CN206014242U - A kind of aid for lifting insulator - Google Patents

A kind of aid for lifting insulator Download PDF

Info

Publication number
CN206014242U
CN206014242U CN201621063738.3U CN201621063738U CN206014242U CN 206014242 U CN206014242 U CN 206014242U CN 201621063738 U CN201621063738 U CN 201621063738U CN 206014242 U CN206014242 U CN 206014242U
Authority
CN
China
Prior art keywords
splint
insulator
hoisting
clamping plate
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621063738.3U
Other languages
Chinese (zh)
Inventor
王海锋
张旭
刘涛
唐洋
陆剑春
汪洋
强宝亭
金国柱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Hangzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201621063738.3U priority Critical patent/CN206014242U/en
Application granted granted Critical
Publication of CN206014242U publication Critical patent/CN206014242U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本实用新型公开了一种用于吊装绝缘子的辅助工具,包括:第一夹板和第二夹板,第一夹板和第二夹板的两端可拆卸连接,第一夹板和第二夹板相互接触的中部均设有用于夹持绝缘子上部的两个绝缘盘连接处的凹槽。在进行吊装之前,通过第一夹板和第二夹板上的凹槽夹持于绝缘子上部的两个绝缘子连接处,然后将第一夹板和第二夹板进行固定后,通过将吊运设备的吊钩固定在第一夹板和第二夹板上,进行吊装即可。其中在吊装的过程中,第一夹板和第二夹板不仅可以大面积对绝缘子进行支撑,还可以防止绝缘子从凹槽中脱落,因此提高了吊装绝缘子的可靠性和安全性。

The utility model discloses an auxiliary tool for hoisting an insulator, which comprises: a first splint and a second splint, the two ends of the first splint and the second splint are detachably connected, and the middle part of the first splint and the second splint is in contact with each other. Both are provided with a groove for clamping the joint of the two insulating disks on the upper part of the insulator. Before hoisting, the grooves on the first splint and the second splint are clamped at the connection of the two insulators on the upper part of the insulator, and then the first splint and the second splint are fixed, and the hook of the lifting equipment It can be fixed on the first plywood and the second plywood, and can be hoisted. During the hoisting process, the first splint and the second splint can not only support the insulator in a large area, but also prevent the insulator from falling out of the groove, thus improving the reliability and safety of the hoisting insulator.

Description

一种用于吊装绝缘子的辅助工具An auxiliary tool for hoisting insulators

技术领域technical field

本实用新型涉及电力输电线路设备技术领域,特别是涉及一种用于吊装绝缘子的辅助工具。The utility model relates to the technical field of power transmission line equipment, in particular to an auxiliary tool for hoisting insulators.

背景技术Background technique

更换绝缘子的传统方式,主要是工作人员在地面用绳索将绝缘子捆绑好,然后通过绳索吊运至铁塔横担处,高空作业人员在高空解开绳索,再进行绝缘子的安装。但是此种作业方式,存在以下问题:由于每个人捆扎绳索打结的方法各种各样,可能会给高空作业人员带来不必要的麻烦,而且由于高空作业条件的限制,一些绳结甚至无法打开,因此造成工作效率极其低下。也可能存在绳索未捆紧的情况,容易使绝缘子在吊运的过程中脱落,存在一定的安全隐患。另外在吊运的过程中,绝缘子容易产生打转、晃动的情况,若与铁塔进行碰撞,不仅会损坏绝缘子,还有可能产生高空掉落的风险,为了避免绝缘子发生碰撞,通常需要两个人进行起吊,无法实现单人起吊作业。The traditional way of replacing insulators is mainly that the staff bind the insulators with ropes on the ground, and then lift them to the cross arm of the iron tower through the ropes, and the high-altitude workers untie the ropes at high altitude, and then install the insulators. But this kind of operation method has the following problems: due to the various methods of tying knots for each person, it may cause unnecessary troubles to high-altitude workers, and due to the limitation of high-altitude operation conditions, some knots cannot even be used. open, thus causing extremely low work efficiency. There may also be situations where the ropes are not tied tightly, which may easily cause the insulator to fall off during the lifting process, posing a certain safety hazard. In addition, in the process of hoisting, the insulator is prone to spinning and shaking. If it collides with the iron tower, it will not only damage the insulator, but also cause the risk of falling from high altitude. In order to avoid the collision of the insulator, two people are usually required to lift it , unable to achieve single-person lifting operations.

因此,如何解决绝缘子在吊运的过程中脱落的风险,是本领域技术人员急需解决的技术问题。Therefore, how to solve the risk of the insulator falling off during hoisting is a technical problem urgently needed by those skilled in the art.

