CN205741822U - A kind of monoblock type water drainage curb - Google Patents

A kind of monoblock type water drainage curb Download PDF

Info

Publication number
CN205741822U
CN205741822U CN201620478224.8U CN201620478224U CN205741822U CN 205741822 U CN205741822 U CN 205741822U CN 201620478224 U CN201620478224 U CN 201620478224U CN 205741822 U CN205741822 U CN 205741822U
Authority
CN
China
Prior art keywords
curb
longitudinal
type water
monoblock type
drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620478224.8U
Other languages
Chinese (zh)
Inventor
白钧夫
孙雅珍
顾章义
李凯翔
苑学众
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201620478224.8U priority Critical patent/CN205741822U/en
Application granted granted Critical
Publication of CN205741822U publication Critical patent/CN205741822U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Road Paving Structures (AREA)

Abstract

一种整体式排水路缘石,属于道路基础设施技术领域。由立缘石部分与平缘石部分浇注形成带折弯的整体,在折弯处开有多个横向排水孔,在平缘石表面上设置多个竖向排水孔,在平缘石部分的内部设有贯穿的纵向汇水通道,横向排水孔和竖向排水孔分别与纵向汇水通道相连通。本实用新型立缘石与平缘石合二为一,方便施工,增强了结构的整体性。在路缘石内部设排水通道,相当于在道路两侧设了一排泄水井,大大加快了路面排水能力。由于横向排水孔洞分布于每块路缘石上,因此孔洞不至于太大而导致路缘石承载力不足而破坏。纵向汇水通道的纵坡是由于通道两侧的高差实现的,施工时只需对其两相邻的路缘石即可,改善了传统的以基座形成高差的模式,为施工带来方便。

The utility model relates to an integral drainage curb stone, which belongs to the technical field of road infrastructure. The edge stone part and the flat edge stone part are poured to form a whole with a bend. There are multiple horizontal drainage holes at the bend, and multiple vertical drainage holes are set on the surface of the flat edge stone. The longitudinal water collection channel, the horizontal drainage hole and the vertical drainage hole are respectively connected with the longitudinal water collection channel. The utility model combines the vertical edge stone and the flat edge stone into one, which is convenient for construction and enhances the integrity of the structure. Setting drainage channels inside the curb is equivalent to setting up a drainage well on both sides of the road, which greatly speeds up the drainage capacity of the road surface. Since the horizontal drainage holes are distributed on each curb, the holes will not be too large to cause the curb to be damaged due to insufficient bearing capacity. The longitudinal slope of the longitudinal water catchment channel is realized due to the height difference on both sides of the channel. During construction, only two adjacent curbstones are required. convenient.

Description

一种整体式排水路缘石An integral drainage curb stone

技术领域technical field

本发明属于道路基础设施技术领域,特别是涉及一种整体式排水路缘石。The invention belongs to the technical field of road infrastructure, in particular to an integral drainage curb.

背景技术Background technique

目前,在城市道路边缘常设有立缘石用于支撑路面或路肩边缘。有时为了便于边缘处沥青面层的压实及避免其经常被雨水浸泡而降低使用寿命,在路缘石内侧还设有平缘石。这种分开的构造给施工带来了不便,而且结构的整体性较差。At present, there are always curbs on the edge of urban roads to support the road surface or the edge of the shoulder. Sometimes in order to facilitate the compaction of the asphalt surface layer at the edge and avoid its frequent rainwater soaking and reduce its service life, flat curb stones are also provided inside the curb stones. This separate structure brings inconvenience to the construction, and the integrity of the structure is poor.

另外,城市道路排水问题目前也不是十分理想,仅20~50m一个的排水井不足以给车辆行驶及行人带来舒适感。时常看见降雨时路两侧及中间分隔带,两侧分隔带出现带状及层状水流。当降雨量较大时,由于两侧的排水井的过水断面不足以及时排除雨水,就会导致路面积水太深而阻断交通。目前,对此种现象的路段采取的措施是加大排水井的尺寸,但过大的排水断面大大削弱了路缘石的承载力,因此很多设有排水井的路缘石都被剪坏,使排水效率降低。如果是用雨水井箅子,由于其大都采用金属制成,被盗现象频发,一旦箅子被盗走,暴露在外的雨水口容易造成交通事故。In addition, the drainage problem of urban roads is not very ideal at present, and only a drainage well of 20-50m is not enough to bring comfort to vehicles and pedestrians. It is common to see banded and layered water flows on both sides of the road and in the middle divider during rainfall. When the rainfall is large, due to the lack of cross-sections of the drainage wells on both sides to remove rainwater in time, it will cause the road to be too deep and block traffic. At present, the measures taken to deal with this phenomenon are to increase the size of drainage wells, but the excessively large drainage section greatly weakens the bearing capacity of curb stones, so many curb stones with drainage wells are cut and damaged, making drainage Reduced efficiency. If the rainwater well grate is used, since it is mostly made of metal, the phenomenon of theft occurs frequently. Once the grate is stolen, the exposed rainwater outlet will easily cause traffic accidents.

发明内容Contents of the invention

针对上述存在的技术问题,本发明提供一种整体式排水路缘石,其排水效果好,易于施工。In view of the above technical problems, the present invention provides an integral drainage curb, which has good drainage effect and is easy to construct.

本发明的目的是通过以下技术方案来实现的:The purpose of the present invention is achieved through the following technical solutions:

一种整体式排水路缘石,由立缘石部分与平缘石部分浇注形成带折弯的整体,在折弯处开有多个横向排水孔,在平缘石表面上设置多个竖向排水孔,在平缘石部分的内部设有贯穿的纵向汇水通道,横向排水孔和竖向排水孔分别与纵向汇水通道相连通。An integral drainage curb, which is formed by pouring the vertical curb part and the flat curb part into a whole with a bend. There are multiple horizontal drainage holes at the bend, and multiple vertical drainage holes are set on the surface of the flat curb. The interior of the flat edge stone part is provided with a through longitudinal water collection channel, and the horizontal drainage holes and the vertical drainage holes are respectively connected with the longitudinal water collection channel.

进一步地,在所述折弯处的上、下表面均倒圆角,形成弧形连接。Further, the upper and lower surfaces of the bend are rounded to form an arc connection.

进一步地,所述平缘石部分的顶面带有横坡度,横坡度为2%~5%,平缘石部分顶面的端部高于折弯端。Further, the top surface of the flat edge stone part has a transverse slope, the transverse slope is 2% to 5%, and the end of the top surface of the flat edge stone part is higher than the bent end.

进一步地,所述横向排水孔洞直径在2~4cm。Further, the diameter of the lateral drainage hole is 2-4cm.

进一步地,所述竖向排水孔沿纵向长为8~10cm,宽为2~4cm。Further, the vertical drainage hole is 8-10 cm long and 2-4 cm wide.

本发明用于纵坡较大的道路上时,所述路缘石的纵向汇水通道的两端等高。When the present invention is used on a road with a large longitudinal slope, the two ends of the longitudinal water collection channel of the curb are of the same height.

进一步地,相邻两块路缘石间采用灌封的形式连接,即:预先在一块路缘石纵向汇水通道处设置一个薄壁钢环,相邻另一块路缘石插接在该薄壁钢环上,相邻两块路缘石间的勾缝小于1cm。Furthermore, two adjacent curbstones are connected in the form of potting, that is, a thin-walled steel ring is pre-set at the longitudinal water collection channel of one curbstone, and the adjacent curbstone is inserted on the thin-walled steel ring, and the adjacent curbstone is inserted into the thin-walled steel ring. The pointing between two curb stones is less than 1cm.

