CN205666535U - Transmission line steel pipe tower electrified conducting wire promotes fixture - Google Patents
Transmission line steel pipe tower electrified conducting wire promotes fixture Download PDFInfo
- Publication number
- CN205666535U CN205666535U CN201620543345.6U CN201620543345U CN205666535U CN 205666535 U CN205666535 U CN 205666535U CN 201620543345 U CN201620543345 U CN 201620543345U CN 205666535 U CN205666535 U CN 205666535U
- Authority
- CN
- China
- Prior art keywords
- adjusting
- insulation
- rod
- adjusting screw
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 29
- 239000010959 steel Substances 0.000 title claims abstract description 29
- 230000005540 biological transmission Effects 0.000 title claims abstract description 16
- 238000009413 insulation Methods 0.000 claims abstract description 29
- 239000007787 solid Substances 0.000 claims 2
- 241000282472 Canis lupus familiaris Species 0.000 claims 1
- 239000004020 conductor Substances 0.000 abstract description 2
- 239000012212 insulator Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
本实用新型具体为一种输电线路钢管塔带电导线提升卡具,解决了输电线路钢管塔带电导线没有专用提升卡具的问题。输电线路钢管塔带电导线提升卡具,包括水平布置的槽钢,槽钢两侧面穿有左右两个调节丝杆固定轴和中部两个调节螺杆固定轴,中部两个调节螺杆固定轴上均套固有调节螺杆,两个调节螺杆下端连接到固定横板,两个调节丝杆固定轴下方套固有调节丝杆,调节丝杆上设有丝杆手柄,调节丝杆下端连接有绝缘调节拉杆,绝缘调节拉杆与调节丝杆通过调节丝杆与绝缘调节拉杆固定螺栓连接,绝缘调节拉杆固定螺栓下方通过连杆连接有导线挂钩。本实用新型结构简单、安全可靠,特别适合于输电线路钢管塔带电导线的提升。
The utility model is specifically a lifting jig for the live wire of the steel pipe tower of the transmission line, which solves the problem that there is no special lifting jig for the live wire of the steel pipe tower of the power transmission line. The lifting fixture for the live wire of the steel pipe tower of the transmission line includes a horizontally arranged channel steel. Two left and right adjusting screw fixing shafts and two middle adjusting screw fixing shafts are worn on the two sides of the channel steel. The two middle adjusting screw fixing shafts are evenly sleeved Intrinsic adjustment screw, the lower ends of the two adjustment screws are connected to the fixed horizontal plate, and the lower ends of the two adjustment screw rods are covered with inherent adjustment screw rods. The adjustment screw rods are provided with screw handles, and the lower ends of the adjustment screw rods are connected with insulating adjustment pull rods, which are insulated The adjusting pull rod and the adjusting screw rod are connected with the fixing bolt of the insulation adjusting pull rod through the adjusting screw rod, and the lower part of the fixing bolt of the insulation adjusting pull rod is connected with a wire hook through a connecting rod. The utility model has the advantages of simple structure, safety and reliability, and is especially suitable for lifting live conductors of steel pipe towers of power transmission lines.
Description
技术领域technical field
本实用新型涉及输电线路辅助工具,具体为一种输电线路钢管塔带电导线提升卡具。The utility model relates to an auxiliary tool for a power transmission line, in particular to a lifting jig for a steel pipe tower live wire of a power transmission line.
背景技术Background technique
钢管塔是采用了钢管型材的输电线路铁塔。目前,输电线路钢管塔带电导线金具及绝缘子串存在缺陷需要更换时,暂无专用提升卡具。The steel pipe tower is a transmission line tower that uses steel pipe profiles. At present, there is no special lifting fixture when the live wire fittings and insulator strings of the steel pipe tower of the transmission line are defective and need to be replaced.
发明内容Contents of the invention
本实用新型为了解决输电线路钢管塔带电导线没有专用提升卡具的问题,提供了一种输电线路钢管塔带电导线提升卡具。In order to solve the problem that there is no special lifting jig for the live wire of the steel pipe tower of the transmission line, the utility model provides a lifting jig for the live wire of the steel pipe tower of the power transmission line.
本实用新型是采用如下技术方案实现的:输电线路钢管塔带电导线提升卡具,包括水平布置的槽钢,槽钢两侧面穿有左右两个调节丝杆固定轴和中部两个调节螺杆固定轴,左右两个调节丝杆固定轴具体为穿在轴孔内,中部两个调节螺杆固定轴具体为穿在滑槽内,中部两个调节螺杆固定轴上均套固有调节螺杆,两个调节螺杆下端连接到固定横板,具体为调节螺杆穿过固定横板并利用调节螺母固定,两个调节丝杆固定轴下方套固有调节丝杆,调节丝杆上设有丝杆手柄,调节丝杆下端连接有绝缘调节拉杆,绝缘调节拉杆与调节丝杆通过调节丝杆与绝缘调节拉杆固定螺栓连接,绝缘调节拉杆下端开设有绝缘调节拉杆调节孔,绝缘调节拉杆调节孔内穿有绝缘调节拉杆固定螺栓,绝缘调节拉杆固定螺栓下方通过连杆连接有导线挂钩。The utility model is realized by adopting the following technical scheme: the lifting jig for the live wire of the steel pipe tower of the transmission line includes a horizontally arranged channel steel, and two left and right adjusting screw fixing shafts and two middle adjusting screw fixing shafts are worn on the two sides of the channel steel , the left and right two adjusting screw fixing shafts are specifically worn in the shaft holes, the middle two adjusting screw fixing shafts are specifically worn in the chute, and the middle two adjusting screw fixing shafts are both covered with inherent adjusting screws, and the two adjusting screws The lower end is connected to the fixed horizontal plate. Specifically, the adjusting screw passes through the fixed horizontal plate and is fixed by the adjusting nut. The two adjusting screw rods are covered with an inherent adjusting screw rod under the fixed shaft. The adjusting screw rod is provided with a screw rod handle, and the lower end of the adjusting screw rod The insulation adjustment rod is connected with the insulation adjustment rod, and the insulation adjustment rod and the adjustment screw rod are connected with the insulation adjustment rod fixing bolt through the adjustment screw rod. The lower end of the insulation adjustment rod is provided with an insulation adjustment rod adjustment hole, and the insulation adjustment rod adjustment hole is pierced with an insulation adjustment rod fixing bolt. , the lower part of the fixing bolt of the insulation adjustment pull rod is connected with a wire hook through a connecting rod.
使用时,将槽钢横放在钢管塔地线横担上,通过调节螺杆在滑槽内移动将两调节螺杆卡在横担两侧并利用调节螺母将固定横板固定卡固在钢管塔地线横担上,然后调节两调节丝杆的长度以及绝缘调节拉杆的长度,将两导线挂钩勾在导线上,通过丝杆手柄收紧调节丝杆从而将地线提升,方便地线提升后更换金具或绝缘子串。绝缘调节拉杆起到绝缘的作用。When in use, place the channel steel horizontally on the cross arm of the steel pipe tower ground wire, move the adjusting screw in the chute to clamp the two adjusting screws on both sides of the cross arm and use the adjusting nut to fix the fixed horizontal plate on the steel pipe tower ground Then adjust the length of the two adjustment screw rods and the length of the insulation adjustment rod, hook the two wire hooks on the wire, and tighten the adjustment screw rod through the screw rod handle to lift the ground wire, which is convenient for replacement after the ground wire is lifted. Fittings or strings of insulators. The insulation adjustment rod plays the role of insulation.
本实用新型的有益效果如下:利用合理的提升机构和绝缘结构,实现了输电线路钢管塔带电导线的提升功能。调节螺杆以及绝缘调节拉杆的结构和布置是针对钢管塔带电导线横担设计的,调节丝杆的设计大大节约了人工操作,绝缘调节拉杆不但提供了绝缘的功能也有一定的调节能力。本实用新型结构简单、安全可靠,特别适合于输电线路钢管塔带电导线的提升。The beneficial effects of the utility model are as follows: the lifting function of the live wire of the steel pipe tower of the transmission line is realized by using a reasonable lifting mechanism and an insulating structure. The structure and arrangement of the adjusting screw and the insulating adjusting rod are designed for the cross arm of the live wire of the steel pipe tower. The design of the adjusting screw greatly saves manual operation. The insulating adjusting rod not only provides the function of insulation but also has a certain adjustment ability. The utility model has the advantages of simple structure, safety and reliability, and is especially suitable for lifting live conductors of steel pipe towers of power transmission lines.
附图说明Description of drawings
图1为本实用新型正视结构示意图;Fig. 1 is a schematic view of the front view structure of the utility model;
图2为本实用新型侧视结构示意图;Fig. 2 is the utility model side view structure diagram;
图中,1-槽钢,2-调节螺杆,3-调节螺杆移动槽,4-固定横板,5-调节螺母,6-调节丝杆,7-丝杆手柄,8-调节丝杆固定轴,9-调节螺杆固定轴,10-绝缘调节拉杆,11-绝缘调节拉杆调节孔,12-绝缘调节拉杆固定螺栓,13-导线挂钩,14-调节丝杆与绝缘调节拉杆固定螺栓。In the figure, 1-channel steel, 2-adjusting screw, 3-moving groove of adjusting screw, 4-fixed horizontal plate, 5-adjusting nut, 6-adjusting screw, 7-screw handle, 8-adjusting screw fixed shaft , 9-adjustment screw fixed shaft, 10-insulation adjustment rod, 11-insulation adjustment rod adjustment hole, 12-insulation adjustment rod fixing bolt, 13-wire hook, 14-adjustment screw and insulation adjustment rod fixing bolt.
具体实施方式detailed description
输电线路钢管塔带电导线提升卡具,包括水平布置的槽钢1,槽钢1两侧面穿有左右两个调节丝杆固定轴8和中部两个调节螺杆固定轴9,左右两个调节丝杆固定轴8具体为穿在轴孔内,中部两个调节螺杆固定轴9具体为穿在滑槽内,中部两个调节螺杆固定轴9上均套固有调节螺杆2,两个调节螺杆2下端连接到固定横板4,具体为调节螺杆2穿过固定横板4并利用调节螺母5固定,两个调节丝杆固定轴8下方套固有调节丝杆6,调节丝杆6上设有丝杆手柄7,调节丝杆6下端连接有绝缘调节拉杆10,绝缘调节拉杆10与调节丝杆6通过调节丝杆与绝缘调节拉杆固定螺栓14连接,绝缘调节拉杆10下端开设有绝缘调节拉杆调节孔11,绝缘调节拉杆调节孔11内穿有绝缘调节拉杆固定螺栓12,绝缘调节拉杆固定螺栓12下方通过连杆连接有导线挂钩13。Transmission line steel pipe tower live wire lifting jig, including horizontally arranged channel steel 1, two left and right adjusting screw fixing shafts 8 on the two sides of the channel steel 1, two adjusting screw fixing shafts 9 in the middle, and two left and right adjusting screw rods The fixed shaft 8 is specifically worn in the shaft hole, and the two adjusting screw fixed shafts 9 in the middle are specifically worn in the chute. The two adjusting screw fixed shafts 9 in the middle are both covered with the inherent adjusting screw 2, and the lower ends of the two adjusting screws 2 are connected. To the fixed horizontal plate 4, specifically, the adjusting screw 2 passes through the fixed horizontal plate 4 and is fixed by the adjusting nut 5, and the inherent adjusting screw 6 is set under the two adjusting screw fixing shafts 8, and the adjusting screw 6 is provided with a screw handle 7. The lower end of the adjusting screw rod 6 is connected with an insulating adjusting rod 10. The insulating adjusting rod 10 and the adjusting screw rod 6 are connected with the fixing bolt 14 of the insulating adjusting rod through the adjusting screw rod. The lower end of the insulating adjusting rod 10 is provided with an insulating adjusting rod adjusting hole 11. An insulation adjusting pull rod fixing bolt 12 is worn in the adjusting hole 11 of the insulation adjusting pull rod, and a wire hook 13 is connected to the bottom of the insulation adjusting pull rod fixing bolt 12 through a connecting rod.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620543345.6U CN205666535U (en) | 2016-06-07 | 2016-06-07 | Transmission line steel pipe tower electrified conducting wire promotes fixture |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620543345.6U CN205666535U (en) | 2016-06-07 | 2016-06-07 | Transmission line steel pipe tower electrified conducting wire promotes fixture |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205666535U true CN205666535U (en) | 2016-10-26 |
Family
ID=57156412
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620543345.6U Active CN205666535U (en) | 2016-06-07 | 2016-06-07 | Transmission line steel pipe tower electrified conducting wire promotes fixture |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205666535U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108599006A (en) * | 2018-07-24 | 2018-09-28 | 国网山东省电力公司烟台供电公司 | A kind of livewire work lifting wire equipment |
CN109052250A (en) * | 2018-07-24 | 2018-12-21 | 国网山东省电力公司烟台供电公司 | Livewire work lifting wire equipment |
CN109326988A (en) * | 2018-11-22 | 2019-02-12 | 国网新疆电力有限公司阿克苏供电公司 | Linear Tower Adjustable Live Wire Lifter |
CN109873364A (en) * | 2018-04-28 | 2019-06-11 | 广东电网有限责任公司 | Transmission line of electricity profession shaft tower overhead-groundwire lifter |
CN109873359A (en) * | 2018-04-28 | 2019-06-11 | 广东电网有限责任公司 | The dedicated line lifter of concurrent |
CN110571704A (en) * | 2019-08-30 | 2019-12-13 | 贵州电网有限责任公司 | Tool and method suitable for disassembling B-phase drainage line insulator of strain tower |
CN112713546A (en) * | 2020-06-15 | 2021-04-27 | 符建波 | Lead rod loading device |
CN115149455A (en) * | 2022-05-13 | 2022-10-04 | 国网江苏省电力有限公司超高压分公司 | Tool and method for replacing tension insulator of extra-high voltage line |
-
2016
- 2016-06-07 CN CN201620543345.6U patent/CN205666535U/en active Active
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109873364A (en) * | 2018-04-28 | 2019-06-11 | 广东电网有限责任公司 | Transmission line of electricity profession shaft tower overhead-groundwire lifter |
CN109873359A (en) * | 2018-04-28 | 2019-06-11 | 广东电网有限责任公司 | The dedicated line lifter of concurrent |
CN109873359B (en) * | 2018-04-28 | 2024-10-01 | 广东电网有限责任公司 | Special wire lifter for concrete electric pole |
CN109873364B (en) * | 2018-04-28 | 2024-10-01 | 广东电网有限责任公司 | Air ground wire lifter for professional pole tower of power transmission line |
CN108599006A (en) * | 2018-07-24 | 2018-09-28 | 国网山东省电力公司烟台供电公司 | A kind of livewire work lifting wire equipment |
CN109052250A (en) * | 2018-07-24 | 2018-12-21 | 国网山东省电力公司烟台供电公司 | Livewire work lifting wire equipment |
CN109326988A (en) * | 2018-11-22 | 2019-02-12 | 国网新疆电力有限公司阿克苏供电公司 | Linear Tower Adjustable Live Wire Lifter |
CN110571704A (en) * | 2019-08-30 | 2019-12-13 | 贵州电网有限责任公司 | Tool and method suitable for disassembling B-phase drainage line insulator of strain tower |
CN112713546A (en) * | 2020-06-15 | 2021-04-27 | 符建波 | Lead rod loading device |
CN115149455A (en) * | 2022-05-13 | 2022-10-04 | 国网江苏省电力有限公司超高压分公司 | Tool and method for replacing tension insulator of extra-high voltage line |
CN115149455B (en) * | 2022-05-13 | 2024-10-01 | 国网江苏省电力有限公司超高压分公司 | Tool and method for replacing tension insulator of extra-high voltage line |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205666535U (en) | Transmission line steel pipe tower electrified conducting wire promotes fixture | |
CN107508192B (en) | An adjustable wire inspection pulley | |
CN105923457A (en) | Wire coil paying-off device | |
CN203747299U (en) | A detachable dual-purpose airfoil fixture | |
CN203871745U (en) | Double-hoisting-point rod head fixture for live changing of linear insulator on steel pipe pole of 220kV line | |
CN111697487B (en) | Pressure-measurable live replacement device for double insulator strings and operation method | |
CN103510739A (en) | Multifunctional combinatorial insulation cross arm | |
CN204053905U (en) | Electrified fastening device clamp erecting tools | |
CN204205395U (en) | Cross-arm bracket | |
CN201484214U (en) | Universal airfoil fixture for live replacement of single-strand insulators | |
CN105846356A (en) | Ground wire lifting fixture of steel tube tower for power transmission line | |
CN203205770U (en) | V-shaped pull-bar clamp for live replacement of great tensioned strain insulator | |
CN202050215U (en) | Current-shunt wire clip | |
CN202622631U (en) | Grounding wire hardware fitting bolt fastening wrench | |
CN205666534U (en) | Transmission line steel pipe tower ground wire promotes fixture | |
CN204205402U (en) | UHVDC Transmission Lines changes tangent tower wire clamp tool | |
CN204131004U (en) | Four loop straight line steel tube tower circle cross-arm jigs | |
CN203871746U (en) | Rod head fixture used for live change of linear insulator on steel pipe pole of 66kV line | |
CN104201611B (en) | UHVDC Transmission Lines change tangent tower wire clamp tool | |
CN103715628B (en) | Clamp for charged replacement of tangent tower insulators | |
CN208401501U (en) | Novel adjustable cable stationary fixture | |
CN203707674U (en) | Special tool for electrified adjustment of distance between double-bundled sub-conductor | |
CN203531492U (en) | Multifunctional combined insulating cross arm | |
CN103928867A (en) | 220kV line steel pipe rod live replacement linear insulator used double suspension point rod head fixture | |
CN204035842U (en) | A kind of fixture for track return cable heat release weldering soldering set |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |