- CN206135210U CN206135210U CN201621092973.3U CN201621092973U CN206135210U CN 206135210 U CN206135210 U CN 206135210U CN 201621092973 U CN201621092973 U CN 201621092973U CN 206135210 U CN206135210 U CN 206135210U
- Authority
- CN
- China
- Prior art keywords
- bus
- controller
- busbar
- cut
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本实用新型提供一种双母线分段的新型主接线,通过设置至少一个电力电子变压器,实现潮流的双向按需调配、有功无功复合支撑、电能质量隔离和控制、故障限流等综合控制功能。在两条母线之间、每条母线的相邻分段母线之间设置开断控制器,当所述开断控制器使用母联柔性控制器时,不仅能控制两条母线之间以及每条母线的相邻分段母线之间的通断状态,而且可以实现潮流的灵活分配。当与所述变压器连接的开断装置采用电力电子快速开断装置时,能实现系统故障的快速切除。与传统变电站双母线分段的主接线相比,本实用新型在传统主接线的基础上融入了电力电子设备,具备灵活可控、反应迅速等优势,实现了一系列综合控制功能。
The utility model provides a new type of main wiring with double bus bars segmented. By setting at least one power electronic transformer, comprehensive control functions such as two-way on-demand deployment of power flow, active and reactive composite support, power quality isolation and control, and fault current limiting are realized. . A breaking controller is set between two busbars and between adjacent subsection buses of each busbar. When the busbar flexible controller is used for the breaking controller, it can not only control the The on-off status between the adjacent sub-section buses of the busbar can realize the flexible distribution of the power flow. When the breaking device connected with the transformer adopts the power electronic quick breaking device, the system fault can be removed quickly. Compared with the main wiring of the traditional substation double-bus section, the utility model integrates power electronic equipment on the basis of the traditional main wiring, has the advantages of flexible controllability, rapid response, etc., and realizes a series of comprehensive control functions.
Description
技术领域technical field
本实用新型涉及电力技术领域,具体涉及一种双母线分段的新型主接线。The utility model relates to the technical field of electric power, in particular to a novel main connection with double bus bars segmented.
背景技术Background technique
随着智能电网建设步伐的加快,变电站由单一的电压变换节点逐渐向电网调控节点转变。未来变电站需要完成对电网潮流的灵活分配、快速控制保护等综合调控功能。With the accelerated pace of smart grid construction, substations are gradually changing from a single voltage conversion node to a grid regulation node. In the future, substations need to complete comprehensive control functions such as flexible distribution of grid power flow, rapid control and protection.
在传统变电站的双母线分段主接线结构中,通常采用传统一次设备,如铁磁式变压器、机械式断路器等。首先,现有双母线分段的主接线中普遍采用铁磁式变压器,该变压器只能实现变压,无法实现潮流灵活控制、有功无功支撑、电能质量控制、故障限流等一系列综合控制功能;其次,在传统的主接线方式中,两条母线之间以及每条母线的相邻分段母线之间的母联开关只有“分合”两种状态,无法实现潮流于两条母线以及每条母线的相邻分段母线的灵活分配;再次,机械式断路器开断延时较长,无法满足未来变电站对于快速切除故障的实际需求。In the double-bus section main wiring structure of traditional substations, traditional primary equipment, such as ferromagnetic transformers and mechanical circuit breakers, are usually used. First of all, ferromagnetic transformers are generally used in the main wiring of existing double busbar sections. This transformer can only realize voltage transformation, but cannot realize a series of comprehensive controls such as flexible power flow control, active and reactive power support, power quality control, and fault current limiting. function; secondly, in the traditional main wiring mode, the bus tie switch between two busbars and between the adjacent section busbars of each busbar only has two states of "opening and closing", which cannot realize the power flow between two busbars and The flexible allocation of adjacent sub-sections of each bus; thirdly, the opening delay of mechanical circuit breakers is long, which cannot meet the actual needs of future substations for rapid fault removal.
因此,面向未来智能电网对于变电站的功能需求,需要设置新的主接线形式。Therefore, in order to meet the functional requirements of the future smart grid for substations, it is necessary to set up a new main wiring form.
实用新型内容Utility model content
本实用新型要解决的第一个技术问题在于克服现有技术中的传统变压器无法实现潮流灵活控制等综合控制功能的缺陷;The first technical problem to be solved by the utility model is to overcome the defect that the traditional transformer in the prior art cannot realize comprehensive control functions such as flexible power flow control;
此外,本实用新型要解决的第二个技术问题在于现有技术中的母联开关无法实现潮流在两条母线之间以及每条母线的相邻分段母线之间灵活分配的缺陷;In addition, the second technical problem to be solved by the utility model lies in the defect that the bus tie switch in the prior art cannot realize the flexible distribution of power flow between two bus bars and between the adjacent section bus bars of each bus bar;
此外,本实用新型要解决的第三技术问题在于现有技术中的传统断路器无法快速切除故障的缺陷。In addition, the third technical problem to be solved by the utility model lies in the defect that the traditional circuit breaker in the prior art cannot quickly remove the fault.
有鉴于此,本实用新型提供一种双母线分段的新型主接线,包括第一母线和第二母线,所述第二母线包括多条分段母线,所述第一母线和所述第二母线的每条分段母线分别连接至少一条出线,至少包括:In view of this, the utility model provides a new type of main wiring with double bus bars segmented, including a first bus bar and a second bus bar, the second bus bar includes a plurality of segmented bus bars, the first bus bar and the second bus bar Each segmented bus of the bus is connected to at least one outgoing line, including at least:
第一变压器,所述第一变压器是电力电子变压器,所述第一变压器与第一开断装置的一端连接,所述第一开断装置的另一端通过第一隔离开关与所述第一母线连接、通过第二隔离开关与所述第二母线中的一条分段母线连接;A first transformer, the first transformer is a power electronic transformer, the first transformer is connected to one end of the first breaking device, and the other end of the first breaking device is connected to the first bus through a first isolating switch Connected, connected to a segmented bus in the second bus through a second isolating switch;
所述第二母线两端的两条分段母线,分别通过第一开断控制器与所述第一母线连接;The two segmented buses at both ends of the second bus are respectively connected to the first bus through a first breaking controller;
在所述第二母线的相邻分段母线之间设置有用于联络相邻分段母线的第二开断控制器。A second breaking controller for connecting adjacent segmented buses is arranged between adjacent segmented buses of the second busbar.
优选地,还包括一个或多个第二变压器,所述第二变压器与第二开断装置的一端连接,所述第二开断装置的另一端通过第三隔离开关与所述第一母线连接、通过第四隔离开关与所述第二母线的另一条分段母线连接。Preferably, it also includes one or more second transformers, the second transformer is connected to one end of the second breaking device, and the other end of the second breaking device is connected to the first bus through a third disconnector . Connect to another section bus of the second bus through the fourth disconnector.
优选地,所述第二变压器为常规变压器或电力电子变压器。Preferably, the second transformer is a conventional transformer or a power electronic transformer.
优选地,所述第一母线包括多条分段母线,且第一母线分段母线的条数与第二母线分段母线的条数相同,所述第一母线的每条分段母线分别连接至少一条出线,所述第一开断装置的另一端通过第一隔离开关与所述第一母线中的一条分段母线连接、通过第二隔离开关与所述第二母线中的相应分段母线连接。Preferably, the first busbar includes a plurality of segmented busbars, and the number of segmented busbars of the first busbar is the same as the number of segmented busbars of the second busbar, and each segmented busbar of the first busbar is respectively connected to At least one outgoing line, the other end of the first breaking device is connected to a segmented bus in the first bus through the first isolating switch, and connected to the corresponding segmented bus in the second bus through the second isolating switch connect.
优选地,在所述第一母线的分段母线与所述第二母线的相应分段母线之间,设置有用于联络第一母线和第二母线的第三开断控制器。Preferably, a third breaking controller for connecting the first bus and the second bus is provided between the section bus of the first bus and the corresponding section bus of the second bus.
优选地,在所述第一母线的相邻分段母线之间设置有用于联络相邻分段母线的第四开断控制器。Preferably, a fourth breaking controller for connecting adjacent segmented buses is provided between adjacent segmented buses of the first busbar.
优选地,所述第一开断装置和第二开断装置部分或全部使用电力电子快速开断装置或常规断路器。Preferably, part or all of the first breaking device and the second breaking device use power electronic quick disconnecting devices or conventional circuit breakers.
优选地,所述第一开断控制器、第二开断控制器、第三开断控制器、第四开断控制器部分或全部使用电力电子快速开断装置或常规断路器。Preferably, some or all of the first breaking controller, the second breaking controller, the third breaking controller and the fourth breaking controller use power electronic quick breaking devices or conventional circuit breakers.
优选地,所述第一开断控制器和第三开断控制器使用母联柔性控制器,所述母联柔性控制器用于调节第一母线和第二母线之间的潮流。Preferably, the first breaking controller and the third breaking controller use a bus-tie flexible controller, and the bus-tie flexible controller is used to adjust the power flow between the first bus and the second bus.
优选地,所述第二开断控制器和第四开断控制器使用母联柔性控制器,所述母联柔性控制器用于调节相邻两段母线之间的潮流。Preferably, the second breaking controller and the fourth breaking controller use a bus-tie flexible controller, and the bus-tie flexible controller is used to adjust the power flow between two adjacent bus sections.
本实用新型技术方案,具有如下优点:The technical scheme of the utility model has the following advantages:
1.本实用新型提供一种双母线分段的新型主接线,通过设置至少一个电力电子变压器,可以实现潮流的双向按需调配、有功无功复合支撑、电能质量隔离和控制、故障限流等综合控制功能。与传统变电站双母线分段的主接线形式相比,本实用新型在传统主接线形式的基础上融入了电力电子设备,具备灵活可控、反应迅速等优势,实现了一系列综合控制功能。1. This utility model provides a new type of main wiring with double bus bars segmented. By setting at least one power electronic transformer, it can realize two-way on-demand deployment of power flow, composite support of active and reactive power, isolation and control of power quality, fault current limiting, etc. Comprehensive control functions. Compared with the main wiring form of the traditional substation double-bus section, the utility model integrates power electronic equipment on the basis of the traditional main wiring form, has the advantages of flexible controllability, rapid response, etc., and realizes a series of comprehensive control functions.
2.本实用新型提供一种双母线分段的新型主接线,在两条母线之间以及每条母线的相邻分段母线之间设置有开断控制器。当所述开断控制器使用母联柔性控制器时,不仅能够控制两条母线之间以及每条母线的相邻分段母线之间的通断状态,而且可以实现潮流于两条母线之间以及每条母线的相邻分段母线之间的灵活分配。2. The utility model provides a new type of main wiring with double bus bars segmented, and a break controller is set between the two bus bars and between the adjacent segmented bus bars of each bus bar. When the break controller uses a bus-connected flexible controller, it can not only control the on-off state between two buses and the adjacent section buses of each bus, but also realize the power flow between two buses. And the flexible allocation between the adjacent segment busbars of each busbar.
3.本实用新型提供一种双母线分段的新型主接线,所述第一变压器与第一开断装置连接、所述第二变压器与第二开断装置连接,当所述开断装置采用电力电子快速开断装置时,可以实现系统故障的快速切除。3. The utility model provides a new type of main wiring with double busbar segments. The first transformer is connected to the first breaking device, and the second transformer is connected to the second breaking device. When the breaking device adopts When the power electronic quick disconnect device is used, the quick removal of system faults can be realized.
附图说明Description of drawings
为了更清楚地说明本实用新型具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本实用新型的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the specific implementation of the utility model or the technical solutions in the prior art, the accompanying drawings that need to be used in the description of the specific implementation or the prior art will be briefly introduced below. Obviously, the following descriptions The accompanying drawings are some implementations of the utility model, and those skilled in the art can also obtain other drawings according to these drawings without any creative work.
图1为一种双母线分段的新型主接线示意图;Figure 1 is a schematic diagram of a new type of main wiring of a double bus section;
图2为一种双母线分段的连接两个变压器的新型主接线示意图;Figure 2 is a schematic diagram of a new type of main wiring connecting two transformers with double busbar segments;
图3为一种双母线双分段的连接两个变压器的新型主接线示意图。Fig. 3 is a schematic diagram of a new type of main wiring connecting two transformers with double busbars and double segments.
其中,附图标记为:Wherein, reference sign is:
11-第一变压器,12-第一开断装置,13-第一隔离开关,14-第二隔离开关;11-the first transformer, 12-the first breaking device, 13-the first isolating switch, 14-the second isolating switch;
21-第二变压器,22-第二开断装置,23-第三隔离开关,24-第四隔离开关;21-the second transformer, 22-the second breaking device, 23-the third isolating switch, 24-the fourth isolating switch;
15、17、25、27-第一母线隔离开关;15, 17, 25, 27- first bus isolating switch;
16、18、26、28-第二母线隔离开关;16, 18, 26, 28-second bus disconnector;
3-第一母线;3- the first busbar;
6-第一母线的第一段,7-第一母线的第二段;6-the first section of the first busbar, 7-the second section of the first busbar;
4-第二母线的第一段,5-第二母线的第二段;4- the first section of the second busbar, 5- the second section of the second busbar;
34、35-第一开断控制器;34, 35-the first breaking controller;
45-第二开断控制器;45 - the second breaking controller;
46、57-第三开断控制器;46, 57-the third breaking controller;
36-第四开断控制器。36 - Fourth disconnect controller.
具体实施方式detailed description
下面将结合附图对本实用新型的技术方案进行清楚、完整地描述,显然,所描述的实施例是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions of the utility model will be clearly and completely described below in conjunction with the accompanying drawings. Apparently, the described embodiments are part of the embodiments of the utility model, but not all of them. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.
在本实用新型的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。此外,术语“第一”、“第二”、“第三”仅用于描述目的,而不能理解为指示或暗示相对重要性。In the description of the present utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" The orientation or positional relationship indicated by etc. is based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, use a specific The azimuth structure and operation, therefore can not be construed as the limitation of the present utility model. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and should not be construed as indicating or implying relative importance.
在本实用新型的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,还可以是两个元件内部的连通,可以是无线连接,也可以是有线连接。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本实用新型中的具体含义。In the description of the present utility model, it should be noted that, unless otherwise clearly stipulated and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection or a flexible connection. Detachable connection, or integral connection; it can be mechanical connection or electrical connection; it can be direct connection or indirect connection through an intermediary, or it can be the internal communication of two components, it can be wireless connection, or it can be wired connection. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present utility model in specific situations.
此外,下面所描述的本实用新型不同实施方式中所涉及的技术特征只要彼此之间未构成冲突就可以相互结合。In addition, the technical features involved in different embodiments of the present invention described below can be combined with each other as long as they do not constitute conflicts with each other.
本实施例提供一种双母线分段的新型主接线,如图1所示,包括第一母线3和第二母线的第一段4以及第二母线的第二段5,第一母线3连接7条出线,第二母线的第一段4和第二母线的第二段5分别连接4条出线。第一变压器11是电力电子变压器,第一变压器11与第一开断装置12的一端连接,第一开断装置12的另一端通过第一隔离开关13与第一母线3连接、通过第二隔离开关14与第二母线的第一段4连接。This embodiment provides a new type of main wiring with double bus sections, as shown in Figure 1, including the first section 4 of the first bus 3 and the second bus and the second section 5 of the second bus, the first bus 3 is connected 7 outgoing lines, the first section 4 of the second busbar and the second section 5 of the second busbar are respectively connected to 4 outgoing lines. The first transformer 11 is a power electronic transformer, the first transformer 11 is connected to one end of the first breaking device 12, the other end of the first breaking device 12 is connected to the first bus 3 through the first isolating switch 13, and the second isolating A switch 14 is connected to the first section 4 of the second busbar.
第一母线3和其对应的出线之间分别设置有第一母线隔离开关15、17、25和27。第二母线的第一段4和其对应的出线之间分别设置有第二母线隔离开关16和18,第二母线的第二段5和其对应的出线之间分别设置有第二母线隔离开关26和28。First bus isolating switches 15, 17, 25 and 27 are respectively arranged between the first bus 3 and its corresponding outgoing lines. Second bus isolating switches 16 and 18 are respectively arranged between the first section 4 of the second bus and its corresponding outlets, and second bus isolating switches are respectively arranged between the second section 5 of the second bus and its corresponding outlets 26 and 28.
第一母线隔离开关15和第二母线隔离开关16的一端分别接入第一母线3和第二母线的第一段4,另一端并接后,接入负载设备、供电电源或储能设备;第一母线隔离开关17和第二母线隔离开关18的一端分别接入第一母线3和第二母线的第一段4,另一端并接后,接入负载设备、供电电源或储能设备。第一母线隔离开关25和第二母线隔离开关26的一端分别接入第一母线3和第二母线的第二段5,另一端并接后,接入负载设备、供电电源或储能设备;第一母线隔离开关27和第二母线隔离开关28的一端分别接入第一母线3和第二母线的第二段5,另一端并接后,接入负载设备、供电电源或储能设备。进一步地,每条分段母线还可以设置更多的出线,以连接负载设备、供电电源或储能设备。One end of the first bus isolating switch 15 and the second bus isolating switch 16 are respectively connected to the first section 4 of the first bus 3 and the second bus, and the other ends are connected in parallel to load equipment, power supply or energy storage equipment; One end of the first bus isolating switch 17 and the second bus isolating switch 18 are respectively connected to the first section 4 of the first bus 3 and the second bus, and the other ends are connected in parallel to load equipment, power supply or energy storage equipment. One end of the first bus isolating switch 25 and the second bus isolating switch 26 are respectively connected to the first bus 3 and the second section 5 of the second bus, and after the other ends are connected in parallel, they are connected to load equipment, power supply or energy storage equipment; One end of the first bus isolating switch 27 and the second bus isolating switch 28 are respectively connected to the first bus 3 and the second section 5 of the second bus, and the other ends are connected in parallel to load equipment, power supply or energy storage equipment. Furthermore, more outgoing lines can be set for each segmented bus to connect load equipment, power supply or energy storage equipment.
第一变压器11采用电力电子变压器,除实现传统的电压变换功能外,还可实现潮流的双向按需调配、有功无功复合支撑、电能质量隔离和控制、故障限流等综合控制功能。The first transformer 11 adopts a power electronic transformer. In addition to realizing the traditional voltage conversion function, it can also realize comprehensive control functions such as two-way on-demand deployment of power flow, composite support of active and reactive power, isolation and control of power quality, and fault current limiting.
第一开断装置12和第一隔离开关13、第二隔离开关14一起用于控制第一变压器11是否接入第一母线3和第二母线的第一段4。例如,当第一开断装置12接通,并且第一隔离开关13闭合时,第一变压器11接入第一母线3,向第一母线3输送电力,实现为第一母线3其他出线的负载设备供电;或者,由第一母线3其他出线的供电电源或储能设备经第一隔离开关13和第一开断装置12向第一变压器11供电。当第一开断装置12断开时,第一变压器11停止向第一母线3和第二母线的第一段4供电;或者,第一母线3和第二母线的第一段4停止向第一变压器11供电。从而实现潮流的双向流动。The first breaking device 12 is used together with the first isolating switch 13 and the second isolating switch 14 to control whether the first transformer 11 is connected to the first section 4 of the first bus 3 and the second bus. For example, when the first breaking device 12 is turned on and the first isolating switch 13 is closed, the first transformer 11 is connected to the first bus bar 3 to transmit power to the first bus bar 3, and is implemented as a load for other outgoing lines of the first bus bar 3 power supply to the equipment; or, power is supplied to the first transformer 11 through the first isolating switch 13 and the first breaking device 12 from the power supply or the energy storage equipment of other outgoing lines of the first bus bar 3 . When the first breaking device 12 is disconnected, the first transformer 11 stops supplying power to the first section 4 of the first bus 3 and the second bus; or, the first section 4 of the first bus 3 and the second bus stops supplying power to the first section 4 of the second bus. A transformer 11 supplies power. In order to realize the two-way flow of the trend.
第二母线两端的两条分段母线,即第二母线的第一段4、第二母线的第二段5,分别通过第一开断控制器34和35与第一母线3连接。当第一开断控制器34和35使用电力电子快速开断装置或常规断路器时,能够控制第一母线3与第二母线的第一段4、第二母线的第二段5之间的通断状态。例如,当第一开断控制器34断开时,第一母线3和第二母线的第一段4分列运行;当第一开断控制器34闭合时,第一母线3和第二母线的第一段4并列运行。当使用电力电子快速开断装置时,能够实现系统故障的快速切除。The two segmented buses at both ends of the second bus, namely the first section 4 of the second bus and the second section 5 of the second bus, are connected to the first bus 3 through the first breaking controllers 34 and 35 respectively. When the first breaking controllers 34 and 35 use power electronic quick disconnecting devices or conventional circuit breakers, it is possible to control the first busbar 3 and the first section 4 of the second busbar, and the second section 5 of the second busbar. on-off state. For example, when the first breaking controller 34 is disconnected, the first section 4 of the first bus 3 and the second bus run separately; when the first breaking controller 34 is closed, the first bus 3 and the second bus The first segment 4 runs in parallel. When the power electronic quick disconnect device is used, the quick removal of system faults can be realized.
进一步地,第一开断控制器34和35还可以使用母联柔性控制器。例如,当第一开断控制器34使用母联柔性控制器时,不仅能够控制第一母线3和第二母线的第一段4之间的通断状态,而且可以实现潮流于第一母线3和第二母线的第一段4之间的灵活分配。Further, the first breaking controllers 34 and 35 can also use bus-tie flexible controllers. For example, when the first breaking controller 34 uses a bus-connected flexible controller, it can not only control the on-off state between the first bus bar 3 and the first section 4 of the second bus bar, but also realize the power flow in the first bus bar 3 and flexible allocation between the first section 4 of the second busbar.
在第二母线的相邻分段母线之间,即在第二母线的第一段4与第二母线的第二段5之间,设置有用于联络相邻分段母线的第二开断控制器45。当第二开断控制器45使用电力电子快速开断装置或常规断路器时,能够控制第二母线的第一段4与第二母线的第二段5之间的通断状态。例如,当第二开断控制器45断开时,第二母线的第一段4与第二母线的第二段5分列运行;当第二开断控制器45闭合时,第二母线的第一段4与第二母线的第二段5并列运行。当使用电力电子快速开断装置时,能够实现系统故障的快速切除。Between the adjacent section busbars of the second busbar, that is, between the first section 4 of the second busbar and the second section 5 of the second busbar, a second breaking control for connecting adjacent section busbars is provided device 45. When the second breaking controller 45 uses a power electronic quick breaking device or a conventional circuit breaker, it can control the on-off state between the first section 4 of the second busbar and the second section 5 of the second busbar. For example, when the second breaking controller 45 was disconnected, the first section 4 of the second busbar and the second section 5 of the second busbar operated in parallel; when the second breaking controller 45 was closed, the second section 5 of the second busbar The first section 4 runs in parallel with the second section 5 of the second busbar. When the power electronic quick disconnect device is used, the quick removal of system faults can be realized.
进一步地,第二开断控制器45还可以使用母联柔性控制器。当使用母联柔性控制器时,不仅能够控制第二母线的第一段4与第二母线的第二段5之间的通断状态,而且可以实现潮流于第二母线的第一段4与第二母线的第二段5之间的灵活分配。Further, the second breaking controller 45 can also use a bus-tie flexible controller. When the flexible controller of the bus is used, it can not only control the on-off state between the first section 4 of the second busbar and the second section 5 of the second busbar, but also realize the power flow between the first section 4 of the second busbar and the second section 5 of the second busbar. Flexible allocation between the second section 5 of the second busbar.
作为另外一种实现方式,在上述设置一个变压器的基础上,还可以进一步延伸设置更多的变压器。例如,该双母线分段的新型主接线中还包括一个或多个第二变压器21,如图2所示。第二变压器21与第二开断装置22的一端连接,第二开断装置22的另一端通过第三隔离开关23与第一母线3连接、通过第四隔离开关24与第二母线的第二段5连接。As another implementation manner, on the basis of setting one transformer above, more transformers may be further extended. For example, the new main connection of the double bus section also includes one or more second transformers 21 , as shown in FIG. 2 . The second transformer 21 is connected to one end of the second breaking device 22, the other end of the second breaking device 22 is connected to the first bus 3 through the third disconnector 23, and connected to the second bus 3 through the fourth disconnector 24. Segment 5 is connected.
第二变压器21为常规变压器或电力电子变压器。当采用电力电子变压器时,除实现传统的电压变换功能外,还可实现潮流的双向按需调配、有功无功复合支撑、电能质量隔离和控制、故障限流等综合控制功能。The second transformer 21 is a conventional transformer or a power electronic transformer. When a power electronic transformer is used, in addition to the traditional voltage conversion function, it can also realize comprehensive control functions such as two-way on-demand deployment of power flow, active and reactive composite support, power quality isolation and control, and fault current limiting.
第二开断装置22和第三隔离开关23、第四隔离开关24一起用于控制第二变压器21是否接入第一母线3和第二母线的第二段5。例如,当第二开断装置22接通,并且第三隔离开关23闭合时,第二变压器21接入第一母线3,向第一母线3输送电力,实现为第一母线3其他出线的负载设备供电;或者,由第一母线3其他出线的供电电源或储能设备经第三隔离开关23和第二开断装置22向第二变压器21供电。当第二开断装置22断开时,第二变压器21停止向第一母线3和第二母线的第二段5供电;或者,第一母线3和第二母线的第二段5停止向第二变压器21供电。从而实现潮流的双向流动。The second breaking device 22 is used together with the third isolating switch 23 and the fourth isolating switch 24 to control whether the second transformer 21 is connected to the first bus 3 and the second section 5 of the second bus. For example, when the second breaking device 22 is turned on and the third isolating switch 23 is closed, the second transformer 21 is connected to the first bus bar 3 to transmit power to the first bus bar 3, which is implemented as a load for other outgoing lines of the first bus bar 3 or, the second transformer 21 is powered by the power supply or the energy storage equipment of other outlets of the first bus bar 3 via the third isolating switch 23 and the second breaking device 22 . When the second breaking device 22 is disconnected, the second transformer 21 stops supplying power to the first bus 3 and the second section 5 of the second bus; or, the first bus 3 and the second section 5 of the second bus stop supplying power to the first bus 3 and the second section 5 of the second bus. The second transformer 21 supplies power. In order to realize the two-way flow of the trend.
第一开断装置12、第二开断装置22可以部分或全部使用电力电子快速开断装置或常规断路器。当采用电力电子快速开断装置时,可以实现系统故障的快速切除。The first breaking device 12 and the second breaking device 22 may partly or entirely use power electronic quick breaking devices or conventional circuit breakers. When the power electronic quick disconnect device is used, the quick removal of system faults can be realized.
作为一个具体的实现方式,第一母线还可以包括多条分段母线,如图3所示。第一母线的第一段6以及第一母线的第二段7分别连接至少一条出线,第一开断装置12的另一端通过第一隔离开关13与第一母线的第一段6连接、通过第二隔离开关14与第二母线的第一段4连接。在第一母线的分段母线与第二母线的相应分段母线之间,设置有用于联络第一母线和第二母线的第三开断控制器。即第一母线的第一段6和第二母线的第一段4之间,第一母线的第二段7和第二母线的第二段5之间,分别设置有用于联络第一母线和第二母线的第三开断控制器46和57。在第一母线的相邻分段母线之间,即第一母线的第一段6和第一母线的第二段7之间,设置有用于联络相邻分段母线的第四开断控制器36。As a specific implementation manner, the first busbar may also include multiple segmented busbars, as shown in FIG. 3 . The first section 6 of the first busbar and the second section 7 of the first busbar are respectively connected to at least one outgoing line, and the other end of the first breaking device 12 is connected to the first section 6 of the first busbar through the first isolating switch 13, through The second isolating switch 14 is connected to the first section 4 of the second busbar. A third breaking controller for connecting the first bus and the second bus is arranged between the section bus of the first bus and the corresponding section of the second bus. That is, between the first section 6 of the first busbar and the first section 4 of the second busbar, between the second section 7 of the first busbar and the second section 5 of the second busbar, there are respectively provided for connecting the first busbar and the second section 5 of the second busbar. Third breaking controllers 46 and 57 for the second busbar. Between the adjacent section buses of the first busbar, that is, between the first section 6 of the first busbar and the second section 7 of the first busbar, a fourth breaking controller for connecting adjacent section busbars is arranged 36.
当第三开断控制器使用电力电子快速开断装置或常规断路器时,能够控制第一母线的分段母线与第二母线的相应分段母线之间的通断状态。当使用电力电子快速开断装置时,能够实现系统故障的快速切除。进一步地,第三开断控制器还可以使用母联柔性控制器。当使用母联柔性控制器时,不仅能够控制第一母线的分段母线与第二母线的相应分段母线之间的通断状态,而且可以实现潮流于第一母线的分段母线与第二母线的相应分段母线之间的灵活分配。When the third breaking controller uses a power electronic quick breaking device or a conventional circuit breaker, it can control the on-off state between the segmented bus bars of the first bus bar and the corresponding segmented bus bars of the second bus bar. When the power electronic quick disconnect device is used, the quick removal of system faults can be realized. Further, the third breaking controller can also use a bus-tie flexible controller. When using the flexible controller of the bus tie, it can not only control the on-off state between the segment bus of the first bus and the corresponding segment bus of the second bus, but also realize the power flow between the segment bus of the first bus and the second bus. Flexible allocation between the corresponding section busbars of the busbar.
在第一母线的相邻分段母线之间,设置有用于联络相邻分段母线的第四开断控制器。当第四开断控制器使用电力电子快速开断装置或常规断路器时,能够控制第一母线的相邻分段母线之间的通断状态。当使用电力电子快速开断装置时,能够实现系统故障的快速切除。进一步地,第四开断控制器还可以使用母联柔性控制器。当使用母联柔性控制器时,不仅能够控制第一母线的相邻分段母线之间的通断状态,而且可以实现潮流于第一母线的相邻分段母线之间的灵活分配。Between the adjacent subsection buses of the first busbar, a fourth breaking controller for connecting adjacent subsection busbars is arranged. When the fourth breaking controller uses a power electronic quick breaking device or a conventional circuit breaker, it can control the on-off state between the adjacent section bus bars of the first bus bar. When the power electronic quick disconnect device is used, the quick removal of system faults can be realized. Further, the fourth breaking controller can also use a bus-tie flexible controller. When using the flexible controller of the bus tie, it can not only control the on-off state between the adjacent sub-buses of the first bus, but also realize the flexible distribution of the power flow between the adjacent sub-buses of the first bus.
显然,上述实施例仅仅是为清楚地说明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本实用新型创造的保护范围之中。Apparently, the above-mentioned embodiments are only examples for clear description, rather than limiting the implementation. For those of ordinary skill in the art, other changes or changes in different forms can be made on the basis of the above description. It is not necessary and impossible to exhaustively list all the implementation manners here. And the obvious changes or variations derived therefrom are still within the scope of protection of the utility model.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621092973.3U CN206135210U (en) | 2016-09-29 | 2016-09-29 | Two bus section's novel main wiring |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621092973.3U CN206135210U (en) | 2016-09-29 | 2016-09-29 | Two bus section's novel main wiring |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206135210U true CN206135210U (en) | 2017-04-26 |
Family
ID=58571666
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201621092973.3U Active CN206135210U (en) | 2016-09-29 | 2016-09-29 | Two bus section's novel main wiring |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206135210U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107069444A (en) * | 2017-06-15 | 2017-08-18 | 潘冠华 | Depression belt hospital bus bar gets in touch with distribution box |
| CN108695968A (en) * | 2018-06-19 | 2018-10-23 | 河南森源电气股份有限公司 | A kind of busbar PT coordinate systems |
-
2016
- 2016-09-29 CN CN201621092973.3U patent/CN206135210U/en active Active
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107069444A (en) * | 2017-06-15 | 2017-08-18 | 潘冠华 | Depression belt hospital bus bar gets in touch with distribution box |
| CN107069444B (en) * | 2017-06-15 | 2023-12-22 | 广西春茂电气自动化工程有限公司 | Low-voltage contact distribution box with bypass bus |
| CN108695968A (en) * | 2018-06-19 | 2018-10-23 | 河南森源电气股份有限公司 | A kind of busbar PT coordinate systems |
| CN108695968B (en) * | 2018-06-19 | 2024-02-20 | 河南森源电气股份有限公司 | Bus PT parallel system |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104465195A (en) | Earthing switch for switch equipment | |
| CN202940470U (en) | Double-bus wiring system | |
| CN206135212U (en) | Take novel main wiring of hospital bus bar | |
| CN107482523B (en) | Double-bus connection GIS equipment and its maintenance method, pressure test method | |
| CN103904564B (en) | High-voltage distribution device with double breakers used for single bus segmentation and application thereof | |
| CN205178525U (en) | Asynchronous conversion device for power grid at both ends of high-voltage DC | |
| CN107994578A (en) | A kind of bus single-subsection and double section wiring anti-incorrect manipulation deadlock control loops | |
| CN201130821Y (en) | Intelligent control device for the electrical system used | |
| CN206135211U (en) | Novel main wiring of double -bus | |
| CN207625288U (en) | A kind of fault disconnection device accessing multiple regional powers suitable for double-bus | |
| CN104218457A (en) | Power distribution device and electric master system thereof | |
| CN103986159B (en) | There is the mounting circuit of THE UPFC in multi transformer station | |
| CN206041215U (en) | Single bus segmentation 's novel main wiring | |
| CN203850833U (en) | Unified power flow controller installation circuit in transformer station with multiple lines | |
| CN113300233A (en) | High-voltage complete emergency power distribution equipment and use method thereof | |
| CN209805224U (en) | Box type substation | |
| CN113037107A (en) | Topological structure of power electronic transformer | |
| CN203367775U (en) | Duplicate-busbar disconnecting switch segmented electric main connection wire | |
| CN115986736A (en) | Electric main wiring circuit with three bus bars mixed, its use method and power supply method | |
| CN210577360U (en) | A metal armored switchgear with the function of maintenance without power failure | |
| CN204424772U (en) | Two main transformer four segmentation integrated automation converting stations | |
| CN201927897U (en) | Novel 220kV combined electrical-apparatus secondary line-collecting terminal box | |
| CN203932698U (en) | A kind of single busbar connection dual-breaker sectional wiring structure | |
| WO2013013347A1 (en) | Grid-like quadrangular electrical main wiring | |
| CN205985758U (en) | Novel electric main wiring of 220kV transformer substation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 102209 Beijing City, the future of science and Technology City Binhe Road, No. 18, No. Co-patentee after: State Grid Corporation of China Patentee after: Global energy Internet Institute, Inc. Address before: 102211 Beijing city Changping District Xiaotangshan town big East Village Road No. 270 Co-patentee before: State Grid Corporation of China Patentee before: GLOBAL ENERGY INTERCONNECTION RESEARCH INSTITUTE |