CN206015895U - Prefabricated assembled detachable one off houses - Google Patents

Prefabricated assembled detachable one off houses Download PDF

Info

Publication number
CN206015895U
CN206015895U CN201621023773.2U CN201621023773U CN206015895U CN 206015895 U CN206015895 U CN 206015895U CN 201621023773 U CN201621023773 U CN 201621023773U CN 206015895 U CN206015895 U CN 206015895U
Authority
CN
China
Prior art keywords
bracket column
basis
floor
prefabricated assembled
houses
Prior art date
Application number
CN201621023773.2U
Other languages
Chinese (zh)
Inventor
孙学明
Original Assignee
青岛新世纪预制构件有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 青岛新世纪预制构件有限公司 filed Critical 青岛新世纪预制构件有限公司
Priority to CN201621023773.2U priority Critical patent/CN206015895U/en
Application granted granted Critical
Publication of CN206015895U publication Critical patent/CN206015895U/en

Links

Abstract

A kind of prefabricated assembled detachable one off houses, including tabernacular framework, wallboard, base plate, floor and roof boarding, the framework includes basis, bracket column, roof girder, the framework further includes floor beam, the basis includes laterally basic and longitudinal basis, the longitudinal direction basis is between adjacent transverse base end, the horizontal base end all installs bracket column, the bracket column bottom is inserted in the mounting groove of horizontal basis instrument, the roof girder is between adjacent bracket column, and it is located at bracket column top, the floor beam is between adjacent bracket column, and be located in the middle part of bracket column.Prefabricated assembled detachably tabernacular frame structure is simple, and structural strength is high, and wind resistance external force resistance ability is strong, and bearing capacity is big.All parts are mainly attached by grafting, overlap joint, are installed easily, and part does not allow fragile, long service life, it is easy to reuse, reusable often, the building waste of generation is few, significantly alleviates the loss of resource.

Description

Prefabricated assembled detachable one off houses
Technical field
This utility model is related to movable plank house technical field, specifically, is a kind of prefabricated assembled detachable interim room Room.
Background technology
Movable plank house is a kind of with light steel as skeleton, with battenboard as cladding, carries out space with standard module series Close, component house with bolts.But there is more deficiency in existing movable plank house:When the 1st, dismantling, structure is easily damaged, Recycling difficulty is big, and reuse number of times is few, and then produces substantial amounts of building waste, causes the wasting of resources;2nd, structural strength Low, parts are more fragile, and wind resistance external force resistance ability, service life are short;3rd, sound insulation and heat-insulated effect are poor, and indoor environment is relaxed Moderately low;4th, fire protecting performance is poor.
Utility model content
A kind of deficiency that this utility model is present for above-mentioned prior art, it is proposed that prefabricated assembled detachable interim room Room.
Prefabricated assembled detachable one off houses of the present utility model, including tabernacular framework, wallboard, base plate, building Plate and roof boarding, the framework include that basis, bracket column, roof girder, the framework further include floor beam, the basis bag Laterally basic and longitudinal basis is included, the longitudinal direction basis is arranged between adjacent transverse base end, the horizontal base end Bracket column is all installed, the bracket column bottom is inserted in the mounting groove of horizontal basis instrument, the roof girder is installed in adjacent Between bracket column, and bracket column top is located at, the floor beam is between adjacent bracket column, and is located in the middle part of bracket column.
Preferably, roof girder is vertical with the mutual antarafacial of floor beam.
Preferably, the floor beam lapping ends are on the post bracket that bracket column is arranged.
Preferably, the bottom of the flooring beam end is provided with link slot, and the post bracket is located in link slot..
Preferably, the cross section of the roof girder is inverted L-shaped, is inserted in the fixing groove of bracket column setting.
Preferably, the bracket column top surface on the outside of fixing groove is higher than to be located at the bracket column top surface on the inside of fixing groove, Gu Determine groove bottom land and the bracket column top surface on the outside of fixing groove is all contacted with roof girder.
Preferably, the panel edges arrange tongue and groove.
Preferably, the wallboard is plugged on the boss of basis instrument.
Preferably, described install groove edge horizontal on the basis of angle bar fixed seat is installed, in the angle bar fixed seat Side is abutted on bracket column outer wall.
The beneficial effects of the utility model are:Prefabricated assembled detachably tabernacular frame structure is simple, and structure is strong Degree is high, and wind resistance external force resistance ability is strong, and bearing capacity is big.All parts are mainly attached by grafting, overlap joint, are installed easily, portion Part does not allow fragile, long service life, it is easy to reuse, reusable often, the building waste of generation is few, significantly Alleviate the loss of resource.House frame intensity is high, enables all parts using precast concrete, and further can increase Strong house intensity, improves weight capacity, and then enables the plate face such as wallboard part using compound insulating material, further enhance every The performance of heat, insulation, fire prevention, waterproof, noise control and environmental protection.
Roof girder is vertical with floor beam antarafacial, and space crossed arrangement, frame structure are more stable, it is not necessary in each aspect Laterally longitudinal direction is required for arranging beam, mitigates the overall weight of frame structure, saves raw material and cost, but also make roof girder and building Face joist support weight stress passes to bracket column, and the stress of bracket column is more uniformly dispersed, and reduces the pressure of bracket column, improves structure Life-span.
Floor beam is overlapped on projection, not only easy for installation, makes floor beam under gravity, fixation that can be stable The stability of structure on projection, is improve, and post bracket is located in link slot, further improves connective stability.Roofing Beam is plugged on bracket column, easy for installation, Stability Analysis of Structures.
By the setting of bracket column top surface height, in the case of making roof girder ensure grafting, its bottom surface is complete with bracket column Contact, enables bracket column stably to support, and also reduces the volume of bracket column, material-saving, reduces weight.
Wallboard all arranges tongue and groove up and down, and on the basis of wallboard is plugged into, also making being capable of the company of being mutually inserted between wallboard Connect, strong using motility, and waterproof can be played a part of.
Bracket column is fixed by angle bar fixed seat, improves stability, while the support strength of bracket column side is increased, Bracket column deflection is prevented, the overall bearing capacity in house and wind resistance external force resistance performance is improve.
Description of the drawings
Accompanying drawing 1 is prefabricated assembled detachably tabernacular structural representation one.
Accompanying drawing 2 is prefabricated assembled detachably tabernacular structural representation two.
Accompanying drawing 3 is the structural representation of roof girder and bracket column connecting portion.
Accompanying drawing 4 is the structural representation of bracket column and basic connecting portion.
Specific embodiment
In order to be able to further appreciate that structure of the present utility model, feature and other purposes, in conjunction with appended preferred embodiment Detailed description is as follows, and illustrated preferred embodiment is merely to illustrate the technical solution of the utility model, and non-limiting practicality New.
Specific embodiment of the present utility model is as follows:
Embodiment one:
As shown in Fig. 1 to 2, the prefabricated assembled detachable one off houses, including tabernacular framework 1 and other plates Face component, plate face part include wallboard 2, base plate 3, floor 4 and roof boarding 5.
Framework 1 includes concrete prefabricated basic 1-1, bracket column 1-2, floor beam 1-3 and roof girder 1-4.
Basic 1-1 includes horizontal basis 1-1-1 and longitudinal direction basis 1-1-2.Longitudinal direction basis 1-1-2 is arranged on adjacent transverse Between basic 1-1-1 ends.
The horizontal basis 1-1-1 of adjacent two and the two longitudinal direction basis 1-1-2 laterally between the 1-1-1 of basis are surrounded The ground of one piece of rectangle, base plate 3 are laid on ground, and overlapping edges are on basic 1-1.It can be in multiple rows of that the arrangement of ground makes board house The military camp formula of word order, the frame that three faces enclose, the Chinese courtyard house formula for enclosing on four sides, the various forms such as dendritic for combining in length and breadth.
There is bracket column 1-2 the corner of ground, and on horizontal basis 1-1-1, bottom is inserted into laterally bracket column 1-2 In the mounting groove 1-1-3 that basic 1-1-1 is arranged, wallboard 2 is vertically installed between bracket column 1-2, base part seat on basic 1-1, Both sides of the edge are affixed with bracket column 1-2 by connectors such as bolts.
Roof girder 1-4 is horizontally arranged between adjacent bracket column 1-2, and is located at bracket column 1-2 tops, and roof boarding 5 is installed Between two roof girder 1-4 above ground.
Floor beam 1-3 is horizontally arranged between adjacent bracket column 1-2, and is located in the middle part of bracket column 1-2, and floor 4 is overlapped on Between two floor beam 1-3 above ground.
Embodiment two:
Embodiment two is essentially identical with the structure composition of embodiment one, and difference is:Roof girder 1-4 and floor beam 1-3 phases Mutually antarafacial is vertical, and space crossed arrangement makes 1 structure of framework more stable, it is not necessary to which in each aspect, laterally longitudinal direction is required for setting Beam is put, is mitigated the overall weight of 1 structure of framework, is saved raw material and cost.As roof boarding 5 is overlapped on roof girder 1-4, roofing Weight transfer is given roof girder 1-4 by plate 5, then passes to bracket column 1-2 by roof girder 1-4 two ends;And floor 4 is overlapped on flooring Beam 1-3, floor 4 deliver load to floor beam 1-3, then pass to bracket column 1-2, bracket column 1-2 by floor beam 1-3 two ends Stress be more uniformly dispersed, reduce bracket column 1-2 pressure, improve structure life-span.
Embodiment three:
Embodiment three is essentially identical with the structure composition of embodiment one, and difference is:Floor beam 1-3 lapping ends are in bracket On the projection 1-3-1 that post 1-2 is arranged, rubber cushion blocks are set between the two, the installation of floor beam 1-3 is simple and convenient.
Example IV:
Example IV is essentially identical with the structure composition of embodiment three, and difference is:As shown in Fig. 2 floor beam 1-3 ends Bottom be provided with link slot 1-3-2, post bracket 1-3-1 is located in link slot 1-3-2.Floor beam 1-3 is connect with projection 1-3-1's Contacting surface is engaged with the top surface of projection 1-3-1, arranges rubber cushion blocks between the two.Post bracket 1-3-1 is inserted with floor beam 1-3 ends Connect, improve the stability of connection.
Embodiment five:
Embodiment five is essentially identical with the structure composition of embodiment one, and difference is:As shown in figure 3, the horizontal stroke of roof girder 1-4 Section is inverted L-shaped, and bottom forms a projection, is inserted in fixing groove 1-2-1 of bracket column 1-2 settings, enables roof girder 1-4 Enough more firmly it is connected with bracket column 1-2.
Embodiment six:
Embodiment six is essentially identical with the structure composition of embodiment five, and difference is:As shown in figure 3, being located at fixing groove 1- Bracket column 1-2 top surfaces on the outside of 2-1 are higher than the bracket column 1-2 top surfaces being located on the inside of fixing groove 1-2-1, fixing groove 1-2-1 bottom land And the bracket column 1-2 top surfaces on the outside of fixing groove 1-2-1 are all contacted with roof girder 1-4.
The bracket column 1-2 apical side heights of fixing groove 1-2-1 both sides are different, and outside height is higher, can support roof girder 1- 4;Inside height is relatively low, reduces bracket column 1-2 volumes, mitigates weight.Roof girder 1-4 bottom surfaces are released completely with bracket column 1-2, Gu Determine bracket column 1-2 top surfaces and fixing groove 1-2-1 bottom land on the outside of groove 1-2-1 and support jointly roof girder 1-4, ensureing that both connections are strong While spending, the stability that roof girder 1-4 is supported is improved.
Embodiment seven:
Embodiment seven is essentially identical with the structure composition of embodiment one, and difference is:2 edge of wallboard arranges tongue and groove 2-1.Wall Between plate 2 and wallboard 2 and miscellaneous part, it is mutually inserted by tongue and groove 2-1, improves bonding strength.
Embodiment eight:
Embodiment eight is essentially identical with the structure composition of embodiment seven, and difference is:Wallboard 2 is plugged on basic 1-1 and arranges Boss 1-1-4 on.Wallboard 2 can not only connect other wallboards 2 by the tongue and groove 2-1 for arranging, additionally it is possible to connection basis 1-1, Motility is strong.
Embodiment nine:
Embodiment nine is essentially identical with the structure composition of embodiment one, and difference is:As shown in figure 4, mounting groove 1-1-3 sides Angle bar fixed seat 1-1-5 is installed on the horizontal basic 1-1-1 of edge, is reclined on the inside of angle bar fixed seat 1-1-5 and is fixed on bracket On post 1-2 outer walls.Angle bar fixed seat 1-1-5 increases the support strength of bracket column side, prevents from lateral support bracket column 1-2 Bracket column deflection, it is possible to increase house wind resistance external force resistance performance.

Claims (9)

1. a kind of prefabricated assembled detachable one off houses, including tabernacular framework (1), wallboard (2), base plate (3), floor (4) and roof boarding (5), described framework (1) includes basic (1-1), bracket column (1-2), roof girder (1-4), it is characterised in that institute State framework and further include floor beam (1-3),
The basis (1-1) includes that laterally basis (1-1-1) and longitudinal direction basis (1-1-2), longitudinal direction basis (1-1-2) are installed Between (1-1-1) end of adjacent transverse basis,
Bracket column (1-2) is all installed in described horizontal basis (1-1-1) end, and bracket column (1-2) bottom is inserted into horizontal base In the mounting groove (1-1-3) that plinth (1-1-1) is arranged,
Roof girder (1-4) is between adjacent bracket column (1-2), and is located at bracket column (1-2) top,
Floor beam (1-3) is between adjacent bracket column (1-2), and is located in the middle part of bracket column (1-2).
2. prefabricated assembled detachable one off houses according to claim 1, it is characterised in that roof girder (1-4) and building Face beam (1-3) mutually antarafacial is vertical.
3. prefabricated assembled detachable one off houses according to claim 1, it is characterised in that floor beam (1-3) Lapping ends are on the post bracket (1-3-1) that bracket column (1-2) is arranged.
4. prefabricated assembled detachable one off houses according to claim 3, it is characterised in that floor beam (1-3) The bottom of end is provided with link slot (1-3-2), and post bracket (1-3-1) is located in link slot (1-3-2).
5. prefabricated assembled detachable one off houses according to claim 1, it is characterised in that roof girder (1-4) Cross section be inverted L-shaped, be inserted in the fixing groove (1-2-1) that bracket column (1-2) is arranged.
6. prefabricated assembled detachable one off houses according to claim 5, it is characterised in that positioned at fixing groove (1-2- 1) bracket column (1-2) top surface on the outside of is higher than bracket column (1-2) top surface being located on the inside of fixing groove (1-2-1), fixing groove (1-2- 1) bottom land and bracket column (1-2) top surface being located on the outside of fixing groove (1-2-1) are all contacted with roof girder (1-4).
7. prefabricated assembled detachable one off houses according to claim 1, it is characterised in that wallboard (2) edge Tongue and groove (2-1) is set.
8. the prefabricated assembled detachable one off houses according to claim 1 or 7, it is characterised in that described wallboard (2) insert It is connected on the boss (1-1-4) that basic (1-1) is arranged.
9. prefabricated assembled detachable one off houses according to claim 1, it is characterised in that the mounting groove (1-1- 3) angle bar fixed seat (1-1-5) is installed on the horizontal basis (1-1-1) at edge, pastes on the inside of angle bar fixed seat (1-1-5) Lean against on bracket column (1-2) outer wall.
CN201621023773.2U 2016-08-31 2016-08-31 Prefabricated assembled detachable one off houses CN206015895U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621023773.2U CN206015895U (en) 2016-08-31 2016-08-31 Prefabricated assembled detachable one off houses

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621023773.2U CN206015895U (en) 2016-08-31 2016-08-31 Prefabricated assembled detachable one off houses

Publications (1)

Publication Number Publication Date
CN206015895U true CN206015895U (en) 2017-03-15

Family

ID=58257885

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621023773.2U CN206015895U (en) 2016-08-31 2016-08-31 Prefabricated assembled detachable one off houses

Country Status (1)

Country Link
CN (1) CN206015895U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740495A (en) * 2017-11-25 2018-02-27 深圳市山月园园艺有限公司 More space simulation tree rooms
CN108005424A (en) * 2017-11-25 2018-05-08 深圳市山月园园艺有限公司 Assembly type artificial tree room
CN108301642A (en) * 2018-02-07 2018-07-20 华北水利水电大学 A kind of prefabricated buildings building structure and its construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740495A (en) * 2017-11-25 2018-02-27 深圳市山月园园艺有限公司 More space simulation tree rooms
CN108005424A (en) * 2017-11-25 2018-05-08 深圳市山月园园艺有限公司 Assembly type artificial tree room
CN108301642A (en) * 2018-02-07 2018-07-20 华北水利水电大学 A kind of prefabricated buildings building structure and its construction method

Similar Documents

Publication Publication Date Title
JP2007536447A (en) Bidirectional building structure system and module support member
JP2007529660A (en) Transportable modular building and construction method thereof
Navyashree et al. Use of flat slabs in multi-storey commercial building situated in high seismic zone
CN103993664A (en) Assembled light house and building and dismounting method thereof
CN102108736B (en) Combined container room
CN102041905B (en) Container house
CN104018581A (en) Prestress concrete F slab and framework structure system
CN105189884A (en) Modular building system
CN102839678B (en) Structure for improving rigidity and stability of foundation pit steel support
CN201953090U (en) Movable modularized inhabitation house
CN103821229B (en) Rapid assembly type integrated house and installation method
CN202969586U (en) Prefabricated concrete beam-column anchor welding combined structure
CN104712055B (en) A kind of wooden building based on concrete frame and construction method thereof
CN205875537U (en) Metal containment system roofing expansion joint resistance to deformation waterproof construction
CN102261129B (en) Beam column connecting piece used for building
WO2011154929A3 (en) A structural infill wall panel module
WO2018018913A1 (en) Flexible hanging type module building structure
RU2631125C1 (en) Structural module for building construction
CN103541463A (en) Wallboard and shear wall allowing floor location provided with post-pouring belt comprising same and construction method for shear wall
KR200447684Y1 (en) Block type of deck assembly
CN107217773A (en) One species wood bidirectional hollow building cover structure and preparation method thereof
CN203412140U (en) Double-layer lightgage steel joist sound proof wall
CN201245896Y (en) Frame type box body structure combination assembled movable building
CN205153116U (en) Prefabricated modularization assembled shock insulation building structure
KR100966090B1 (en) Earthquake-proof access floor system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant