CN206457728U - Bearing construction combined movable security protection - Google Patents
Bearing construction combined movable security protection Download PDFInfo
- Publication number
- CN206457728U CN206457728U CN201720054458.4U CN201720054458U CN206457728U CN 206457728 U CN206457728 U CN 206457728U CN 201720054458 U CN201720054458 U CN 201720054458U CN 206457728 U CN206457728 U CN 206457728U
- Authority
- CN
- China
- Prior art keywords
- fixing pipe
- protective frame
- security protection
- bearing
- combined movable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title abstract description 16
- 230000001681 protective effect Effects 0.000 claims abstract description 26
- 210000003205 muscle Anatomy 0.000 claims description 15
- 230000000694 effects Effects 0.000 claims description 14
- 238000004513 sizing Methods 0.000 claims description 12
- 238000003780 insertion Methods 0.000 claims description 8
- 230000037431 insertion Effects 0.000 claims description 8
- 230000015572 biosynthetic process Effects 0.000 abstract description 3
- 238000000034 method Methods 0.000 abstract description 2
- 238000009434 installation Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 230000007797 corrosion Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 206010000372 Accident at work Diseases 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of construction combined movable security protection of bearing, include the protective frame of the spaced arrangement of two or more, the anti-falling railing of more than one is removably connected between the two neighboring protective frame, the protective frame includes the perpendicular strut of more than two, it is connected between the upper end of adjacent two perpendicular struts by cruciform fastening for falsework between singletree, the bottom of adjacent two perpendicular struts and is connected with bent cap.Intrinsic safety full protection, use cruciform fastening for falsework, not only facilitate connection, and the resistance to overturning of protective frame can be increased, the protective frame of formation combines to form firm support with bent cap, stablize high-strength supporting role so as to be provided for anti-falling railing, and anti-falling railing can not only then form guard rail, and safety belt can be hung, ensure the safety of people, filled up bearing system construction safety and effectively protected blank, can save the safeguard procedures effective time and safeguard using expense more than 60%, and value can be dominated be obviously improved saving input cost.
Description
Technical field
The utility model is related to bridge construction safety measure field, relates in particular to a kind of bearing construction combined movable
Security protection.
Background technology
Safety measure is essential in bridge construction process, and security service work is arrived while construction quality progress monitoring
Position is the key of guarantee project overall efficiency.
For the construction project of bridge, because the bearing pad stone and bearing installation fall arrest in bridge engineering construction are prevented
Shield is directed to security protection, and the necessary demand to security protection is quite big, it is necessary to which each part-to-item project will match phase
How the safety measure answered, fill up the problems such as following effective and safe of bent cap above Installation of beam slab is protected, it is to avoid cause because risk is pre-
Industrial accident, the outward appearance of controlling generation not in place are defective, steel pipe expends excessive using coefficient of losses, artificial effective time
Etc. unnecessary cost, to waste the phenomenon such as big be urgent problem to be solved.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of simple in construction, convenient disassembly, security protection effect
Good bearing construction combined movable security protection.
In order to solve the above-mentioned technical problem, the utility model is adopted the following technical scheme that:Bearing construction combined movable peace
Full protection, includes being removably connected with one between the protective frame of the spaced arrangement of two or more, the two neighboring protective frame
Anti-falling railing more than root, the protective frame is included between the perpendicular strut of more than two, the upper end of adjacent two perpendicular struts
It is connected with by cruciform fastening for falsework between singletree, the bottom of adjacent two perpendicular struts and is connected with bent cap.
Further, the perpendicular strut is provided with sizing fixing pipe, and the anti-falling railing is plugged on the sizing fixing pipe
It is interior, the part that the first fixing muscle activity is shaped in fixing pipe through the insertion of the sizing fixing pipe and the anti-falling railing, with
This realizes being detachably connected between the anti-falling railing and the protective frame.
Further, pull bar is also removably connected between the adjacent two perpendicular struts, the pull bar is located at bent cap
Top.
Further, the top of the perpendicular strut is arranged with perpendicular fixing pipe, and the perpendicular fixing pipe is provided with horizontal fixing pipe, institute
State pull bar to be plugged in the horizontal fixing pipe, the top of the perpendicular strut is provided with two through hole, and two through hole is located at described perpendicular solid respectively
The upper and lower of fixed tube, activity passes through two through hole to two second fixing muscles respectively, the 3rd fixing muscle activity through the horizontal fixing pipe and
Part in the horizontal fixing pipe of insertion of the pull bar, being detachably connected between the pull bar and the perpendicular strut is realized with this.
Further, fastening plug is also plugged between the horizontal fixing pipe and the bent cap.
Further, the lower end of the perpendicular strut is provided with footing, and the footing is connected by level board with vertical plate to be constituted,
The perpendicular strut is vertically fixed on the medial surface of the level board, and more than one is fixed between the level board and vertical plate
Anticreep rinforcement bar.
Further, it is designed to zigzag on the upside of the level board.
Further, the upper end of the perpendicular strut is provided with the jack for being used for inserting coloured flag bar.
The beneficial effects of the utility model are:
The utility model combines protective frame using cruciform fastening for falsework, not only facilitates connection, and can increase the entirety of protective frame
Stability, protective frame and the bent cap of formation combine to form firm support, and high-strength support is stablized so as to be provided for anti-falling railing
Effect, and anti-falling railing can not only then form guard rail, and safety belt can be hung, ensure the safety of people, security protection
Effect is good.
The utility model is simple in construction, convenient disassembly, has filled up bearing system construction safety and has effectively protected blank, can save anti-
Shield measure effective time and maintenance can dominate value using more than the 60% of expense, be obviously improved saving input
Cost.
Brief description of the drawings
Fig. 1 is the structural representation of the embodiment of the utility model one.
Fig. 2 is enlarged drawing at Fig. 1 A.
Fig. 3 is enlarged drawing at Fig. 1 B.
Fig. 4 is the structural representation of the footing in the embodiment of the utility model one.
Fig. 5 is Fig. 4 right view.
In accompanying drawing the mark of each part for:10 protective frames, 101 perpendicular struts, 1011 through holes, 102 singletrees, 103 bent caps,
104 cruciform fastening for falsework, 105 pull bars, 20 anti-falling railings, 30 footing, 301 level boards, 302 vertical plates, 303 anticreep rinforcement bars, 401 are determined
Type fixing pipe, 402 first fixing muscles, 403 perpendicular fixing pipes, 404 horizontal fixing pipes, 405 second fixing muscles, 406 the 3rd fixing muscles,
407 fastening plugs.
Embodiment
The utility model is further described below in conjunction with the accompanying drawings:
Referring to Fig. 1, Fig. 2 and Fig. 3.
The bearing construction combined movable security protection of the embodiment of the utility model one, including the spaced cloth of two or more
The anti-falling railing 20 of more than one is removably connected between the protective frame 10 put, the two neighboring protective frame 10, it is described anti-
Retaining frame 10 includes passing through cruciform fastening for falsework 104 between the perpendicular strut 101 of more than two, the upper end of adjacent two perpendicular struts 101
It is connected between singletree 102, the bottom of adjacent two perpendicular struts 101 and is connected with bent cap 103.
Intrinsic safety full protection uses cruciform fastening for falsework, not only facilitates connection, and can increase the resistance to overturning of protective frame, is formed
Protective frame and bent cap combine to form firm support, stablize high-strength supporting role so as to be provided for anti-falling railing, and anti-fall
Railing can not only then form guard rail, and can hang safety belt, ensure the safety of people.
In the present embodiment, sizing fixing pipe 401 is welded with the perpendicular strut 101, sizing fixing pipe 401 is perpendicular to described
Perpendicular strut 101, the anti-falling railing 20 is plugged in the sizing fixing pipe 401, and the T-shaped activity of the first fixing muscle 402 is worn
The part crossed in the insertion sizing fixing pipe 401 of the sizing fixing pipe 401 and the anti-falling railing 20 is (certainly, corresponding fixed
Part in type fixing pipe 401 and the insertion sizing fixing pipe 401 of anti-falling railing 20 is provided with to be passed through for the activity of the first fixing muscle 402
Through hole), being detachably connected between the anti-falling railing 20 and the protective frame 10 is realized with this.Using this structure, side
Just dismount, and be connected firmly, anti-falling railing 20 is connected on the perpendicular strut 101 between two protective frames 10, can make whole anti-
The structure of shield is more stablized.
In the present embodiment, pull bar 105, the pull bar 105 are also removably connected between adjacent two perpendicular struts 101
Positioned at the top of bent cap 103.Pull bar plays further supporting & stablizing effect, and perpendicular strut and bent cap are formed into firm support.
In the present embodiment, the top of the perpendicular strut 101 is arranged with perpendicular fixing pipe 403, and the perpendicular fixing pipe 403 is provided with
Horizontal fixing pipe 404, horizontal fixing pipe 404 is linked to be T-shaped perpendicular to perpendicular fixing pipe 403, and with perpendicular fixing pipe 403, and the pull bar 105 is inserted
It is connected in the horizontal fixing pipe 404, the top of the perpendicular strut 101 is provided with two through hole 1011, and two through hole 1011 is located at institute respectively
State the upper and lower of perpendicular fixing pipe 403, activity passes through two through hole 1011 to two the second fixing muscles 405 taken the shape of the letter U respectively, T-shaped the
The activity of three fixing muscle 406 through in the horizontal fixing pipe 404 of the insertion of the horizontal fixing pipe 404 and the pull bar 105 part (when
So, the part in corresponding horizontal fixing pipe 404 and the horizontal fixing pipe 404 of insertion of pull bar 105 is provided with passes through for the 3rd fixing muscle 406
Through hole), being detachably connected between the pull bar 105 and the perpendicular strut 101 is realized with this.Likewise, this structure side
Just dismount, be connected firmly, and the position of pull bar 105 can be adjusted.
In the present embodiment, the fastening plug 407 of wedge is also plugged between the horizontal fixing pipe 404 and the bent cap 103.Fastening
Plug 407 can compensate the gap between horizontal fixing pipe 404 and bent cap 103, make the installation of perpendicular fixing pipe 403 more firm, and
Generation is avoided to rock, ensure safety coefficient.
In the security protection illustrated in figure, protective frame 10 sets two, erects strut 101 and sets two, anti-falling railing 20
Set two.So design, it is rational in infrastructure, easily make, excellent in stability.
Referring to Fig. 4 and Fig. 5, in the present embodiment, the lower end of the perpendicular strut 101 is provided with footing 30, the footing 30 by
Level board 301 is connected composition with vertical plate 302, and the perpendicular strut 101 is vertically fixed on the medial surface of the level board 301, and
With the formation L-shaped of level board 301, level board 301 is located at the lower section of bent cap 103, and this mode can increase the company of perpendicular strut and footing 30
Intensity is connect, to further improve stability, the anticreep that more than one can be fixed between level board 301 and vertical plate 302 adds
Gu muscle 303.
The footing 30 of setting, when in use can be fixed footing 30 by fixture, it is possible to realize protective frame 10
Fixation, it is ensured that the stability of intrinsic safety full protection.
In the present embodiment, the upside of the level board 301 is designed to zigzag.So it is designed to prevent in adverse environment
Middle generation efficiency causes protective frame being departed from bent cap by external impacts lower feet.
In the present embodiment, for convenience of coloured flag is installed, the upper end of the perpendicular strut 101, which is provided with, to be used to insert inserting for coloured flag bar
Hole.
In specific implementation, each rod member, pipe fitting are made of coating steel pipe.This material can ensure the corrosion resistant of this protection
Corrosion and portability.
It should be understood that example as described herein and embodiment are not limited to the utility model only for explanation, this
Art personnel can make various modifications or change according to it, all within spirit of the present utility model and principle, be made
Any modification, equivalent substitution and improvements etc., should be included within protection domain of the present utility model.
Claims (8)
- The combined movable security protection 1. bearing is constructed, it is characterised in that:Include the protective frame of the spaced arrangement of two or more (10) anti-falling railing (20) of more than one, the protective frame, are removably connected between the two neighboring protective frame (10) (10) include passing through cruciform fastening for falsework between the perpendicular strut (101) of more than two, the upper end of adjacent two perpendicular struts (101) (104) it is connected between singletree (102), the bottom of adjacent two perpendicular struts (101) and is connected with bent cap (103).
- The combined movable security protection 2. bearing as claimed in claim 1 is constructed, it is characterised in that:The perpendicular strut (101) Provided with sizing fixing pipe (401), the anti-falling railing (20) is plugged in the sizing fixing pipe (401), the first fixing muscle (402) portion that activity is shaped in fixing pipe (401) through the insertion of the sizing fixing pipe (401) and the anti-falling railing (20) Point, being detachably connected between the anti-falling railing (20) and the protective frame (10) is realized with this.
- The combined movable security protection 3. bearing as claimed in claim 1 or 2 is constructed, it is characterised in that:Described in adjacent two Pull bar (105) is also removably connected between perpendicular strut (101), the pull bar (105) is located at the top of bent cap (103).
- The combined movable security protection 4. bearing as claimed in claim 3 is constructed, it is characterised in that:The perpendicular strut (101) Top be arranged with perpendicular fixing pipe (403), the perpendicular fixing pipe (403) is provided with horizontal fixing pipe (404), the pull bar (105) It is plugged in the horizontal fixing pipe (404), the top of the perpendicular strut (101) is provided with two through hole (1011), two through hole (1011) It is located at the upper and lower of the perpendicular fixing pipe (403) respectively, activity passes through two through hole (1011) to two second fixing muscles (405) respectively, The activity of 3rd fixing muscle (406) is interior through the horizontal fixing pipe of insertion (404) of the horizontal fixing pipe (404) and the pull bar (105) Part, being detachably connected between the pull bar (105) and the perpendicular strut (101) is realized with this.
- The combined movable security protection 5. bearing as claimed in claim 4 is constructed, it is characterised in that:The horizontal fixing pipe (404) fastening plug (407) is also plugged between the bent cap (103).
- The combined movable security protection 6. bearing as claimed in claim 1 or 2 is constructed, it is characterised in that:The perpendicular strut (101) lower end is provided with footing (30), and the footing (30) is connected by level board (301) with vertical plate (302) to be constituted, described Perpendicular strut (101) is vertically fixed on the medial surface of the level board (301), between the level board (301) and vertical plate (302) It is fixed with the anticreep rinforcement bar (303) of more than one.
- The combined movable security protection 7. bearing as claimed in claim 6 is constructed, it is characterised in that:The level board (301) Upside be designed to zigzag.
- The combined movable security protection 8. bearing as claimed in claim 1 or 2 is constructed, it is characterised in that:The perpendicular strut (101) upper end is provided with the jack for being used for inserting coloured flag bar.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720054458.4U CN206457728U (en) | 2017-01-16 | 2017-01-16 | Bearing construction combined movable security protection |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720054458.4U CN206457728U (en) | 2017-01-16 | 2017-01-16 | Bearing construction combined movable security protection |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206457728U true CN206457728U (en) | 2017-09-01 |
Family
ID=59695878
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720054458.4U Expired - Fee Related CN206457728U (en) | 2017-01-16 | 2017-01-16 | Bearing construction combined movable security protection |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206457728U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111364789A (en) * | 2020-04-08 | 2020-07-03 | 国网安徽省电力有限公司广德市供电公司 | Combined suspension and protection device for deep foundation pit operation |
-
2017
- 2017-01-16 CN CN201720054458.4U patent/CN206457728U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111364789A (en) * | 2020-04-08 | 2020-07-03 | 国网安徽省电力有限公司广德市供电公司 | Combined suspension and protection device for deep foundation pit operation |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206457728U (en) | Bearing construction combined movable security protection | |
| CN204627010U (en) | A kind of outer guard net being applicable to climbing frame | |
| CN206667042U (en) | Bridge expanssion joint installation and adjustment instrument | |
| CN207829505U (en) | A kind of pin-connected panel floor edge protective fence | |
| CN206769361U (en) | A connection device for attaching and lifting the overall scaffolding and hanging steel mesh | |
| CN104819817A (en) | Detection device for power construction safety belt hanger | |
| CN204038917U (en) | Detachable external hanging type operating platform | |
| CN206494095U (en) | Ship stern synthetic job platform | |
| CN212406019U (en) | Adjustable regularization safety operation platform construction equipment | |
| CN204199183U (en) | Spanning existing railway cast-in-place beam cradle construction safeguard structure in one | |
| CN207863449U (en) | Disk buckle type scaffold new type of safe cat ladder | |
| CN204370828U (en) | Tool-type protective screening | |
| CN204679238U (en) | The pick-up unit of power construction seat belt hanger | |
| CN206693590U (en) | A kind of Quick-mounting aluminium alloy scaffold | |
| CN208858134U (en) | The security platform of high-altitude installation exercise | |
| CN219604147U (en) | Multifunctional maintenance hanging basket | |
| CN207260537U (en) | A kind of scaffold for construction | |
| CN107217912A (en) | It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction | |
| CN212359331U (en) | Movable protective fence for building construction | |
| CN221095940U (en) | A construction elevator platform protection device | |
| CN204778118U (en) | High security elevator cab rail guard | |
| CN206090329U (en) | Device that falls is prevented safely in bridge construction | |
| CN206655455U (en) | A kind of pier stud reinforcing bar binding platform keel shoe | |
| CN217087472U (en) | Supplementary ladder of medium-low speed magnetic levitation contact rail arrester installation | |
| CN205369887U (en) | High strength footboard that construction scaffolding frame was used |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170901 Termination date: 20220116 |