CN206477204U - Punish the soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in bank - Google Patents

Punish the soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in bank Download PDF

Info

Publication number
CN206477204U
CN206477204U CN201720122015.4U CN201720122015U CN206477204U CN 206477204 U CN206477204 U CN 206477204U CN 201720122015 U CN201720122015 U CN 201720122015U CN 206477204 U CN206477204 U CN 206477204U
Authority
CN
China
Prior art keywords
pile
embankment
soft soil
anchor
pull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720122015.4U
Other languages
Chinese (zh)
Inventor
陈昌富
毛凤山
张根宝
赵洪波
李欣
苗晓燕
胡政博
刘俊
刘一俊
高傑
梁晓腾
黄佳彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CN201720122015.4U priority Critical patent/CN206477204U/en
Application granted granted Critical
Publication of CN206477204U publication Critical patent/CN206477204U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本实用新型涉及岸边软土地基处理技术领域,尤其涉及一种处治岸边软土路基的锚拉式桩承加筋土挡墙路堤;包括垫层(9)、路堤(10),该路堤还包括:设在倾斜硬层深端的支护桩(1)、设在倾斜硬层浅端的承重桩(4)、与所述支护桩(1)以及承重桩(4)顶端连接的桩帽(5)、交叉固定于所述桩帽(5)中的拉杆、预应力锚杆(6),所述预应力锚杆(6)一端固定于倾斜硬层中,预应力锚杆(6)的另一端固定在软土浅端承重桩的桩帽上、水平双向加筋体(8)、以及加筋土挡墙(3),在倾斜硬层(12)最深端的一排支护桩(1)通过联系梁(2)相互连接固定;大大提高了地基的稳固性。

The utility model relates to the technical field of shore soft soil foundation treatment, in particular to an anchor-pull type pile bearing reinforced soil retaining wall embankment for treating shore soft soil foundation; It also includes: a support pile (1) arranged at the deep end of the inclined hard layer, a load-bearing pile (4) arranged at the shallow end of the inclined hard layer, and a pile cap connected to the top of the support pile (1) and the load-bearing pile (4) (5), cross-fixed pull rods and prestressed anchors (6) in the pile cap (5), one end of the prestressed anchors (6) is fixed in the inclined hard layer, and the prestressed anchors (6) The other end is fixed on the pile cap of the load-bearing pile at the shallow end of the soft soil, the horizontal two-way reinforced body (8), and the reinforced soil retaining wall (3), and a row of support piles at the deepest end of the inclined hard layer (12) ( 1) The connecting beams (2) are connected and fixed; the stability of the foundation is greatly improved.

Description

处治岸边软土路基的锚拉式桩承加筋土挡墙路堤Embankment of Anchor-pull Pile Bearing Reinforced Soil Retaining Wall Treating Soft Soil Subgrade on the Bank

技术领域technical field

本实用新型涉及岸边软土地基处理技术领域,尤其涉及一种处治下卧有倾斜硬层软土路基的锚拉式桩承加筋土挡墙路堤。The utility model relates to the technical field of shore soft soil foundation treatment, in particular to an anchor pull type pile-bearing reinforced soil retaining wall embankment for treating soft soil subgrades with inclined hard layers underneath.

背景技术Background technique

在公路、铁路等工程领域中,桩承式加筋路堤被国内外广泛用于深厚或有限厚软土区的路基工程中,并取得了良好效果。现有桩承式加筋路堤的做法是:先在软土中设置桩体,再在地表桩顶处现浇钢筋混凝土桩帽,然后在桩帽上铺设水平加筋体和垫层,最后在水平加筋垫层上施工路堤。如果软土厚度有限,软土层下存在有水平硬层,则将桩体置于硬层顶面,或嵌入硬层中。大量的理论分析和工程实践表明:在较高路堤荷载作用下,外侧桩会受到较大的水平推力,仅靠桩帽上水平加筋体与桩帽间的摩阻力,往往不足以约束路堤两侧边桩的水平位移,甚至桩体还会因抗弯能力不够而产生弯折破坏,并进而造成路堤沉降开裂或失稳破坏。为此,实用新型专利“一种新型桩承式加筋技术处理软土路基的方法”(申请号:201010533647.2)提出将水平加筋体固定于桩帽中以提高对外侧桩的约束力;实用新型专利“软土地基组合桩网结构”(申请号:201420055949.7)通过将路堤外侧边桩改为嵌岩的钻孔灌注桩,同时在桩顶套入用连接梁连起来的导筒将各根桩连接起来,以此来限制桩的侧移,实用新型专利“钢筋混凝土桩-素混凝土桩分区组合式复合地基”(申请号:201610064759.5)则通过在外侧一定范围设置钢筋混凝土桩来提高外侧桩的抗弯能力。现有的桩承式路堤技术和上述专利提出的改进措施是针对水平层状软土地基而提出的,将它们用于处理下卧有水平硬层软土路基是有效的。对于下卧有倾斜硬层的软土路基,陈昌富等人发表在《中南大学学报(自然科学版)》2016年第11期上的“岸边软土区碎石桩复合地基沉降正交数值试验分析”论文中报道了一种采用碎石桩复合地基的解决方案,但经分析计算发现,采用该方案时路基仍将产生较大的沉降和差异沉降,而且在高路堤荷载作用下,路基稳定性也难以得到保证。因此,采用现有技术处治如图1所示下卧有倾斜硬层的软土路基,则存在如下突出问题:In engineering fields such as highways and railways, pile-supported reinforced embankments are widely used in subgrade projects in deep or limited soft soil areas at home and abroad, and good results have been achieved. The way of the existing pile-supported reinforced embankment is: first set the pile body in soft soil, then cast in-situ reinforced concrete pile cap at the top of the surface pile, then lay horizontal reinforcement and cushion on the pile cap, and finally place the pile cap on the pile cap. Construction of embankment on horizontally reinforced cushion. If the thickness of the soft soil is limited and there is a horizontal hard layer under the soft soil layer, the pile body is placed on the top of the hard layer or embedded in the hard layer. A large number of theoretical analysis and engineering practice show that under the action of higher embankment loads, the outer piles will receive a greater horizontal thrust, and the frictional resistance between the horizontal reinforcement on the pile cap and the pile cap is often not enough to restrain the two sides of the embankment. The horizontal displacement of the side piles, and even the pile body will cause bending damage due to insufficient bending resistance, and then cause embankment settlement cracking or instability damage. For this reason, the utility model patent "A New Type of Pile Bearing Reinforcement Technology for Treating Soft Soil Subgrade" (application number: 201010533647.2) proposes to fix the horizontal reinforcement body in the pile cap to improve the binding force on the outer pile; practical The new patent "Soft Soil Foundation Combination Pile Network Structure" (application number: 201420055949.7) changes the side piles on the outside of the embankment into rock-socketed bored piles, and at the same time inserts guide cylinders connected by connecting beams on the top of the piles to connect each The root piles are connected to limit the lateral movement of the piles. The utility model patent "reinforced concrete pile-plain concrete pile partition combined composite foundation" (application number: 201610064759.5) improves the outer surface by setting reinforced concrete piles in a certain range on the outside. The bending resistance of the pile. The existing pile-supported embankment technology and the improvement measures proposed in the above-mentioned patents are proposed for the horizontal layered soft soil foundation, and it is effective to use them to deal with the underlying soft soil roadbed with horizontal hard layers. For the soft soil subgrade with inclined hard layer underneath, Chen Changfu et al. published in "Journal of Central South University (Natural Science Edition)" 2016 No. 11 "Orthogonal Numerical Experiment of Settlement of Gravel Pile Composite Foundation in Soft Soil Area on the Bank". Analysis” paper reported a solution using gravel pile composite foundation, but it was found through analysis and calculation that the subgrade will still have large settlement and differential settlement when this scheme is adopted, and the subgrade is stable under high embankment loads. Sex is also difficult to guarantee. Therefore, adopt existing technology to deal with the soft soil embankment that has inclined hard layer lying below as shown in Figure 1, then there are following prominent problems:

①在高路堤荷载作用下,由于软土层一边浅一边厚,复合地基受力不对称,这会导致软土较厚边外侧桩产生较大侧移而使路堤不均匀沉降、开裂或失稳;①Under the action of high embankment load, because the soft soil layer is shallow on one side and thick on the other, the force on the composite foundation is asymmetrical, which will cause a large lateral movement of the outer piles on the thicker side of the soft soil, resulting in uneven settlement, cracking or instability of the embankment ;

②软土较厚边的路堤边坡越往外延伸软土越厚,需要的桩越长,不但使桩的用量增加,而且桩更易造成弯折甚至屈曲破坏。②The embankment slope with thicker soft soil extends outward, the thicker the soft soil becomes, and the longer the piles are required, which not only increases the amount of piles used, but also makes the piles more likely to cause bending or even buckling damage.

实用新型内容Utility model content

本实用新型的目的在于提供一种处治岸边软土路基的锚拉式桩承加筋土挡墙路堤,解决了采用现有技术处治下卧有倾斜硬层软土路基时,软土较厚边外侧桩位移较大、易产生弯折或屈曲破坏,以及路堤不均匀沉降较大、稳定性难以保证等问题。The purpose of the utility model is to provide an anchor-pull type pile-bearing reinforced soil retaining wall embankment for treating soft soil subgrades on the bank, which solves the problem of thicker soft soil when the existing technology is used to treat soft soil subgrades with inclined hard layers underneath. The displacement of piles outside the side is large, prone to bending or buckling damage, and the uneven settlement of the embankment is large, and the stability is difficult to guarantee.

本实用新型是这样实现的,一种处治岸边软土路基的锚拉式桩承加筋土挡墙路堤,包括垫层、路堤,该路堤还包括:设在倾斜硬层深端的支护桩、设在倾斜硬层浅端的承重桩、与所述支护桩以及承重桩顶端连接的桩帽、交叉固定于所述桩帽中的拉杆、预应力锚杆、水平双向加筋体、以及加筋土挡墙;所述预应力锚杆一端固定于倾斜硬层中,预应力锚杆的另一端固定在软土浅端承重桩的桩帽上;在倾斜硬层最深端的一排支护桩通过联系梁相互连接固定;设在倾斜硬层最深端的所述支护桩还设有伸出段;所述支护桩是钢筋混凝土桩。The utility model is achieved in this way, an anchor-pull type pile-supported reinforced soil retaining wall embankment for treating soft soil subgrades on the bank, including a cushion layer and an embankment, and the embankment also includes: supporting piles arranged at the deep end of the inclined hard layer , a load-bearing pile arranged at the shallow end of the inclined hard layer, a pile cap connected with the support pile and the top of the load-bearing pile, a tie rod crossed and fixed in the pile cap, a prestressed anchor rod, a horizontal two-way reinforced body, and a reinforcement Reinforced soil retaining wall; one end of the prestressed anchor rod is fixed in the inclined hard layer, and the other end of the prestressed anchor rod is fixed on the pile cap of the shallow end load-bearing pile in soft soil; a row of support piles at the deepest end of the inclined hard layer The connecting beams are connected and fixed; the support piles arranged at the deepest end of the inclined hard layer are also provided with an extending section; the support piles are reinforced concrete piles.

本实用新型的进一步技术方案是:所述承重桩呈正方形布桩,嵌入倾斜硬层最小深度不小于0.5m;所述承重桩为粘结材料桩。A further technical solution of the present invention is: the load-bearing piles are arranged in a square shape, and the minimum depth embedded in the inclined hard layer is not less than 0.5m; the load-bearing piles are bonded material piles.

本实用新型的进一步技术方案是:所述桩帽为正方形,固定于所述承重桩以及支护桩位于地面的桩顶处,其两条对角线分别位于所述路堤的横向和纵向。A further technical solution of the utility model is: the pile cap is a square, fixed on the pile top of the load-bearing pile and the support pile on the ground, and its two diagonals are respectively located in the horizontal and vertical directions of the embankment.

本实用新型的进一步技术方案是:所述拉杆包括横向拉杆以及纵向拉杆,所述横向拉杆和所述纵向拉杆交叉固定于所述桩帽中;所述横向拉杆还伸至所述联系梁中并与之固定连接。A further technical solution of the utility model is: the tie rods include a transverse tie rod and a longitudinal tie rod, and the transverse tie rods and the longitudinal tie rods are cross-fixed in the pile cap; the transverse tie rods also extend into the connecting beam and permanently connected to it.