进一步地,所述薄壁钢环沿道路纵向的长度为3~5cm,壁厚1mm~2mm,半径略小于纵向汇水通道的半径。Further, the length of the thin-walled steel ring along the longitudinal direction of the road is 3-5 cm, the wall thickness is 1 mm-2 mm, and the radius is slightly smaller than the radius of the longitudinal catchment channel.

本发明用于纵坡比较小的道路时,所述路缘石的纵向汇水通道两端具有高度差,形成0.3%的纵坡。When the present invention is used on a road with a relatively small longitudinal slope, the two ends of the longitudinal water catchment channel of the curb have a height difference, forming a longitudinal slope of 0.3%.

进一步地,所述路缘石沿道路纵向形成锯齿形分布,在每个锯齿的最低点设置雨水收水井。Further, the curbstones are distributed in a zigzag shape longitudinally along the road, and a rainwater collection well is arranged at the lowest point of each zigzag.

本发明的有益效果为:The beneficial effects of the present invention are:

本发明路侧石及路平石合二为一,方便施工,增强了结构的整体性。在路缘石内部设排水通道,相当于在道路两侧设了一排泄水井,大大加快了路面排水能力。由于横向排水孔洞分布于每块路缘石上,因此孔洞不至于太大而导致路缘石承载力不足而破坏。纵向汇水通道的纵坡是由于通道两侧的高差实现的,施工时只需对其两相邻的路缘石即可,改善了传统的以基座形成高差的模式,为施工带来方便。In the invention, the roadside stone and the road leveling stone are combined into one, which is convenient for construction and enhances the integrity of the structure. Setting drainage channels inside the curb is equivalent to setting up a drainage well on both sides of the road, which greatly speeds up the drainage capacity of the road surface. Since the horizontal drainage holes are distributed on each curb, the holes will not be too large to cause the curb to be damaged due to insufficient bearing capacity. The longitudinal slope of the longitudinal water catchment channel is realized due to the height difference on both sides of the channel. During construction, only the two adjacent curbstones are needed. This improves the traditional mode of forming a height difference with the base, and brings more benefits to the construction. convenient.

附图说明Description of drawings

图1是本发明整体式排水路缘石的三维视图;Fig. 1 is a three-dimensional view of the monolithic drainage curb of the present invention;

图2是本发明本整体式排水路缘石的布置形式图;Fig. 2 is a layout form diagram of the integral drainage curbstone of the present invention;

图3是本发明的平面结构示意图;Fig. 3 is the plane structure schematic diagram of the present invention;

图4是图3的A-A截面图;Fig. 4 is the A-A sectional view of Fig. 3;

图5是图3的B-B截面图;Fig. 5 is the B-B sectional view of Fig. 3;

图6是图3的C-C截面图;Fig. 6 is the C-C sectional view of Fig. 3;

图7是本发明路缘石纵向布置的一种方式示意图;Fig. 7 is a schematic diagram of a mode of longitudinal arrangement of curbstones of the present invention;

图8是图7的I部放大示意图。FIG. 8 is an enlarged schematic diagram of part I of FIG. 7 .

图9是本发明路缘石纵向布置的另一种方式示意图。Fig. 9 is a schematic diagram of another way of longitudinal arrangement of curbstones in the present invention.

图中:1为竖向排水孔,2为横向排水孔,3为纵向汇水通道,4为横向排水孔洞与纵向汇水通道相连的通道,5为竖向排水孔洞的下水通道,6.平缘石 部分,7.立缘石部分,8.面层,9.基层,10.垫层,11.土基,12.步道板,13.混凝土基座,14.横坡度,15.雨水收水井,16.纵坡。In the figure: 1 is the vertical drainage hole, 2 is the horizontal drainage hole, 3 is the longitudinal water collection channel, 4 is the channel connecting the horizontal drainage hole and the longitudinal water collection channel, 5 is the sewer channel of the vertical drainage hole, 6. Edge stone part, 7. Edge stone part, 8. Surface layer, 9. Base layer, 10. Cushion layer, 11. Soil foundation, 12. Walkway board, 13. Concrete base, 14. Transverse slope, 15. Rainwater collection well, 16. Longitudinal slope.

具体实施方式detailed description

下面结合附图和实施例对本发明进行详细描述。The present invention will be described in detail below in conjunction with the accompanying drawings and embodiments.

实施例1:如图1所示,本发明一种整体式排水路缘石,其由立缘石部分与平缘石部分浇注形成带折弯的整体,在折弯处开有多个横向排水孔2,在平缘石表面上设置多个竖向排水孔1(本例开有6个),在平缘石部分的内部设有贯穿的纵向汇水通道3,横向排水孔2和竖向排水孔1分别与纵向汇水通道3相连通。Embodiment 1: As shown in Figure 1, the present invention is an integral drainage curb, which is formed by pouring the vertical curb part and the flat curb part into a whole with a bend, and a plurality of horizontal drainage holes 2 are opened at the bend. A plurality of vertical drainage holes 1 (6 in this example) are set on the surface of the flat edge stone, and a vertical water catchment channel 3 penetrating through is provided inside the flat edge stone part, and the horizontal drainage hole 2 and the vertical drainage hole 1 are respectively connected with 3 longitudinal catchment channels are connected.

在所述折弯处的上、下表面均倒圆角,形成弧形连接。Both the upper and lower surfaces of the bend are rounded to form an arc connection.

如图2、图4所示,所述平缘石部分的顶面带有横坡度,横坡度为2%~5%,平缘石部分顶面的端部高于折弯端。As shown in Fig. 2 and Fig. 4, the top surface of the flat edge stone part has a transverse slope of 2% to 5%, and the end of the top surface of the flat edge stone part is higher than the bent end.

所述横向排水孔2的直径为2~4cm。The diameter of the lateral drainage hole 2 is 2-4 cm.

如图3所示,所述竖向排水孔1沿纵向长为8cm,宽为4cm。As shown in Figure 3, the vertical drainage hole 1 is 8cm long and 4cm wide.

如图5、图6所示,本发明的路缘石用混凝土在工厂浇筑养护之后再运到现场。路缘石本体长度为50~100cm,所述本体总高为35~45cm,下顶面宽为20~25cm。纵向汇水通道3断面形状为圆形或U形,宽度应与上部竖向排水孔1相适应。将埋入面层以下的角部去掉以节省材料,但须在此处倒圆角以减小应力集中。As shown in Fig. 5 and Fig. 6, the curb concrete of the present invention is transported to the site after pouring and curing in the factory. The length of the curb stone body is 50-100 cm, the total height of the body is 35-45 cm, and the width of the lower top surface is 20-25 cm. The cross-sectional shape of the longitudinal catchment channel 3 is circular or U-shaped, and the width should be compatible with the upper vertical drainage hole 1. The corners buried under the surface layer are removed to save material, but the corners must be rounded here to reduce stress concentration.

如图2为使用时的示意图。其中外露部分高为15~20cm,埋入地下部分的高为20~25cm(包括纵向汇水通道3的高度)。下顶面要形成2%左右的横坡且边缘要与道路平齐。在铺设路缘石之前要在下面现浇一层混凝土基座厚度大约5~10cm,其作用在于防止路缘石的不均匀沉降。Figure 2 is a schematic diagram in use. The height of the exposed part is 15-20 cm, and the height of the buried part is 20-25 cm (including the height of the longitudinal catchment channel 3). The lower top surface shall form a transverse slope of about 2% and the edge shall be flush with the road. Before laying the curb stones, a layer of concrete base with a thickness of about 5-10 cm should be poured below, and its function is to prevent uneven settlement of the curb stones.

如图7、图8所示,本发明用于纵坡较大的道路上时,所述的纵向汇水通道3的两端等高,不设纵坡,所有路缘石规格一致。施工时铺好水泥混凝土基座后,分段布设路缘石以提高效率,需要注意段与段之间要紧密接合。每两块路缘石间采用灌封的形式连接,这需要预先在一块路缘石纵向汇水通道3处插入一个薄壁钢环,再将另一块路缘石插到其上,两块路缘石间的勾缝要小于1cm。钢环沿道路纵向的长度为3cm,壁厚1mm即可,半径略小于纵向汇水通道的半径。然后就向缝内灌注砂浆,钢环即能防止砂浆流入纵向汇水通道。这样,全部修筑完之后,当降雨量较大时也不必担心会出现积水现象。As shown in Fig. 7 and Fig. 8, when the present invention is used on a road with a large longitudinal slope, the two ends of the longitudinal water catchment channel 3 are of the same height, no longitudinal slope is set, and all curbstones have the same specifications. After the cement concrete base is laid during construction, curb stones are arranged in sections to improve efficiency, and attention should be paid to the tight connection between sections. Every two curb stones are connected in the form of potting, which requires inserting a thin-walled steel ring at the longitudinal water collection channel 3 of a curb stone in advance, and then inserting another curb stone on it, the pointing joint between the two curb stones It should be less than 1cm. The length of the steel ring along the longitudinal direction of the road is 3cm, the wall thickness is 1mm, and the radius is slightly smaller than the radius of the longitudinal catchment channel. Then pour mortar into the seam, and the steel ring can prevent the mortar from flowing into the longitudinal catchment channel. In this way, after all the construction is completed, there is no need to worry about water accumulation when the rainfall is relatively large.

实施例2:本例与实施例1不同的是:如图9所示,本例用于纵坡比较小的道路时,所述的纵向汇水通道3两端具有高度差,形成0.3%的纵坡16,并且沿 道路纵向形成锯齿形分布,在每个锯齿的最低点设置雨水收水井,大约每100米设一个。如图8所示,由于展现的路段过长,因此只是示意图。其施工方式与实施例1相同,只是路缘石的规格不一样,施工前要分好堆以免弄混。可以看出来,由于纵向汇水通道设在路缘石内部,因此路缘石本身不用形成纵坡,这就为施工带来了极大的方便,但对制造路缘石模板的精度要求要高一些。Embodiment 2: The difference between this example and Embodiment 1 is: as shown in Figure 9, when this example is used for roads with relatively small longitudinal slopes, the two ends of the longitudinal catchment channel 3 have a height difference, forming a 0.3% The longitudinal slope is 16, and a zigzag distribution is formed along the longitudinal direction of the road. Rainwater collection wells are set at the lowest point of each zigzag, and one is set about every 100 meters. As shown in Figure 8, since the displayed road section is too long, it is only a schematic diagram. Its construction method is identical with embodiment 1, just the specification of curb stone is not the same, and will divide into good piles before construction so as not to confuse. It can be seen that since the longitudinal water catchment channel is set inside the curb stone, the curb stone itself does not need to form a longitudinal slope, which brings great convenience to the construction, but the precision requirement for manufacturing the curb stone formwork is higher.

本例所述平缘石部分的顶面带有横坡度,横坡度为5%,平缘石部分顶面的端部高于折弯端。钢环沿道路纵向的长度为5cm,壁厚2mm。所述竖向排水孔1沿纵向长为10cm,宽为2cm。The top surface of the flat edge stone part in this example has a transverse slope, the transverse slope is 5%, and the end of the top surface of the flat edge stone part is higher than the bending end. The length of the steel ring along the longitudinal direction of the road is 5cm, and the wall thickness is 2mm. The vertical drainage hole 1 is 10 cm long and 2 cm wide.

实施例3:本例与实施例1不同的是:本例所述平缘石部分的顶面带有横坡度,横坡度为4%,平缘石部分顶面的端部高于折弯端。钢环沿道路纵向的长度为4cm,壁厚1.5mm。所述竖向排水孔1沿纵向长为9cm,宽为3cm。Embodiment 3: The difference between this example and Embodiment 1 is that the top surface of the flat edge stone part described in this example has a transverse slope of 4%, and the end of the top surface of the flat edge stone part is higher than the bent end. The length of the steel ring along the longitudinal direction of the road is 4cm, and the wall thickness is 1.5mm. The vertical drainage hole 1 is 9 cm long and 3 cm wide.

以上各实施例仅用以说明本路缘石的技术及施工方案,而非对其限制;尽管参照前述各实施例对本发明进行了详细的说明,该领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的范围。The above embodiments are only used to illustrate the technology and construction scheme of this curbstone, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: it can still The technical solutions described in the foregoing embodiments are modified, or some or all of the technical features are replaced equivalently; and these modifications or replacements do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the various embodiments of the present invention.

Claims (10)

1. a monoblock type water drainage curb, it is characterised in that: formed band bending by vertical curb part with the cast of flush curb part Entirety, have multiple transverse drainage hole at bending part, flush curb surface arrange multiple vertical drainage hole, in orle Plumbum preparatium The inside divided is provided with the longitudinal charge for remittance passage run through, transverse drainage hole and vertical drainage hole and is connected with longitudinal charge for remittance passage respectively Logical.
Monoblock type water drainage curb the most according to claim 1, it is characterised in that: on the upper and lower surface of described bending part All roundings, form arc and connect.
Monoblock type water drainage curb the most according to claim 1, it is characterised in that: the end face of described flush curb part with Transverse slope, transverse slope is 2%~5%, and the end of flush curb portion top surface is higher than bending end.
Monoblock type water drainage curb the most according to claim 1, it is characterised in that: described transverse drainage hole diameter is 2 ~4cm.
Monoblock type water drainage curb the most according to claim 1, it is characterised in that: described vertical drainage hole is along the most a length of 8~10cm, a width of 2~4cm.
Monoblock type water drainage curb the most according to claim 1, it is characterised in that: time on the road that longitudinal gradient is bigger, The two ends of longitudinal charge for remittance passage of described kerbstone are contour.
Monoblock type water drainage curb the most according to claim 6, it is characterised in that: use embedding between adjacent two pieces of kerbstones Form connect, it may be assumed that a thin-walled steel loop, another block kerbstone adjacent are set in advance at one piece of kerbstone longitudinal direction charge for remittance passage Being plugged on this thin-walled steel loop, the jointing between adjacent two pieces of kerbstones is less than 1cm.
Monoblock type water drainage curb the most according to claim 7, it is characterised in that: described thin-walled steel loop is along road longitudinal direction A length of 3~5cm, wall thickness 1mm~2mm, radius is slightly less than the radius of longitudinal charge for remittance passage.
Monoblock type water drainage curb the most according to claim 1, it is characterised in that: when the road that longitudinal gradient is smaller, Longitudinal charge for remittance passage two ends of described kerbstone have difference in height, form the longitudinal gradient of 0.3%.
Monoblock type water drainage curb the most according to claim 1, it is characterised in that: described kerbstone is along road longitudinal direction shape Toothing is distributed, and the minimum point at each sawtooth arranges rainwater collection well.
CN201620478224.8U 2016-05-24 2016-05-24 A kind of monoblock type water drainage curb Expired - Fee Related CN205741822U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620478224.8U CN205741822U (en) 2016-05-24 2016-05-24 A kind of monoblock type water drainage curb

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620478224.8U CN205741822U (en) 2016-05-24 2016-05-24 A kind of monoblock type water drainage curb

Publications (1)

Publication Number Publication Date
CN205741822U true CN205741822U (en) 2016-11-30

Family

ID=57361860

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620478224.8U Expired - Fee Related CN205741822U (en) 2016-05-24 2016-05-24 A kind of monoblock type water drainage curb

Country Status (1)

Country Link
CN (1) CN205741822U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700311A (en) * 2017-11-20 2018-02-16 杭州京兆岩新型建材有限公司 A kind of permeable curb
CN107740325A (en) * 2017-09-28 2018-02-27 中国十七冶集团有限公司 A kind of new shallow trench monoblock type curb structure of area of heavy rainfull road and construction method
CN107869102A (en) * 2017-11-20 2018-04-03 杭州京兆岩新型建材有限公司 A kind of curb, road paving structure and construction method using the curb
CN107893354A (en) * 2017-11-20 2018-04-10 杭州京兆岩新型建材有限公司 A kind of drainage type curb
CN108442205A (en) * 2018-04-24 2018-08-24 福建建工集团有限责任公司 A kind of prefabricated built-in water drainage curb
CN108532406A (en) * 2018-05-08 2018-09-14 深圳市市政工程咨询中心有限公司 Can rapid construction high-bearing capacity pervious surface and laying method
CN111455773A (en) * 2020-05-14 2020-07-28 西藏天路股份有限公司 A kind of permeable prefabricated concrete pavement and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740325A (en) * 2017-09-28 2018-02-27 中国十七冶集团有限公司 A kind of new shallow trench monoblock type curb structure of area of heavy rainfull road and construction method
CN107700311A (en) * 2017-11-20 2018-02-16 杭州京兆岩新型建材有限公司 A kind of permeable curb
CN107869102A (en) * 2017-11-20 2018-04-03 杭州京兆岩新型建材有限公司 A kind of curb, road paving structure and construction method using the curb
CN107893354A (en) * 2017-11-20 2018-04-10 杭州京兆岩新型建材有限公司 A kind of drainage type curb
CN108442205A (en) * 2018-04-24 2018-08-24 福建建工集团有限责任公司 A kind of prefabricated built-in water drainage curb
CN108532406A (en) * 2018-05-08 2018-09-14 深圳市市政工程咨询中心有限公司 Can rapid construction high-bearing capacity pervious surface and laying method
CN111455773A (en) * 2020-05-14 2020-07-28 西藏天路股份有限公司 A kind of permeable prefabricated concrete pavement and construction method thereof

Similar Documents

Publication Publication Date Title
CN205741822U (en) A kind of monoblock type water drainage curb
CN105239485B (en) Water drainage curb and the asphalt roads with discharge structure
CN105937196A (en) Subgrade pile-plank type widening structure and construction method thereof
CN110983907A (en) Assembled self-draining sidewalk
CN209584767U (en) An integrated drainage curb stone
CN104195913A (en) Movable temporary road structure
CN106087639A (en) A kind of highway, Irish bridge structure and Irish bridge construction method
CN102322094A (en) Road surface combined drainage system
CN210596882U (en) Pedestrian road
CN108411728A (en) Surface drainage
CN208009193U (en) A kind of highway engineering assembling type steel reinforced concrete gutter structure
CN111304989A (en) Stable ecological permeable pavement and manufacturing method thereof
CN207987673U (en) A substation curb stone
CN102251458A (en) Kerbstone and road comprising the same
CN209243482U (en) A kind of town road for receiving water function with face formula
CN206521661U (en) A kind of Prefabricated block and Prefabricated block group for roadside drainage
CN211713548U (en) A stable ecological permeable pavement
CN211057526U (en) Road bed for municipal road engineering
CN211547155U (en) Water permeable flat curb for road
CN209760401U (en) Prefabricated reinforced concrete well periphery reinforcing structure
CN113308960A (en) High-turnover assembly type curb cushion block and mold and construction method thereof
CN210066404U (en) A central separation area curb for highway
CN108179677A (en) Sponge urban water-through pavement
CN209443316U (en) A kind of permeable tile work pavement structure that closely knit asphalt macadam concrete layer is set
CN220301098U (en) Road curbstone with drainage structures

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161130

Termination date: 20170524

CF01 Termination of patent right due to non-payment of annual fee