CN205874982U - High base stone pier hanging flower basket - Google Patents
High base stone pier hanging flower basket Download PDFInfo
- Publication number
- CN205874982U CN205874982U CN201620767749.3U CN201620767749U CN205874982U CN 205874982 U CN205874982 U CN 205874982U CN 201620767749 U CN201620767749 U CN 201620767749U CN 205874982 U CN205874982 U CN 205874982U
- Authority
- CN
- China
- Prior art keywords
- steel
- steel component
- bridge pier
- pinner
- guard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Revetment (AREA)
Abstract
The utility model relates to a high base stone pier hanging flower basket. Conventional pier hanging flower basket adopts in pier tray outside embedded steel, welds with shaped steel and bolted connection steel component and set up the steel grating and form again, and on -the -spot structrual joint is complicated, and it is loaded down with trivial details to be under construction. The utility model discloses a high support base stone, tray top is concrete guard wall, stand steel component and go along with sb. To guard him steel component all around, high support base stone sets up in the tray top of pier, and tray top concrete guard wall all around sets up in tray top border, and stand steel component is pre -buried in tray top concrete guard wall top all around, goes along with sb. To guard him steel component and passes stand steel component and effective the connection with the perforation mode. The utility model discloses a simple structure, appearance pleasing to the eye, the construction is simple and easy, the atress is clear and definite. Optimized the work progress of conventional hanging flower basket, and the whole appearance of structure is coordinated beautifully by a wide margin.
Description
Technical field
This utility model relates to transport development technical field, is specifically related to a kind of high pinner bridge pier hanging basket.
Background technology
At present, conventional bridge pier hanging basket is used in pre-buried shaped steel outside bridge pier pallet, then carries out with shaped steel welding and bolt company
Direct type steel beam column is also set up steel grating and is formed, but the method scene component connects complexity, constructs loaded down with trivial details, and bridge pier overall structure regards
Feel property is poor.
Summary of the invention
The purpose of this utility model be to provide a kind of easy construction, profile coordinate attractive in appearance, economy is higher, highly versatile
High pinner bridge pier hanging basket.
The technical scheme that this utility model is used is:
A kind of high pinner bridge pier hanging basket, it is characterised in that:
Support pinner, pallet top circumferential concrete revetment, pillar steel component including high and go along with sb. to guard him Steel section member;
The high pinner that supports is arranged at the tray top of bridge pier, and pallet top circumferential concrete revetment is arranged at tray top limit
Edge, pillar steel component is embedded in circumferential concrete revetment top, pallet top in advance, go along with sb. to guard him Steel section member on pillar steel component with
Perforation means passes and effectively connects.
Pillar steel component is all vertically arranged, and goes along with sb. to guard him Steel section member and is formed through laterally connecting between pillar steel component
Connect.
Pallet top circumferential concrete revetment and bridge pier are one-piece casting structure, respective steel bar overall binding.
Outside the circumferential concrete revetment of pallet top concordant with outside pallet top.
This utility model has the advantage that
This utility model use simple in construction, good looking appearance, construction is simple, stress is clear and definite.Routine is greatly optimized hang
The work progress of basket, and the coordination attractive in appearance of structure monnolithic case.
Accompanying drawing explanation
Fig. 1 is this utility model plane graph.
Fig. 2 is this utility model front elevational view.
Fig. 3 is this utility model sectional side view.
In figure, 1-height supports pinner, and 2-pallet top circumferential concrete revetment, 3-pillar steel component, 3-goes along with sb. to guard him shaped steel structure
Part.
Detailed description of the invention
Below in conjunction with detailed description of the invention, this utility model is described in detail.
The high pinner bridge pier hanging basket that this utility model relates to, the concrete guard wall of concordant bridge pier pallet, revetment outside employing
Upper (or interior) shaped steel column and surrounding go along with sb. to guard him shaped steel, bridge pier and the coordination attractive in appearance of hanging basket overall structure, site operation simple and convenient, with
Time reduce rolled steel dosage and Site Welding and screwing process has suitable economic benefit.
This utility model includes high support pinner 1, pallet top circumferential concrete revetment 2, pillar steel component 3 and goes along with sb. to guard him type
Steel beam column 4.The high pinner 1 that supports is arranged at the tray top of bridge pier, and the high pinner 1 that supports is arranged in tray top both sides.Pallet top
Circumferential concrete revetment 2 is arranged at tray top edge.Pallet top circumferential concrete revetment 2 and bridge pier are one-piece casting structure,
Each steel bar overall binding.Pillar steel component 3 is embedded in circumferential concrete revetment 2 top, pallet top in advance, goes along with sb. to guard him Steel section member 4 and leads to
Cross bolt or welding manner is connected to revetment Steel section member 3.The more common bridge pier in pallet top section is bigger, in order to strengthening pinner to hanging
Between basket, space is for safeguarding that maintenance is used.Pillar steel component 3 is all vertically arranged, and goes along with sb. to guard him Steel section member 4 at pillar steel component 3
Between pass and formed lateral connection with punch format, connect simple and reliable between each parts, construct simple and convenient.
Outside pallet top circumferential concrete revetment 2 concordant with outside pallet top, the most concordant and bridge outside whole barrel structure
Outside pier pallet top, barrel structure simple structure is generous, simple attractive in appearance, harmonious with whole bridge pier structure.
Pallet top circumferential concrete revetment 2, pillar steel component 3 and go along with sb. to guard him Steel section member 4 in the pre-buried or bolt in scene even
Connect, reduce hanging basket steel material by adding high pier pinner and easily change work progress.
During construction:
1, overall binding bridge pier and pallet top circumferential concrete revetment 2 reinforcing bar, one-piece casting bridge pier and pallet top surrounding are mixed
Solidifying soil revetment 2, and pre-buried revetment upper pillar stand Steel section member 3.
2, prefabrication or in-situ precast pillar steel component 3 and go along with sb. to guard him Steel section member 4, waits to have poured bridge pier and pallet top
Circumferential concrete revetment 2 concrete maintenance are to after some strength, and on-the-spot connection by bolt or welding manner goes along with sb. to guard him shaped steel structure
Part 4 and revetment upper pillar stand Steel section member 3.
Content of the present utility model is not limited to cited by embodiment, and those of ordinary skill in the art are new by reading this practicality
Type description and the conversion of any equivalence of taking technical solutions of the utility model, be claim of the present utility model institute
Contain.
Claims (4)
1. one kind high pinner bridge pier hanging basket, it is characterised in that:
Support pinner (1), pallet top circumferential concrete revetment (2), pillar steel component (3) including high and go along with sb. to guard him Steel section member
(4);
The high pinner (1) that supports is arranged at the tray top of bridge pier, and pallet top circumferential concrete revetment (2) is arranged at tray top limit
Edge, pillar steel component (3) is embedded in circumferential concrete revetment (2) top, pallet top in advance, goes along with sb. to guard him Steel section member (4) at pillar steel
Pass with perforation means on component (3) and effectively connect.
One the most according to claim 1 high pinner bridge pier hanging basket, it is characterised in that:
Pillar steel component (3) is all vertically arranged, and goes along with sb. to guard him Steel section member (4) and is formed through horizontal stroke between pillar steel component (3)
To connection.
One the most according to claim 1 high pinner bridge pier hanging basket, it is characterised in that:
Pallet top circumferential concrete revetment (2) and bridge pier are one-piece casting structure, respective steel bar overall binding.
One the most according to claim 1 high pinner bridge pier hanging basket, it is characterised in that:
Outside, pallet top circumferential concrete revetment (2) is concordant with outside pallet top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620767749.3U CN205874982U (en) | 2016-07-21 | 2016-07-21 | High base stone pier hanging flower basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620767749.3U CN205874982U (en) | 2016-07-21 | 2016-07-21 | High base stone pier hanging flower basket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205874982U true CN205874982U (en) | 2017-01-11 |
Family
ID=57696688
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620767749.3U Active CN205874982U (en) | 2016-07-21 | 2016-07-21 | High base stone pier hanging flower basket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205874982U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111827069A (en) * | 2020-07-29 | 2020-10-27 | 中国铁路设计集团有限公司 | High wall protection and high stone pad pier structure |
-
2016
- 2016-07-21 CN CN201620767749.3U patent/CN205874982U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111827069A (en) * | 2020-07-29 | 2020-10-27 | 中国铁路设计集团有限公司 | High wall protection and high stone pad pier structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206289751U (en) | A kind of assembled steel plate concrete combined shear wall and floor support plate connecting node | |
CN208347011U (en) | A kind of assembled shears orthogonal wall profiled sheet perps connection unit | |
CN205575408U (en) | Concrete precast component shedder | |
CN204940915U (en) | Dish button construction safety cat ladder | |
CN109024298A (en) | capping beam construction method | |
CN105201204B (en) | A kind of method and structure of rotten when preventing pouring reinforcement concrete column suspension column | |
CN205874982U (en) | High base stone pier hanging flower basket | |
CN201835440U (en) | Anti-deformation concrete steel pipe column | |
CN204040515U (en) | Cat ladder | |
CN206562765U (en) | For the alter-pouring strips mould plate and ahead of time branch stake tool of dismantling concrete framework template | |
CN205735475U (en) | Web steel bar binding clamping fixture at the bottom of a kind of prefabricated case beam | |
CN204475183U (en) | A kind of hoop platform for bridge pier column construction | |
CN105317146A (en) | Steel structure earthquake-resistant floor for construction and manufacturing method | |
CN204023417U (en) | For building the bearing pin bracket of high pier 0# block concrete | |
CN104141354A (en) | Concrete floor and production process thereof | |
CN205502426U (en) | Wood system railing convenient to installation | |
CN104264668B (en) | Stake mould of X-shaped Model Pile and preparation method thereof | |
CN204531401U (en) | Special template for cone-shaped column cap | |
CN209682557U (en) | A kind of prefabricated cylinder uprightly makes bed die | |
CN209620764U (en) | Assembled moves construction guard fender | |
CN207245155U (en) | A kind of composite shuttering of aluminium frame bamboo slab rubber | |
CN205313978U (en) | Whole ann of bridge cantilever construction tears protector open | |
CN205616260U (en) | Landing stage frame bracket and whole structure of watering of support girder | |
CN203795610U (en) | Steel plate welded type beam-column joint of concrete frame structure | |
CN203821832U (en) | Precast structure horizontal joint grouting steel formwork |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant |