CN206320728U - Attemperation water system of boiler superheater - Google Patents

Attemperation water system of boiler superheater Download PDF

Info

Publication number
CN206320728U
CN206320728U CN201621355643.9U CN201621355643U CN206320728U CN 206320728 U CN206320728 U CN 206320728U CN 201621355643 U CN201621355643 U CN 201621355643U CN 206320728 U CN206320728 U CN 206320728U
Authority
CN
China
Prior art keywords
water
desuperheating water
superheater
desuperheating
economizer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621355643.9U
Other languages
Chinese (zh)
Inventor
刘建强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Original Assignee
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd filed Critical China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority to CN201621355643.9U priority Critical patent/CN206320728U/en
Application granted granted Critical
Publication of CN206320728U publication Critical patent/CN206320728U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Control Of Steam Boilers And Waste-Gas Boilers (AREA)

Abstract

本实用新型涉及一种锅炉过热器减温水系统,包括高压加热器、省煤器和过热器,高压加热器和省煤器的进水口之间连通有连接管道,省煤器的出水口与过热器之间连通有减温水主管道,减温水主管道和连接管道之间连通有减温水辅助管道。相对于省煤器出水口引出的减温水而言,由于经过减温水辅助管道的减温水从高压加热器直接进入过热器,因此从过减温水辅助管道引出的减温水压差更大,温差也更大,使更好地控制汽温。当锅炉燃用劣质煤时,在并网初期及切缸过程中,增加从减温水辅助管道进入过热器的减温水,大大提高过热器减温水压差,增大点火及并网过程中的减温水投入量,避免过热器超温,保证过热器和机组的运行安全。

The utility model relates to a boiler superheater desuperheating water system, which comprises a high-pressure heater, an economizer and a superheater. A connecting pipe is connected between the water inlet of the high-pressure heater and the economizer, and the water outlet of the economizer is connected to the superheater. The desuperheating water main pipeline is communicated between the devices, and the desuperheating water auxiliary pipeline is communicated between the desuperheating water main pipeline and the connecting pipeline. Compared with the desuperheating water drawn from the economizer water outlet, since the desuperheating water passing through the desuperheating water auxiliary pipeline directly enters the superheater from the high-pressure heater, the pressure difference of the desuperheating water drawn from the desuperheating water auxiliary pipeline is larger, and the temperature difference is also smaller. Larger for better control of steam temperature. When the boiler burns low-quality coal, the desuperheating water entering the superheater from the desuperheating water auxiliary pipeline will be increased at the initial stage of grid connection and during the cylinder cut-off process, which will greatly increase the pressure difference of superheater desuperheating water and increase the desuperheating during ignition and grid connection. The amount of warm water input can avoid overheating of the superheater and ensure the safe operation of the superheater and the unit.

Description

锅炉过热器减温水系统Boiler superheater desuperheating water system

技术领域technical field

本实用新型涉及锅炉过热器降温技术领域,特别涉及一种锅炉过热器减温水系统。The utility model relates to the technical field of boiler superheater cooling, in particular to a boiler superheater cooling water system.

背景技术Background technique

锅炉过热器减温水用来降低进入高温过热器的蒸汽温度,保护高温过热器,同时对进入汽轮机的蒸汽温度进行调节,维持主蒸汽温度一定,保证机组安全。目前锅炉厂设计的过热器减温水系统为了提高机组热效率和延长减温器使用寿命,将过热器减温水引出点引自省煤器出口管道上,但该方案存在以下问题:针对劣质无烟煤的W型火焰锅炉,当锅炉过热器减温水从省煤器出口引出,在启动初期减温水与过热器压差较小,减温水调门全开时减温水流量仍较低。当燃用煤质挥发分较低时,由于着火较差、燃烧滞后,过热器容易超温;尤其是在并网初期及切缸过程中燃烧需要加强,而此时蒸汽流量低,过热器减温水前后压差小、减温水流量太小,过热器壁温极易超温,无法保证过热器安全。The desuperheating water of the boiler superheater is used to reduce the temperature of the steam entering the high temperature superheater, protect the high temperature superheater, and at the same time adjust the temperature of the steam entering the steam turbine to maintain a constant temperature of the main steam and ensure the safety of the unit. At present, in order to improve the thermal efficiency of the unit and prolong the service life of the desuperheater in the superheater desuperheating water system designed by the boiler factory, the outlet point of the superheater desuperheating water is led from the outlet pipe of the economizer, but this scheme has the following problems: W for inferior anthracite coal For the type flame boiler, when the desuperheating water of the boiler superheater is drawn from the outlet of the economizer, the pressure difference between the desuperheating water and the superheater is small at the beginning of start-up, and the desuperheating water flow rate is still low when the desuperheating water valve is fully opened. When the volatile content of coal is low, the superheater is easy to overheat due to poor ignition and combustion lag; especially in the initial stage of grid connection and the process of cutting cylinders, the combustion needs to be strengthened, and at this time the steam flow rate is low, and the superheater decreases The pressure difference before and after the warm water is small, the flow rate of the desuperheating water is too small, the wall temperature of the superheater is easy to overheat, and the safety of the superheater cannot be guaranteed.

实用新型内容Utility model content

本实用新型的目的在于提供一种锅炉过热器减温水系统,能够提高过热器减温水压差和流量,避免过热器超温,保证过热器的安全。The purpose of the utility model is to provide a boiler superheater desuperheating water system, which can increase the pressure difference and flow rate of the superheater desuperheating water, avoid overheating of the superheater, and ensure the safety of the superheater.

为实现本实用新型的目的,采取的技术方案是:For realizing the purpose of this utility model, the technical scheme that takes is:

一种锅炉过热器减温水系统,包括高压加热器、省煤器和过热器,高压加热器和省煤器的进水口之间连通有连接管道,省煤器的出水口与过热器之间连通有减温水主管道,减温水主管道和连接管道之间连通有减温水辅助管道。A boiler superheater desuperheating water system, including a high-pressure heater, an economizer and a superheater, a connecting pipe is connected between the water inlet of the high-pressure heater and the economizer, and the water outlet of the economizer is connected with the superheater There is a main pipeline for desuperheating water, and an auxiliary pipeline for desuperheating water is communicated between the main pipeline for desuperheating water and the connecting pipeline.

相对于省煤器出水口引出的减温水而言,由于经过减温水辅助管道的减温水从高压加热器直接进入过热器,因此从过减温水辅助管道引出的减温水压差更大,温差也更大,使更好地控制汽温。当锅炉燃用劣质煤时,在并网初期及切缸过程中,增加从减温水辅助管道进入过热器的减温水,大大提高过热器减温水压差,增大点火及并网过程中的减温水投入量,避免过热器超温,保证过热器和机组的运行安全。Compared with the desuperheating water drawn from the economizer water outlet, since the desuperheating water passing through the desuperheating water auxiliary pipeline directly enters the superheater from the high-pressure heater, the pressure difference of the desuperheating water drawn from the desuperheating water auxiliary pipeline is larger, and the temperature difference is also smaller. Larger for better control of steam temperature. When the boiler burns low-quality coal, the desuperheating water entering the superheater from the desuperheating water auxiliary pipeline will be increased at the initial stage of grid connection and during the cylinder cut-off process, which will greatly increase the pressure difference of superheater desuperheating water and increase the desuperheating during ignition and grid connection. The amount of warm water input can avoid overheating of the superheater and ensure the safe operation of the superheater and the unit.

下面对技术方案进一步说明:The technical scheme is further described below:

进一步的是,减温水主管道设有止回阀、及与减温水辅助管道连通的第一连接位置,止回阀位于第一连接位置和省煤器的出水口之间。通过止回阀防止从减温水辅助管道出来的水倒流进省煤器,保证机组的运行安全。Further, the main pipeline of desuperheating water is provided with a check valve and a first connection position communicating with the auxiliary pipeline of desuperheating water, and the check valve is located between the first connection position and the water outlet of the economizer. The check valve prevents the water from the desuperheating water auxiliary pipeline from flowing back into the economizer to ensure the safe operation of the unit.

进一步的是,减温水主管道设有第一控制阀门,第一控制阀门位于止回阀和省煤器的出水口之间。当锅炉燃用劣质煤且负荷升高后,则开启第一控制阀门,过热器从省煤器的出水口引入的减温水。Further, the main pipeline of desuperheating water is provided with a first control valve, and the first control valve is located between the check valve and the water outlet of the economizer. When the boiler burns low-quality coal and the load increases, the first control valve is opened, and the superheater introduces desuperheating water from the water outlet of the economizer.

