back of the body thick stick on.
6. the trussing as claimed in claim 5 for exempting to support steel form, it is characterised in that the steel bar girder includes being linked as The orthogonal crossbeam and vertical beam of one, the vertical beam are located at the two ends of the crossbeam, and the suspension member is hung on the crossbeam On, the vertical beam is welded on girder steel.
7. the trussing as claimed in claim 6 for exempting to support steel form, it is characterised in that being provided with the crossbeam is used for If supporting the dry support arm of the steel form.
8. the trussing as claimed in claim 7 for exempting to support steel form, it is characterised in that the support member includes being linked as one An edge on the leg and support of body, the leg supports the steel form, and the support is rotationally connected to the horizontal stroke Liang Shang.
9. exempt to support the trussing of steel form as claimed in claim 7 or 8, it is characterised in that if the dry support arm It is uniformly distributed along the length direction of the crossbeam.
10. exempt to support the trussing of steel form as claimed in claim 7 or 8, it is characterised in that the support member is by plastics It is made.
CN201621362079.3U 2016-12-12 2016-12-12 A kind of trussing for exempting to support steel form Expired - Fee Related CN206477497U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621362079.3U CN206477497U (en) 2016-12-12 2016-12-12 A kind of trussing for exempting to support steel form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621362079.3U CN206477497U (en) 2016-12-12 2016-12-12 A kind of trussing for exempting to support steel form

Publications (1)

Publication Number Publication Date
CN206477497U true CN206477497U (en) 2017-09-08

Family

ID=59757321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621362079.3U Expired - Fee Related CN206477497U (en) 2016-12-12 2016-12-12 A kind of trussing for exempting to support steel form

Country Status (1)

Country Link
CN (1) CN206477497U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760184A (en) * 2016-12-12 2017-05-31 中建钢构有限公司 A kind of trussing for exempting to support steel form
CN108979001A (en) * 2018-07-24 2018-12-11 昆山市信诺达精密模具有限公司 A kind of steady type longitudinal bracing reinforcing bar system
CN110281382A (en) * 2019-07-25 2019-09-27 万特福建筑构件有限公司 A kind of PC component girder rib sheath

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760184A (en) * 2016-12-12 2017-05-31 中建钢构有限公司 A kind of trussing for exempting to support steel form
CN108979001A (en) * 2018-07-24 2018-12-11 昆山市信诺达精密模具有限公司 A kind of steady type longitudinal bracing reinforcing bar system
CN110281382A (en) * 2019-07-25 2019-09-27 万特福建筑构件有限公司 A kind of PC component girder rib sheath
CN110281382B (en) * 2019-07-25 2024-01-23 万特福建筑构件有限公司 Truss rib sheath for PC component

Similar Documents

Publication Publication Date Title
CN105569331B (en) A kind of simple support method of concrete cylindrical template
CN201614738U (en) A combined support device for steel reinforced concrete transfer beam formwork
CN204401997U (en) A kind of suspension type ceiling construction scaffold
CN103352563A (en) Self plate-bearing type steel bar mesh support combined template and construction method thereof
CN208122301U (en) A kind of floor support plate supporting apparatus
CN102661019A (en) Heat preservation and decoration integrated construction method for outer wall of building
CN110700112A (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method
CN201406844Y (en) Support of middle flange plate construction formwork of concrete-steel beam
CN206477497U (en) A kind of trussing for exempting to support steel form
CN111691300A (en) A concrete placement support device for steel-concrete composite beam
CN106284103A (en) Steel reinforced concrete combination beam roof steel bar concrete high-altitude cantilever pouring construction method
CN108086674A (en) A kind of roof boarding hangs the construction method of mould and roof boarding
CN107237437A (en) Combined type reinforced truss floor support plate and its construction method
CN103321155A (en) Viaduct pier construction platform system and method for building system and pouring piers
CN205857697U (en) The anti-form bracing constructing device hanging template
CN205857660U (en) Steel structure cornices exterior finish construction suspension platform
CN206438764U (en) One kind is exempted to support detachable steel bar truss floor support plate
CN107401279A (en) Disposable one-piece casting staircase wall ladder combined steel formwork installation construction method
CN204753397U (en) Temporary mounting hanger for steel box bridge
CN203307733U (en) Construction platform system of concrete pier of viaduct
CN206737229U (en) A kind of assembled architecture floor
CN103015713B (en) High-altitude-spanned steel reinforced concrete truss template
CN209568359U (en) A kind of falsework for the construction of outer-enwraped type Guard fence base
CN103615103A (en) Hanging type assembled movable platform
CN205100550U (en) Detachable no steel bar truss lifts by crane isolated plant

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Truss system for support-free steel template

Effective date of registration: 20180129

Granted publication date: 20170908

Pledgee: Bank of Beijing Limited by Share Ltd. Shenzhen branch

Pledgor: China Construction Steel Structure Corp.,Ltd.

Registration number: 2018440020010

PE01 Entry into force of the registration of the contract for pledge of patent right
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Science And Industry Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Futian District Che Kung Temple Binhe Tairan industry tipping 17 storey building No. 17A

Patentee before: China Construction Steel Structure Corp.,Ltd.

CP03 Change of name, title or address
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20221207

Granted publication date: 20170908

Pledgee: Bank of Beijing Limited by Share Ltd. Shenzhen branch

Pledgor: China Construction Steel Structure Corp.,Ltd.

Registration number: 2018440020010

PC01 Cancellation of the registration of the contract for pledge of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170908

CF01 Termination of patent right due to non-payment of annual fee