本实用新型的进一步技术方案是:所述水平双向加筋体为至少一层的高强双向土工格栅,纵向拉筋与路堤横向成45°斜交,横向拉筋与路堤横向成45°斜交。The further technical solution of the utility model is: the horizontal two-way reinforcement body is at least one layer of high-strength two-way geogrid, the longitudinal reinforcement and the embankment form a 45° oblique cross direction, and the transverse reinforcement and the embankment form a 45° oblique cross direction .

本实用新型的进一步技术方案是:所述加筋土挡墙的面板紧靠所述支护桩伸出段,所述加筋土挡墙在所述支护桩伸出段范围内设置短筋带,在所述短筋带的上面设置长筋带。The further technical scheme of the utility model is: the panel of the reinforced earth retaining wall is close to the extension section of the support pile, and the reinforced earth retaining wall is provided with short ribs within the extension section of the support pile The belt is provided with a long rib on the top of the short rib.

本实用新型的进一步技术方案是:所述支护桩伸出段长度为所述加筋土挡墙高度的1/3~1/2;所述短筋带长度为长筋带长度的1/2~3/4。A further technical solution of the present invention is: the length of the extension section of the support pile is 1/3 to 1/2 of the height of the reinforced earth retaining wall; the length of the short rib is 1/2 of the length of the long rib 2~3/4.

本实用新型的进一步技术方案是:所述横向拉杆和纵向拉杆为钢筋、钢绞线、纤维增强塑料筋或钢筋混凝土拉杆。A further technical solution of the utility model is: the horizontal tie rod and the longitudinal tie rod are steel bars, steel strands, fiber reinforced plastic bars or reinforced concrete tie rods.

本实用新型的有益效果是:通过设置纵、横向拉杆将桩连接成一个整体,大大提高了地基的稳固性;通过在与支护桩相连的横向拉杆的另一端设置预应力锚杆,既限制了支护桩的侧移,又极大地降低了内侧承重桩因路堤荷载产生的水平推力,改善了整个地基的受力特性,从而大大降低了路基沉降和不均匀沉降,保证了路堤稳定性;去掉了较厚软土区长细比较大的桩,使外侧桩长度变短,抗弯能力提高,同时用桩量也有较大幅度的降低;通过在最外侧支护桩上设置伸出段支挡在加筋土挡墙上,即分担了一部分侧压力,又改善了桩的弯矩分布;为在下卧有倾斜硬层软土区修筑路基提供了一种技术经济优良的可靠解决方案。The beneficial effects of the utility model are: the piles are connected as a whole by setting longitudinal and transverse tie rods, which greatly improves the stability of the foundation; The lateral displacement of the supporting piles is greatly reduced, and the horizontal thrust of the inner load-bearing piles due to the load of the embankment is greatly reduced, and the mechanical characteristics of the entire foundation are improved, thereby greatly reducing the settlement and uneven settlement of the embankment, and ensuring the stability of the embankment; The piles with relatively large length and slenderness in the thicker soft soil area are removed, the length of the outer piles is shortened, the bending resistance is improved, and the amount of piles is also greatly reduced; Retaining on the reinforced soil retaining wall not only shares part of the lateral pressure, but also improves the distribution of the bending moment of the pile; it provides a reliable technical and economical solution for building subgrades in soft soil areas with inclined hard layers underneath.

附图说明Description of drawings

图1为现有处治有倾斜硬层软土路基的桩承式路堤剖面图;Fig. 1 is the sectional view of the pile-supported embankment with inclined hard layer soft soil embankment for existing treatment;

图2是本实用新型提供的一种处治岸边软土路基的锚拉式桩承加筋土挡墙路堤剖面图;Fig. 2 is a sectional view of an anchor-pull type pile bearing reinforced soil retaining wall embankment for treating soft soil embankment provided by the utility model;

图3是处治岸边软土路基的锚拉式桩承加筋土挡墙路堤的桩帽、拉杆与水平加筋体布置平面图。Fig. 3 is a layout plan view of pile caps, tie rods and horizontal reinforcements of the anchor-pull type pile-supported reinforced soil retaining wall embankment for treating soft soil embankment on the bank.

附图标记:1-支护桩;101-伸出段;2-联系梁;3-加筋土挡墙;301-面板;302-短筋带;303-长筋带;4-承重桩;5-桩帽;6-预应力锚杆;701-横向拉杆;702-纵向拉杆;8-水平双向加筋体;9-垫层;10-路堤;11-软土层;12-倾斜硬层。Reference signs: 1-supporting pile; 101-extending section; 2-connecting beam; 3-reinforced soil retaining wall; 301-panel; 302-short rib; 303-long rib; 4-load-bearing pile; 5-pile cap; 6-prestressed anchor rod; 701-transverse tie rod; 702-longitudinal tie rod; 8-horizontal two-way reinforcement; 9-cushion layer; 10-embankment; 11-soft soil layer; 12-inclined hard layer .

具体实施方式detailed description

图1-图2示出了一种处治岸边软土路基的锚拉式桩承加筋土挡墙路堤,该路堤包括:在软土层较深一侧的路堤下设置一排~四排支护桩1,最外一排支护桩在地表处设置有联系梁2将其连接,对于内侧支护桩,则在地表桩顶处设置桩帽5;最外一排支护桩带有伸出段101,伸出段101长度等于(1/3~1/2)倍加筋土挡墙3的高度;支护桩1采用预制或者现浇的钢筋混凝土桩,桩径300mm~1000mm。在路堤范围内、支护桩1的内侧设置承重桩4,采用正方形布桩,其嵌入倾斜硬层最小深度0.5m;承重桩4采用预制桩,或者现浇钢筋混凝土桩,或者现浇素混凝土桩,或者现浇水泥粉煤灰碎石桩,或者水泥土桩,或者加筋水泥土桩,或者塑料套管灌注桩,或是注浆微型桩等各种形式的粘结材料桩;桩帽5为正方形,固定于所述承重桩4或支护桩1位于地面的桩顶处,其两条对角线分别位于路堤10的横向和纵向;横向拉杆701和纵向拉杆702交叉固定于承重桩4和支护桩1的桩帽5中,横向拉杆701还伸至联系梁2中并与之固接;横向拉杆701和纵向拉杆702采用钢筋,或者纤维增强塑料筋(FRP),或者钢绞线,或者钢筋混凝土杆;在软土较浅端承重桩4的桩帽上设置预应力锚杆6,预应力锚杆6的一端固定于下卧倾斜硬岩土层中,对所述预应力锚杆6施加预应力,并通过预应力锚杆另一端将其锁定于位于软土较浅端承重桩的桩帽上,利用锚杆提供的锚固力通过与承重桩4和支护桩1相连的横向拉杆701约束支护桩1的侧向位移;填筑第一层砂石垫层并压实,使其顶面与桩帽5顶面平齐,砂石最大粒径小于5cm;在桩帽5底面铺设一层高强刚塑双向土工格栅,其纵、横向拉筋与路堤横向成45°斜交;填筑第二层砂石垫层并压实,厚度为20cm~30cm,砂石粒径大于加筋体的孔径;填筑路堤10,填筑高度3m~8m;与此同步,施工加筋土挡墙3,使加筋土挡墙3的面板301紧靠支护桩伸出段101;同时,在支护桩伸出段101范围内设置短筋带 302,在短筋带302的上面设置长筋带303,短筋带302的长度等于(1/2~3/4)倍长筋带 303的长度。Fig. 1-Fig. 2 show a kind of anchor pull type pile bearing reinforced earth retaining wall embankment for treating the soft soil embankment on the bank, the embankment includes: one row to four rows are arranged under the embankment on the deeper side of the soft soil layer Supporting piles 1, the outermost row of supporting piles is provided with a connecting beam 2 on the surface to connect them, and for the inner supporting piles, a pile cap 5 is set at the top of the surface pile; the outermost row of supporting piles has The extension section 101, the length of the extension section 101 is equal to (1/3-1/2) times the height of the reinforced earth retaining wall 3; the support pile 1 is a prefabricated or cast-in-place reinforced concrete pile with a pile diameter of 300mm-1000mm. Load-bearing piles 4 are arranged inside the embankment and inside the support pile 1, using square piles, and the minimum depth of which is embedded in the inclined hard layer is 0.5m; load-bearing piles 4 are prefabricated piles, or cast-in-place reinforced concrete piles, or cast-in-place plain concrete piles, or cast-in-situ cement fly ash gravel piles, or cement-soil piles, or reinforced cement-soil piles, or plastic casing pouring piles, or grouting micro piles and other forms of bonding material piles; pile caps 5 is a square, fixed on the load-bearing pile 4 or the pile top of the support pile 1 on the ground, and its two diagonal lines are respectively located in the horizontal and vertical directions of the embankment 10; 4 and the pile cap 5 of the supporting pile 1, the transverse tie rod 701 is also extended to the connection beam 2 and fixedly connected with it; line, or a reinforced concrete rod; a prestressed anchor 6 is set on the pile cap of the load-bearing pile 4 at the shallower end of the soft soil, and one end of the prestressed anchor 6 is fixed in the underlying inclined hard rock soil layer. The anchor rod 6 applies prestress, and locks it on the pile cap of the load-bearing pile at the shallower end of the soft soil through the other end of the prestressed anchor rod, and uses the anchoring force provided by the anchor rod to connect the load-bearing pile 4 and the support pile 1 The horizontal tie rod 701 constrains the lateral displacement of the support pile 1; the first layer of sand and gravel cushion is filled and compacted so that its top surface is flush with the top surface of the pile cap 5, and the maximum particle size of the sand and gravel is less than 5cm; A layer of high-strength rigid-plastic two-way geogrid is laid on the bottom of hat 5, and its longitudinal and transverse reinforcements are obliquely intersected with the embankment at 45 degrees; The particle size is larger than the pore diameter of the reinforced body; the embankment 10 is filled, and the filling height is 3m to 8m; at the same time, the reinforced soil retaining wall 3 is constructed so that the panel 301 of the reinforced soil retaining wall 3 protrudes close to the support piles Section 101; Simultaneously, short rib 302 is set within the scope of supporting pile extension section 101, long rib 303 is set above short rib 302, and the length of short rib 302 is equal to (1/2~3/4) Double the length of the ribs 303.

