CN206113321U - High -effect waste water reclamation hot water constant temperature supply system - Google Patents

High -effect waste water reclamation hot water constant temperature supply system Download PDF

Info

Publication number
CN206113321U
CN206113321U CN201620974525.XU CN201620974525U CN206113321U CN 206113321 U CN206113321 U CN 206113321U CN 201620974525 U CN201620974525 U CN 201620974525U CN 206113321 U CN206113321 U CN 206113321U
Authority
CN
China
Prior art keywords
water
hot water
heat
supply system
constant temperature
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620974525.XU
Other languages
Chinese (zh)
Inventor
黄伟军
梁华易
刘永丽
覃鐶
何燕
韦媛元
梁锋华
盘英靖
赵代龙
莫文贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGXI TEAMRUN ENERGY-SAVING TECHNOLOGY Co Ltd
Original Assignee
GUANGXI TEAMRUN ENERGY-SAVING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGXI TEAMRUN ENERGY-SAVING TECHNOLOGY Co Ltd filed Critical GUANGXI TEAMRUN ENERGY-SAVING TECHNOLOGY Co Ltd
Priority to CN201620974525.XU priority Critical patent/CN206113321U/en
Application granted granted Critical
Publication of CN206113321U publication Critical patent/CN206113321U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Steam Or Hot-Water Central Heating Systems (AREA)

Abstract

The utility model discloses a high -effect waste water reclamation hot water constant temperature supply system, include effluent water sump and the sewage pipe of being connected with the effluent water sump, be equipped with the multistage heat exchanger who is used for the heat exchange in the sewage pipe, its characterized in that: still include cold water conduit, cold water conduit carries out temperature exchange back through multistage heat exchanger, and one end is connected with the holding water box top, is connected with the cold water conduit other end bottom the holding water box, holding water box is connected with the heat supply heat pump, the heat supply heat pump is equipped with heating device, heat supply heat pump rear portion is connected with a plurality of water gauges, and every water gauge is connected with card reader and delivery port, be equipped with total accuse valve on the water pipe that heat supply heat pump and water gauge are connected, every water gauge department all is equipped with sub -control valve, the effluent water sump is including being divided into a plurality of compartments, and the S form is arranged into to the water inlet between the compartment.

Description

A kind of high-effect waste water reclamation hot water constant temperature supply system
Technical field
This utility model is related to energy regeneration and reclaims field, and in particular to a kind of high-effect waste water reclamation hot water constant temperature supply System.
Background technology
Water resource heat pump hot-water heating system is by the independently installed water resource heat pump hot water main frame for independently using of each household and public water source Exchange source constitutes.Wherein family formula water resource heat pump hot water main frame dispersion is installed to every household and realizes that independent start-stop, hot water temperature are only The institute of vertical control is functional.Public water source is exchanged, and exchanged water source temperature is low to be avoided losing heat in pipeline is circulated, and supplies with concentrating Hot water compares saving use cost.Its operation principle is the native sewage water produced by house itself, more than native sewage water Heat store after draw heat to water tank with public exchange that user uses using Regenerated energy exchange system, is pumped to building by supercharging Top water collector is further separated into pipeline by water knockout drum again and delivers to the water resource heat pump hot water main frame installed in user family, when user needs The hot water water tank supporting with which is heated using water resource heat pump hot water main frame is opened during hot water(Capacity can be selected)Heated. Regenerated energy exchange system is back to by the exchange water source using after when water resource heat pump hot water main frame is heated, is pressurized after exchange again Looped cycle is formed to roof to use.
And existing residual neat recovering system, temperature exchange is carried out by multistage exchanger and cooling water pipe typically, but its There is Railway Project, one when being to carry out cooling water pipe heat exchange in winter, and such as water temperature is too low, then can substantial amounts of consumption full section exchanger In heat, cause cooling water temperature to rise slow, if additionally, existing hydraulic pressure not enough in the case of, the hot water for being gone out is not yet Be well positioned to meet using crowd needs this;
Additionally, when the use of crowd being students, there is destruction water meter in order to save living expense, usually in students Situation, this is accomplished by this and is accomplished by a kind of more advanced method and apparatus, solves a difficult problem of the prior art.
Utility model content
This utility model is for, in existing residual neat recovering system, the unreasonable structure for existing, waste heat amount of translation are not enough, water The defect that table is more easily damaged, there is provided a kind of high-effect waste water reclamation hot water constant temperature supply system is solving the above problems.
It is of the present utility model to be realized in:A kind of high-effect waste water reclamation hot water constant temperature supply system, including sewage Pond and the soil pipe being connected with cesspool, are provided with the multi-stage heat-exchanger for heat exchange, also including cold in the soil pipe Waterpipe, after multi-stage heat-exchanger carries out water temperature exchange, one end is connected the cold water pipes with the top of attemperater, insulation Water tank bottom is connected with the cold water pipes other end;The attemperater be connected for heat driven heat pump, the confession heat driven heat pump is provided with heating Device, the confession heat driven heat pump rear portion are connected with multiple water meters, and each water meter is connected with card reader and outlet;The confession heat driven heat pump The water pipe being connected with water meter is provided with master control valve, each water meter and is equipped with sub-control valve, and the cesspool includes being divided into Multiple compartments, the water inlet between compartment are arranged in S shapes, such that it is able to realize the constant temperature effect of sewage.
In this utility model, as further scheme, the cold water pipes are connected with reflux line, and the reflux line leads to Cross Intelligent three-way valve to be connected with cold water pipes, in the loop that reflux line is formed with cooling water pipe, be provided with heat exchanger;It is described Intelligent three-way valve goes out the temperature measuring equipment for being connected with measurement cold water pipes temperature, and the temperature measuring equipment is by PLC systems System is connected with Intelligent three-way valve.The effect of reflux line is, when water flow temperature is too low, in order to avoid in heat exchanger Heat reduce too fast, by the way of cold-water reflux so that the temperature of current is circulated in the exchanger of single area, so as to The initial temperature of cold water is improved, is easy to be brought rapidly up.
In this utility model, as further scheme, the soil pipe goes out to be provided with slag-discharging device, and the slag-discharging device includes shell Body, is provided with liquid outlet at the housing, be provided with deslagging swivel knife in the housing, and the housing afterbody is slag-drip opening, the row Slag charge collection port is provided with cinder notch, at the slag charge collection port, meausring apparatus is provided with.By measuring bed drain purge, it will be appreciated that local The dregginess of sewage, so as to tackle different degrees of sewage scheme.
In this utility model, as further scheme, hot water moisturizing pipeline in the reflux line, is provided with, the hot water is mended Airflow calculator is provided with waterpipe.Moisturizing pipeline is hot water pipeline, when heat exchanger cannot at short notice in cold water pipe Water when being heated up, by filling into hot water such that it is able to improve the initial temperature of cooling pipe.By being by flow rate calculation Device, can calculate rate of water make-up, to understand the moisturizing demand of locality, so as to calculate the energy value of heat exchange amount.
In this utility model, as further scheme, the moisturizing pipeline is connected with electric heating system, the electric heating system and Moisturizing pipeline valve is controlled by PLC system, and the PLC system is connected with temperature measuring equipment.The unlatching of moisturizing pipeline, and The unlatching of Intelligent three-way valve, feeds back to PLC system by temperature measuring equipment, enters trip temperature management and control by which, so as to realize The intellectuality of temperature.
In this utility model, as further scheme, in the cold water pipes, accumulator tank is provided with;Set in the confession heat driven heat pump There is water-pressure survey instrument, when water-pressure survey instrument index is less than accumulator tank index, accumulator tank starts water-retention by PLC.
In this utility model, as further scheme, when system is arranged on school, with dormitory longitudinal direction as each unit, By the water meter concentrated setting of every dormitory in unit in a casing, each water meter individually connects card reader by wire.
In this utility model, as further scheme, each water meter is equipped with independent corresponding sub-control valve and water temperature water Pressure detection means, the master control valve and sub-control valve have PLC system to be controlled according to the temperature of temperature detector. In existing split water meter, easily there is the water pipe near water-main end and hot water, and the water pipe of end are used up from the feelings without hot water Condition.
By, in the corresponding distributive pipe of each water meter, being respectively provided with single sub-control valve and water temperature control valve door;When only When having water meter to operate, the hydraulic pressure of distributive pipe is very big, and substantial amounts of hot water can be caused quickly to pour in distributive pipe, this when When time water temperature hydraulic pressure detection dress detects excessive hydraulic pressure and water temperature over-high, then PLC system control master control valve closing minor valve, subtracts Few hydraulic pressure;
When multiple water meters are operated simultaneously, the water temperature hydraulic pressure that such as multiple water temperature device for detecting water pressure are detected in water pipe differs During cause, then the size of the control valve together of the sub-control valve in distributive pipe, to realize that the water yield and temperature of multiple water pipes oneself are put down Weighing apparatus;
When water temperature device for detecting water pressure detects water temperature is far less than design temperature for a long time, then sub-control valve is automatically switched off, Human body is avoided to catch a cold using cold water.
The compartment right-to-left of the cesspool includes first time sand sediment trap, the second sand sediment trap, pump platform and blowoff basin, described Limber is provided between pump platform and blowoff basin.By secondary desilting, the impurity in sewage can be reduced in a large number, and passes through pump Platform coordinates limber filter out oarse-grained sandstone.
The beneficial effects of the utility model are:
1. this utility model carries out operational control using full automatic PLC control system, possesses reliability, safety, entirely Automatically wait technical characteristic, with the preferable market competitiveness, can according to preventing using water when heat exchange is carried out, due to Water temperature is too low, and causes temperature to heat up slow defect.
2. the waste residue of sewage and rate of water make-up can be counted by this utility model, form statistical data, in order to be directed to Sewage Environment and rate of water make-up carry out pipe design, and the impure content of sewage is low, and impurity particle degree is little.
3. this utility model simple structure, by existing equipment, and carries out Electronic Design according to this utility model, then may be used Realize, which is easy to the industry to promote the use.
4. this utility model can effectively solve the problems, such as existing student's destruction water meter, so as to solve to keep in repair a difficult problem.
5. this utility model can be in effectively existing dormitory, and the unbalanced problem of hydraulic pressure water temperature is easy to balanced management.
6. this utility model can solve the problems, such as that pressure of hot water is not enough, be easy to promote the use in each family.
Description of the drawings
Fig. 1 is overall structure diagram of the present utility model;
Fig. 2 is slag-discharging device structural representation of the present utility model;
Fig. 3 is the structural representation of cesspool 2 in this utility model;
Waste residue pond 1, cesspool 2, soil pipe 3, slag-discharging device 4, cold water pipes 5, sewage discharge pond 6, the first temperature measuring set 7th, second temperature measuring instrument 8, the first reflux line 9, the second reflux line 10, attemperater 11, moisturizing pipeline 12, supply heat driven heat pump 13rd, accumulator tank 14, water meter 15, card reader 16, master control valve 17, temperature hydraulic pressure measuring instrument 18, sub-control valve 19;
First sand sediment trap 2.1, the second sand sediment trap 2.2, pump platform 2.3, filtering holes 2.4, blowoff basin 2.5, water inlet 2.6;
Motor 4.1, sewage inlet 4.2, housing 4.3, limber 4.4, slag charge outlet 4.5.
Specific embodiment
This utility model is described below in conjunction with drawings and Examples, following examples are solved with utility model optimal effectiveness Release explanation.
Embodiment 1:
Such as Fig. 1, it is overall structure diagram of the present utility model, including cesspool 2, cesspool 2 is connected with soil pipe 3, Cesspool 2 includes being divided into 4 compartments, and right-to-left includes water inlet 2.6, the first sand sediment trap 2.1, the second sand sediment trap 2.2, pump The water inlet of platform 2.3, filtering holes 2.4 and blowoff basin 2.5, wherein each compartment is presented S-shaped discharge, with balanced water temperature.Soil pipe 3 In be provided with slag-discharging device 4, slag-discharging device 4 includes housing 4.3, is provided with sewage inlet 4.2 and limber 4.4 on housing 4.3, and sewage leads to Cross sewage inlet 4.2 to enter in housing 4.3, by the rotating mechanism in housing 4.3(Driven by motor 4.1), debris are arranged Go out, and sewage continue to flow in soil pipe 3 by limber 4.4, in systems including First Heat Exchanger, the second heat exchanger, Three heat exchangers and the 4th heat exchanger, its according to being from left to right arranged in order, in above-mentioned heat exchanger, soil pipe 3 from left to right with Above-mentioned heat exchanger is sequentially connected;Cold water pipes 5 are provided with right side, 5 right-to-left of cold water pipes is connected with above-mentioned heat exchanger successively, So as to sewage and cold water carry out heat exchange in above-mentioned heat exchanger;
In First Heat Exchanger and the 4th heat exchanger, the first reflux line 9 and the second reflux line 10 are respectively equipped with, upper State reflux line Intelligent three-way valve is provided with 5 junction of cold water pipes(It is not drawn in figure), its control continuation stream of cold water pipes 5 It is logical, or liquid is flow in reflux line, it is warm first to be respectively equipped with the first reflux line 9 and the second reflux line 10 Degree measuring instrument 7 and second temperature measuring instrument 8, Intelligent three-way valve, the first temperature measuring set 7 and second temperature measuring instrument 8 and PLC System connects;
Cold water pipes 5 are finally flowed at the top of attemperater 11, and 11 bottom of attemperater is connected with cold water pipes 5 and is formed back Road, and accumulator tank 14 is provided with cold water pipes 5, is connected with attemperater 11 for heat driven heat pump 13, attemperater 11 and water meter 15 and card reader 16 connect;The water pipe being connected with water meter 15 for heat driven heat pump 13 is provided with master control valve 17, each water meter and is all provided with There are sub-control valve 19 and temperature hydraulic pressure measuring instrument 18, master control valve 17, sub-control valve 19 are by PLC system control, this enforcement 4 water meters 15 are provided with example, after each water meter 15, card reader 16 and outlet is singly connected with.When only one of which water meter 15 is transported When making, the hydraulic pressure of distributive pipe is very big, and substantial amounts of hot water can be caused quickly to pour in distributive pipe, this when of water temperature hydraulic pressure inspection Survey fills 18 and detects that hydraulic pressure is excessive and during water temperature over-high, then PLC system control master control valve 17 closes minor valve, reduces hydraulic pressure;
When multiple water meters operate simultaneously, such as multiple water temperature device for detecting water pressure 18 detect water temperature hydraulic pressure in water pipe not When consistent, then the size of the control valve together of the sub-control valve 19 in distributive pipe, to realize the water yield and temperature of multiple water pipes oneself Degree balance;
When water temperature device for detecting water pressure 18 detects water temperature is far less than design temperature for a long time, then sub-control valve is automatically switched off 19, it is to avoid human body is caught a cold using cold water.In addition the soil pipe 3 is connected with sewage discharge pond 6.
In the present embodiment, moisturizing pipeline 12 is provided with the second reflux line 10, is provided with flow rate calculation in moisturizing pipeline 12 Device(It is not drawn in figure), the moisturizing pipeline 12 is connected with electric heating system, and which can be with hot-water supply, electric heating system and moisturizing pipeline Valve is controlled by PLC system.
During operation, after 2 water-retention of cesspool, first carry out desilting, filter out rate, later on soil pipe 3 to First Heat Exchanger, Second heat exchanger, the 3rd heat exchanger and the 4th heat exchanger carry out heat exchange, after heat exchange temperature is lifted, open cold water pipes 5 Carry out temperature exchange so that the temperature in cold water pipes 5 is lifted.
When 5 water temperature of cold water pipes is less than setting value(Such as 20 degree)When, second temperature measuring instrument 8 detects temperature, PLC systems System control Intelligent three-way valve, in reflux line 10 open, until the water temperature in cold water pipes 5 is higher than after 20 degree, PLC system 5 valve opening of cold water pipes in control Intelligent three-way valve, the valve closing of reflux line 10.When 5 water temperature of cold water pipes it is low In setting value more than 10 minutes, then open moisturizing pipeline 12 and inject hot water, when water temperature is higher than 20 degree, moisturizing pipeline 12 is closed Close.So circulate, then continuous hot water can be provided for attemperater 11.When water temperature is not high, can be by entering for heat driven heat pump 13 Row electric heating warming causes water temperature to rise, and water-pressure survey instrument is additionally provided with for heat driven heat pump 13, and water-pressure survey instrument is controlled with PLC system Device connect, PLC system control accumulator tank 14 unlatching, when hydraulic pressure detector detect hydraulic pressure it is too low when, then PLC system control store Pressure tank 14 is opened, and carries out water-retention, to ensure the abundance of the water yield.
Embodiment 2:
Difference from Example 1, is provided with moisturizing pipeline at the First Heat Exchanger, remaining working method and principle and reality Apply example 1 identical.
Embodiment 3:
Difference from Example 1, when system is arranged on school, with dormitory longitudinal direction as each unit, will be every in unit Between dormitory water meter concentrated setting in a casing, each water meter individually connects card reader by wire, is arranged so that and avoids Water meter can be destroyed in dormitory and arbitrarily abuse the problem of hot water by student.Simple structure and convenience, and arrange water meter and According to prior art, card reader can realize that here is not described further.
Finally it should be noted that:Obviously, above-described embodiment is used for the purpose of clearly illustrating the act made by this utility model Example, and the not restriction to implementing.For the those of ordinary skill in the field, on the basis of the above description can be with Make other changes in different forms.There is no need to all of embodiment party's formula with exhaustion.And thus institute Among the obvious change amplified out or variation are still in protection domain of the present utility model.

Claims (10)

1. a kind of high-effect waste water reclamation hot water constant temperature supply system, including cesspool and the soil pipe being connected with cesspool, The multi-stage heat-exchanger for heat exchange is provided with the soil pipe, it is characterised in that:Also include cold water pipes, the cold water pipe After multi-stage heat-exchanger carries out water temperature exchange, one end is connected with the top of attemperater in road, attemperater bottom and cold water pipe Road other end connection;The attemperater be connected for heat driven heat pump, the confession heat driven heat pump is provided with heater, the confession heat driven heat pump Rear portion is connected with multiple water meters, and each water meter is connected with card reader and outlet;The water pipe that the confession heat driven heat pump is connected with water meter It is provided with master control valve, each water meter and is equipped with sub-control valve;
The cesspool includes being divided into multiple compartments, and the water inlet between compartment is arranged in S shapes.
2. high-effect waste water reclamation hot water constant temperature supply system according to claim 1, it is characterised in that:The cold water pipe Road is connected with reflux line, and the reflux line is connected with cold water pipes by Intelligent three-way valve, reflux line and cooling water In the loop that pipe is formed, heat exchanger is provided with;The Intelligent three-way valve goes out to be connected with the temperature of measurement cold water pipes temperature and surveys Amount device, the temperature measuring equipment are connected with Intelligent three-way valve by PLC system.
3. high-effect waste water reclamation hot water constant temperature supply system according to claim 2, it is characterised in that:The heat exchange Device is distributed with level Four from left to right, is wherein provided with reflux line in one-level heat exchanger and level Four, sets in the reflux line There is check valve.
4. high-effect waste water reclamation hot water constant temperature supply system according to claim 1, it is characterised in that:The soil pipe Go out and be provided with slag-discharging device, the slag-discharging device includes housing, at the housing, be provided with liquid outlet, in the housing, be provided with deslagging rotation Knife, the housing afterbody are slag-drip opening, and slag charge collection port is provided with the slag-drip opening, and weighing dress is provided with the slag charge collection port Put.
5. high-effect waste water reclamation hot water constant temperature supply system according to claim 2, it is characterised in that:The return duct Hot water moisturizing pipeline is provided with road, in the hot water moisturizing pipeline, airflow calculator is provided with.
6. high-effect waste water reclamation hot water constant temperature supply system according to claim 5, it is characterised in that:The filling pipe Road is connected with electric heating system, and the electric heating system and moisturizing pipeline valve are by PLC system control, the PLC system and temperature Measurement apparatus connect.
7. high-effect waste water reclamation hot water constant temperature supply system according to claim 1, it is characterised in that:The cold water pipe Accumulator tank is provided with road;Water-pressure survey instrument is provided with the confession heat driven heat pump, when water-pressure survey instrument index is less than accumulator tank index, Accumulator tank starts water-retention by PLC.
8. high-effect waste water reclamation hot water constant temperature supply system according to claim 1, it is characterised in that:When system is arranged In school, with dormitory longitudinal direction as each unit, by the water meter concentrated setting of every dormitory in unit in a casing, each Water meter individually connects card reader by wire.
9. high-effect waste water reclamation hot water constant temperature supply system according to claim 1, it is characterised in that:Each water meter is equal Independent corresponding sub-control valve and water temperature device for detecting water pressure are provided with, the master control valve and sub-control valve have PLC system root It is controlled according to the temperature of temperature detector.
10. high-effect waste water reclamation hot water constant temperature supply system according to claim 1, it is characterised in that:The sewage The compartment right-to-left in pond includes first time sand sediment trap, the second sand sediment trap, pump platform and blowoff basin, between the pump platform and blowoff basin It is provided with limber.
CN201620974525.XU 2016-08-29 2016-08-29 High -effect waste water reclamation hot water constant temperature supply system Expired - Fee Related CN206113321U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620974525.XU CN206113321U (en) 2016-08-29 2016-08-29 High -effect waste water reclamation hot water constant temperature supply system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620974525.XU CN206113321U (en) 2016-08-29 2016-08-29 High -effect waste water reclamation hot water constant temperature supply system

Publications (1)

Publication Number Publication Date
CN206113321U true CN206113321U (en) 2017-04-19

Family

ID=58514296

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620974525.XU Expired - Fee Related CN206113321U (en) 2016-08-29 2016-08-29 High -effect waste water reclamation hot water constant temperature supply system

Country Status (1)

Country Link
CN (1) CN206113321U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106196598A (en) * 2016-08-29 2016-12-07 广西天涌节能科技股份有限公司 A kind of high-effect waste water reclamation hot water constant temperature supply system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106196598A (en) * 2016-08-29 2016-12-07 广西天涌节能科技股份有限公司 A kind of high-effect waste water reclamation hot water constant temperature supply system
CN106196598B (en) * 2016-08-29 2022-06-10 广西天涌节能科技股份有限公司 High-effect waste water recovery hot water constant temperature supply system

Similar Documents

Publication Publication Date Title
CN107490189A (en) A kind of modularization pressure-bearing heat pump and its control method
CN207365408U (en) A kind of modularization pressure-bearing heat pump system
CN207422345U (en) Hot-water heating system comprising bath water waste heat recovery and water resource heat pump
CN206113107U (en) Split type constant temperature supply system of campus hot water
CN208983651U (en) A solar collector water supply system
CN206113321U (en) High -effect waste water reclamation hot water constant temperature supply system
CN206113336U (en) Energy -conserving waste water reclamation hot water constant temperature supply system
CN206113357U (en) Split type supply system of campus hot water
CN100582597C (en) Solar energy water heater with circulation water saving device
CN203754732U (en) Integral heat exchanger unit capable of comprehensively utilizing residual heat of slag flushing water
CN206113706U (en) Multistage waste water reclamation hot water supply system
CN206113707U (en) Multistage waste water recovery system
CN102519274A (en) Intelligent Boiler Waste Heat Recovery and Utilization System
CN101943528A (en) Smooth heat exchanger of sewage or surface water source heat pump and system thereof
CN106197068B (en) A kind of Multistage wastewater recycling hot water supply system
CN106196259A (en) A kind of campus hot water split type constant temperature supply system
CN205367782U (en) Imitate intelligent level pressure moisturizing degasification unit by force
CN207422671U (en) A kind of waste heat recovery hot water system
CN106196598A (en) A kind of high-effect waste water reclamation hot water constant temperature supply system
CN106196627A (en) A kind of campus split type supply system of hot water
CN207166953U (en) A kind of water-cooling system applied to automobile charging pile
CN206330236U (en) A kind of air-conditioning system by the use of the complementary photovoltaic pile tube of fishing light as earth source heat pump thermal source well
CN106197069B (en) Multistage wastewater recovery system
CN106196601A (en) A kind of energy-conservation waste water reclamation hot water constant temperature supply system
CN208419223U (en) Water tank system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170419