进一步的是,第一控制阀门为电动闸阀。使第一控制阀门的控制更智能。Further, the first control valve is an electric gate valve. Make the control of the first control valve more intelligent.

进一步的是,减温水辅助管道上设有第二控制阀门。当锅炉燃用劣质煤时,在并网初期及切缸过程中,打开第二控制阀门,使从高压加热器出来的水通过减温水辅助管道输送至过热器;当机组在其他运行状态下,则使第二控制阀门关闭。Further, a second control valve is provided on the desuperheating water auxiliary pipeline. When the boiler burns low-quality coal, the second control valve is opened at the initial stage of grid connection and during cylinder cut-off, so that the water from the high-pressure heater is sent to the superheater through the desuperheating water auxiliary pipeline; when the unit is in other operating states, Then the second control valve is closed.

进一步的是,第二控制阀门为电动闸阀。使第二控制阀门的控制更智能。Further, the second control valve is an electric gate valve. Make the control of the second control valve more intelligent.

进一步的是,连接管道设有给水操作台、及与减温水辅助管道连通的第二连接位置,第二连接位置位于给水操作台和高压加热器之间。使从减温水辅助管道引入的减温水压差更大。Further, the connecting pipeline is provided with a water supply operation platform and a second connection position communicated with the desuperheating water auxiliary pipeline, and the second connection position is located between the water supply operation platform and the high-pressure heater. Make the pressure difference of the desuperheating water introduced from the desuperheating water auxiliary pipeline larger.

进一步的是,连接管道上还设有流量测量喷嘴,流量测量喷嘴位于给水操作台和省煤器的进水口之间。Further, the connecting pipeline is also provided with a flow measuring nozzle, and the flow measuring nozzle is located between the water supply operation table and the water inlet of the economizer.

与现有技术相比,本实用新型具有以下有益效果:Compared with the prior art, the utility model has the following beneficial effects:

本实用新型相对于省煤器出水口引出的减温水而言,由于经过减温水辅助管道的减温水从高压加热器直接进入过热器,因此从过减温水辅助管道引出的减温水压差更大,温差也更大,使更好地控制汽温。当锅炉燃用劣质煤时,在并网初期及切缸过程中,增加从减温水辅助管道进入过热器的减温水,大大提高过热器减温水压差,增大点火及并网过程中的减温水投入量,避免过热器超温,保证过热器和机组的运行安全。Compared with the desuperheating water drawn from the water outlet of the economizer, because the desuperheating water passing through the desuperheating water auxiliary pipeline directly enters the superheater from the high-pressure heater, the pressure difference of the desuperheating water drawn from the desuperheating water auxiliary pipeline is larger , the temperature difference is also larger, so that better control of steam temperature. When the boiler burns low-quality coal, the desuperheating water entering the superheater from the desuperheating water auxiliary pipeline will be increased at the initial stage of grid connection and during the cylinder cut-off process, which will greatly increase the pressure difference of superheater desuperheating water and increase the desuperheating during ignition and grid connection. The amount of warm water input can avoid overheating of the superheater and ensure the safe operation of the superheater and the unit.

附图说明Description of drawings

图1是本实用新型实施例锅炉过热器减温水系统的结构示意图。Fig. 1 is a schematic structural view of a boiler superheater desuperheating water system according to an embodiment of the present invention.

附图标记说明:Explanation of reference signs:

10.高压加热器,20.省煤器,210.进水口,220.出水口,30.过热器,310.一级减温器,320.二级减温器,40.连接管道,410.给水操作台,411.第一给水管道,412.第二给水管道,413.第三控制阀门,414.气动调节阀,415.第四控制阀门,416.第五控制阀门,420.流量测量喷嘴,430.第二连接位置,50.减温水主管道,510.止回阀,520.第一连接位置,530.第一控制阀门,60.减温水辅助管道,610.第二控制阀门。10. High pressure heater, 20. Economizer, 210. Water inlet, 220. Water outlet, 30. Superheater, 310. Primary desuperheater, 320. Secondary desuperheater, 40. Connecting pipeline, 410. Water supply console, 411. First water supply pipe, 412. Second water supply pipe, 413. Third control valve, 414. Pneumatic regulating valve, 415. Fourth control valve, 416. Fifth control valve, 420. Flow measurement nozzle , 430. The second connection position, 50. The desuperheating water main pipeline, 510. Check valve, 520. The first connection position, 530. The first control valve, 60. The desuperheating water auxiliary pipeline, 610. The second control valve.

具体实施方式detailed description

下面结合附图对本实用新型的实施例进行详细说明:Embodiment of the utility model is described in detail below in conjunction with accompanying drawing:

如图1所示,一种锅炉过热器减温水系统,包括高压加热器10、省煤器20和过热器30,高压加热器10和省煤器20的进水口210之间连通有连接管道40,省煤器20的出水口220与过热器30之间连通有减温水主管道50,减温水主管道50和连接管道40之间连通有减温水辅助管道60。As shown in Figure 1, a boiler superheater desuperheating water system includes a high-pressure heater 10, an economizer 20, and a superheater 30, and a connecting pipe 40 is communicated between the high-pressure heater 10 and the water inlet 210 of the economizer 20 , between the water outlet 220 of the economizer 20 and the superheater 30 is communicated with a desuperheating water main pipeline 50 , and between the desuperheating water main pipeline 50 and the connecting pipeline 40 is communicated with a desuperheating water auxiliary pipeline 60 .

相对于省煤器20出水口220引出的减温水而言,由于经过减温水辅助管道60的减温水从高压加热器10直接进入过热器30,因此从过减温水辅助管道60引出的减温水压差更大,温差也更大,使更好地控制汽温。当锅炉燃用劣质煤时,在并网初期及切缸过程中,增加从减温水辅助管道60进入过热器30的减温水,大大提高过热器30减温水压差,增大点火及并网过程中的减温水投入量,避免过热器30超温,保证过热器30和机组的运行安全。Compared with the desuperheated water drawn from the water outlet 220 of the economizer 20, since the desuperheated water passing through the desuperheated water auxiliary pipeline 60 directly enters the superheater 30 from the high pressure heater 10, the pressure of the desuperheated water drawn from the desuperheated water auxiliary pipeline 60 The larger the difference, the larger the temperature difference, so that better control of the steam temperature. When the boiler burns low-quality coal, at the initial stage of grid connection and during the cylinder cut-off process, the desuperheating water entering the superheater 30 from the desuperheating water auxiliary pipeline 60 is increased to greatly increase the pressure difference of the superheater 30 desuperheating water, and increase the ignition and grid connection process The input amount of the desuperheating water in can avoid overheating of the superheater 30 and ensure the safe operation of the superheater 30 and the unit.

在本实施例中,过热器30包括一级减温器310和二级减温器320,以600MW超临界W型锅炉为例,在180MW负荷工况下,高压加热器10出口工质压力约为11.5MPa,省煤器20出水口220压力约为9.7MPa,而一级减温器310和二级减温器320减温水入口工质压力在9.2-9.3MPa之间,省煤器20出水口220减温水与一级减温器310和二级减温器320减温水入口工质压差在0.4-0.5MPa左右,而减温水辅助管道60与一级减温器310和二级减温器320减温水入口工质压差在2.2-2.3MPa左右,是省煤器20出水口220减温水与一级减温器310和二级减温器320减温水入口工质压差的5倍多,这将有利于保证过热器30超温时有足够的减温水流量;且高压加热器10出口工质温度在210-220℃之间,省煤器20出水口220工作温度在280-290℃之间,减温水辅助管道60引出的减温水比省煤器20引出的减温水低70℃左右,同等减温水量,将有助于更好的控制汽温。当锅炉燃用劣质煤时启动阶段(尤其是使用劣质无烟煤),过热器30超温问题更加突出,此外,当水分较高时(大于10%),在调试期间或投产后的制粉系统运行不正常(如堵煤)情况下,超温情况可能持续时间长,利用辅助减温水的高压差与低水温,将有助于保障开机过程中受热面安全,同时也有利于锅炉对入炉煤质的适用性。In this embodiment, the superheater 30 includes a primary desuperheater 310 and a secondary desuperheater 320. Taking a 600MW supercritical W-type boiler as an example, under the load condition of 180MW, the pressure of the working medium at the outlet of the high pressure heater 10 is about The pressure at the water outlet 220 of the economizer 20 is about 9.7MPa, while the pressure of the desuperheating water inlet of the primary desuperheater 310 and the secondary desuperheater 320 is between 9.2-9.3MPa, and the outlet of the economizer 20 The working fluid pressure difference between the outlet 220 desuperheating water and the primary desuperheater 310 and the secondary desuperheater 320 desuperheating water inlet is about 0.4-0.5MPa, while the desuperheating water auxiliary pipeline 60 and the primary desuperheater 310 and the secondary desuperheater The working fluid pressure difference at the desuperheating water inlet of the economizer 320 is about 2.2-2.3MPa, which is 5 times the pressure difference between the desuperheating water at the outlet 220 of the economizer 20 and the desuperheating water inlet of the primary desuperheater 310 and the secondary desuperheater 320 This will help to ensure that there is sufficient desuperheating water flow when the superheater 30 is overheated; and the temperature of the working medium at the outlet of the high pressure heater 10 is between 210-220°C, and the working temperature of the outlet 220 of the economizer 20 is at 280-290°C ℃, the desuperheating water drawn from the desuperheating water auxiliary pipeline 60 is about 70 ℃ lower than the desuperheated water drawn from the economizer 20, and the same amount of desuperheating water will help to better control the steam temperature. When the boiler burns low-quality coal in the start-up phase (especially when using low-quality anthracite), the problem of overheating of the superheater 30 is more prominent. In addition, when the moisture content is high (greater than 10%), the pulverizing system is running during commissioning or after commissioning Under abnormal conditions (such as coal blockage), the over-temperature situation may last for a long time. Using the high pressure difference and low water temperature of the auxiliary desuperheating water will help to ensure the safety of the heating surface during the start-up process, and it is also conducive to the boiler’s protection of the coal into the furnace. qualitative applicability.

