CN206305205U - A kind of roll changing carriage for steel band manufacture line - Google Patents
A kind of roll changing carriage for steel band manufacture line Download PDFInfo
- Publication number
- CN206305205U CN206305205U CN201621290354.5U CN201621290354U CN206305205U CN 206305205 U CN206305205 U CN 206305205U CN 201621290354 U CN201621290354 U CN 201621290354U CN 206305205 U CN206305205 U CN 206305205U
- Authority
- CN
- China
- Prior art keywords
- roll
- grappling fixture
- slide rail
- frame
- coaster
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 30
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 27
- 239000010959 steel Substances 0.000 title claims abstract description 27
- 238000000151 deposition Methods 0.000 claims abstract description 13
- 230000033001 locomotion Effects 0.000 claims description 8
- 238000009434 installation Methods 0.000 abstract description 2
- 230000003321 amplification Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000003199 nucleic acid amplification method Methods 0.000 description 2
- 229910001220 stainless steel Inorganic materials 0.000 description 2
- 239000010935 stainless steel Substances 0.000 description 2
- 241000208340 Araliaceae Species 0.000 description 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 description 1
- 235000003140 Panax quinquefolius Nutrition 0.000 description 1
- 230000033228 biological regulation Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 235000008434 ginseng Nutrition 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
Landscapes
- Bending Of Plates, Rods, And Pipes (AREA)
Abstract
The utility model provides a kind of roll changing carriage for steel band manufacture line, including coaster, support frame and grappling fixture device, two guide rails are provided with coaster horizontally-parallelly, coaster one end is longitudinally provided with first gear slide rail and the first guide groove slide rail forms fixed set of rails, fixed set of rails is for installation grappling fixture device, support frame is slidably mounted on two guide rails of coaster, support frame include underframe and be formed in underframe both sides deposit roll stand, on underframe second gear slide rail and the second guide groove slide rail are relatively provided with two opposite sides for depositing roll stand, form the intermediate rail group of support frame, grappling fixture device includes frame and the roll change grappling fixture mechanism that can be slided up and down with respect to frame in frame, by slide holder so that intermediate rail group is aligned with fixed set of rails, intermediate rail group is slipped into for grappling fixture device.The utility model roll changing carriage fast changeable roll body, improves the production efficiency of roll change efficiency and rolled plate.
Description
Technical field
The utility model is related to the roll-changing equipment of rolled stainless steel production line, more particularly to a kind of for steel band manufacture line
Roll changing carriage.
Background technology
In order to ensure the efficiency of rolled plate, on rolling line, the working roll and intermediate calender rolls of rolled plate are used
After a period of time, it is necessary to be repaired or replaced to roll body, the roll change efficiency that current roll change mechanism changes roll body is low, especially
To the roll body being arranged side by side, and then influence production efficiency.
Utility model content
In view of the above, the utility model is necessary to provide a kind of changing for steel band manufacture line for improving roll change efficiency
Roller car.
The technical scheme that the utility model is provided is as follows:A kind of roll changing carriage for steel band manufacture line, including coaster, support
Frame and grappling fixture device, are provided with two guide rails horizontally-parallelly on coaster, one end of coaster is longitudinally provided with first gear slide rail
And the first guide groove slide rail, fixed set of rails is formed, and two T-shaped connections of guide rail, fixed set of rails is for installing grappling fixture dress
Put, support frame is slidably mounted on two guide rails of coaster, support frame includes underframe and is formed in depositing for underframe both sides
Roll stand, is relatively provided with second gear slide rail and the second guide groove slide rail, to form support on underframe in two opposite sides for depositing roll stand
The intermediate rail group of frame, grappling fixture device includes frame and in frame and can the roll change grappling fixture that slide up and down of relative frame
Mechanism, by sliding support frame as described above so that intermediate rail group is aligned with fixed set of rails, in being slipped into for grappling fixture device
Between set of rails.
Further, the grappling fixture device includes being used in the frame ordering about that grappling fixture device is relative deposits roll stand motion
Drive component, the frame includes base plate, and the drive component is electric including the motor on base plate, installed in driving
Driving wheel on owner's axle and the driven pulley with driving wheel cooperation, driving wheel are placed in base plate bottom, are intermeshed with driven pulley,
Driven pulley is intermeshed with supratrochlear first gear slide rail.
Further, the roll change grappling fixture mechanism includes main body arm, is arranged on the grappling fixture structure and shape of main body arm one end
Into the sliding panel in the main body arm other end, driver includes main body cylinder and the connection being hinged with the expansion link end on main body cylinder
Arm, the other end of linking arm is connected with sliding panel.
Further, the grappling fixture structure includes that, in two holders being oppositely arranged up and down, each holder includes support
Frame, be connected on bracket and can opposing brackets rotate clinching and be used to order about clinching in bracket along carriage turns
Actuator, bracket is arranged on one end of main body arm, and the bracket outside is formed with holding body.
Further, the clinching is arranged on the top surface of bracket, and the middle part of clinching is connected on bracket by a bearing pin, made
The front end and rear end for obtaining clinching can be around bearing pin rotations, and clinching one end is formed with and supports projection, telescopic end and the clinching of actuator
The other end is connected.
Further, the frame includes vertical rod long, and the two ends of the vertical rod long are provided with two tracks, the sliding panel
On be provided with slide rail, slide rail coordinates installs in orbit, and can be slided up and down along track.
Further, the main body cylinder of the driver is installed between two vertical rods long, the piston-rod end of the main body cylinder
Linking arm is hinged with, lifting pilot hole is offered in the vertical rod long, the connecting rod passes through lifting pilot hole, and and sliding panel
Connection.
Further, it is each to deposit inner support and support arm of the roll stand including longitudinally parallel setting, inner support and support arm
Between opposite side top be provided with support protrusion, be used to carry roll body.
Further, the support arm is adjacent to the outside of underframe, inner support adjacent to underframe central side, between two inner supports
With gap, each depositing has gap between the inner support of roll stand and support arm, roller is deposited in the gap between two inner supports with each
Gap width between the inner support and support arm of frame is identical.
Compared with prior art, the utility model is used for the roll changing carriage of steel band manufacture line by setting transversely movable branch
Support, sets three groups of tracks on support frame, and every group of track can be aligned with carrier group trapped orbit, be easy to old roller
Storage and new roller take, roll body is rapidly changed in realization, improves roll change efficiency, and then improve the production effect of rolled plate
Rate.
Brief description of the drawings
Fig. 1 is the structural representation of the roll changing carriage that the utility model is used for steel band manufacture line;
Fig. 2 is the top view of the roll changing carriage that the utility model is used for steel band manufacture line;
Fig. 3 is the front view of the grappling fixture device of the roll changing carriage that the utility model is used for steel band manufacture line;
Fig. 4 is the left view of the grappling fixture device of the roll changing carriage that the utility model is used for steel band manufacture line;
Fig. 5 is the amplification assumption diagram in I portions in Fig. 3;
Fig. 6 is the amplification assumption diagram in II portions in Fig. 3;
Fig. 7 is the structural representation of another embodiment of the utility model roll changing carriage.
Specific embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment, in the case where not conflicting, the feature in embodiment and embodiment in the application can be mutually combined, below will ginseng
Examine accompanying drawing and describe the utility model in detail in conjunction with the embodiments.
Fig. 1, Fig. 2 are referred to, a kind of roll changing carriage for steel band manufacture line is used to change the roll body on steel band manufacture line,
Such as working roll, intermediate calender rolls.Roll changing carriage includes coaster 100, on coaster 100 and can the relative transverse movement of coaster 100 (i.e.
The direction vertical with the direction of motion of coaster 100 in the horizontal plane) support frame 200 and be arranged on coaster 100 and can be relative
The grappling fixture device 300 of the lengthwise movement of support frame 200.
The bottom of coaster 100 is provided with some rollers 102, and roller 102 is arranged in correspondence with rail, with by a drive device
(not shown) drives makes coaster 100 be moved on rail, and close to steel band manufacture line, grappling fixture device 300 can capture steel near roll body
With the roll body in processing line roll compacting equipment, roll body is extracted out and is changed.Coaster plate body 101, coaster plate are formed with coaster 100
Two guide rails 1011 are abreast provided with body 101, two horizontally sets of guide rail 1011, the direction of motion with coaster 100 is vertical, two
Support frame as described above 200 is installed, support frame 200 can be slided along two on coaster 100 guide rail 1011 on bar guide rail 1011.
One end of coaster 100 is formed as carrier, be installed with carrier the first gear slide rail 103 that extends longitudinally with
And the first guide groove slide rail 104, the guide groove slide rail 104 of first gear slide rail 103 and first extends parallel to the guide rail of neighbour
1011 side, the bearing of trend with guide rail 1011 is vertical, and 103 and first guide groove slide rail of first gear slide rail 104 coordinates shape
As the fixed set of rails on coaster 100, it is used to grappling fixture device 300, fixed set of rails and the T-shaped company of two guide rail 1011 are installed
Connect, grappling fixture device 300 can be slided in fixed set of rails.
Support frame 200 is arranged on two guide rails 1011 of coaster 100, and can be moved on two guide rails 1011, is supported
Sensor (not shown) is installed, to control sliding stroke of the support frame 200 on two guide rails 1011 on frame 200.Support frame
200 sides are provided with drive mechanism, are used to drive support frame 200 to be slided on guide rail 1011, can so be easy to implement to setting side by side
The roll body put in steel band manufacture line roll compacting equipment is aligned respectively.
Support frame 200 include underframe 201 and be formed in both sides on underframe 201 deposit roll stand 202.Open the bottom of underframe 201
It is provided with the chute coordinated with guide rail 1011.It is each to deposit inner support 2021 and support arm of the roll stand 202 including longitudinally parallel setting
2022, support arm 2022 adjacent to the outside of underframe 201, inner support 2021 adjacent to underframe 201 central side, two inner supports 2021 it
Between have gap, it is each deposit between the inner support 2021 of roll stand 202 and support arm 2022 have gap, two inner supports 2021 it
Between gap it is identical with each gap width deposited between the inner support 2021 of roll stand 202 and support arm 2022.It is each to deposit roll stand
Opposite side top between 202 inner support 2021 and support arm 2022 is provided with support protrusion 2023, is used to carry roll body.Bottom
The opposite side of two inner supports 2021 is relatively provided with the guide groove slide rail 205 of second gear slide rail 204 and second on frame 201, is formed as
The intermediate rail group of support frame 200, intermediate rail group is slided with for grappling fixture device 300.The teeth groove of second gear slide rail 204 with
The facewidth of the teeth groove of first gear slide rail 103 is identical, after first gear slide rail 103 is docked with second gear slide rail 204, to grab
Head device 300 slides into the second of support frame 200 between the guide groove slide rail 104 of first gear slide rail 103 and first of coaster 100
Between the guide groove slide rail 205 of gear slide rail 204 and second.
Fig. 1,3 are please referred to, grappling fixture device 300 is slidably disposed on the fixed set of rails on the carrier of coaster 100
On.Grappling fixture device 300 includes frame 10, in frame 10 and can the roll change grappling fixture mechanism that slide up and down of relative frame 10
20th, the driver 30 of the up and down motion of roll change grappling fixture mechanism 20 is ordered about, is used in the frame 10 to order about grappling fixture device 300 and is moved
Drive component 40.
Frame 10 includes base plate 12 and a pair of supporting being set in parallel on base plate 12.Each support frame includes long vertical
Bar 13, short stanchion 14 and it is connected to the connecting rod 15 of vertical rod long 13 and the top of short stanchion 14.Vertical rod long 13 is located at neighbouring support
The side of frame 200, short stanchion 14 is located remotely from the side of support frame 200.Installed towards the side of support frame 200 in vertical rod long 13
There is track 11, be used to coordinate roll change grappling fixture mechanism 20, slide to rise in frame 10 along track 11 for roll change grappling fixture mechanism 20
Drop.Refer to Fig. 4, offered in vertical rod long 13 lifting pilot hole 131, for roll change grappling fixture mechanism 20 pass through and with driver 30
Connection.Additionally, referring to Fig. 5, the circumferential lateral surface subscript of vertical rod long 13 is provided with scale, is used to reference to roll change grappling fixture mechanism 20 with respect to machine
The sliding distance of frame 10.Diagrammatically shown graduated scale is set to -100mm to+100mm, and is a scale division value per 1mm, is set by mark
Scale, in order to the slip spacing of precisely regulation roll change grappling fixture mechanism 20, realizes the degree of accuracy of roll change.
Fig. 3 is referred to, roll change grappling fixture mechanism 20 is liftably arranged in frame 10, and roll change grappling fixture mechanism 20 is used to clamp
Roll body.Roll change grappling fixture mechanism 20 includes main body arm 21, is arranged on the grappling fixture structure of the one end of main body arm 21 and is formed in main body arm
The sliding panel 23 of 21 other ends.Grappling fixture structure is included in two holders 22 being oppositely arranged up and down, in case two can be captured simultaneously
Individual roll body.Fig. 6 is referred to, each holder 22 includes bracket 221, clinching 222 and actuator 223.Bracket 221 is connected to master
On the end face of body arm 21, cavity is formed with bracket 221, to house actuator 223, bracket 221 is away from the end face of main body arm 21
Surface is formed with holding body 2211, the top surface of the top surface less than bracket 221 of holding body 2211;Clinching 222 is arranged on bracket 221
Top surface, the middle part of clinching 222 is connected on bracket 221 by a bearing pin 2222 so that the front end of clinching 222 can be around pin with rear end
The rotation of axle 2222, the front end of clinching 222 has been formed down and has supported raised 2221, and the rear end of clinching 222 offers hinge hole and actuator
223 telescopic end is hinged, and when the expansion link of actuator 223 is ejected upwards, the front end of clinching 222 rotates down around bearing pin 2222,
Support raised 2221 to push, and coordinate with the top surface of holding body 2211, roll body 400 is clamped, during Fig. 6 is shown, upper and lower two clampings
Part 22 is clamped with two roll bodies 400 simultaneously.In the present embodiment, actuator 223 uses cylinder.
Fig. 2 and Fig. 3 is referred to, slide rail 231 is provided with sliding panel 23 and is coordinated with the track 11 in two vertical rods long 13, slide rail
231 can slide up and down along track 11.Driver 30 is built up in frame 10, is used to drive sliding panel 23 to lift.Driver 30 is wrapped
Include main body cylinder and linking arm 232.Main body cylinder is installed between two vertical rods long 13, and specifically, main body cylinder is fixed on a fix bar
On, fix bar is laterally positioned between two vertical rods long 13, and the two ends of fix bar are connected with vertical rod long 13, in this way, driver 30
Regularly it is built up in the side of sliding panel 23.The end of the expansion link on linking arm 232 and main body cylinder is hinged, linking arm 232
The other end is connected through lifting pilot hole 131 with sliding panel 23, is stretched by the flexible rod end of driver 30, drives sliding panel 23
Slided along track 11 and lifted, so as to drive the lifting of roll change grappling fixture mechanism 20.In the present embodiment, main body cylinder is oil cylinder.Further
Ground, the middle part of the side of sliding panel 23 can be provided with indicating arm 233, and indicating arm 233 indicates the scale in the circumferential lateral surface of vertical rod long 13, with
Easily and accurately adjust the adjustable height of roll change grappling fixture mechanism 20, it is ensured that the degree of accuracy of roll change.
Drive component 40 is used to order about grappling fixture device 300 and moves, and drive component 40 includes the driving on base plate 12
Motor 41, the driving wheel (not shown) on the main shaft of motor 41 and the driven pulley 42 coordinated with driving wheel.Drive
Dynamic motor 41 is fixed on base plate 12 and the main shaft of motor 41 passes through base plate 12, and master is provided with the main shaft of motor 41
Driving wheel (not shown), driving wheel is placed in the bottom of base plate 12, is intermeshed with driven pulley 42.On driven pulley 42 and coaster 100 the
One gear slide rail 103 is intermeshed, and is rotated with by motor 41, drives driven pulley 42 to rotate, and then drive roll change grappling fixture
Mechanism 20 moves along first gear slide rail 103, and after first gear slide rail 103 is docked with gear slide rail 204, drive component 40 connects
Two being entered to grappling fixture device 300 and depositing intermediate rail group between roll stand 202, driven pulley 42 is engaged with second gear slide rail 204.
Grappling fixture device 300 further includes that being arranged on the outside of frame 10 is used to and the first guide groove slide rail 104 and the second guide groove
The guide pad 50 that slide rail 205 coordinates.Guide pad 50 is fixed on the side away from driven pulley 42 of base plate 12, the side shape of guide pad 50
Into there is guide protrusions 52, guide protrusions 52 are placed in the gathering sill of the first guide groove slide rail 104 of coaster 100.By motor
41 rotate, and drive grappling fixture device 300 that the intermediate rail group of support frame 200, driven pulley are slid into by the fixed set of rails of coaster 100
42 are engaged with second gear slide rail 204, and guide protrusions 52 are slided in the gathering sill of the second guide groove slide rail 205.
During work, coaster 100 is moved at steel band manufacture line roll compacting equipment along rail, and support frame 200 is slided along guide rail 1011
It is dynamic so that second gear slide rail 204 and second guide groove slide rail of the axis direction of roll body 400 in the opposite side of two inner support 2021
Between 205 gap, and on the advance decline line of holder 22;Drive component 40 starts, and drive component 40 is grabbed together with roll change
Head mechanism 20 is slid into the intermediate rail group of support frame 200 by the fixed set of rails of coaster 100, and driver 30 orders about roll change grappling fixture
Mechanism 20 lifts, and roll change grappling fixture mechanism 20 grasps one end of roll body 400, and then roll change grappling fixture mechanism 20 is along second gear slide rail
In 204 return to the fixed set of rails of coaster 100, then roll body 400 can be extracted out.When roll change grappling fixture mechanism 20 grasps roll body,
Ejected upwards by the piston rod of drive cylinder 223, supporting for the one end of clinching 222 raised 2221 is pushed, and with holding body 2211
Coordinate, clamp roll body.Drive component 40 orders about roll change grappling fixture mechanism 20 and returns back to cunning by the intermediate rail group slip of support frame 200
The fixed set of rails of car 100, now, the roll body clamped by roll change grappling fixture mechanism 20 is located at the top of support frame 200, then drives branch
Support 200 is to a side shifting so that clamped roll body deposits the top of roll stand 202 positioned at one, and then, driver 30 orders about roll change and grabs
Head mechanism 20 declines, and roll body is deposited to the corresponding projection for depositing support protrusion 2023 in roll stand 202;Drive support frame 200
It is another to deposit that the top of roll stand 202 is standby new to another side shifting so that another roll stand 202 of depositing is aligned with grappling fixture device 300
Roller, the roll change grappling fixture mechanism 20 of grappling fixture device 300 starts the new roller lifting of grasping, then drives support frame 200 to move again so that
First gear slide rail 103 is docked with second gear slide rail 204, and then, drive component 40 drives roll change grappling fixture mechanism 20 by coaster
100 fixed set of rails slides into the intermediate rail group of support frame 200, and new roller is loaded to old roller into the roll body pilot hole after extracting out
In.In this way, roll change is completed.
Fig. 7 is referred to, in order to improve roll change efficiency, the inner support 2021 and the phase of support arm 2022 of roll stand 202 is deposited at two
Offside is respectively provided with the second gear slide rail 204 and the second guide groove slide rail 205, is formed as the first avris set of rails and second
Avris set of rails.In this way, coaster 100 is moved at rolled stainless steel line along rail, support frame 200 is slided along guide rail 1011,
Deposit roll stand 202 with behind the relative position of grappling fixture device 300, after roll change grappling fixture mechanism 20 directly captures old roll body, the return of grappling fixture device 300
To after between the guide groove slide rail 104 of first gear slide rail 103 and first of coaster 100, roll change grappling fixture mechanism 20 declines, then old roll body
Directly it is carried in the support protrusion 2023 that this is deposited in roll stand 202, when roll change grappling fixture mechanism 20 grasps roll body, by driving gas
The piston rod of cylinder 223 is ejected upwards, and the projection 2221 that supports of the one end of clinching 222 is pushed, and is coordinated with holding body 2211, clamps work
Make roller or intermediate calender rolls;Then support frame 200 is moved, and another to deposit the contraposition grappling fixture of roll stand 202 device 300, roll change grappling fixture mechanism 20 will
In depositing the standby new roller crawl in roll stand 202 and directly pushing to roll body pilot hole, in this way, needing not move through intermediate rail
Conjunction grappling fixture device 300 is assembled, roll change process can be simplified.
In sum, the utility model roll changing carriage is set by setting transversely movable support frame 200 on support frame 200
Put two and deposit roll stand, two to deposit and set intermediate rail between roll stand and assemble the fixed set of rails closed on one end carrier of coaster 100, fixation
Moveable grappling fixture device 300 is set in set of rails, and crawl roll body is moved back after being moved on support frame 200 by grappling fixture device 300
Fix set of rails after returning, then transverse shifting support frame 200, make to deposit on roll stand and carrier for placing grappling fixture device 300
The contraposition of fixed set of rails, be easy to that being stored in for old roller one is deposited in roll stand and taken in another new roller purchased in roll stand of depositing
Take, transverse shifting support frame 200 makes to fix set of rails and installs the contraposition of intermediate rail group again, realizes the installation to new roller, leads to
Cross and liftable roll change grappling fixture mechanism 20 is set, be easy to be adjusted the height of roll body and place roll body, additionally, further may be used
Setting avris set of rails in roll stand is deposited two, can further simplify the movement of support frame 200.Above-mentioned roll changing carriage can be realized rapidly
Roll body is changed, roll change efficiency is improved, and then improve the production efficiency of steel band processing.
Embodiment of the present utility model is the foregoing is only, the scope of the claims of the present utility model is not thereby limited, it is every
The equivalent structure or equivalent flow conversion made using the utility model description, or directly or indirectly it is used in other phases
The technical field of pass, is similarly included in scope of patent protection of the present utility model.
Claims (9)
1. a kind of roll changing carriage for steel band manufacture line, it is characterised in that:Including coaster (100), support frame (200) and grappling fixture
Device (300), is provided with two guide rails (1011) horizontally-parallelly on coaster (100), one end of coaster (100) is longitudinally provided with
One gear slide rail (103) and the first guide groove slide rail (104), form fixed set of rails, with two T-shaped companies of guide rail (1011)
Connect, for installing grappling fixture device (300), be slidably mounted in coaster (100) two lead support frame (200) fixed set of rails
On rail (1011), support frame (200) including underframe (201) and be formed in underframe (201) both sides deposit roll stand (202), underframe
(201) second gear slide rail (204) and the second guide groove slide rail (205) are relatively provided between in two depositing roll stand (202) on, with shape
Into the intermediate rail group of support frame (200), grappling fixture device (300) is including frame (10) and in frame (10) and can phase
The roll change grappling fixture mechanism (20) slided up and down to frame (10), by slide support frame as described above (200) cause intermediate rail group with
Fixed set of rails is aligned, so that grappling fixture device (300) is slipped into intermediate rail group.
2. the roll changing carriage for steel band manufacture line according to claim 1, it is characterised in that:The grappling fixture device (300)
Including being used to order about the relative drive component (40) for depositing roll stand (202) motion of grappling fixture device (300), machine in frame (10)
Frame (10) includes base plate (12), and drive component (40) is including the motor (41) on base plate (12), installed in driving
Driving wheel on motor (41) main shaft and the driven pulley (42) with driving wheel cooperation, driving wheel are placed in base plate (12) bottom, with
Driven pulley (42) is intermeshed, and driven pulley (42) is intermeshed with the first gear slide rail (103) on coaster (100).
3. the roll changing carriage for steel band manufacture line according to claim 2, it is characterised in that:The roll change grappling fixture mechanism
(20) including main body arm (21), be arranged on the grappling fixture structure of main body arm (21) one end and be formed in main body arm (21) other end
Sliding panel (23), the linking arm (232) that driver (30) is hinged including main body cylinder and with the expansion link end on main body cylinder, even
The other end for connecing arm (232) is connected with sliding panel (23).
4. the roll changing carriage for steel band manufacture line according to claim 3, it is characterised in that:The grappling fixture structure includes
Two holders (22) being oppositely arranged up and down, each holder (22) including bracket (221), be connected on bracket (221) and
The clinching (222) that rotates of opposing brackets (221) and can be used to order about clinching (222) along bracket in the bracket (221)
(221) actuator (223) for rotating, bracket (221) on the end face of main body arm (21), the bracket (221) outside shape
Into there is holding body (2211).
5. the roll changing carriage for steel band manufacture line according to claim 4, it is characterised in that:The clinching (222) is installed
In the top surface of bracket (221), the middle part of clinching (222) is connected on bracket (221) by a bearing pin (2222) so that clinching
(222) front end can be around bearing pin (2222) rotation with rear end, and clinching (222) one end is formed with and supports raised (2221), actuator
(223) telescopic end is connected with the other end of clinching (222).
6. the roll changing carriage for steel band manufacture line according to claim 3, it is characterised in that:The frame (10) is including length
Vertical rod (13), the two ends of the vertical rod (13) long are provided with track (11), and slide rail (231) is provided with the sliding panel (23),
Slide rail (231) coordinates on track (11), and can be slided up and down along track (11).
7. the roll changing carriage for steel band manufacture line according to claim 6, it is characterised in that:The master of the driver (30)
Body cylinder is installed between two vertical rods (13) long, and the piston-rod end of the main body cylinder is hinged with the linking arm (232), the length
Offer lifting pilot hole (131) in vertical rod (13), the linking arm (232) is through lifting pilot hole (131), and and sliding panel
(23) connect.
8. the roll changing carriage for steel band manufacture line according to claim 1, it is characterised in that:It is each to deposit roll stand (202) bag
The inner support (2021) and support arm (2022) of longitudinally parallel setting are included, between inner support (2021) and support arm (2022)
Opposite side top is provided with support protrusion (2023), is used to carry roll body.
9. the roll changing carriage for steel band manufacture line according to claim 8, it is characterised in that:The support arm (2022) is adjacent
The outside of nearly underframe (201), the central side of the neighbouring underframe (201) of inner support (2021), between having between two inner supports (2021)
Gap, has gap, between two inner supports (2021) between each inner support (2021) for depositing roll stand (202) and support arm (2022)
Gap it is identical with the gap width between each inner support (2021) for depositing roll stand (202) and support arm (2022).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621290354.5U CN206305205U (en) | 2016-11-29 | 2016-11-29 | A kind of roll changing carriage for steel band manufacture line |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621290354.5U CN206305205U (en) | 2016-11-29 | 2016-11-29 | A kind of roll changing carriage for steel band manufacture line |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206305205U true CN206305205U (en) | 2017-07-07 |
Family
ID=59250806
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201621290354.5U Active CN206305205U (en) | 2016-11-29 | 2016-11-29 | A kind of roll changing carriage for steel band manufacture line |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206305205U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106424148A (en) * | 2016-11-29 | 2017-02-22 | 福建宏旺实业有限公司 | Roll changing carriage for steel belt machining line and roll changing method |
| CN109261722A (en) * | 2018-07-27 | 2019-01-25 | 合肥神诺机械有限公司 | Combined guide roller |
| CN114029840A (en) * | 2021-11-02 | 2022-02-11 | 浙江谋皮环保科技有限公司 | Steel plate surface treatment system |
-
2016
- 2016-11-29 CN CN201621290354.5U patent/CN206305205U/en active Active
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106424148A (en) * | 2016-11-29 | 2017-02-22 | 福建宏旺实业有限公司 | Roll changing carriage for steel belt machining line and roll changing method |
| CN109261722A (en) * | 2018-07-27 | 2019-01-25 | 合肥神诺机械有限公司 | Combined guide roller |
| CN114029840A (en) * | 2021-11-02 | 2022-02-11 | 浙江谋皮环保科技有限公司 | Steel plate surface treatment system |
| CN114029840B (en) * | 2021-11-02 | 2022-11-08 | 浙江谋皮环保科技有限公司 | Steel sheet surface treatment system |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206665557U (en) | Roll changing carriage | |
| CN206305205U (en) | A kind of roll changing carriage for steel band manufacture line | |
| CN206253785U (en) | A kind of multi-head straight gas cutting machine | |
| CN106734225A (en) | The roll-changing method of roll changing carriage and the roll changing carriage | |
| CN106424148B (en) | A kind of roll changing carriage and roll-changing method for steel band manufacture line | |
| CN103658442B (en) | Ladle body automatic sealing package bottom, bind lid machine | |
| CN208308354U (en) | A kind of automobile maintenance lifting platform | |
| CN110935980B (en) | Flame cutting machine for steel plate machining | |
| CN210414585U (en) | Clamping and overturning bolt reversing device for bearing cover of engine cylinder cover | |
| CN206605149U (en) | A kind of auxiliary support mechanism of automobile absorber oil drum seam welder | |
| CN209554238U (en) | Coating and polishing machine noise reduction equipment | |
| CN105236129A (en) | Mechanical arm grabbing mechanism | |
| CN110255203A (en) | A kind of door sash product piece transmission code material equipment | |
| CN205183320U (en) | Calender | |
| CN110091581B (en) | Automatic bag removing equipment | |
| CN2827651Y (en) | Device for withdrawing bearing race of support roller of rolling mill | |
| CN203998069U (en) | Manipulator captures mechanism | |
| CN203410650U (en) | Profile steel collecting device | |
| CN214263299U (en) | Feeding device of square and rectangular tube forming machine | |
| CN109277804A (en) | An automatic clamping machine | |
| CN210140287U (en) | Paper feeding mechanism of automatic collating machine | |
| CN210790871U (en) | Steel pipe supports frock for cutting | |
| CN210498157U (en) | Vertical ring rolling mill | |
| CN207656197U (en) | A kind of roll-changing equipment of strip machining production line | |
| CN106925475A (en) | Full-automatic fuel injection equipment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder | ||
| CP01 | Change in the name or title of a patent holder |
Address after: 355006 Wan Wu Zhen Shang Yang Cun, Fu'an City, Ningde City, Fujian Province Patentee after: FUJIAN HONGWANG INDUSTRIAL Co.,Ltd. Patentee after: Hongwang Holding Group Co.,Ltd. Address before: 355006 Wan Wu Zhen Shang Yang Cun, Fu'an City, Ningde City, Fujian Province Patentee before: FUJIAN HONGWANG INDUSTRIAL Co.,Ltd. Patentee before: HONGWANG INVESTMENT GROUP Co.,Ltd. |