CN205764557U - A kind of weld jig combines robot automatic welding production line - Google Patents

A kind of weld jig combines robot automatic welding production line Download PDF

Info

Publication number
CN205764557U
CN205764557U CN201620749715.1U CN201620749715U CN205764557U CN 205764557 U CN205764557 U CN 205764557U CN 201620749715 U CN201620749715 U CN 201620749715U CN 205764557 U CN205764557 U CN 205764557U
Authority
CN
China
Prior art keywords
station
workpiece
welding
production line
cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620749715.1U
Other languages
Chinese (zh)
Inventor
蔡勇
蔡瑞红
林铭立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU GUANGRI LOGISTICS CO Ltd
Original Assignee
GUANGZHOU GUANGRI LOGISTICS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU GUANGRI LOGISTICS CO Ltd filed Critical GUANGZHOU GUANGRI LOGISTICS CO Ltd
Priority to CN201620749715.1U priority Critical patent/CN205764557U/en
Application granted granted Critical
Publication of CN205764557U publication Critical patent/CN205764557U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Automatic Assembly (AREA)

Abstract

本实用新型提供的一种焊接夹具结合机器人自动焊接生产线,包括第一工位、第二工位、第三工位、用于焊接的六轴机器人和控制所述六轴机器人在第一工位、第二工位和第三工位之间进行循环焊接的控制器,所述第一工位、第二工位和第三工位呈等腰三角形分布,所述第一工位位于所述等腰三角形的顶点位置,所述六轴机器人位于所述等腰三角形的中心位置,所述第一工位设置有将工件进行固定的第一夹紧机构和将工件顶出的第一顶出机构,所述第二工位设置有将工件进行固定的第二夹紧机构和将工件顶出的第二顶出机构,所述第三工位设置有将工件进行固定的第三夹紧机构和将工件顶出的第三顶出机构。焊接夹具结合机器人自动焊接生产线,其焊接工装利用率高,焊接效率高。

The utility model provides a welding fixture combined with a robot automatic welding production line, including a first station, a second station, a third station, a six-axis robot used for welding and controlling the six-axis robot at the first station , a controller for cyclic welding between the second station and the third station, the first station, the second station and the third station are distributed in an isosceles triangle, and the first station is located at the The apex position of the isosceles triangle, the six-axis robot is located at the center of the isosceles triangle, and the first station is provided with a first clamping mechanism for fixing the workpiece and a first ejector for ejecting the workpiece mechanism, the second station is provided with a second clamping mechanism for fixing the workpiece and a second ejection mechanism for pushing the workpiece out, and the third station is provided with a third clamping mechanism for fixing the workpiece And the third ejection mechanism that ejects the workpiece. The welding fixture is combined with the robot automatic welding production line, the utilization rate of the welding fixture is high, and the welding efficiency is high.

Description

一种焊接夹具结合机器人自动焊接生产线A welding fixture combined with a robot automatic welding production line

技术领域technical field

本实用新型涉及一种焊接夹具结合机器人自动焊接生产线。The utility model relates to a welding fixture combined with a robot automatic welding production line.

背景技术Background technique

现有的焊接夹具比较单一,工件不能在一个夹具上通用,更换工件时要重新定位更改夹具,对重架和导轨撑架夹具不是一个整体,要多人来操作。此种生产方式效率低下,需要生产员工注意力高度集中,操作危险,焊接时的辐射对员工的健康伤害很大,生产员工的劳动强度大,人力成本较高,存在的原因是由于普通焊接夹具不能自动化操作,每一个对重架夹具至少需要两位生产员工全程操作,给生产带来很大不便。并且,现有的焊接工装利用率低,焊接效率低下。Existing welding fixtures are relatively simple, and the workpiece cannot be used in common on one fixture. When changing the workpiece, the fixture needs to be repositioned and changed. This kind of production method is inefficient, requires the production staff to be highly concentrated, the operation is dangerous, the radiation during welding is very harmful to the health of the staff, the labor intensity of the production staff is high, and the labor cost is high. The reason for the existence is that ordinary welding fixtures It cannot be operated automatically, and each counterweight frame fixture requires at least two production employees to operate the whole process, which brings great inconvenience to production. Moreover, the utilization rate of the existing welding tool is low, and the welding efficiency is low.

实用新型内容Utility model content

基于以上不足,本实用新型要解决的技术问题是提供一种焊接夹具结合机器人自动焊接生产线,其焊接工装利用率高,焊接效率高。Based on the above deficiencies, the technical problem to be solved by the utility model is to provide a welding fixture combined with a robot automatic welding production line, which has high utilization rate of welding fixtures and high welding efficiency.

为了解决以上技术问题,本实用新型采用了以下技术方案:In order to solve the above technical problems, the utility model adopts the following technical solutions:

一种焊接夹具结合机器人自动焊接生产线,包括第一工位、第二工位、第三工位、用于焊接的六轴机器人和控制所述六轴机器人在第一工位、第二工位和第三工位之间进行循环焊接的控制器,所述第一工位、第二工位和第三工位呈等腰三角形分布,所述第一工位位于所述等腰三角形的顶点位置,所述六轴机器人位于所述等腰三角形的中心位置,所述第一工位设置有将工件进行固定的第一夹紧机构和将工件顶出的第一顶出机构,所述第二工位设置有将工件进行固定的第二夹紧机构和将工件顶出的第二顶出机构,所述第三工位设置有将工件进行固定的第三夹紧机构和将工件顶出的第三顶出机构。A welding fixture combined with a robot automatic welding production line, including a first station, a second station, a third station, a six-axis robot for welding and controlling the six-axis robot at the first station and the second station and a controller for circular welding between the third station, the first station, the second station and the third station are distributed in an isosceles triangle, and the first station is located at the apex of the isosceles triangle position, the six-axis robot is located at the center of the isosceles triangle, the first station is provided with a first clamping mechanism for fixing the workpiece and a first ejection mechanism for ejecting the workpiece, the first The second station is provided with a second clamping mechanism for fixing the workpiece and a second ejection mechanism for ejecting the workpiece. The third station is provided with a third clamping mechanism for fixing the workpiece and a second ejection mechanism for ejecting the workpiece. The third ejection mechanism.

所述第一夹紧机构包括成对设置的将工件沿长度方向夹紧的第一气缸、成对设置的将工件沿宽度方向夹紧的第二气缸以及将工件压紧固定的第三气缸。The first clamping mechanism includes a pair of first air cylinders for clamping the workpiece along the length direction, a pair of second air cylinders for clamping the workpiece along the width direction, and a third air cylinder for pressing and fixing the workpiece.

所述第一顶出机构包括基座、安装在基座上的至少一个顶出气缸、与所述顶出气缸的活塞杆连接的用于放置工件的顶出板。The first ejection mechanism includes a base, at least one ejection cylinder installed on the base, and an ejection plate connected with the piston rod of the ejection cylinder for placing workpieces.

在所述第一工位还设置有将工件翻转的翻转机构,所述翻转机构为焊接变位机,所述焊接变位机包括底座、设置在底座上的动力头与从动头,所述动力头包括首座、设置在所述首座上的电机以及与所述电机的输出端连接的第一工件安装座,所述从动头包括安装在底座上的尾座以及安装在所述尾座上的第二工件安装座,所述尾座与所述第二工件安装座通过轴承连接,所述第一工件安装座与所述第二工件安装座相对设置。The first station is also provided with an overturning mechanism for overturning the workpiece. The overturning mechanism is a welding positioner, and the welding positioner includes a base, a power head and a driven head arranged on the base. The power head includes a first seat, a motor arranged on the first seat, and a first workpiece mounting seat connected to the output end of the motor, and the driven head includes a tailstock installed on the base and a tailstock installed on the tailstock. The second workpiece mounting seat, the tailstock is connected to the second workpiece mounting seat through a bearing, and the first workpiece mounting seat is opposite to the second workpiece mounting seat.

所述第二夹紧机构和第三夹紧机构均包括机架,所述机架上设置有工作台,所述工作台上设置有气缸支架,所述气缸支架上设置有夹具调节板和旋压气缸,所述旋压气缸的输出端设置有旋转压块,所述夹具调节板上设置有将工件定位的第一定位块和第二定位块,所述第一定位块和所述第二定位块与所述旋转压块相对设置。Both the second clamping mechanism and the third clamping mechanism include a frame, the frame is provided with a workbench, the workbench is provided with a cylinder support, and the cylinder support is provided with a clamp adjustment plate and a rotary Press the air cylinder, the output end of the spinning cylinder is provided with a rotary pressing block, and the fixture adjustment plate is provided with a first positioning block and a second positioning block for positioning the workpiece, and the first positioning block and the second positioning block The positioning block is set opposite to the rotary pressing block.

所述第二夹紧机构为多个,并且排列设置;所述第三夹紧机构均设置为多个,并且排列设置。There are multiple second clamping mechanisms arranged in rows; the third clamping mechanisms are arranged in plurality and arranged in rows.

采用以上技术方案,本实用新型取得了以下技术效果:By adopting the above technical scheme, the utility model has achieved the following technical effects:

本实用新型的生产线适用于对重架和导轨撑架的生产,生产原材料为槽钢型材和板料,槽钢和板料放入第一工位组装自动夹紧,机器人对多个面进行自动焊接,焊接完之后第一顶出机构自动将料顶出,吊车将料吊走,人工即时进行下一次上料,第一工位上料的时间范围内,机器人会到第二工位进行焊接,第二工位完成焊接后,将料取走即时进行下次上料,上料的时间范围内,机器人再到第三工位作业,焊接完成,待再次上料时,机器人再次回到第一工位焊接,如此循环作业,可以提高生产效率,并且消除了人工加工的危险性,降低了生产成本。The production line of the utility model is suitable for the production of counterweight frames and guide rail brackets. The raw materials for production are channel steel profiles and sheet materials. The channel steel and sheet materials are put into the first station for assembly and automatic clamping. Welding, after welding, the first ejector mechanism automatically ejects the material, the crane lifts the material away, and the next material is loaded manually, and the robot will go to the second station for welding within the time limit for loading the first station , after the second station completes the welding, the material is taken away and the next loading is carried out immediately. Within the time limit of loading, the robot will go to the third station to work, and the welding is completed. When the material is loaded again, the robot will return to the first One-station welding, such a cycle operation, can improve production efficiency, eliminate the danger of manual processing, and reduce production costs.

附图说明Description of drawings

图1为本实用新型焊接夹具结合机器人自动焊接生产线的结构图;Fig. 1 is the structural diagram of the utility model welding fixture combined with the robot automatic welding production line;

图2为本实用新型焊接夹具结合机器人自动焊接生产线的第一夹紧机构的结构图;Fig. 2 is a structural diagram of the first clamping mechanism of the welding fixture combined with the robot automatic welding production line of the present invention;

图3为本实用新型焊接夹具结合机器人自动焊接生产线的第一顶出机构的结构图;Fig. 3 is a structural diagram of the first ejection mechanism of the welding fixture combined with the robot automatic welding production line of the present invention;

图4为本实用新型焊接夹具结合机器人自动焊接生产线的翻转机构的结构图;Fig. 4 is the structural diagram of the turning mechanism of the welding fixture combined with the robot automatic welding production line of the present invention;

图5为本实用新型焊接夹具结合机器人自动焊接生产线的第二夹紧机构的结构图。Fig. 5 is a structural diagram of the second clamping mechanism of the welding fixture combined with the robot automatic welding production line of the present invention.

具体实施方式detailed description

如图1-图5所示,本实用新型提供了一种焊接夹具结合机器人自动焊接生产线,包括第一工位1、第一工位2、第三工位3、用于焊接的六轴机器人4和控制所述六轴机器人4在第一工位1、第一工位2和第三工位3之间进行循环焊接的控制器,所述第一工位1、第一工位2和第三工位3呈等腰三角形分布,所述第一工位1位于所述等腰三角形的顶点位置,所述六轴机器人位于所述等腰三角形的中心位置,所述第一工位1设置有将工件进行固定的第一夹紧机构5和将工件顶出的第一顶出机构6,所述第一工位2设置有将工件进行固定的第二夹紧机构7和将工件顶出的第二顶出机构8,所述第三工位3设置有将工件进行固定的第三夹紧机构和将工件顶出的第三顶出机构。机器人采用ABB机器人,型号为IRB1600-10。本实用新型的生产线适用于对重架和导轨撑架的生产,分为第一工位、第二工位和第三工位的工序,生产原材料为槽钢型材和板料,槽钢和板料放入第一工位组装自动夹紧,机器人对多个面进行自动焊接,焊接完之后第一顶出机构自动将料顶出,吊车将料吊走,人工即时进行下一次上料,第一工位上料的时间范围内,机器人会到第二工位进行焊接,第二工位完成焊接后,将料取走即时进行下次上料,上料的时间范围内,机器人再到第三工位作业,焊接完成,待再次上料时,机器人再次回到第一工位焊接,如此循环作业,可以提高生产效率,并且消除了人工加工的危险性,降低了生产成本。As shown in Figures 1-5, the utility model provides a welding fixture combined with a robot automatic welding production line, including the first station 1, the first station 2, the third station 3, and a six-axis robot for welding 4 and a controller for controlling the six-axis robot 4 to perform circular welding between the first station 1, the first station 2 and the third station 3, the first station 1, the first station 2 and the third station 3 The third station 3 is distributed in an isosceles triangle, the first station 1 is located at the apex of the isosceles triangle, the six-axis robot is located at the center of the isosceles triangle, and the first station 1 A first clamping mechanism 5 for fixing the workpiece and a first ejection mechanism 6 for ejecting the workpiece are provided, and the first station 2 is provided with a second clamping mechanism 7 for fixing the workpiece and a second ejection mechanism for ejecting the workpiece. The third station 3 is provided with a third clamping mechanism for fixing the workpiece and a third ejection mechanism for ejecting the workpiece. The robot adopts ABB robot, the model is IRB1600-10. The production line of the utility model is suitable for the production of the counterweight frame and the guide rail bracket, and is divided into the first station, the second station and the third station. The production raw materials are channel steel profiles and plates, channel steel and plates The material is put into the first station, assembled and automatically clamped, and the robot performs automatic welding on multiple surfaces. After welding, the first ejector mechanism automatically ejects the material, and the crane lifts the material away. The next material is loaded manually in real time. Within the time limit for loading materials at one station, the robot will go to the second station for welding. After the welding is completed at the second station, the material will be taken away immediately for the next loading. Within the time limit for loading materials, the robot will go to the second station Three-station operation, after welding is completed, when the material is loaded again, the robot returns to the first station to weld again. This cycle of operation can improve production efficiency, eliminate the danger of manual processing, and reduce production costs.

第一工位1上设置有将工件固定的第一夹紧机构5,如图2所示,所述第一夹紧机构5包括成对设置的将工件沿长度方向夹紧的第一气缸51、将成对设置的工件沿宽度方向夹紧的第二气缸52以及将工件压紧固定的第三气缸53。安装时,将工件沿其长度方向的两端通过第一气缸51夹紧,将工件沿其宽度方向的两端通过第二气缸52夹紧,然后再通过第三气缸53将工件压紧固定。其中,第一气缸51为转角气缸,第二气缸52为双杆气缸。The first station 1 is provided with a first clamping mechanism 5 that fixes the workpiece. As shown in FIG. , the second air cylinder 52 for clamping the paired workpieces along the width direction, and the third air cylinder 53 for pressing and fixing the workpieces. During installation, the two ends of the workpiece along its length direction are clamped by the first cylinder 51, the two ends of the workpiece along its width direction are clamped by the second cylinder 52, and then the workpiece is pressed and fixed by the third cylinder 53. Wherein, the first cylinder 51 is a corner cylinder, and the second cylinder 52 is a double-rod cylinder.

如图3所示,所述第一顶出机构6包括基座61、安装在基座61上的至少一个顶出气缸62、与所述顶出气缸62的活塞杆连接的用于放置工件的顶出板63。具体地,本实施例中,顶出气缸62设置为两个,顶出气缸62并列设置在基座61上,顶出气缸62的活塞杆均与顶出板63连接,顶出板63上放置待焊接工件。As shown in FIG. 3 , the first ejection mechanism 6 includes a base 61, at least one ejection cylinder 62 installed on the base 61, and a cylinder connected to the piston rod of the ejection cylinder 62 for placing workpieces. Ejector plate 63 . Specifically, in this embodiment, there are two ejection cylinders 62, and the ejection cylinders 62 are arranged side by side on the base 61. The piston rods of the ejection cylinders 62 are all connected to the ejection plate 63, and placed on the ejection plate The workpiece to be welded.

如图4所示,在所述第一工位1还设置有将工件翻转的翻转机构9,所述翻转机构9为焊接变位机,所述焊接变位机包括底座91、设置在底座91上的动力头92与从动头93,所述动力头92包括首座921、安装在首座921里的电机以及与所述电机的输出端连接的第一工件安装座922,所述从动头93包括安装在底座91上的尾座931以及安装在所述尾座931上的第二工件安装座932,所述尾座931与所述第二工件安装座932通过轴承连接,所述第一工件安装座922与所述第二工件安装座932相对设置。第一工件安装座922和第二工件安装座932均为L形板。使用时,将工件安装在第一工件安装座922和第二工件安装座932上,电机转动带动第一工件安装座转动从而带动安装在第一工件安装座和第二工件安装座上的工件转动。As shown in FIG. 4 , the first station 1 is also provided with an overturning mechanism 9 for turning over the workpiece. The overturning mechanism 9 is a welding positioner. The power head 92 and the driven head 93 on the top, the power head 92 includes a first seat 921, a motor installed in the first seat 921 and a first workpiece mounting seat 922 connected to the output end of the motor, the driven head 93 It includes a tailstock 931 installed on the base 91 and a second workpiece mounting seat 932 installed on the tailstock 931, the tailstock 931 is connected with the second workpiece mounting seat 932 through a bearing, and the first workpiece The mounting seat 922 is opposite to the second workpiece mounting seat 932 . Both the first workpiece mounting base 922 and the second workpiece mounting base 932 are L-shaped plates. During use, the workpiece is installed on the first workpiece mounting seat 922 and the second workpiece mounting seat 932, and the rotation of the motor drives the first workpiece mounting seat to rotate, thereby driving the workpieces installed on the first workpiece mounting seat and the second workpiece mounting seat to rotate .

如图5所示,所述第二夹紧机构7和第三夹紧机构均包括机架71,所述机架71上设置有工作台72,所述工作台72上设置有气缸支架73,所述气缸支架73上设置有夹具调节板731和旋压气缸732,所述旋压气缸732的输出端设置有旋转压块733,所述夹具调节板731上设置有将工件定位的第一定位块734和第二定位块735,所述第一定位块734和所述第二定位块735与所述旋转压块732相对设置。安装时,将工件定位在第一定位块734和第二定位块上735,并通过旋压气缸732的动力将工件压紧固定。所述第二夹紧机构7为多个,并且排列设置;所述第三夹紧机构设置为多个,并且排列设置。可以固定多个工件进行焊接加工。As shown in Figure 5, the second clamping mechanism 7 and the third clamping mechanism both include a frame 71, a workbench 72 is arranged on the frame 71, and a cylinder support 73 is arranged on the workbench 72, The cylinder bracket 73 is provided with a jig adjusting plate 731 and a spinning cylinder 732, the output end of the spinning cylinder 732 is provided with a rotary pressing block 733, and the jig adjusting plate 731 is provided with a first positioning position for positioning the workpiece. A block 734 and a second positioning block 735 , the first positioning block 734 and the second positioning block 735 are arranged opposite to the rotary pressing block 732 . During installation, the workpiece is positioned on the first positioning block 734 and the second positioning block 735, and the workpiece is compressed and fixed by the power of the spinning cylinder 732. There are multiple second clamping mechanisms 7 arranged in rows; the third clamping mechanisms are arranged in plurality and arranged in rows. Multiple workpieces can be fixed for welding processing.

最后应说明的是:以上仅为本实用新型的优选实施例而已,并不用于限制本实用新型,尽管参照实施例对本实用新型进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换,但是凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。Finally, it should be noted that the above are only preferred embodiments of the utility model, and are not intended to limit the utility model. Although the utility model has been described in detail with reference to the embodiments, for those skilled in the art, it is still It is possible to modify the technical solutions recorded in the foregoing embodiments, or to perform equivalent replacements on some of the technical features, but within the spirit and principles of the present utility model, any modifications, equivalent replacements, improvements, etc. Included within the protection scope of the present utility model.

Claims (6)

1.一种焊接夹具结合机器人自动焊接生产线,其特征在于:包括第一工位、第二工位、第三工位、用于焊接的六轴机器人和控制所述六轴机器人在第一工位、第二工位和第三工位之间进行循环焊接的控制器,所述第一工位、第二工位和第三工位呈等腰三角形分布,所述第一工位位于所述等腰三角形的顶点位置,所述六轴机器人位于所述等腰三角形的中心位置,所述第一工位设置有将工件进行固定的第一夹紧机构和将工件顶出的第一顶出机构,所述第二工位设置有将工件进行固定的第二夹紧机构和将工件顶出的第二顶出机构,所述第三工位设置有将工件进行固定的第三夹紧机构和将工件顶出的第三顶出机构。1. A welding fixture combined with a robotic automatic welding production line, characterized in that: it comprises a first station, a second station, a third station, a six-axis robot for welding and controls the six-axis robot to operate in the first station. A controller for circular welding between the first station, the second station and the third station, the first station, the second station and the third station are distributed in an isosceles triangle, and the first station is located at the The apex position of the isosceles triangle, the six-axis robot is located at the center of the isosceles triangle, and the first station is provided with a first clamping mechanism for fixing the workpiece and a first ejector for pushing the workpiece out. The second station is provided with a second clamping mechanism for fixing the workpiece and a second ejection mechanism for pushing the workpiece out, and the third station is provided with a third clamping mechanism for fixing the workpiece mechanism and a third ejection mechanism that ejects the workpiece. 2.根据权利要求1所述的焊接夹具结合机器人自动焊接生产线,其特征在于:所述第一夹紧机构包括成对设置的将工件沿长度方向夹紧的第一气缸、成对设置的将工件沿宽度方向夹紧的第二气缸以及将工件压紧固定的第三气缸。2. The welding fixture combined with robot automatic welding production line according to claim 1, characterized in that: the first clamping mechanism includes first cylinders arranged in pairs to clamp the workpiece along the length direction, and cylinders arranged in pairs to The second cylinder clamps the workpiece along the width direction and the third cylinder presses and fixes the workpiece. 3.根据权利要求1所述的焊接夹具结合机器人自动焊接生产线,其特征在于:所述第一顶出机构包括基座、安装在基座上的至少一个顶出气缸、与所述顶出气缸的活塞杆连接的用于放置工件的顶出板。3. The welding fixture combined with robot automatic welding production line according to claim 1, characterized in that: the first ejection mechanism includes a base, at least one ejection cylinder installed on the base, and the ejection cylinder The ejector plate connected by the piston rod is used to place the workpiece. 4.根据权利要求1所述的焊接夹具结合机器人自动焊接生产线,其特征在于:在所述第一工位还设置有将工件翻转的翻转机构,所述翻转机构为焊接变位机,所述焊接变位机包括底座、设置在底座上的动力头与从动头,所述动力头包括首座、设置在所述首座上的电机以及与所述电机的输出端连接的第一工件安装座,所述从动头包括安装在底座上的尾座以及安装在所述尾座上的第二工件安装座,所述尾座与所述第二工件安装座通过轴承连接,所述第一工件安装座与所述第二工件安装座相对设置。4. The welding fixture combined with robot automatic welding production line according to claim 1, characterized in that: the first station is also provided with an overturning mechanism for overturning the workpiece, the overturning mechanism is a welding positioner, the The welding positioner includes a base, a power head and a driven head arranged on the base, the power head includes a first seat, a motor arranged on the first seat, and a first workpiece mounting seat connected to the output end of the motor, The driven head includes a tailstock installed on the base and a second workpiece mounting seat installed on the tailstock, the tailstock is connected with the second workpiece mounting seat through a bearing, and the first workpiece is installed The seat is arranged opposite to the second workpiece mounting seat. 5.根据权利要求1所述的焊接夹具结合机器人自动焊接生产线,其特征在于:所述第二夹紧机构和第三夹紧机构均包括机架,所述机架上设置有工作台,所述工作台上设置有气缸支架,所述气缸支架上设置有夹具调节板和旋压气缸,所述旋压气缸的输出端设置有旋转压块,所述夹具调节板上设置有将工件定位的第一定位块和第二定位块,所述第一定位块和所述第二定位块与所述旋转压块相对设置。5. The welding fixture combined with robot automatic welding production line according to claim 1, characterized in that: the second clamping mechanism and the third clamping mechanism both include a frame, and a workbench is arranged on the frame, so that The workbench is provided with a cylinder bracket, the cylinder bracket is provided with a jig adjusting plate and a spinning cylinder, the output end of the spinning cylinder is provided with a rotary pressing block, and the jig adjusting plate is provided with a tool for positioning the workpiece. A first positioning block and a second positioning block, the first positioning block and the second positioning block are arranged opposite to the rotary pressing block. 6.根据权利要求1所述的焊接夹具结合机器人自动焊接生产线,其特征在于:所述第二夹紧机构为多个,并且排列设置;所述第三夹紧机构均设置为多个,并且排列设置。6. The welding fixture combined with robot automatic welding production line according to claim 1, characterized in that: there are multiple second clamping mechanisms arranged in a row; multiple third clamping mechanisms are arranged, and Arrange settings.
CN201620749715.1U 2016-07-13 2016-07-13 A kind of weld jig combines robot automatic welding production line Expired - Fee Related CN205764557U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620749715.1U CN205764557U (en) 2016-07-13 2016-07-13 A kind of weld jig combines robot automatic welding production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620749715.1U CN205764557U (en) 2016-07-13 2016-07-13 A kind of weld jig combines robot automatic welding production line

