CN205933036U - Pipe truss installation is with high altitude parts overhead hoist - Google Patents

Pipe truss installation is with high altitude parts overhead hoist Download PDF

Info

Publication number
CN205933036U
CN205933036U CN201620951776.6U CN201620951776U CN205933036U CN 205933036 U CN205933036 U CN 205933036U CN 201620951776 U CN201620951776 U CN 201620951776U CN 205933036 U CN205933036 U CN 205933036U
Authority
CN
China
Prior art keywords
suspension rod
pulley
tubular truss
fixed part
handling apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620951776.6U
Other languages
Chinese (zh)
Inventor
张�杰
郭静萍
刘德发
吴晏平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan construction machinery manufacturing and Installation Engineering Co., Ltd.
Original Assignee
Fourteen Metallurgical Construction Group Yunnan Machinery Manufacturing Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourteen Metallurgical Construction Group Yunnan Machinery Manufacturing Installation Engineering Co Ltd filed Critical Fourteen Metallurgical Construction Group Yunnan Machinery Manufacturing Installation Engineering Co Ltd
Priority to CN201620951776.6U priority Critical patent/CN205933036U/en
Application granted granted Critical
Publication of CN205933036U publication Critical patent/CN205933036U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a pipe truss installation is with high altitude parts overhead hoist, including jib, pulley, steel cable, hoist engine, set up the staple bolt on the jib, the staple bolt includes fixed part and digging arm, and the digging arm sets up in fixed part both sides and articulated with the fixed part, and the counter bore has been offered to the fixed part, has offered the through -hole on the jib, and the staple bolt is fixed on the jib through the through -hole that the bolt passed on counter bore and the jib, and the digging arm is connected on pipe truss's lower chord, and the outer cladding of jib has the pulley holder of the type of falling U, and the hoist engine is installed on pipe truss, and steel cable one end is passed through the pulley and is connected the hoist engine. The utility model discloses an install parts overhead hoist aloft on the pipe truss, avoided the large -tonnage crane choose for use and the supplementary of ground is laid, reduced installation cost with hoist and mount the degree of difficulty, this overhead hoist can adjust with pipe truss's mounted position, pulley holder and pipe truss's mounted position at will, makes things convenient for the constructor operation, and the parts all hangs one's own department or unit, has guaranteed the installation accuracy.

Description

A kind of tubular truss is installed and is used high-altitude loose mail handling apparatus
Technical field
This utility model is related to a kind of tubular truss hanging apparatus and in particular to a kind of structure is simple, flexible for installation, dismounting side Just tubular truss is installed and is used high-altitude loose mail handling apparatus.
Background technology
In recent years, large span spatial pipe truss steel construction was because its steel content is low, the unique grace of moulding, short construction period etc. Advantage be widely used for the Factory Building of large span, exhibition center, conference and exhibition center, large-scale stadium, airport, market, Trade City, In the large-scale civilian public sign building such as station, music hall, theater, bridge.The space structure being made up of two power bars is truss Structure, its have gently, span big, the big feature of load, play load-bearing effect.In conventional construction and installation, for this large span Tubular truss, typically all adopts in factory and makes rod member, field ground sectional or overall package, from truck crane or crawler belt Formula truck crane carries out segmentation or integral hoisting.This installation method, crane hoisting equipment will select large-tonnage truck crane, also Load supporting ability of ground is had higher requirements, is limited by place, and installation accuracy is not high, the chord member of truss structure is irregular Body, and the many moulding of the number of components are complicated irregular.The installation site necessarily requiring each rod member in bulk reaches drawing requirement, right The installation accuracy of structure has high demands.
Utility model content
The purpose of this utility model is to provide that a kind of structure is simple, flexible for installation, convenient disassembly tubular truss is installed and used High-altitude loose mail handling apparatus.
The purpose of this utility model is achieved in that including suspension rod, pulley, steel cable, hoist engine, and described suspension rod is arranged Anchor ear, described anchor ear includes fixed part and lever arm, and described lever arm is arranged at fixed part both sides and hinged with fixed part, described Fixed part offers counterbore, and described suspension rod offers through hole, and described anchor ear passes through the through hole on counterbore and suspension rod by bolt It is fixed on suspension rod, described lever arm is connected on the lower boom of tubular truss, described suspension rod is coated with the pulley base of inverted U, Described pulley base bottom arranges pulley, and described hoist engine is arranged on tubular truss, and described steel cable one end connects elevator by pulley Machine.
This utility model passes through to install loose mail handling apparatus on the tubular truss of high-altitude, it is to avoid the selection of large-tonnage truck crane And the auxiliary laying of ground, reduce installation cost and hoisting difficulty;The installation site of this handling apparatus and tubular truss, pulley Seat can arbitrarily be adjusted with the installation site of tubular truss, convenient construction human users, and loose mail all hangs one's own department or unit it is ensured that installing essence Degree.
Brief description
Fig. 1 is this utility model and tubular truss assembling structure schematic diagram;
Fig. 2 is suspension rod and tubular truss connection diagram;
Fig. 3 is pulley base and tubular truss connection diagram;
Fig. 4 is connected another embodiment structural representation for pulley base with tubular truss;
In figure:1- suspension rod, 2- anchor ear, 21- fixed part, 22- lever arm, 3- pulley, 4- steel cable, 5- pulley base, 6- pipe purlin Frame, 7- hoist engine.
Specific embodiment
Below in conjunction with the accompanying drawings this utility model is further described, but must not by any way to this utility model plus With restriction, any change made based on this utility model training centre or improvement, belong to protection domain of the present utility model.
As shown in Fig. 1 ~ 4, this utility model includes suspension rod 1, pulley 3, steel cable 4, hoist engine 7, and setting on described suspension rod 1 is embraced Hoop 2, described anchor ear 2 includes fixed part 21 and lever arm 22, and described lever arm 22 is arranged at fixed part 21 both sides and and fixed part 21 is hinged, and described fixed part 21 offers counterbore, and described suspension rod 1 offers through hole, and described anchor ear 2 passes through counterbore by bolt It is fixed on suspension rod 1 with the through hole on suspension rod 1, described lever arm 22 is connected on the lower boom of tubular truss 6, outside described suspension rod 1 It is coated with the pulley base 5 of inverted U, described pulley base 5 bottom arranges pulley 3, and described hoist engine 7 is arranged on tubular truss 6, described Steel cable 4 one end connects hoist engine 7 by pulley 3.
On described suspension rod 1, multiple through holes are set.
Described suspension rod 1 is hollow pipe or square tube, and the shape of pulley base 5 is adapted with its shape.
The upper end setting installing hole of described pulley base 5, described pulley base 5 is passed through on installing hole and suspension rod 1 by bolt Through hole is fixed on suspension rod 1.
Described pulley base 5 is the parallel row of the falling U structure in both sides.
The row of the falling U structure that described pulley base 5 closes up for bottom.
Described lever arm 22 upper end arranges otic placode, and otic placode arranges bolt hole, and two lever arms 22 pass through spiral shell by bolt Keyhole is fixed on the lower boom of tubular truss 6.
Operation principle of the present utility model and work process are as follows:
When this utility model leads to use, first set up scaffold mounting portion tubular truss, then loose mail is installed on tubular truss and hang Shipping unit, it is to avoid large-tonnage truck crane from and ground auxiliary laying, reduce installation cost and hoisting difficulty;Should Handling apparatus can arbitrarily be adjusted with the installation site of the installation site, pulley base and tubular truss of tubular truss, convenient construction personnel Operation, loose mail all hangs one's own department or unit it is ensured that installation accuracy.

Claims (7)

1. a kind of tubular truss is installed and is used high-altitude loose mail handling apparatus, including suspension rod(1), pulley(3), steel cable(4), hoist engine(7), It is characterized in that:Described suspension rod(1)Upper setting anchor ear(2), described anchor ear(2)Including fixed part(21)And lever arm(22), described Lever arm(22)It is arranged at fixed part(21)Both sides and and fixed part(21)Hinged, described fixed part(21)Offer counterbore, institute State suspension rod(1)On offer through hole, described anchor ear(2)Counterbore and suspension rod are passed through by bolt(1)On through hole be fixed on suspension rod (1)On, described lever arm(22)It is connected to tubular truss(6)Lower boom on, described suspension rod(1)It is coated with the pulley of inverted U Seat(5), described pulley base(5)Bottom arranges pulley(3), described hoist engine(7)It is arranged on tubular truss(6)On, described steel cable(4) Pulley is passed through in one end(3)Connect hoist engine(7).
2. tubular truss according to claim 1 is installed and is used high-altitude loose mail handling apparatus, it is characterized in that:Described suspension rod(1)On Multiple through holes are set.
3. tubular truss according to claim 1 and 2 is installed and is used high-altitude loose mail handling apparatus, it is characterized in that:Described suspension rod(1) For hollow pipe or square tube, pulley base(5)Shape and its shape be adapted.
4. tubular truss according to claim 1 is installed and is used high-altitude loose mail handling apparatus, it is characterized in that:Described pulley base(5) Upper end setting installing hole, described pulley base(5)Installing hole and suspension rod are passed through by bolt(1)On through hole be fixed on suspension rod (1)On.
5. the high-altitude loose mail handling apparatus of the tubular truss installation according to claim 1 or 4, is characterized in that:Described pulley base (5)For the parallel row of the falling U structure in both sides.
6. the high-altitude loose mail handling apparatus of the tubular truss installation according to claim 1 or 4, is characterized in that:Described cunning Wheel seat(5)The row of the falling U structure closing up for bottom.
7. tubular truss according to claim 1 is installed and is used high-altitude loose mail handling apparatus, it is characterized in that:Described lever arm(22) Upper end arranges otic placode, and otic placode arranges bolt hole, two lever arms(22)Tubular truss is fixed on by bolt passing through bolt hole(6) Lower boom on.
CN201620951776.6U 2016-08-27 2016-08-27 Pipe truss installation is with high altitude parts overhead hoist Active CN205933036U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620951776.6U CN205933036U (en) 2016-08-27 2016-08-27 Pipe truss installation is with high altitude parts overhead hoist

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620951776.6U CN205933036U (en) 2016-08-27 2016-08-27 Pipe truss installation is with high altitude parts overhead hoist

Publications (1)

Publication Number Publication Date
CN205933036U true CN205933036U (en) 2017-02-08

Family

ID=57954804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620951776.6U Active CN205933036U (en) 2016-08-27 2016-08-27 Pipe truss installation is with high altitude parts overhead hoist

Country Status (1)

Country Link
CN (1) CN205933036U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517959A (en) * 2018-05-05 2018-09-11 十四冶建设集团云南安装工程有限公司 Large-scale research and development centre's tubular truss construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517959A (en) * 2018-05-05 2018-09-11 十四冶建设集团云南安装工程有限公司 Large-scale research and development centre's tubular truss construction
CN108517959B (en) * 2018-05-05 2019-11-22 十四冶建设集团云南安装工程有限公司 Large-scale research and development centre's tubular truss construction

Similar Documents

Publication Publication Date Title
CN101672102B (en) Steel structural overhead ceiling construction platform
CN209686836U (en) Frame body for attached lifting scaffolding
CN109184061B (en) Space structure overhanging eave suspended ceiling system structure and construction method
US8672092B2 (en) Wire rope tension grid improvements
CN213418441U (en) Safety protection and operation platform for light production well
CN205892588U (en) Hoisting equipment
CN204434116U (en) A kind of hanging device for interior courtyard lifting pipeline
CN203128099U (en) Slipping type pipeline lifting device
CN205933036U (en) Pipe truss installation is with high altitude parts overhead hoist
CN116005810A (en) Combined hanging building structure system of steel truss and steel inhaul cable and construction method thereof
CN106245986A (en) The method for assembling of power network line steel tower and device
CN215052128U (en) Platform in tower column shaft
CN211775988U (en) A kind of high-altitude protection device for steel structure high-rise tower
CN108718058A (en) A kind of cantilever crossing frame from lifting rotary type
CN207228591U (en) A kind of architectural engineering scaffold
CN206088824U (en) A simple and easy hoisting frame device for it is indoor
CN216113032U (en) Lifting support of monitoring sensor
CN205688778U (en) A kind of elevating scaffold special over sling structure
CN103899078B (en) Attachment automatic lifting protecting screen mounting method
CN117027352A (en) Large-span high altitude vestibule curtain wall construction operation platform
CN115075585A (en) Installation method of special-shaped space twisted steel pipe truss
CN203225074U (en) Advertising board of net rack structure
CN115719938B (en) Integral tubular busbar hoisting scheme special for wind power stepped concrete tower
CN205973671U (en) Hanging flower basket linkage
CN206328690U (en) A kind of big discrepancy in elevation, large span stiff skeleton external wrapping concrete template construction equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 650000 Songming, Yunnan, Yang Linzhen,

Patentee after: Yunnan construction machinery manufacturing and Installation Engineering Co., Ltd.

Address before: 650000 Songming, Yunnan, Yang Linzhen,

Patentee before: Fourteen Metallurgical Construction Group Yunnan Machinery Manufacturing Installation Engineering Co., Ltd.