CN205802813U - The double pre-buried joint of a kind of tower crane - Google Patents

The double pre-buried joint of a kind of tower crane Download PDF

Info

Publication number
CN205802813U
CN205802813U CN201620757552.1U CN201620757552U CN205802813U CN 205802813 U CN205802813 U CN 205802813U CN 201620757552 U CN201620757552 U CN 201620757552U CN 205802813 U CN205802813 U CN 205802813U
Authority
CN
China
Prior art keywords
buried joint
joint
tower crane
buried
big
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620757552.1U
Other languages
Chinese (zh)
Inventor
包纯南
窦金胜
陈滨雄
陶日进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN201620757552.1U priority Critical patent/CN205802813U/en
Application granted granted Critical
Publication of CN205802813U publication Critical patent/CN205802813U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

This utility model provides the double pre-buried joint of a kind of tower crane, including big pre-buried joint, little pre-buried joint, connecting rod, bearing diagonal and brace, little pre-buried joint is arranged in big pre-buried joint, and little pre-buried joint is connected by connecting rod with big pre-buried joint, and big pre-buried joint and little pre-buried joint are cast in same concrete foundation cushion cap.The beneficial effects of the utility model are: efficiently solve the technical barrier that big small-sized tower crane is replaced in construction, reduce tower crane operating cost, it is ensured that the job safety of tower crane displacement, reduce difficulty of construction, good integrity, fix simple, easy to operate.

Description

The double pre-buried joint of a kind of tower crane
Technical field
This utility model relates to the construction field of derrick crane, concretely relates to the double pre-buried joint of a kind of tower crane.
Background technology
Along with the increase of construction project scale, the tower crane of conventional model cannot meet construction requirement, the most large-scale public affairs Build in project and multi-storey basement project, often there is local or specific construction part, it is necessary to use the tower crane of larger number to replace The generation tower crane of conventional model is constructed.
Pre-buried joint for be embedded in concrete foundation in advance, the portion being connected with foundation for tower crane joint or the superstructure such as standard knot Point, be typically different the tower crane of model and need to arrange in pairs or groups the pre-buried joint of respective model is installed, the specification of tower crane model the most pre-buried different joint and Form is the most different, and the tower crane of different model cannot use the pre-buried joint of same to construct.
Meanwhile, the size of concrete foundation, arrangement of reinforcement etc. require to carry out respective design, if by difference also according to the model of tower crane The tower crane of model arbitrarily uses the different tower crane that the concrete foundation cushion cap of same model, especially performance parameter differ bigger with, Will result in bigger potential safety hazard, even result in tower crane and the security incident such as topple.
If desired use different model tower crane in the different construction stages, then original concrete foundation cushion cap must be carried out weight New construction, makes the tower crane concrete foundation cushion cap meeting construction requirement.But, construction concrete foundation cushion cap is not only subject to again To the strict restriction of site condition, also it is greatly increased construction cost, affects the normal progress of construction, unfavorable to construction.
Therefore, practice of construction the most just considers large-scale tower crane is installed, and large-scale tower crane lease, use etc. take With costly, roll up the input of construction cost.
Summary of the invention
The deficiency existed for prior art, the purpose of this utility model is to provide a kind of tower crane double pre-buried joint, effectively Solve the technical barrier that big small-sized tower crane is replaced in construction, not only greatly reduce tower crane operating cost, it is ensured that tower crane The job safety of displacement, structural safety is reliable, simple to operation.
For achieving the above object, this utility model provides following technical scheme: the double pre-buried joint of a kind of tower crane, including big pre- Bury joint, little pre-buried joint, connecting rod, bearing diagonal and brace.Wherein, little pre-buried joint is arranged in big pre-buried joint, and little pre-buried joint is pre-with big Bury joint to be connected by connecting rod.
Preferably, in described little pre-buried joint, it is provided with bearing diagonal and brace, in big pre-buried joint, also is provided with brace, increase structure Bonding strength.
Preferably, described connecting rod is arranged on big pre-buried joint diagonal position, is connected with the supporting leg of little pre-buried joint, both can play Interconnection function may also function as skewed horizontal load effect, strengthens structural integrity.
Preferably, described big pre-buried joint is parallel with little pre-buried joint upper surface, it is ensured that the flatness of upper surface.
Preferably, described big pre-buried joint and little pre-buried joint are cast in same concrete foundation cushion cap.
Preferably, the described size of concrete foundation cushion cap, arrangement of reinforcement etc. require to be satisfied by the design requirement of big pre-buried joint.
Preferably, described connecting rod, bearing diagonal and brace are all fixed by welding in structure.
Preferably, described big pre-buried joint and little pre-buried joint are in the double pre-buried joint of same tower crane, by same special manufacturer Family designs and produces.
The beneficial effects of the utility model are: the double pre-buried joint of a kind of tower crane, with the entirety of the embedded little pre-buried joint of big pre-buried joint Form is buried as in tower crane concrete foundation, it is not necessary to the most embedding, not only efficiently solves what big small-sized tower crane was replaced in construction Technical barrier, greatly reduces tower crane operating cost, it is ensured that the job safety of tower crane displacement, double pre-buried joint upper surfaces flat Whole degree is guaranteed the most simultaneously, and only need to pour tower crane concrete foundation once reduces difficulty of construction, has ensured construction speed, This device good integrity, has been effectively ensured double pre-buried joint location, pre-buried accuracy, fixing simple, easy to operate.
Below in conjunction with specification drawings and specific embodiments, the utility model is described in further detail.
Accompanying drawing explanation
Fig. 1 is the structural representation of the double pre-buried joint of a kind of tower crane.
Fig. 2 is the profile of the double pre-buried joint of a kind of tower crane.
In accompanying drawing: 1, big pre-buried joint, 2, little pre-buried joint, 3, connecting rod, 4, bearing diagonal, 5, brace, 6, supporting leg, 7, coagulation soil matrix Plinth cushion cap.
Detailed description of the invention
As shown in Figure 1 and Figure 2, the double pre-buried joint of a kind of tower crane that this utility model provides, including big pre-buried joint 1, little pre-buried joint 2, connecting rod 3, bearing diagonal 4 and brace 5.Wherein, little pre-buried joint 2 is arranged in big pre-buried joint 1, and little pre-buried joint 2 leads to big pre-buried joint 1 Cross connecting rod 3 to connect, in little pre-buried joint 2, be provided with bearing diagonal 4 and brace 5, in big pre-buried joint 1, also be provided with brace 5, increase structure and connect Intensity, connecting rod 3 is arranged on big pre-buried joint 1 diagonal position, is connected with the supporting leg 6 of little pre-buried joint 2, both can play interconnection function and also may be used Playing skewed horizontal load effect, strengthen structural integrity, described big pre-buried joint 1 is parallel with little pre-buried joint 2 upper surface, it is ensured that upper table The flatness in face, big pre-buried joint 1 and little pre-buried joint 2 be cast in same concrete foundation cushion cap 7, concrete foundation cushion cap 7 Size, arrangement of reinforcement etc. require to be satisfied by the design requirement of big pre-buried joint 1, and described connecting rod 3, bearing diagonal 4 and brace 5 is all by welding Fixing structurally, big pre-buried joint 1 and the little pre-buried joint 2 of the double pre-buried joint of same tower crane are designed and produced by same specialized factory.
Above-described embodiment, to specific descriptions of the present utility model, is served only for being further described this utility model, no It is understood that for the restriction to this utility model protection domain, the technician of this area is according to the content pair of above-mentioned utility model This utility model makes some nonessential improvement and within adjustment each falls within protection domain of the present utility model.

Claims (8)

1. the double pre-buried joint of tower crane, it is characterised in that: include big pre-buried joint (1), little pre-buried joint (2), connecting rod (3), bearing diagonal (4) and brace (5), wherein, little pre-buried joint (2) is arranged in big pre-buried joint (1), and little pre-buried joint (2) is passed through with big pre-buried joint (1) Connecting rod (3) connects.
The double pre-buried joint of a kind of tower crane the most according to claim 1, it is characterised in that: it is provided with in described little pre-buried joint (2) Bearing diagonal (4) and brace (5), also be provided with brace (5) in big pre-buried joint (1).
The double pre-buried joint of a kind of tower crane the most according to claim 1, it is characterised in that: described connecting rod (3) is arranged on big pre- Bury joint (1) diagonal position, be connected with the supporting leg (6) of little pre-buried joint (2).
The double pre-buried joint of a kind of tower crane the most according to claim 1, it is characterised in that: described big pre-buried joint (1) and little pre- Bury joint (2) upper surface parallel.
The double pre-buried joint of a kind of tower crane the most according to claim 1, it is characterised in that: described big pre-buried joint (1) and little pre- Bury joint (2) to be cast in same concrete foundation cushion cap (7).
The double pre-buried joint of a kind of tower crane the most according to claim 5, it is characterised in that: described concrete foundation cushion cap (7) Size, the requirement of arrangement of reinforcement be satisfied by big pre-buried joint (1) design requirement.
The double pre-buried joint of a kind of tower crane the most according to claim 1, it is characterised in that: described connecting rod (3), bearing diagonal (4) All it is fixed by welding in structure with brace (5).
The double pre-buried joint of a kind of tower crane the most according to claim 1, it is characterised in that: described big pre-buried joint (1) and little pre- Bury joint (2) in the double pre-buried joint of same tower crane, same specialized factory design and produce.
CN201620757552.1U 2016-07-19 2016-07-19 The double pre-buried joint of a kind of tower crane Expired - Fee Related CN205802813U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620757552.1U CN205802813U (en) 2016-07-19 2016-07-19 The double pre-buried joint of a kind of tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620757552.1U CN205802813U (en) 2016-07-19 2016-07-19 The double pre-buried joint of a kind of tower crane

Publications (1)

Publication Number Publication Date
CN205802813U true CN205802813U (en) 2016-12-14

Family

ID=57508579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620757552.1U Expired - Fee Related CN205802813U (en) 2016-07-19 2016-07-19 The double pre-buried joint of a kind of tower crane

Country Status (1)

Country Link
CN (1) CN205802813U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106315431A (en) * 2016-07-19 2017-01-11 中天建设集团有限公司 Tower crane dual embedded section and construction method thereof
CN107840256A (en) * 2017-11-15 2018-03-27 江苏江都建设集团有限公司 A kind of steel platform of derrick crane

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106315431A (en) * 2016-07-19 2017-01-11 中天建设集团有限公司 Tower crane dual embedded section and construction method thereof
CN107840256A (en) * 2017-11-15 2018-03-27 江苏江都建设集团有限公司 A kind of steel platform of derrick crane

Similar Documents

Publication Publication Date Title
CN106315431A (en) Tower crane dual embedded section and construction method thereof
CN205802813U (en) The double pre-buried joint of a kind of tower crane
CN205531399U (en) Interim support frame is installed in high -order steel truss segmentation
CN102733506A (en) Assembly type seismic insulation house structure
CN102936967B (en) Old house masonry structure transforms safe refuge warehouse
CN102587402A (en) Sparse pile foundation of building composite foundation
CN204370429U (en) A kind of foundation pit earth pressure-controlled structure
CN202954437U (en) Reinforced steel concrete beam column
CN105858501B (en) Itself tower crane of attachment with foundation underpinning device and its construction method
CN105002930A (en) Beam column joint structure constructed through steel annular plate and method of beam column joint structure
CN109019371A (en) A kind of turnable support device and tower crane climbing method
CN204624885U (en) A kind of standard knot support chassis of elevator
CN104328798B (en) Integral type ground beam structure
CN208733814U (en) A kind of exposed shear structure of suspension column having rotating property
CN204491420U (en) A kind of reinforcement structure of bracket
CN209243748U (en) A kind of connecting node of prefabricated panel and prefabricated foundation
CN106638733A (en) Method for reinforcing fan foundation through additionally-arranged horizontal steel bars
CN206220534U (en) The pump line support meanss of concrete pumping equipment
CN204850058U (en) Curtain and steel room lid and lower floor's large -span concrete platform connection structure that encorbelments
CN206220461U (en) A kind of packaged type I-steel hoistway operation platform
CN204023600U (en) Pillar crane composite base structure
CN105672488A (en) Structure for connecting steel frame with steel beams of unit bathroom
CN205421316U (en) Tower jack -up lattice column steel platform welding basis
CN206486988U (en) A kind of temporary steel structural support
CN104762986B (en) Beam foundation structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161214

Termination date: 20190719

CF01 Termination of patent right due to non-payment of annual fee