CN205778988U - A kind of PM2.5 mine dust dedusting and purifying air system - Google Patents
A kind of PM2.5 mine dust dedusting and purifying air system Download PDFInfo
- Publication number
- CN205778988U CN205778988U CN201620533287.9U CN201620533287U CN205778988U CN 205778988 U CN205778988 U CN 205778988U CN 201620533287 U CN201620533287 U CN 201620533287U CN 205778988 U CN205778988 U CN 205778988U
- Authority
- CN
- China
- Prior art keywords
- water
- mine
- water curtain
- dust
- return air
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Special Spraying Apparatus (AREA)
Abstract
本实用新型公开了一种PM2.5矿井粉尘空气除尘净化系统,它包括设在矿井回风口内壁面上的水帷幕装置和矿井回风口之外的供水循环系统;水帷幕装置的构造是在回风口一侧内壁面设有水帷幕雾化器,另一侧内壁面设有集水槽,水帷幕雾化器的喷水可被对面的集水槽接受汇集在一起;供水循环系统是在过滤池中设有高压水泵,高压水泵通过送水管路与水帷幕雾化器连通。本实用新型利用设在回风口的水帷幕雾化降尘系统喷射水雾,还可相互喷射水雾,不仅能够对井下回风巷道含粉尘空气进行净化,而且可以安装在回风井通风机出口处对粉尘进行净化,消除PM2.5矿井粉尘对大气环境的污染,以达到最佳的PM2.5矿井粉尘治理效果。
The utility model discloses a PM2.5 mine dust air dust removal and purification system, which comprises a water curtain device arranged on the inner wall surface of the mine return air outlet and a water supply circulation system outside the mine return air outlet; The inner wall of one side of the tuyere is equipped with a water curtain atomizer, and the inner wall of the other side is equipped with a water collection tank. The water sprayed by the water curtain atomizer can be collected by the opposite water collection tank; A high-pressure water pump is provided, and the high-pressure water pump communicates with the water curtain atomizer through a water delivery pipeline. The utility model uses the water curtain atomization and dust suppression system installed at the air return port to spray water mist, and can also spray water mist to each other. It can not only purify the dust-containing air in the underground return air tunnel, but also can be installed at the outlet of the return air shaft ventilator. Purify the dust and eliminate the pollution of PM2.5 mine dust to the atmospheric environment, so as to achieve the best PM2.5 mine dust control effect.
Description
技术领域technical field
本实用新型涉及矿用除尘设备。The utility model relates to mine dust removal equipment.
背景技术Background technique
目前,在矿井的通风系统中,地面的新鲜空气进入到井下,流经由井下生产工作面、回风巷道再由通风机直接排放到地面大气中。由于矿井巷道空气始终处于流动状态,矿井产尘区域或扬尘点(即生产工作面)产生的PM2.5矿井粉尘一旦处于游离状态,扩散速度较快,常规降尘方法不易处理。PM2.5矿井粉尘属于浮游粉尘(亦称之可呼吸性粉尘),能够长期悬浮于空气中,而不沉降。长期以来回风巷道内的空气中含有的大量浮游粉尘,均通过通风方式直接排放到大气中了。这种PM2.5矿井粉尘的粒径大多在0.1~2.0μm,以0.5μm粒径的粉尘居多。为区别于大气PM2.5,将这类污染大气的矿井粉尘统一称之为PM2.5矿井粉尘。静止状态下的PM2.5矿井粉尘,在受到风流扰动或空气温度变化后,极易做游离运动(受地表温度升高影响后极易作浮升运动),所以矿区上空常常是灰蒙蒙的天气,是造成雾霾的污染源因素之一。目前,虽然井下每个产尘点采用常规的防治措施,如喷头式洒水除尘等手段,但对于PM2.5矿井粉尘极难捕捉,可谓无能为力。At present, in the ventilation system of the mine, the fresh air on the ground enters the underground, flows through the underground production working face, the return air tunnel, and is directly discharged into the ground atmosphere by the ventilator. Since the air in the mine roadway is always in a flowing state, once the PM2.5 mine dust generated in the mine dust producing area or dust raising point (i.e. the production working face) is in a free state, the diffusion speed is fast, and the conventional dust suppression method is not easy to deal with. PM2.5 mine dust belongs to floating dust (also known as respirable dust), which can be suspended in the air for a long time without settling. For a long time, a large amount of floating dust contained in the air in the return air tunnel has been directly discharged into the atmosphere through ventilation. The particle size of this PM2.5 mine dust is mostly in the range of 0.1-2.0 μm, and the dust with a particle size of 0.5 μm is the majority. In order to distinguish it from atmospheric PM2.5, this kind of mine dust that pollutes the atmosphere is collectively referred to as PM2.5 mine dust. The PM2.5 mine dust in the static state is very easy to do free movement after being disturbed by wind flow or air temperature change (it is very easy to do buoyancy movement after being affected by the increase of surface temperature), so the sky above the mining area is often gray. , is one of the pollution source factors that cause smog. At present, although conventional prevention and control measures are adopted for each dust-producing point underground, such as sprinkler-type watering and dust removal, it is extremely difficult to capture PM2.5 mine dust, and it can be said that there is nothing that can be done.
发明内容Contents of the invention
本实用新型的目的是设计一种PM2.5矿井粉尘空气除尘净化系统,解决矿区大气污染问题。The purpose of this utility model is to design a PM2.5 mine dust air dust removal and purification system to solve the problem of air pollution in mining areas.
本实用新型所采用的技术方案是:The technical scheme adopted in the utility model is:
一种PM2.5矿井粉尘空气除尘净化系统,包括设在矿井回风口内壁面上的水帷幕装置和矿井回风口之外的供水循环系统;上述水帷幕装置的构造是,在回风口一侧内壁面设有水帷幕雾化器,另一侧内壁面设有集水槽,水帷幕雾化器的喷水可被对面的集水槽接受汇集在一起;上述供水循环系统设在回风口低于集水槽水平线以下的高度位置;供水循环系统的构造是,在过滤池中设有高压水泵,高压水泵通过送水管路与水帷幕雾化器连通;高压水泵工作时水帷幕雾化器产生覆盖回风口整个断面的水帷幕,水帷幕的水吸收粉尘并被对面的集水槽接受汇集在一起,自然流入过滤池,沉淀过滤成净水,再进入高压水泵,形成水循环系统。A PM2.5 mine dust air dust removal and purification system, including a water curtain device arranged on the inner wall of the mine return air outlet and a water supply circulation system outside the mine return air outlet; There is a water curtain atomizer on the wall, and a water collection tank on the inner wall on the other side. The water sprayed by the water curtain atomizer can be collected by the water collection tank on the opposite side; The height position below the horizontal line; the structure of the water supply circulation system is that a high-pressure water pump is installed in the filter tank, and the high-pressure water pump communicates with the water curtain atomizer through the water supply pipeline; The water curtain of the section, the water of the water curtain absorbs dust and is collected by the opposite sump, flows naturally into the filter pool, precipitates and filters into clean water, and then enters the high-pressure water pump to form a water circulation system.
上述的水帷幕装置设有一套或两套,设有两套时水帷幕装置对称布置。当设有两套时水帷幕装置时,上述的供水循环系统可设两套,两套供水循环系统对称布置,各自为距离它最近的水帷幕雾化器供水并与它距离最近的集水槽连通。The above-mentioned water curtain device is provided with one or two sets, and when two sets are provided, the water curtain device is arranged symmetrically. When there are two sets of water curtain devices, the above-mentioned water supply circulation system can be provided with two sets, and the two sets of water supply circulation systems are arranged symmetrically, each supplying water to the nearest water curtain atomizer and communicating with its nearest water collection tank .
上述的过滤池可设三级过滤池,集水槽与一级过滤池连通,一级过滤池依次与二级过滤池和三级过滤池连通,高压水泵设在三级过滤池中。The above-mentioned filter pool can be provided with a three-stage filter pool, the sump is connected with the first-stage filter pool, the first-stage filter pool is connected with the second-stage filter pool and the three-stage filter pool in turn, and the high-pressure water pump is arranged in the three-stage filter pool.
上述的矿井回风口可以是井下回风巷道,也可以是回风井地面回风口。The above-mentioned mine return air outlet can be an underground air return roadway, and can also be a return air return shaft ground return air outlet.
进一步,为了保证循环水的水质和水位,在过滤池中设有水质监控器和水位监控器。当设有三级过滤池时,水质监控器和水位监控器设在第三级过滤池中。Further, in order to ensure the water quality and water level of the circulating water, a water quality monitor and a water level monitor are installed in the filter tank. When a three-stage filter pool is provided, the water quality monitor and the water level monitor are arranged in the third-stage filter pool.
上述的水帷幕雾化器的构造是,包括平行排列的2-4根管子,管子长度满足回风口的断面边长,所有管子一端用连通器连接在一起,另一端用封堵板连接在一起,连通器上设有与送水管路连接的管接头,所有管子上均设有轴向的狭缝,供水时可形成覆盖回风口整个断面的2-4层水帷幕。The structure of the above-mentioned water curtain atomizer is to include 2-4 pipes arranged in parallel, the length of the pipes meets the side length of the cross-section of the air return port, and all the pipes are connected together with a connector at one end and connected with a blocking plate at the other end. At the same time, the connector is provided with a pipe joint connected to the water supply pipeline, and all the pipes are provided with axial slits, which can form a 2-4 layer water curtain covering the entire section of the return air outlet when water is supplied.
上述的管子可为PVC管或注塑管。The above-mentioned pipes can be PVC pipes or injection molded pipes.
与现有技术相比,本实用新型具有以下优点:Compared with the prior art, the utility model has the following advantages:
本实用新型的PM2.5矿井粉尘空气除尘净化系统,利用设在回风口的水帷幕雾化降尘系统喷射水雾,还可相互喷射水雾,不仅能够对井下回风巷道含粉尘空气进行净化,而且可以安装在回风井通风机出口处对粉尘进行净化,消除PM2.5矿井粉尘对大气环境的污染,以达到最佳的PM2.5矿井粉尘治理效果。利用供水循环系统可节约水资源。The PM2.5 mine dust air dedusting and purification system of the utility model uses the water curtain atomization and dust suppression system installed at the air return port to spray water mist, and can also spray water mist to each other, which can not only purify the dust-containing air in the underground return air tunnel, Moreover, it can be installed at the outlet of the ventilator in the return air shaft to purify the dust and eliminate the pollution of PM2.5 mine dust to the atmospheric environment, so as to achieve the best PM2.5 mine dust control effect. Utilizing the water supply circulation system can save water resources.
附图说明Description of drawings
图1是本实用新型实施例一的结构示意图;Fig. 1 is the structural representation of the utility model embodiment one;
图2是本实用新型实施例二的结构示意图;Fig. 2 is the structural representation of the second embodiment of the utility model;
图3是本实用新型实施例三的结构示意图;Fig. 3 is the structural representation of the utility model embodiment three;
图4是本实用新型实施例四的结构示意图;Fig. 4 is a schematic structural view of Embodiment 4 of the present utility model;
图5是本实用新型的水帷幕雾化器结构示意图。Fig. 5 is a schematic structural view of the water curtain atomizer of the present invention.
图中:1-回风口,2-水帷幕雾化器,3-集水槽,4-送水管路,5-高压水泵,6-水质监控器和水位监控器,7-过滤池,8-第二级过滤池,9-第三级过滤池,10-封堵板,11-管接头,12-连通器,13-管子,14-狭缝。In the figure: 1-air return port, 2-water curtain atomizer, 3-water collection tank, 4-water delivery pipeline, 5-high pressure water pump, 6-water quality monitor and water level monitor, 7-filter pool, 8-the first Secondary filter tank, 9-third-stage filter tank, 10-blocking plate, 11-pipe joint, 12-communicator, 13-pipe, 14-slit.
具体实施方式detailed description
下面结合附图和实施例对本实用新型作进一步的详细说明。Below in conjunction with accompanying drawing and embodiment the utility model is described in further detail.
实施例1:Example 1:
如图1所示,一种PM2.5矿井粉尘空气除尘净化系统,包括设在矿井回风口1内壁面上的水帷幕装置和矿井回风口之外的供水循环系统;上述水帷幕装置的构造是,在回风口1一侧内壁面设有水帷幕雾化器2,另一侧内壁面设有集水槽3,水帷幕雾化器2的喷水可被对面的集水槽3接受汇集在一起;上述供水循环系统设在回风口1低于集水槽3水平线以下的高度位置;供水循环系统的构造是,在过滤池7中设有高压水泵5,高压水泵5通过送水管路4与水帷幕雾化器2连通;高压水泵5工作时水帷幕雾化器2产生覆盖回风口1整个断面的水帷幕,水帷幕的水吸收粉尘并被对面的集水槽3接受汇集在一起,自然流入过滤池7,沉淀过滤成净水,再进入高压水泵5,形成水循环系统。As shown in Figure 1, a kind of PM2.5 mine dust air dedusting purification system comprises the water curtain device that is located on the mine return air outlet 1 inner wall surface and the water supply circulation system outside the mine return air outlet; the structure of above-mentioned water curtain device is A water curtain atomizer 2 is provided on one side of the return air outlet 1, and a water collection tank 3 is provided on the other side of the inner wall. The water sprayed by the water curtain atomizer 2 can be received and collected by the opposite water collection tank 3; The above-mentioned water supply circulation system is set at the height position below the return air outlet 1 below the horizontal line of the sump 3; The atomizer 2 is connected; when the high-pressure water pump 5 is working, the water curtain atomizer 2 produces a water curtain covering the entire section of the return air outlet 1, and the water in the water curtain absorbs dust and is collected by the opposite water collection tank 3, and flows naturally into the filter pool 7 , precipitate and filter into clean water, and then enter the high-pressure water pump 5 to form a water circulation system.
进一步,为了保证循环水的水质和水位,在过滤池7中设有水质监控器和水位监控器6。Further, in order to ensure the water quality and water level of the circulating water, a water quality monitor and a water level monitor 6 are provided in the filter tank 7 .
上述的水帷幕雾化器的构造见图5,包括平行排列的2-4根管子13,管子13长度满足回风口1的断面边长,所有管子13一端用连通器12连接在一起,另一端用封堵板10连接在一起,连通器12上设有与送水管路4连接的管接头11,所有管子13上均设有轴向的狭缝14,供水时可形成覆盖回风口1整个断面的2-4层水帷幕。The structure of the above-mentioned water curtain atomizer is shown in Figure 5, including 2-4 pipes 13 arranged in parallel, the length of the pipes 13 meets the side length of the section of the air return port 1, and one end of all the pipes 13 is connected together by a connector 12, and the other One end is connected together with a blocking plate 10, the connector 12 is provided with a pipe joint 11 connected with the water supply pipeline 4, and all the pipes 13 are provided with axial slits 14, which can form a cover covering the entire return air outlet 1 during water supply. Sectional 2-4 layer water curtain.
上述的管子13可为PVC管或注塑管。The above-mentioned pipe 13 can be a PVC pipe or an injection molding pipe.
上述的矿井回风口1可以是井下回风巷道,也可以是回风井地面回风口。The above-mentioned mine return air outlet 1 may be an underground return air tunnel, or a return air return shaft ground return air outlet.
实施例2:Example 2:
从如图2看出,实施例2的构造与实施例1基本相同,相同部分不再重复。其区别是,供水循环系统中的过滤池设有三级过滤池,包括过滤池7、第二级过滤池8和第三级过滤池9,过滤池7作为第一级过滤池,集水槽3与过滤池7连通,过滤池7依次与第二级过滤池8和第三级过滤池9连通,高压水泵5设在第三级过滤池9中。As can be seen from Figure 2, the structure of Embodiment 2 is basically the same as that of Embodiment 1, and the same parts will not be repeated. The difference is that the filter pool in the water supply circulation system is provided with a three-stage filter pool, including a filter pool 7, a second-stage filter pool 8 and a third-stage filter pool 9, the filter pool 7 is used as the first-stage filter pool, and the sump 3 It communicates with the filter pool 7, and the filter pool 7 communicates with the second-stage filter pool 8 and the third-stage filter pool 9 in turn, and the high-pressure water pump 5 is arranged in the third-stage filter pool 9.
实施例3:Example 3:
从如图3看出,实施例3的构造与实施例2基本相同,相同部分不再重复。其区别是,水帷幕装置1设有两套,两套水帷幕装置对称布置。As can be seen from Figure 3, the structure of Embodiment 3 is basically the same as that of Embodiment 2, and the same parts will not be repeated. Its difference is that the water curtain device 1 is provided with two sets, and two sets of water curtain devices are arranged symmetrically.
实施例4:Example 4:
从如图4看出,实施例4的构造与实施例3基本相同,相同部分不再重复。其区别是供水循环系统设有两套,两套供水循环系统对称布置,各自为距离它最近的水帷幕雾化器2供水并与它距离最近的集水槽3连通;图4中还看出,供水循环系统中的过滤池为三级过滤池。As can be seen from Figure 4, the structure of Embodiment 4 is basically the same as that of Embodiment 3, and the same parts will not be repeated. The difference is that there are two sets of water supply circulation systems, and the two sets of water supply circulation systems are arranged symmetrically, each supplying water to the water curtain atomizer 2 closest to it and communicating with the water collection tank 3 closest to it; it can also be seen from Figure 4 that The filter pool in the water supply circulation system is a three-stage filter pool.
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620533287.9U CN205778988U (en) | 2016-06-02 | 2016-06-02 | A kind of PM2.5 mine dust dedusting and purifying air system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620533287.9U CN205778988U (en) | 2016-06-02 | 2016-06-02 | A kind of PM2.5 mine dust dedusting and purifying air system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205778988U true CN205778988U (en) | 2016-12-07 |
Family
ID=58136332
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620533287.9U Expired - Fee Related CN205778988U (en) | 2016-06-02 | 2016-06-02 | A kind of PM2.5 mine dust dedusting and purifying air system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205778988U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106837405A (en) * | 2017-03-13 | 2017-06-13 | 中钢集团马鞍山矿山研究院有限公司 | A kind of underground mine returnairshaft dirt wind demisting dust falling system |
CN109184777A (en) * | 2018-10-08 | 2019-01-11 | 平顶山市安泰华矿用安全设备制造有限公司 | A kind of water curtain dust fall device of mine pneumatic underworkings |
-
2016
- 2016-06-02 CN CN201620533287.9U patent/CN205778988U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106837405A (en) * | 2017-03-13 | 2017-06-13 | 中钢集团马鞍山矿山研究院有限公司 | A kind of underground mine returnairshaft dirt wind demisting dust falling system |
CN109184777A (en) * | 2018-10-08 | 2019-01-11 | 平顶山市安泰华矿用安全设备制造有限公司 | A kind of water curtain dust fall device of mine pneumatic underworkings |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205778988U (en) | A kind of PM2.5 mine dust dedusting and purifying air system | |
CN104415628A (en) | Wet efficient dehumidification dedusting apparatus for dust-containing steam flow flue gas | |
CN206237976U (en) | A kind of planting fruit trees spray irrigation system | |
CN208347819U (en) | A kind of three-level dust removal system based on PLC control | |
CN206233926U (en) | Coal machine sprayer unit | |
CN204060768U (en) | A kind of underground chamber control of dust foam dust-removing device and dust pelletizing system | |
CN204659735U (en) | The new wind sand protecting and dust removing device of rail vehicle air conditioner group | |
CN204299608U (en) | A kind of air water two-phase flow device for reducing dust | |
CN106422609A (en) | Full-automatic multi-purpose energy-saving and environment-friendly equipment with self-cleaning function | |
CN203971677U (en) | Air cleaning system for engineering shop | |
CN207131436U (en) | A kind of mining reducing dust lowering car | |
CN204457841U (en) | A kind of mining wet precipitator | |
CN203285477U (en) | Combined underground coal mine dust falling device | |
CN203347830U (en) | Roadway water film dust removing device | |
CN204238972U (en) | The two air-drafting and dust-removing device of mine whitewashing | |
CN203750757U (en) | Paint mist treatment system | |
CN204983297U (en) | Built -in decoration curtain that has rivers passageway | |
CN205832849U (en) | Down-hole kaolin suspension Wind Volume atomization Wen's cleaner | |
CN202122893U (en) | Oil smoke-removing and dust-removing dual-purpose machine | |
CN103239964B (en) | Dust arrester | |
CN207137682U (en) | Recirculating fluidized bed desulphurization system | |
CN106761880B (en) | A tunnel ventilation filter system | |
CN207178004U (en) | Vehicle Exhaust Particulate filter | |
CN206397540U (en) | A kind of underground coal mine air cleaning unit | |
CN204745963U (en) | Novel antifog haze power generation system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161207 Termination date: 20170602 |