实用新型内容Utility model content

本实用新型的目的是提供一种用于吊装绝缘子的辅助工具,可以有效解决绝缘子在吊运时,容易掉落的问题。The purpose of the utility model is to provide an auxiliary tool for hoisting insulators, which can effectively solve the problem that the insulators are easy to fall during hoisting.

为解决上述技术问题,本实用新型提供了如下技术方案:In order to solve the above technical problems, the utility model provides the following technical solutions:

一种用于吊装绝缘子的辅助工具,包括:第一夹板和第二夹板,所述第一夹板和所述第二夹板的两端可拆卸连接,所述第一夹板和所述第二夹板相互接触的中部均设有用于夹持绝缘子上部的两个绝缘盘连接处的凹槽。An auxiliary tool for hoisting an insulator, comprising: a first splint and a second splint, both ends of the first splint and the second splint are detachably connected, and the first splint and the second splint are connected to each other The middle part of the contact is provided with a groove for clamping the joint of the two insulating discs on the upper part of the insulator.

优选地,所述凹槽为半圆形凹槽。Preferably, the groove is a semicircular groove.

优选地,所述第一夹板的两端通过第一螺栓分别和所述第二夹板的两端连接,所述第一螺栓上设有吊环。Preferably, both ends of the first splint are respectively connected to both ends of the second splint by first bolts, and lifting rings are provided on the first bolts.

优选地,所述第一夹板的一端和所述第二夹板的一端通过铰接轴铰接,所述第一夹板的另一端和所述第二夹板的另一端通过第二螺栓连接,所述铰接轴和所述第二螺栓上设有起吊部。Preferably, one end of the first splint is hinged to one end of the second splint by a hinge shaft, the other end of the first splint is connected to the other end of the second splint by a second bolt, and the hinge shaft And the second bolt is provided with a lifting part.

优选地,所述第一螺栓上设有防松装置。Preferably, an anti-loosening device is provided on the first bolt.

与现有技术相比,上述技术方案具有以下优点:Compared with the prior art, the above-mentioned technical solution has the following advantages:

本实用新型所提供的一种用于吊装绝缘子的辅助工具,包括:第一夹板和第二夹板,第一夹板和第二夹板的两端可拆卸连接,第一夹板和第二夹板相互接触的中部均设有用于夹持绝缘子上部的两个绝缘盘连接处的凹槽。在进行吊装之前,通过第一夹板和第二夹板上的凹槽夹持于绝缘子上部的两个绝缘子连接处,然后将第一夹板和第二夹板进行固定后,通过将吊运设备的吊钩固定在第一夹板和第二夹板上,进行吊装即可。其中在吊装的过程中,第一夹板和第二夹板不仅可以大面积对绝缘子进行支撑,还可以防止绝缘子从凹槽中脱落,因此提高了吊装绝缘子的可靠性和安全性。The utility model provides an auxiliary tool for hoisting insulators, comprising: a first splint and a second splint, the two ends of the first splint and the second splint are detachably connected, and the first splint and the second splint are in contact with each other The middle part is provided with a groove for clamping the joint of the two insulating discs on the upper part of the insulator. Before hoisting, clamp the connection between the two insulators on the upper part of the insulator through the grooves on the first splint and the second splint, then fix the first splint and the second splint, and then use the hook of the lifting equipment It can be fixed on the first plywood and the second plywood, and can be hoisted. During the hoisting process, the first splint and the second splint can not only support the insulator in a large area, but also prevent the insulator from falling out of the groove, thus improving the reliability and safety of the hoisting insulator.

附图说明Description of drawings

为了更清楚地说明本实用新型或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the utility model or the technical solution in the prior art, the accompanying drawings that need to be used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the accompanying drawings in the following description are the present invention. For some embodiments of the utility model, those skilled in the art can also obtain other drawings based on these drawings without creative work.

图1为本实用新型一种具体实施方式所提供的一种用于吊装绝缘子的辅助工具打开时的结构示意图;Fig. 1 is a schematic structural view of an auxiliary tool for hoisting insulators provided by a specific embodiment of the present invention when it is opened;

图2为本实用新型一种具体实施方式所提供的一种用于吊装绝缘子的辅助工具合拢时的结构示意图;Fig. 2 is a schematic structural view of an auxiliary tool for hoisting insulators provided by a specific embodiment of the present invention when it is closed;

图3为本实用新型一种具体实施方式所提供的一种用于吊装绝缘子的辅助工具安装在绝缘子上时的结构示意图。Fig. 3 is a schematic structural view of an auxiliary tool for hoisting an insulator provided by a specific embodiment of the present invention when it is installed on the insulator.

