CN205804616U - Embedded part for fixing I-shaped steel in building construction - Google Patents

Embedded part for fixing I-shaped steel in building construction Download PDF

Info

Publication number
CN205804616U
CN205804616U CN201620509530.3U CN201620509530U CN205804616U CN 205804616 U CN205804616 U CN 205804616U CN 201620509530 U CN201620509530 U CN 201620509530U CN 205804616 U CN205804616 U CN 205804616U
Authority
CN
China
Prior art keywords
screw rod
plate
steel
cover plate
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620509530.3U
Other languages
Chinese (zh)
Inventor
冷济洪
翁力军
廖凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201620509530.3U priority Critical patent/CN205804616U/en
Application granted granted Critical
Publication of CN205804616U publication Critical patent/CN205804616U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses an embedded part that is arranged in building construction fixed I-steel, its characterized in that: comprises a dropping plate (1), a screw rod (2) arranged on the dropping plate (1), a cover plate (3) sleeved on the screw rod (2) and a screw cap (5) arranged on the screw rod (2) and positioned above the cover plate (3). The utility model is not only simple in structure, low cost moreover can install at the in-process of building construction, and simple to operate can also demolish after accomplishing the construction, consequently repeatedly usable to can not cause the potential safety hazard, still greatly practice thrift material loss cost simultaneously, consequently be fit for using widely.

Description

A kind of built-in fitting fixing I-steel in construction
Technical field
This utility model relates to a kind of built-in fitting for construction, specifically refers to a kind of fixing in construction The built-in fitting of I-steel.
Background technology
Existing I-steel of encorbelmenting is fixing mostly is tradition " U " type ring with pre-buried ring, this component can only single use, waste Amount is big;And trouble is installed in work progress, easily deviate pre-buried position when casting concrete, it is impossible to ensure construction matter Amount;And the later stage cuts off numerous and diverse, floor easily causes potential safety hazard, strengthens project cost expenditure simultaneously.
Utility model content
The purpose of this utility model be to overcome encorbelment at present the fixing pre-buried ring of I-steel can only single use, waste Amount is big;And be not easy to install, the later stage also needs to cut off, easily causes the defect of potential safety hazard, it is provided that one is not only simple in structure, becomes This is cheap, and easy for installation, moreover it is possible to the reusable built-in fitting fixing I-steel in construction.
This utility model is achieved through the following technical solutions:
A kind of built-in fitting fixing I-steel in construction, including falling plate, the screw rod being arranged on pendant plate, being enclosed within Cover plate on screw rod and be arranged on screw rod and be positioned at the nut above cover plate.
Further, described screw rod is set to two, and pendant plate is fixed on the bottom of screw rod.
Further, described pendant plate is provided with the jack matched with screw rod, and described screw rod is weldingly fixed on pendant plate In jack.
And described pendant plate is set to two, described screw rod connects one to one with pendant plate.
Further, described cover plate is provided with two and screw rod through hole one to one, between described screw rod and through hole For matched in clearance.
In order to this utility model is better achieved, described screw rod is provided with the pad between cover plate and nut.
In order to ensure effect, described screw rod is that top arranges threaded reinforcing bar, and described pendant plate is steel plate.
This utility model compared with prior art, has the following advantages and beneficial effect:
(1) this utility model is not only simple in structure, and with low cost, can install during construction, Easy for installation, moreover it is possible to remove after completing construction, the most reusable, thus do not result in potential safety hazard, also simultaneously Greatly save spillage of material cost.
(2) screw rod of the present utility model is set to two, can facilitate and is fixed on by I-steel between two screw rods, and cover plate is then Cover on I-steel, thus can the left and right of I-steel and above I-steel is carried out spacing, I-steel can be fixed on building On plate.
(3) pendant plate of the present utility model is provided with jack, and convenient by the way of welding, screw rod being fixed on falls inserting of plate Kong Zhong, compares the mode on the upper surface that screw rod is relatively directly fixed on pendant plate, is fixed on by screw rod in the jack of pendant plate and can make That fixes between screw rod and pendant plate is more firm.
(4) pendant plate of the present utility model is set to and screw rod two one to one mutually, can be readily accessible, consequently facilitating repeat Use.
(5) cover plate of the present utility model is provided with two and screw rod through hole one to one, can be led to by two of cover plate Cover plate is connected on two screw rods by hole, compares and uses the mode of two cover plates, uses a cover plate can ensure I-steel The balance of the pressure of upper surface, can make pressure evenly;And between screw rod and through hole, it is matched in clearance, can be easily installed and tear open Unload cover plate.
(6) pad that screw rod of the present utility model is provided with between cover plate and nut, can make nut be locked by cover plate More firm.
(7) screw rod of the present utility model is that top arranges threaded reinforcing bar, and falling plate is steel plate, it is ensured that this practicality is new The intensity of the built-in fitting of type and rigidity.
Accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present utility model.
Fig. 2 is the structural representation of pendant plate of the present utility model.
Fig. 3 is the structural representation of cover plate of the present utility model.
Fig. 4 is structural representation during this utility model construction.
Description of reference numerals: 1 pendant plate, 2 screw rods, 3 cover plates, 4 pads, 5 nuts, 6 jacks, 7 through holes, 8 pvc pipes.
Detailed description of the invention
Below in conjunction with embodiment, this utility model is described in further detail, but embodiment of the present utility model is not It is limited to this.
Embodiment
As shown in figures 1-4, built-in fitting of the present utility model includes two pendant plates 1 and two screw rods 2, and described pendant plate 1 is square Shape steel plate, described screw rod 2 arranges threaded reinforcing bar for top, and described screw rod 2 connects one to one with pendant plate 1.Concrete, institute State pendant plate 1 and be provided with the jack 6 matched with screw rod 2, as in figure 2 it is shown, the bottom of described screw rod 2 is fixed on pendant plate by plug welding In the jack 6 of 1.Described jack 6 is arranged on the center of pendant plate 1, is additionally provided with connecting hole on described pendant plate 1, can during construction Screw is used to be fixed on slab form by pendant plate 1 after connecting hole, in order to dismounting.
Being additionally provided with cover plate 3 on described screw rod 2, described cover plate 3 is enclosed within screw rod 2, as shown in Figure 1.Concrete, described cover plate 3 are provided with two and screw rod 2 through hole 7 one to one, and described through hole 7 is oval, as shown in Figure 3.And described screw rod 2 is with logical It is matched in clearance between hole 7, cover plate 3 can be enclosed within two screw rods 7 the most in use, also can be by when reclaiming after completing construction Cover plate 3 takes from screw rod 7.
Need during use to use cover plate 3 to fix I-steel, for the ease of being fixed on screw rod 7 by cover plate 3, in order to fixing I-steel, is additionally provided with the nut 5 being positioned at above cover plate 3 on described screw rod 2, described each screw rod 2 is provided with two nuts 5, as shown in Figure 1.In order to enable preferably to fasten cover plate 3, described screw rod 2 is additionally provided with the pad between cover plate 3 and nut 5 4。
During enforcement, after slab form has been set up, use screw or iron nail that two pendant plates 1 are fixed on building slab On plate, to prevent built-in fitting in work progress from skew dislocation occurring, then two screw rod 2 correspondences are weldingly fixed on two pendants On plate 1.Then need to overlap pvc pipe 8 on screw rod 2, as shown in Figure 4, screw rod 2 overlaps pvc pipe 8 can prevent concrete with Screw rod 2 contacts after stain screw rod 2, mixed earth can also be prevented simultaneously to be fixed on after condensing and be not easy to disassembly & recycling spiral shell on screw rod 2 Bar 2 and pendant plate 1.During enforcement, on pendant plate 1, two reinforcing bars of placement are as reinforcement, then use iron wire or steel wire by pvc pipe 8 Binding is fixed on reinforcement, and makes the bottom surface of pvc pipe 8 be close to fall on plate 1, with prevent concrete enter pvc pipe and with Screw rod 2 contacts and pollutes screw rod 2, and the top of pvc pipe 8 then uses adhesive tape to block.
Then carry out concreting, form floor after concreting, then I-steel is installed on floor.To be installed Before I-steel, after concrete floor reaches people's execution conditions, the pvc pipe 8 being sleeved on screw rod 2 is cut off along slab surfaces. When I-steel is installed, I-steel is placed on the floor between two screw rods 2, inserts wood a tree, used in making timber for boats in I-steel web both sides, so After a sleeper a tree, used in making timber for boats is set on the upper surface of I-steel.Cover plate 3 is enclosed within two screw rods 2 bonnet on I-steel upper surface On wood a tree, used in making timber for boats, then on screw rod 2, lay pad 4, then use nut 5 to tighten cover plate 3.
It is dismountable built-in fitting after completing construction, before built-in fitting is removed, it is ensured that slab form is complete dismounting.Removing During slab form, the connector being fixed on slab form by pendant plate 1 extracted by use instrument, if using iron nail to use Pliers is pulled out, if using the screw being that screwdriver can be used to screw out, if using other connectors, uses corresponding Connector is extracted by instrument, can be split with pendant plate 1 by slab form, the most dismountable slab form.When I-steel is removed, first First nut 5 is screwed out, then take off pad 4 and cover plate 3, and the wooden a tree, used in making timber for boats on I-steel is taken out, then I-steel is removed.Adopt Tap screw rod 2 the most gently with iron hammer, screw rod 2 drops on lower floor's floor with pendant plate 1.
It is reusable that the built-in fitting more than taken apart includes falling plate 1, screw rod 2, cover plate 3, pad 4 and nut 5, next time During use, directly pendant plate 1 is fixedly mounted on slab form, the step being weldingly fixed on by screw rod 2 on pendant plate 1 can be saved, Remaining uses process identical with the process using built-in fitting for the first time.
As it has been described above, just can preferably realize this utility model.

Claims (7)

1. the built-in fitting fixing I-steel in construction, it is characterised in that: include falling plate (1), being arranged on pendant plate (1) screw rod (2) on, the cover plate (3) being enclosed within screw rod (2) and to be arranged on screw rod (2) upper and be positioned at the spiral shell of cover plate (3) top Cap (5).
A kind of built-in fitting fixing I-steel in construction the most according to claim 1, it is characterised in that: described Screw rod (2) is set to two, and pendant plate (1) is fixed on the bottom of screw rod (2).
A kind of built-in fitting fixing I-steel in construction the most according to claim 2, it is characterised in that: described Pendant plate (1) is provided with the jack (6) matched with screw rod (2), and described screw rod (2) is weldingly fixed on the jack (6) of pendant plate (1) In.
A kind of built-in fitting fixing I-steel in construction the most according to claim 3, it is characterised in that: described Pendant plate (1) is set to two, and described screw rod (2) connects one to one with pendant plate (1).
5. according to a kind of built-in fitting fixing I-steel in construction described in any one of claim 2~4, its feature It is: described cover plate (3) is provided with two and screw rod (2) through hole one to one (7), between described screw rod (2) and through hole (7) For matched in clearance.
6., according to a kind of built-in fitting fixing I-steel in construction described in any one of claim 5, its feature exists In: described screw rod (2) is provided with the pad (4) being positioned between cover plate (3) and nut (5).
7., according to a kind of built-in fitting fixing I-steel in construction described in any one of claim 6, its feature exists In: described screw rod (2) is that top arranges threaded reinforcing bar, and described pendant plate (1) is steel plate.
CN201620509530.3U 2016-05-30 2016-05-30 Embedded part for fixing I-shaped steel in building construction Expired - Fee Related CN205804616U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620509530.3U CN205804616U (en) 2016-05-30 2016-05-30 Embedded part for fixing I-shaped steel in building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620509530.3U CN205804616U (en) 2016-05-30 2016-05-30 Embedded part for fixing I-shaped steel in building construction

Publications (1)

Publication Number Publication Date
CN205804616U true CN205804616U (en) 2016-12-14

Family

ID=57501580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620509530.3U Expired - Fee Related CN205804616U (en) 2016-05-30 2016-05-30 Embedded part for fixing I-shaped steel in building construction

Country Status (1)

Country Link
CN (1) CN205804616U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114164947A (en) * 2021-11-30 2022-03-11 上海森松制药设备工程有限公司 Box column foot connecting structure, box building and assembling method of box building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114164947A (en) * 2021-11-30 2022-03-11 上海森松制药设备工程有限公司 Box column foot connecting structure, box building and assembling method of box building

Similar Documents

Publication Publication Date Title
CN105625621B (en) Waffle beam formwork is fixed and electromechanical pipeline fixes Versatile apparatus and method
CN205875734U (en) Concrete placement splices template
CN204402005U (en) A kind of novel overhanging unloading platform anchor ring
CN202099933U (en) Precast column and lifting appliance thereof
CN205804616U (en) Embedded part for fixing I-shaped steel in building construction
CN207633740U (en) The novel anchor of builder's jack
CN206091265U (en) Detachable anchor ring device
CN203514807U (en) Formwork supporting device
CN208056692U (en) A kind of basement track circulation type bracing members device
CN203445512U (en) cable tunnel ground anchor
CN105926455B (en) A kind of bottom die of box-beam overall pulling down method
CN204475886U (en) A kind of protective cover plate of reserved opening
CN206942120U (en) A kind of pre-embedded device of builder's jack
CN206616842U (en) Recyclable pre-embedded bolt for builder's jack
CN206903186U (en) Adjustable detachable wall-connecting device of scaffold
CN201786013U (en) Reusable anchor member for cantilever scaffold
CN102745608A (en) Fixing structure of wall-attached ear plate of tower crane
CN211923485U (en) Recyclable wall connecting piece
CN206903185U (en) Pre-buried board-like carrier setting bolt structure
CN203361676U (en) Temporary protective guard for building construction
CN202022685U (en) Fixing structure of wall-attached ear plate of tower crane
CN204959986U (en) Detachable earth anchor of I -steel of encorbelmenting
CN206158182U (en) A support system for single -side supporting formwork
CN205530893U (en) Cast -in -place sky is anti come -up ribbon of base plate reinforcing bar for core plate
CN204386166U (en) A kind of cast-in-situ floor reserved holes of pipes sleeve

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161214

Termination date: 20170530