One kind washing eddy flow tower Download PDFInfo
- Publication number
- CN206262310U CN206262310U CN201621402641.0U CN201621402641U CN206262310U CN 206262310 U CN206262310 U CN 206262310U CN 201621402641 U CN201621402641 U CN 201621402641U CN 206262310 U CN206262310 U CN 206262310U
- Authority
- CN
- China
- Prior art keywords
- eddy flow
- tower
- tower body
- ash bucket
- water tank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Cyclones (AREA)
Abstract
The utility model discloses one kind washing eddy flow tower, including ash bucket support, the ash bucket support restocking is provided with ash bucket, cyclone dust collectors are installed at the top of ash bucket, the outlet with its inner space is provided with the top of cyclone dust collectors, the back side of cyclone dust collectors is provided with the import with its inner space, cyclic water tank is provided with the left of the ash bucket support, the one side of cyclic water tank is provided with water circulating pump, the water inlet pipe of the water circulating pump and the inner space of cyclic water tank, the both sides of cyclic water tank are provided with tower body support.The washing eddy flow tower, rotation using the windmill blade in eddy flow tower tower body makes gas rotating upward, dust is rotated and is centrifuged, reach the purpose of dedusting, in this course, the water in cyclic water tank is pumped into eddy flow tower tower body using water circulating pump and dust is sprayed such that it is able to the dirt absorption in gas, absorb more thoroughly, impurity-eliminating effect is preferable.
Description
Technical field
The utility model is related to technical field of dust removal equipment, specially a kind of washing eddy flow tower.
Background technology
Industrial dedusting equipment is the equipment that industrial dust is separated from flue gas, be widely used in metallurgy, mine,
In the industries such as building materials, casting, chemical industry, tobacco, electronics, pitch, cement, machinery, grain, machining, boiler, Flour production
The recycling of workshop dust purification body and dusty gas, the performance of deduster passes through to remove with accessible gas flow, gas
Drag losses and efficiency of dust collection during dirt device are expressed.Meanwhile, the price of deduster, operation and maintenance cost, long service life
Short and operational administrative difficulty or ease are also the key factor for considering its performance.Current industrial dedusting equipment be difficult to make mostly dust with
Gas is sufficiently separated, and is difficult to be purged the peculiar smell in gas.
Utility model content
(One)The technical problem of solution
In view of the shortcomings of the prior art, the utility model provides a kind of washing eddy flow tower, solves current industry and removes
Dirt equipment mostly is difficult to make dust be sufficiently separated with gas, and be difficult to the problem for being purged the peculiar smell in gas.
(Two)Technical scheme
To realize object above, the utility model is achieved by the following technical programs:One kind washing eddy flow tower, including
Ash bucket support, the ash bucket support restocking is provided with ash bucket, and cyclone dust collectors, the top of cyclone dust collectors are provided with the top of ash bucket
The outlet with its inner space is provided with, the back side of cyclone dust collectors is provided with the import with its inner space, the ash bucket branch
Be provided with cyclic water tank on the left of frame, the one side of cyclic water tank is provided with water circulating pump, the water inlet pipe of the water circulating pump with
The inner space of cyclic water tank, the both sides of cyclic water tank are provided with tower body support, and the welded top of two tower body supports has eddy flow
Tower tower body, the bottom of eddy flow tower tower body is provided with the outlet pipe with its inner space, is provided with and it in the middle part of eddy flow tower tower body
The circulating water intake of inner space, is connected, the rotation between the circulating water intake and the delivery port of water circulating pump by water pipe
The back side of stream tower tower body is provided with the tower body air inlet with its inner space, at the top of the tower body air inlet and cyclone dust collectors
Connected by the second bend pipe between outlet, blower fan is provided with the left of the cyclic water tank, be provided with the outlet of blower fan vertical
The blast pipe of setting, is provided with air inlet on the right side of blower fan, by the between the air inlet and tower body air outlet
One bend pipe is connected.
Preferably, the blast pipe top set rain hat, the rain cap be circular plate-like shape, the edge of rain cap bottom surface with
Welded by bonding jumper between the tip edge of blast pipe.
Preferably, it is provided with muffler between the outlet of the bottom and blower fan of the blast pipe.
Preferably, the ash bucket is funnel-form, and dust bucket is placed with below ash bucket, and the bottom of the ash bucket is run through and prolonged
Reach the inner chamber of dust bucket.
Preferably, annular bung is covered with the top of the dust bucket, annular bung is set in the outside of ash bucket, dust bucket
Bottom roller is installed, the side of dust bucket is connected with handle.
Preferably, the distance between the bottom of eddy flow tower tower body bottom outlet pipe and cyclic water tank inner chamber bottom surface are less than
One centimetre.
(Three)Beneficial effect
The utility model provides a kind of washing eddy flow tower.Possesses following beneficial effect:
(1), the washing eddy flow tower, the large-scale dust in gas is separated first with cyclone dust collectors, and using collection
Dust barrel is collected to large-scale dust, facilitates the treatment to dust, and what is do not removed in cyclone dust collectors miniature enters into eddy flow
In tower tower body, using the rotation of the windmill blade in eddy flow tower tower body make gas rotating upwards, dust is rotated and from
The heart, reaches the purpose of dedusting, in this course, the water in cyclic water tank is pumped into eddy flow tower tower body using water circulating pump
Dust is sprayed, the comprehensive work such as flue dust collides, adheres to, condensing with the absorbing liquid by being atomized, centrifugation
With, the inwall of eddy flow tower tower body is thrown to, the outlet pipe of eddy flow tower tower body is flowed to the moisture film of inwall such that it is able to in gas
Dirt absorption, absorb more thoroughly, and recirculated water sulfur dioxide in gas etc. can be also harmful to and contain peculiar smell
Material absorbed, impurity-eliminating effect is preferable.
(2), the washing eddy flow tower, the sewage that eddy flow tower tower body inner bottom part outlet pipe is discharged is received using cyclic water tank
Collection, facilitates focusing on for sewage, and bottom and cyclic water tank inner chamber bottom surface due to eddy flow tower tower body bottom outlet pipe
The distance between be less than one centimetre, so as to reduce the pressure loss in eddy flow tower tower body, efficiency of dust collection is higher, the setting of blower fan
Tower body air outlet can be made to form negative pressure suction force, facilitate the discharge of gas, setting for muffler can be to blast pipe discharge
Gas carries out noise reduction treatment, reduces noise pollution.
Brief description of the drawings
Fig. 1 is the utility model right flank dimensional structure diagram;
Fig. 2 is the utility model left surface dimensional structure diagram.
In figure:1 blower fan, 2 mufflers, 3 blast pipes, 4 rain caps, 5 first bend pipes, 6 eddy flow tower tower bodies, 7 tower body air outlets, 8
Second bend pipe, 9 cyclone dust collectors, 10 ash buckets, 11 ash bucket supports, 12 dust buckets, 13 water circulating pumps, 14 cyclic water tanks, 15 tower bodies
Support, 16 air inlets, 17 tower body air inlets, 18 circulating water intakes.
Specific embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment for being obtained, belongs to the scope of the utility model protection.
Fig. 1-2 is referred to, the utility model provides a kind of technical scheme:One kind washing eddy flow tower, including ash bucket support 11,
The restocking of ash bucket support 11 is provided with ash bucket 10, and ash bucket 10 is funnel-form, and the lower section of ash bucket 10 is placed with dust bucket 12, the bottom of ash bucket 10
End is run through and extends to the inner chamber of dust bucket 12, prevents the top of the splashing of dust, dust bucket 12 to be covered with annular bung, can
Barrier effect is played to dust, annular bung is set in the outside of ash bucket 10, facilitate the taking-up of annular bung, sealed more tight
Real, the bottom of dust bucket 12 is provided with roller, facilitates the movement of dust bucket 12, and the side of dust bucket 12 is connected with handle, ash
The top of bucket 10 is provided with cyclone dust collectors 9, the large-scale dust in gas is separated using cyclone dust collectors 9, and utilize
Dust bucket 12 is collected to large-scale dust, facilitates the treatment to dust, and the top of cyclone dust collectors 9 is provided with and its inner chamber
The outlet of connection, the back side of cyclone dust collectors 9 is provided with the import with its inner space, and the left side of ash bucket support 11 is provided with to be followed
Ring water tank 14, the one side of cyclic water tank 14 is provided with water circulating pump 13, water inlet pipe and the cyclic water tank 14 of water circulating pump 13
Inner space, the both sides of cyclic water tank 14 are provided with tower body support 15, and the welded top of two tower body supports 15 has eddy flow tower tower
Body 6, the bottom of eddy flow tower tower body 6 is provided with the outlet pipe with its inner space, the bottom of the bottom outlet pipe of eddy flow tower tower body 6 with
The distance between inner chamber bottom surface of cyclic water tank 14 is less than one centimetre, using cyclic water tank 14 to the inner bottom part water outlet of eddy flow tower tower body 6
The sewage of pipe discharge is collected, and facilitates focusing on for sewage, and due to the bottom of the bottom outlet pipe of eddy flow tower tower body 6
One centimetre is less than with the distance between the inner chamber bottom surface of cyclic water tank 14, so as to reduce the pressure loss in eddy flow tower tower body 6, is removed
Dirt efficiency is higher, and the middle part of eddy flow tower tower body 6 is provided with the circulating water intake 18 with its inner space, circulating water intake 18 with follow
Connected by water pipe between the delivery port of ring water pump 13, the back side of eddy flow tower tower body 6 is provided with to be entered with the tower body of its inner space
Air port 17, is connected, in cyclone dust collectors 9 between the outlet at tower body air inlet 17 and the top of cyclone dust collectors 9 by the second bend pipe 8
Do not remove it is miniature enter into eddy flow tower tower body 6, the rotation using the windmill blade in eddy flow tower tower body 6 makes gas rotating
Upwards, dust is rotated and is centrifuged, reached the purpose of dedusting, in this course, using water circulating pump 13 by recirculated water
Water in case 14 is pumped into eddy flow tower tower body 6 and dust is sprayed, and flue dust collides with the absorbing liquid by being atomized, attached
, condense, the comprehensive effect such as centrifugation, be thrown to the inwall of eddy flow tower tower body 6, flow to eddy flow tower with the moisture film of inwall
The outlet pipe of tower body 6 such that it is able to the dirt absorption in gas, absorbs more thoroughly, and recirculated water also can be to gas
Interior sulfur dioxide etc. the is harmful to and material containing peculiar smell is absorbed, and impurity-eliminating effect is preferable.
The left side of cyclic water tank 14 is provided with blower fan 1, and vertically arranged blast pipe 3 is provided with the outlet of blower fan 1, exhaust
Muffler 2 is provided between the outlet of the bottom and blower fan 1 of pipe 3, setting for muffler 2 can be to the gas of the discharge of blast pipe 3
Noise reduction treatment is carried out, noise pollution is reduced, the top of blast pipe 3 sets rain hat 4, and rain cap 4 is circular plate-like shape, the bottom of rain cap 4
Welded by bonding jumper between the edge in face and the tip edge of blast pipe 3, prevent rainwater from pouring in down a chimney in blast pipe 3, blower fan 1
Right side is provided with air inlet 16, is connected by the first bend pipe 5 between air inlet 16 and tower body air outlet 7, blower fan 1
Setting can make tower body air outlet 7 form negative pressure suction force, facilitate the discharge of gas.
In sum, the washing eddy flow tower, thoroughly and efficiency high, efficient low energy is reliable, wide using scope for dedusting,
Cost of investment is low, and floor space is small, solves current industrial dedusting equipment and is difficult to make dust be sufficiently separated with gas mostly, and
The problem for being difficult to be purged the peculiar smell in gas.
It should be noted that herein, such as first and second or the like relational terms are used merely to a reality
Body or operation make a distinction with another entity or operation, and not necessarily require or imply these entities or deposited between operating
In any this actual relation or order.And, term " including ", "comprising" or its any other variant be intended to
Nonexcludability is included, so that process, method, article or equipment including a series of key elements not only will including those
Element, but also other key elements including being not expressly set out, or also include being this process, method, article or equipment
Intrinsic key element.In the absence of more restrictions.By sentence " including one ... the key element for limiting, it is not excluded that
Also there is other identical element in the process including the key element, method, article or equipment ".
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art,
It is appreciated that these embodiments can be carried out various changes in the case where principle of the present utility model and spirit is not departed from, repaiies
Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of washing eddy flow tower, including ash bucket support(11), it is characterised in that:The ash bucket support(11)Restocking is provided with ash bucket
(10), ash bucket(10)Top cyclone dust collectors are installed(9), cyclone dust collectors(9)Top be provided with and its inner space
Outlet, cyclone dust collectors(9)The back side be provided with import with its inner space, the ash bucket support(11)Left side set
There is cyclic water tank(14), cyclic water tank(14)One side water circulating pump is installed(13), the water circulating pump(13)Water inlet
Pipe and cyclic water tank(14)Inner space, cyclic water tank(14)Both sides tower body support is installed(15), two tower body supports
(15)Welded top have eddy flow tower tower body(6), eddy flow tower tower body(6)Bottom be provided with outlet pipe with its inner space,
Eddy flow tower tower body(6)Middle part be provided with circulating water intake with its inner space(18), the circulating water intake(18)With follow
Ring water pump(13)Delivery port between by water pipe connect, the eddy flow tower tower body(6)The back side be provided with and its inner space
Tower body air inlet(17), the tower body air inlet(17)With cyclone dust collectors(9)Pass through the second bend pipe between the outlet at top
(8)Connection, the cyclic water tank(14)Left side be provided with blower fan(1), blower fan(1)Outlet on vertically arranged row is installed
Tracheae(3), blower fan(1)Right side be provided with air inlet(16), the air inlet(16)With tower body air outlet(7)It
Between pass through the first bend pipe(5)Connection.
2. one kind according to claim 1 washes eddy flow tower, it is characterised in that:The blast pipe(3)Top be provided with
Rain cap(4), the rain cap(4)It is circular plate-like shape, rain cap(4)The edge and blast pipe of bottom surface(3)Tip edge between pass through
Bonding jumper is welded.
3. one kind according to claim 1 washes eddy flow tower, it is characterised in that:The blast pipe(3)Bottom and blower fan
(1)Outlet between be provided with muffler(2).
4. one kind according to claim 1 washes eddy flow tower, it is characterised in that:The ash bucket(10)It is funnel-form, ash bucket
(10)Lower section be placed with dust bucket(12), the ash bucket(10)Bottom run through and extend to dust bucket(12)Inner chamber.
5. one kind according to claim 4 washes eddy flow tower, it is characterised in that:The dust bucket(12)Top be covered with
Annular bung, annular bung is set in ash bucket(10)Outside, dust bucket(12)Bottom roller, dust bucket are installed(12)'s
Side is connected with handle.
6. one kind according to claim 1 washes eddy flow tower, it is characterised in that:The eddy flow tower tower body(6)Bottom water outlet
The bottom of pipe and cyclic water tank(14)The distance between inner chamber bottom surface is less than one centimetre.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621402641.0U CN206262310U (en) | 2016-12-20 | 2016-12-20 | One kind washing eddy flow tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621402641.0U CN206262310U (en) | 2016-12-20 | 2016-12-20 | One kind washing eddy flow tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206262310U true CN206262310U (en) | 2017-06-20 |
Family
ID=59045946
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621402641.0U Expired - Fee Related CN206262310U (en) | 2016-12-20 | 2016-12-20 | One kind washing eddy flow tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206262310U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107261734A (en) * | 2017-08-18 | 2017-10-20 | 安徽天顺环保设备股份有限公司 | A kind of cyclone type industrial dedusting equipment |
-
2016
- 2016-12-20 CN CN201621402641.0U patent/CN206262310U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107261734A (en) * | 2017-08-18 | 2017-10-20 | 安徽天顺环保设备股份有限公司 | A kind of cyclone type industrial dedusting equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207126318U (en) | A kind of sintered discharge gas waste heat recovery and purifier | |
CN2765660Y (en) | Multi-stage adjustable desulfurization dust collector | |
CN202835409U (en) | Smoke dust waste-heat utilization and dust removing device of low-capacity boiler | |
CN201320442Y (en) | Flue-gas dust removal and purification device | |
CN211216039U (en) | Industrial waste gas treatment device | |
CN201375870Y (en) | Environment-friendly flue gas purification dust collector | |
CN215539480U (en) | Atomizing dust removal device for mining | |
CN206262310U (en) | One kind washing eddy flow tower | |
CN103816759A (en) | Coaxial integrated multilayered centrifugal washing gas-clearing machine | |
CN202962190U (en) | Welding dedusting and purifying device | |
CN208959593U (en) | A kind of environment-friendly type industrial waste-gas purifier | |
CN208583122U (en) | A kind of dedusting and desulfurizing tower | |
CN208553596U (en) | A kind of industrial fan dust-extraction unit | |
CN104606989B (en) | High-gravity technology processes dust device | |
CN203635016U (en) | Steam dedusting hood of industrial chimney | |
CN205042310U (en) | Novel limekiln flue gas desulfurization dust pelletizing system | |
CN204952542U (en) | Novel frit stove flue gas dust removal device | |
CN210045025U (en) | Forging furnace dust collector | |
CN208642189U (en) | Coal-burning boiler tail fume and dust device | |
CN206404545U (en) | A kind of efficient phosphoric acid tail gas wash mill | |
CN203441518U (en) | Mining wet-type multi-channel dust remover | |
CN112354319A (en) | Multifunctional comprehensive rotational flow plate tower | |
CN201959693U (en) | Vortex type auto-excitation wet deduster | |
CN208824151U (en) | Improved high-efficiency rotating stream tray scrubber | |
CN221015131U (en) | Cyclone water film spray washing tower |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170620 Termination date: 20211220 |