Publications (1)

Publication Number Publication Date
CN205764557U true CN205764557U (en) 2016-12-07

Family

ID=58123231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620749715.1U Expired - Fee Related CN205764557U (en) 2016-07-13 2016-07-13 A kind of weld jig combines robot automatic welding production line

Country Status (1)

Country Link
CN (1) CN205764557U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107598456A (en) * 2017-10-17 2018-01-19 广东利迅达机器人系统股份有限公司 A kind of automatic welding equipment of carrying machine people
CN110508964A (en) * 2019-09-05 2019-11-29 亚太绿建(北京)智能机器人科技有限公司 A kind of environment protection Side fascia connector robot Full-automatic welding equipment
CN113070552A (en) * 2021-04-09 2021-07-06 郑州越达科技装备有限公司 Robot welding method for aluminum guide rod

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107598456A (en) * 2017-10-17 2018-01-19 广东利迅达机器人系统股份有限公司 A kind of automatic welding equipment of carrying machine people
CN110508964A (en) * 2019-09-05 2019-11-29 亚太绿建(北京)智能机器人科技有限公司 A kind of environment protection Side fascia connector robot Full-automatic welding equipment
CN110508964B (en) * 2019-09-05 2024-04-05 张美玲 Full-automatic welding equipment of environmental protection integrated side fascia connecting piece robot
CN113070552A (en) * 2021-04-09 2021-07-06 郑州越达科技装备有限公司 Robot welding method for aluminum guide rod

Similar Documents

Publication Publication Date Title
CN205271248U (en) Truck chassis tail lamp scaffold weldment frock
CN205021039U (en) Welding robot workstation
CN218695646U (en) An automatic welding, clamping and displacement tooling for large plate structural parts
CN205342324U (en) Welding jig tilting mechanism
CN204800199U (en) Vapour car skeleton robot welds double -layered device
CN201309088Y (en) Fixture of milling machine
CN208409325U (en) Workpiece quickly overturns transfer mechanism
CN206356783U (en) A kind of comprehensive steel cylinder welder
CN107671879B (en) Multifunctional furnace frame robot clamp
CN206882986U (en) Transformer turbine blade core is punctuated welder
CN108247273A (en) A semi-trailer chassis welding tooling platform
CN216680906U (en) Frock clamp is used in auto-parts welding
CN104308326A (en) Automatic welding device and welding process thereof
CN108941984B (en) Efficient machining mechanism for grid plate machining and working method thereof
CN203976219U (en) A kind of automobile rear-row seat-backrest special hoisting fixture that rolls off the production line
CN209754632U (en) multi-station steel pipe cutting clamp for steel pipe production line
CN222001351U (en) A movable gantry straightening machine
CN202781823U (en) Double-station rotary type balancing ring hot plate welding machine
CN212286855U (en) Workpiece feeding manipulator
CN205021040U (en) Welding finished product ejection mechanism
CN204771099U (en) Cushion basin and reinforcing plate stamping workpiece spot welding device
CN211028631U (en) Laser welder loading attachment with dysmorphism clamping function
CN210358630U (en) Long shaft part straightening device
CN209021474U (en) Efficient welding machine
CN209754336U (en) A special automatic welding device for high stroke jack base

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161207