以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present utility model shall be included in this utility model. within the scope of protection of utility models.

Claims (8)

1. a kind of pull-type pile reinforced earth barricade embankment of the soft soil roadbed anchor in punishment bank, including bed course (9), embankment (10), its It is characterised by:The embankment also includes:It is located at and tilts the support pile (1) of hard formation deep end, is located at the bearing pile for tilting hard formation shallow end (4), drawing of the pile cover (5), cross-fixing being connected with the support pile (1) and bearing pile (4) top in the pile cover (5) Bar, prestressed anchor (6), horizontal bidirectional reinforcing body (8) and reinforced earth bulkhead (3);Described prestressed anchor (6) one end is solid Due to tilting in hard formation, the other end of prestressed anchor (6) is fixed on the pile cover of weak soil shallow end bearing pile;Tilting hard formation (12) row's support pile (1) of most deep end is interconnected and fixed by connection beam (2);It is located at the branch for tilting hard formation most deep end Fender pile (1) is additionally provided with section of stretching out (101);The support pile (1) is reinforced concrete pile.
2. a kind of soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in punishment bank according to claim 1, it is special Levy and be:The bearing pile (4) is square to be laid out pile, and the embedded hard formation minimum-depth that tilts is not less than 0.5m;The bearing pile (4) For binding material stake.
3. a kind of soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in punishment bank according to claim 1, it is special Levy and be:The pile cover (5) is square, is fixed on the bearing pile (4) and support pile (1) is located at the stake top on ground, Its two diagonal are respectively positioned at the horizontal and vertical of the embankment (10).
4. a kind of soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in punishment bank according to claim 1, it is special Levy and be:The pull bar includes cross-tie (701) and longitudinal tie (702), the cross-tie (701) and the longitudinal direction Pull bar (702) cross-fixing is in the pile cover (5);The cross-tie (701) also extends in the connection beam (2) and therewith It is fixedly connected.
5. a kind of soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in punishment bank according to claim 1, it is special Levy and be:The horizontal bidirectional reinforcing body (8) is at least one layer of high-strength direction earthwork grille, longitudinal lacing wire and embankment laterally into 45 ° of obliques, the horizontal oblique at 45 ° of horizontal lacing wire and embankment.
6. a kind of soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in punishment bank according to claim 5, it is special Levy and be:The panel (301) of the reinforced earth bulkhead (3) abuts the support pile section of stretching out (101), the reinforced earth bulkhead (3) short rib tape (302) is set in the range of the support pile section of stretching out (101), length is set above the short rib tape (302) Rib tape (303).
7. a kind of soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in punishment bank according to claim 6, it is special Levy and be:Support pile section of stretching out (101) length is the 1/3~1/2 of the reinforced earth bulkhead (3) height;The short rib tape (302) length is the 1/2~3/4 of long rib tape (303) length.
8. a kind of soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in punishment bank according to claim 5, it is special Levy and be:The cross-tie (701) and longitudinal tie (702) are reinforcing bar, steel strand wires, fiber reinforced plastic rod or reinforced concrete Native pull bar.
CN201720122015.4U 2017-02-10 2017-02-10 Punish the soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in bank Withdrawn - After Issue CN206477204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720122015.4U CN206477204U (en) 2017-02-10 2017-02-10 Punish the soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in bank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720122015.4U CN206477204U (en) 2017-02-10 2017-02-10 Punish the soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in bank

Publications (1)

Publication Number Publication Date
CN206477204U true CN206477204U (en) 2017-09-08

Family

ID=59748637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720122015.4U Withdrawn - After Issue CN206477204U (en) 2017-02-10 2017-02-10 Punish the soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in bank

Country Status (1)

Country Link
CN (1) CN206477204U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106702840A (en) * 2017-02-10 2017-05-24 湖南大学 Embankment of Anchor-pull Pile Bearing Reinforced Soil Retaining Wall Treating Soft Soil Subgrade on the Bank
CN112049009A (en) * 2020-08-13 2020-12-08 中铁大桥勘测设计院集团有限公司 Shallow formula raft type anchorage that buries

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106702840A (en) * 2017-02-10 2017-05-24 湖南大学 Embankment of Anchor-pull Pile Bearing Reinforced Soil Retaining Wall Treating Soft Soil Subgrade on the Bank
CN112049009A (en) * 2020-08-13 2020-12-08 中铁大桥勘测设计院集团有限公司 Shallow formula raft type anchorage that buries
CN112049009B (en) * 2020-08-13 2022-11-18 中铁大桥勘测设计院集团有限公司 Shallow formula raft type anchorage that buries

Similar Documents

Publication Publication Date Title
CN106702840B (en) Anchor-pull type pile-bearing reinforced earth retaining wall embankment for treating soft soil roadbed on shoreside
CN101476325B (en) Rigid Grid and Pile Composite Foundation and Its Applied Method for Soft Soil Foundation Reinforcement
CN102619150A (en) Anchored roadbed widening method
CN215977211U (en) Structure is handled to compound foundation of tubular pile combination cement mixing pile
CN114990948B (en) A Construction Method for Reinforcing Soaked Subgrade with Reinforcement
CN202323922U (en) Tilted stratum soft foundation reinforcing structure of high-speed railway
CN108824097A (en) Prefabricated GFRP pipe concrete stake and armoured concrete slab overhead type roadbed pile slab structure
CN111560970B (en) Well-shaped ground beam refuge foundation and fixing structure thereof
CN203270559U (en) Roadbed structure of screw pile network structure composite foundation
CN202809501U (en) Reinforced load reducing structure of motorway high filling culvert in mountainous area
CN108517882B (en) A kind of geocell reinforced high and steep side slope and construction method thereof
CN207714057U (en) A kind of anti-settling road structure
CN114960305B (en) A high-speed railway foundation expansion soil reinforcement structure and construction method
CN208803305U (en) Prefabricated GFRP tubular concrete pile and concrete slab top-mounted subgrade pile-slab structure
CN109487793A (en) Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment
CN113737592B (en) Highway subgrade widening structure
CN215104344U (en) Zero investigation of land road bed widens structure suitable for soft foundation
CN206233257U (en) A Combined Composite Foundation for Reinforcing Inclined Soft Foundation
CN109113069A (en) Precipitous section tunnel immediately adjacent to bridge foundation pit support device and construction method
CN205662796U (en) Highway medium -and -large -sized solution cavity punishment structure that underlies
CN205223763U (en) Reinforced structure of retaining wall and road bed
CN208279959U (en) Pile formula barricade embankment
CN114808583B (en) Submerged roadbed and construction method thereof
CN201343736Y (en) Rigid grid and pile composite foundation
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170908

Effective date of abandoning: 20220524

AV01 Patent right actively abandoned

Granted publication date: 20170908

Effective date of abandoning: 20220524