如图1所示,减温水主管道50设有止回阀510、及与减温水辅助管道60连通的第一连接位置520,止回阀510位于第一连接位置520和省煤器20的出水口220之间,通过止回阀510防止从减温水辅助管道60出来的水倒流进省煤器20,保证机组的运行安全。As shown in FIG. 1 , the desuperheating water main pipeline 50 is provided with a check valve 510 and a first connection position 520 communicating with the desuperheating water auxiliary pipeline 60 . The check valve 510 is located at the outlet of the first connection position 520 and the economizer 20. Between the water ports 220, the check valve 510 is used to prevent the water from the desuperheating water auxiliary pipeline 60 from flowing back into the economizer 20, so as to ensure the safe operation of the unit.

如图1所示,减温水主管道50设有第一控制阀门530,第一控制阀门530位于止回阀510和省煤器20的出水口220之间,减温水辅助管道60上设有第二控制阀门610。当锅炉燃用劣质煤时,在并网初期及切缸过程中,关闭第一控制阀门530,打开第二控制阀门610,使从高压加热器10出来的水通过减温水辅助管道60输送至过热器30;当锅炉负荷(大于35%)升高后,则开启第一控制阀门530,关闭第二控制阀门610,过热器30从省煤器20的出水口220引入的减温水。As shown in Figure 1, the main pipeline 50 of desuperheating water is provided with a first control valve 530, and the first control valve 530 is located between the check valve 510 and the water outlet 220 of the economizer 20, and the auxiliary pipeline 60 of desuperheating water is provided with a second control valve 530. Two control valves 610 . When the boiler burns low-quality coal, at the initial stage of grid connection and during cylinder cut-off, the first control valve 530 is closed, and the second control valve 610 is opened, so that the water from the high-pressure heater 10 is sent to the superheated boiler through the desuperheating water auxiliary pipeline 60 When the boiler load (greater than 35%) rises, the first control valve 530 is opened, the second control valve 610 is closed, and the superheater 30 introduces desuperheating water from the water outlet 220 of the economizer 20 .

在本实施例中,第一控制阀门530和第二控制阀门610均为电动闸阀,使第一控制阀门530和第二控制阀门610的控制更智能。第一控制阀门530和第二控制阀门610还可以根据实际需要设置为其他类型的控制阀。In this embodiment, both the first control valve 530 and the second control valve 610 are electric gate valves, which makes the control of the first control valve 530 and the second control valve 610 more intelligent. The first control valve 530 and the second control valve 610 can also be set as other types of control valves according to actual needs.

如图1所示,连接管道40设有给水操作台410、流量测量喷嘴420、及与减温水辅助管道60连通的第二连接位置430,流量测量喷嘴420位于给水操作台410和省煤器20的进水口210之间,第二连接位置430位于给水操作台410和高压加热器10之间,使从减温水辅助管道60引入的减温水压差更大。第二连接位置430还可以根据实际需要设置在连接管道40的其他位置。As shown in Figure 1, the connecting pipeline 40 is provided with a water supply operation platform 410, a flow measurement nozzle 420, and a second connection position 430 communicating with the desuperheating water auxiliary pipeline 60, and the flow measurement nozzle 420 is located at the water supply operation platform 410 and the economizer 20 Between the water inlets 210, the second connection position 430 is located between the water supply console 410 and the high-pressure heater 10, so that the pressure difference of the desuperheating water introduced from the desuperheating water auxiliary pipeline 60 is greater. The second connection position 430 can also be set at other positions of the connection pipeline 40 according to actual needs.

在本实施例中,给水操作台410包括并联布置于连接管道40上的第一给水管道411和第二给水管道412,第一给水管道411上设有第三控制阀门413、气动调节阀414、第四控制阀门415,第二给水管道上设有第五控制阀门416,通过给水操作台410控制进入省煤器20的介质。In this embodiment, the water supply console 410 includes a first water supply pipeline 411 and a second water supply pipeline 412 arranged in parallel on the connecting pipeline 40. The first water supply pipeline 411 is provided with a third control valve 413, a pneumatic regulating valve 414, The fourth control valve 415 and the fifth control valve 416 are provided on the second water supply pipeline to control the medium entering the economizer 20 through the water supply console 410 .

以上所述实施例的各技术特征可以进行任意的组合,为使描述简洁,未对上述实施例中的各个技术特征所有可能的组合都进行描述,然而,只要这些技术特征的组合不存在矛盾,都应当认为是本说明书记载的范围。The technical features of the above-mentioned embodiments can be combined arbitrarily. To make the description concise, all possible combinations of the technical features in the above-mentioned embodiments are not described. However, as long as there is no contradiction in the combination of these technical features, should be considered as within the scope of this specification.

以上所述实施例仅表达了本实用新型的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对实用新型专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本实用新型构思的前提下,还可以做出若干变形和改进,这些都属于本实用新型的保护范围。因此,本实用新型专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only express several implementation modes of the utility model, and the description thereof is relatively specific and detailed, but it should not be understood as limiting the scope of the utility model patent. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the scope of protection of the utility model patent should be based on the appended claims.

Claims (8)

1. a kind of Attemperation water system of boiler superheater, it is characterised in that described including high-pressure heater, economizer and superheater Connecting pipe, the delivery port of the economizer and the overheat are communicated between the water inlet of high-pressure heater and the economizer Desuperheating water main pipeline is communicated between device, desuperheating water auxiliary tube is communicated between the desuperheating water main pipeline and the connecting pipe Road.
2. Attemperation water system of boiler superheater according to claim 1, it is characterised in that the desuperheating water main pipeline is provided with Check-valves and the first link position connected with the desuperheating water subsidiary conduit, the check-valves are located at first connection position Put between the delivery port of the economizer.
3. Attemperation water system of boiler superheater according to claim 2, it is characterised in that the desuperheating water main pipeline is provided with First control valve, first control valve is located between the check-valves and the delivery port of the economizer.
4. Attemperation water system of boiler superheater according to claim 3, it is characterised in that first control valve is electricity Dynamic gate valve.
5. Attemperation water system of boiler superheater according to claim 1, it is characterised in that on the desuperheating water subsidiary conduit Provided with the second control valve.
6. Attemperation water system of boiler superheater according to claim 5, it is characterised in that second control valve is electricity Dynamic gate valve.
7. the Attemperation water system of boiler superheater according to any one of claim 1 to 6, it is characterised in that the connecting tube Road is provided with water-supplying operation platform and the second link position connected with the desuperheating water subsidiary conduit, the second connection position set Between the water-supplying operation platform and the high-pressure heater.
8. Attemperation water system of boiler superheater according to claim 7, it is characterised in that be additionally provided with the connecting pipe Flow nozzle, the flow nozzle is located between the water-supplying operation platform and the water inlet of the economizer.
CN201621355643.9U 2016-12-09 2016-12-09 Attemperation water system of boiler superheater Expired - Fee Related CN206320728U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621355643.9U CN206320728U (en) 2016-12-09 2016-12-09 Attemperation water system of boiler superheater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621355643.9U CN206320728U (en) 2016-12-09 2016-12-09 Attemperation water system of boiler superheater

Publications (1)

Publication Number Publication Date
CN206320728U true CN206320728U (en) 2017-07-11

Family

ID=59266821

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621355643.9U Expired - Fee Related CN206320728U (en) 2016-12-09 2016-12-09 Attemperation water system of boiler superheater

Country Status (1)

Country Link
CN (1) CN206320728U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107620947A (en) * 2017-08-28 2018-01-23 浙江海洋大学 A kind of desuperheating water of superheater water system
CN109945159A (en) * 2019-02-27 2019-06-28 哈尔滨锅炉厂有限责任公司 A kind of super critical boiler or ultra-supercritical boiler Attemperation water system and its application method
CN112303613A (en) * 2020-10-30 2021-02-02 西安热工研究院有限公司 Two-stage superheater desuperheating water system capable of independently fetching water
CN112377891A (en) * 2020-11-10 2021-02-19 西安热工研究院有限公司 Energy-conserving power plant boiler over heater temperature reduction water system of degree of depth

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107620947A (en) * 2017-08-28 2018-01-23 浙江海洋大学 A kind of desuperheating water of superheater water system
CN107620947B (en) * 2017-08-28 2019-05-21 浙江海洋大学 A superheater desuperheating water supply system
CN109945159A (en) * 2019-02-27 2019-06-28 哈尔滨锅炉厂有限责任公司 A kind of super critical boiler or ultra-supercritical boiler Attemperation water system and its application method
CN112303613A (en) * 2020-10-30 2021-02-02 西安热工研究院有限公司 Two-stage superheater desuperheating water system capable of independently fetching water
CN112377891A (en) * 2020-11-10 2021-02-19 西安热工研究院有限公司 Energy-conserving power plant boiler over heater temperature reduction water system of degree of depth

Similar Documents

Publication Publication Date Title
CN104763485B (en) A kind of concurrent heating type ultrahigh pressure/subcritical back pressure thermal power plant unit thermodynamic system
CN106678770A (en) System and method for heating feed water of evaporator of nuclear power unit
CN110686227B (en) Intermediate reheat steam power generation system
CN107218591B (en) An external steam cooler system for heating hot primary air
CN107166360A (en) New-type boiler main steam temperature adjusting means and control method
CN107664045A (en) A kind of HTGR Turbine Steam gland sealing steam supply system and method
CN103711532A (en) Steam power plant with steam turbine extraction control
CN107620947A (en) A kind of desuperheating water of superheater water system
CN209978005U (en) Primary Frequency Modulation Control System for Secondary Reheat Unit
CN206695107U (en) Using the primary frequency modulation control system of feedwater throttling
CN106194284B (en) A kind of method of the parameter adjustment of steam turbine jacket steam and operation
CN204552846U (en) A kind of back pressure steam turbines utilization system
CN106761991A (en) One kind is applied to waste incineration and generating electricity steam circulation reheating and improves heat utilization efficiency system
CN103542399B (en) Boiler feed water system and feed water adjusting method thereof
CN112944321B (en) System and method for increasing boiler feed water temperature during pipe blowing
CN202692429U (en) Waterway system of direct thermal circulation type heat pump water heater
CN112197252A (en) A main steam heating system with supplementary steam bypass
CN104074561A (en) Throttling adjusting system of cogeneration turbine unit and method of ordering power by heat
CN103939886B (en) Extra-supercritical unit switchable type double reheat steam convection-type desuperheater system
CN206257684U (en) Generating set draws gas backheat image-stabilization FCS system
CN203810382U (en) Switchable secondary reheat steam surface type desuperheater system of ultra-supercritical unit
CN106524200A (en) Steam extraction regenerative heating type stable-pressure pipe blowing system of generator set
CN116291791A (en) Bypass system control system of steam turbine unit
CN115573783B (en) A peak regulation system and method for thermal power unit boiler in wet operation mode
CN105650851A (en) Steam extraction backheating and pressure stabilizing blowpipe system of generator set

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170711