附图标记如下:The reference signs are as follows:

1为第一夹板,2为第二夹板,3为凹槽,4为吊环,5为吊绳,6为绝缘盘。1 is the first splint, 2 is the second splint, 3 is the groove, 4 is the suspension ring, 5 is the suspension rope, and 6 is the insulating disc.

具体实施方式detailed description

正如背景技术部分所述,目前通过绳子捆绑绝缘子,然后进行吊装,不仅容易使绝缘子掉落,还不便高空作业人员进行操作。As mentioned in the background technology section, at present, insulators are bound with ropes and then hoisted, which not only makes the insulators fall easily, but also makes it inconvenient for workers working at heights to operate.

基于上述研究的基础上,本实用新型实施例提供了一种用于吊装绝缘子的辅助工具,在进行吊装之前,通过第一夹板和第二夹板上的凹槽夹持于绝缘子上部的两个绝缘子连接处,然后将第一夹板和第二夹板进行固定后,通过将吊运设备的吊钩固定在第一夹板和第二夹板上,进行吊装即可。其中在吊装的过程中,第一夹板和第二夹板不仅可以大面积对绝缘子进行支撑,还可以防止绝缘子从凹槽中脱落,因此提高了吊装绝缘子的可靠性和安全性。Based on the above research, the embodiment of the utility model provides an auxiliary tool for hoisting insulators. Before hoisting, the two insulators on the upper part of the insulator are clamped by the grooves on the first splint and the second splint. At the joint, after fixing the first splint and the second splint, the hook of the hoisting equipment is fixed on the first splint and the second splint for hoisting. During the hoisting process, the first splint and the second splint can not only support the insulator in a large area, but also prevent the insulator from falling out of the groove, thus improving the reliability and safety of the hoisting insulator.

为了使本实用新型的上述目的、特征和优点能够更为明显易懂,下面结合附图对本实用新型的具体实施方式做详细的说明。In order to make the above purpose, features and advantages of the utility model more obvious and easy to understand, the specific implementation of the utility model will be described in detail below in conjunction with the accompanying drawings.

在以下描述中阐述了具体细节以便于充分理解本实用新型。但是本实用新型能够以多种不同于在此描述的其它方式来实施,本领域技术人员可以在不违背本实用新型内涵的情况下做类似推广。因此本实用新型不受下面公开的具体实施方式的限制。In the following description, specific details are set forth in order to provide a full understanding of the present invention. However, the utility model can be implemented in many other ways different from those described here, and those skilled in the art can make similar extensions without violating the connotation of the utility model. Therefore, the utility model is not limited by the specific embodiments disclosed below.

请参考图1至图3,图1为本实用新型一种具体实施方式所提供的一种用于吊装绝缘子的辅助工具的结构示意图;图2为本实用新型一种具体实施方式所提供的一种用于吊装绝缘子的辅助工具合拢时的结构示意图;图3为本实用新型一种具体实施方式所提供的一种用于吊装绝缘子的辅助工具安装在绝缘子上时的结构示意图。Please refer to Figures 1 to 3, Figure 1 is a schematic structural view of an auxiliary tool for hoisting insulators provided by a specific embodiment of the present invention; Figure 2 is a schematic diagram of an auxiliary tool provided by a specific embodiment of the present invention A schematic diagram of the structure of an auxiliary tool for hoisting insulators when it is closed; Figure 3 is a schematic structural diagram of an auxiliary tool for hoisting insulators provided by a specific embodiment of the present invention when it is installed on the insulator.

本实用新型的一种具体实施方式提供了一种用于吊装绝缘子的辅助工具,包括:第一夹板1和第二夹板2,第一夹板1和第二夹板2的两端可拆卸连接,第一夹板1和第二夹板2相互接触的中部均设有用于夹持绝缘子上部的两个绝缘盘6连接处的凹槽3。A specific embodiment of the utility model provides an auxiliary tool for hoisting insulators, including: a first splint 1 and a second splint 2, the two ends of the first splint 1 and the second splint 2 are detachably connected, the second The middle parts of the first clamping plate 1 and the second clamping plate 2 which are in contact with each other are provided with grooves 3 for clamping the junction of two insulating discs 6 on the upper part of the insulator.

在本实施例中,通过第一夹板1和第二夹板2上的凹槽3夹持于绝缘子上部的两个绝缘盘6连接处,然后将第一夹板1和第二夹板2进行固定后,通过将吊运设备的吊绳5上的吊钩固定在第一夹板1和第二夹板2上,进行吊装即可。其中在吊装的过程中,第一夹板1和第二夹板2不仅可以大面积对绝缘子进行支撑,还可以防止绝缘子从凹槽中脱落,因此提高了吊装绝缘子的可靠性和安全性。In this embodiment, the groove 3 on the first splint 1 and the second splint 2 is clamped at the joint of the two insulating disks 6 on the upper part of the insulator, and then the first splint 1 and the second splint 2 are fixed, By fixing the hook on the sling 5 of the hoisting equipment on the first splint 1 and the second splint 2, the hoisting can be carried out. During the hoisting process, the first splint 1 and the second splint 2 can not only support the insulator in a large area, but also prevent the insulator from falling out of the groove, thus improving the reliability and safety of the hoisting insulator.

进一步地,凹槽3优选为半圆形凹槽。当然也可以为其它形状的凹槽3,具体根据实际情况而定,本实施例对此不做限定。Further, the groove 3 is preferably a semicircular groove. Of course, other shapes of grooves 3 may also be used, depending on the actual situation, which is not limited in this embodiment.

为了便于将第一夹板1和第二夹板2进行连接,进而提高工作效率,第一夹板1的两端通过第一螺栓分别和第二夹板2的两端连接,第一螺栓上设有吊环4。通过吊环4可以方便吊运设备上的吊钩进行连接。其中可以在第一夹板1和第二夹板2的两端分别设置折弯部,然后在折弯部上设置通孔,通过第一螺栓进行连接即可,在具体使用的时候,可以将其中连接的一端进行永久固定,将另一端通过第一螺栓进行可拆卸连接即可。另外为了提高吊装的稳定性,第一夹板1和第二夹板2应处于同一平面内。In order to facilitate the connection of the first splint 1 and the second splint 2, thereby improving work efficiency, the two ends of the first splint 1 are respectively connected to the two ends of the second splint 2 through the first bolts, and the first bolts are provided with suspension rings 4 . The hooks on the hoisting equipment can be conveniently connected through the hoisting ring 4 . Among them, bending parts can be respectively set at the two ends of the first splint 1 and the second splint 2, and then through holes are set on the bending parts, and the first bolts can be used to connect them. One end is permanently fixed, and the other end is detachably connected by the first bolt. In addition, in order to improve the stability of hoisting, the first splint 1 and the second splint 2 should be in the same plane.

进一步地,第一夹板1的一端和第二夹板2的一端通过铰接轴铰接,第一夹板1的另一端和第二夹板2的另一端通过第二螺栓连接,铰接轴和第二螺栓上设有起吊部。可以将铰接轴铰接的一端进行固定,在使用的时候,不对其进行拆卸,只拆卸第二螺栓,然后夹持完绝缘子后,再将第二螺栓进行固定,然后将吊运设备上的吊钩安装在吊装部上即可进行起吊作业,因此可以提高绝缘子吊装的效率。Further, one end of the first splint 1 and one end of the second splint 2 are hinged by a hinge shaft, the other end of the first splint 1 and the other end of the second splint 2 are connected by a second bolt, and the hinge shaft and the second bolt are provided with There is a lifting department. The hinged end of the hinge shaft can be fixed. When in use, it is not disassembled, only the second bolt is removed, and after the insulator is clamped, the second bolt is fixed, and then the hook on the lifting device is fixed. The hoisting operation can be performed by installing it on the hoisting part, so the efficiency of insulator hoisting can be improved.

为了进一步地提高吊装的安全性,第一螺栓或第二螺栓上设有防松装置。其中防松装置可以为设置在第一螺栓或第二螺栓上的止动垫片,也通过在第一螺栓或第二螺栓的径向穿插铁丝来防止其松动,当然也可以通过双螺母的方式进行防松,具体根据实际情况而定,本实施例对此不做限定。In order to further improve the safety of hoisting, an anti-loosening device is provided on the first bolt or the second bolt. The anti-loosening device can be a stop washer arranged on the first bolt or the second bolt, and it can also be prevented from loosening by inserting iron wires in the radial direction of the first bolt or the second bolt, of course, it can also be used by means of double nuts The anti-loosening is determined according to the actual situation, which is not limited in this embodiment.

需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体与另一个实体区分开来,而不一定要求或者暗示这些实体之间存在任何这种实际的关系或顺序。It should be noted that in this article, relational terms such as first and second etc. are only used to distinguish one entity from another, and do not necessarily require or imply any such actual existence between these entities. relationship or sequence.

以上对本实用新型所提供的一种用于吊装绝缘子的辅助工具进行了详细介绍。本文中应用了具体个例对本实用新型的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本实用新型的核心思想。应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理的前提下,还可以对本实用新型进行若干改进和修饰,这些改进和修饰也落入本实用新型权利要求的保护范围内。An auxiliary tool for hoisting insulators provided by the utility model has been introduced in detail above. In this paper, specific examples are used to illustrate the principle and implementation of the present utility model, and the descriptions of the above embodiments are only used to help understand the core idea of the present utility model. It should be pointed out that for those of ordinary skill in the art, without departing from the principle of the utility model, some improvements and modifications can also be made to the utility model, and these improvements and modifications also fall into the protection of the claims of the utility model. within range.

Claims (5)

1. a kind of aid for lifting insulator, it is characterised in that include:First clamping plate and second clamping plate, described The two ends of one clamping plate and the second clamping plate are detachably connected, the middle part that the first clamping plate and the second clamping plate contact with each other It is equipped with for clamping the groove of two insulating disc junctions on insulator top.
2. aid according to claim 1, it is characterised in that the groove is semi-circular recesses.
3. aid according to claim 2, it is characterised in that the two ends of the first clamping plate are by the first bolt point The two ends connection of other and described second clamping plate, first bolt are provided with suspension ring.
4. aid according to claim 2, it is characterised in that one end of the first clamping plate and the second clamping plate One end be hinged by jointed shaft, the other end of the other end of the first clamping plate and the second clamping plate is connected by the second bolt Connect, the jointed shaft and second bolt have been provided with hanging part.
5. aid according to claim 3, it is characterised in that first bolt is provided with locking device.
CN201621063738.3U 2016-09-19 2016-09-19 A kind of aid for lifting insulator Expired - Fee Related CN206014242U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621063738.3U CN206014242U (en) 2016-09-19 2016-09-19 A kind of aid for lifting insulator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621063738.3U CN206014242U (en) 2016-09-19 2016-09-19 A kind of aid for lifting insulator

Publications (1)

Publication Number Publication Date
CN206014242U true CN206014242U (en) 2017-03-15

Family

ID=58261076

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621063738.3U Expired - Fee Related CN206014242U (en) 2016-09-19 2016-09-19 A kind of aid for lifting insulator

Country Status (1)

Country Link
CN (1) CN206014242U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109928302A (en) * 2019-03-22 2019-06-25 国网上海市电力公司 A kind of insulator lifting device
CN112193981A (en) * 2020-09-24 2021-01-08 浙江海亮股份有限公司 Coil support base and split device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109928302A (en) * 2019-03-22 2019-06-25 国网上海市电力公司 A kind of insulator lifting device
CN112193981A (en) * 2020-09-24 2021-01-08 浙江海亮股份有限公司 Coil support base and split device
CN112193981B (en) * 2020-09-24 2025-03-21 浙江海亮股份有限公司 Coil support base and split device

Similar Documents

Publication Publication Date Title
CN201713215U (en) Flange pipe hanger
CN204848091U (en) Steel sheet cross arm hoisting accessory
CN203760908U (en) Cement pole crossarm installation tool
CN206014242U (en) A kind of aid for lifting insulator
CN203112383U (en) Boom root connecting device of tower crane
CN103979403A (en) Wire cable terminal lifting fixture as well as wire cable lifting method
CN101378153A (en) Diverter for grounding wire
CN204407790U (en) A kind of insulation gin pole for getting out wire jumper
CN207211918U (en) Internally lifting pole
CN110552936A (en) Wire pole staple bolt device of balanced acting as go-between
CN205622144U (en) Portable transmission line overhead ground wire elevating gear
CN220317073U (en) TRD shaped steel hoist and mount stability fixture and hoist thereof
CN203806962U (en) Cable terminal head lifting fixture
CN204265218U (en) A kind of power station unit internal head cover special hanger
CN203660422U (en) 500 kV overhead ground wire lifting tool
CN103072888A (en) Hoisting equipment and hoisting method for generator in wind generating set
CN203607750U (en) Suspension ring device for loosening-tightening line pulley
CN202594599U (en) Tool special for hoisting casing
CN209805246U (en) A Lifting System Based on Insulator Strings
CN107381324A (en) A kind of ultralong overweight wire insulation substring hangs auxiliary lifting appliance
CN207158591U (en) A kind of ultralong overweight wire insulation substring hangs auxiliary lifting appliance
CN207276078U (en) Portable hoisting device
CN203208568U (en) Safety belt hanger
CN206487204U (en) A kind of Novel electric line bar
CN222781294U (en) A pole switch hoisting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170315