CN205619323U - Rubbish combustion processing device - Google Patents
Rubbish combustion processing device Download PDFInfo
- Publication number
- CN205619323U CN205619323U CN201620218719.7U CN201620218719U CN205619323U CN 205619323 U CN205619323 U CN 205619323U CN 201620218719 U CN201620218719 U CN 201620218719U CN 205619323 U CN205619323 U CN 205619323U
- Authority
- CN
- China
- Prior art keywords
- chamber
- casing
- pipe
- movable plate
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E20/00—Combustion technologies with mitigation potential
- Y02E20/30—Technologies for a more efficient combustion or heat usage
Abstract
The utility model discloses a rubbish combustion processing device, including shell body, interior casing, box, first baffle, second baffle, blow off pipe, first movable plate, second movable plate, a power pack, the 2nd power pack, connecting pipe, the inboard of shell body is placed in to interior casing, and the inside of interior casing is equipped with the burning chamber, the box is installed on the shell body, has the appearance chamber in the box, is equipped with the feed inlet on the roof of box, is equipped with the discharge gate on the diapire of box, the discharge gate and the chamber intercommunication that burns, first baffle, second baffle are all placed in to hold the intracavity and will hold the chamber and are divided into in proper order and firstly hold that chamber, second hold the chamber, the third holds the chamber, first chamber and the third of holding holds the chamber and is linked together, and above -mentioned feed inlet, discharge gate all hold the chamber with the second and communicate, be equipped with the drain on the first baffle, the box outside is arranged in to the first end of blow off pipe, and the second end of blow off pipe passes the box and is connected with the drain. The utility model discloses refuse treatment is effectual, and is efficient, and exhaust -gas treatment is effectual.
Description
Technical field
This utility model relates to technical field of waste treatment, particularly relates to a kind of garbage burning treatment installation.
Background technology
Garbage disposal problem is always whole world focus of attention, and traditional trash processing way mainly has landfill
With burning two ways, use filling type to process rubbish and can cause the waste of a large amount of land resource, meanwhile, also
The pollution of environment, present this mode can be caused the most gradually to be eliminated;The mode burned is used to carry out at rubbish
Reason, can not only recycle and burn the heat produced, additionally it is possible to the contaminative cigarette produced in burning process
Gas carries out filtration treatment, it is to avoid pollute environment and air.
Present incineration firing effect is not ideal enough, is further improved.
Utility model content
In order to solve technical problem present in background technology, the utility model proposes at a kind of incineration firing
Reason device, effective.
A kind of garbage burning treatment installation, including shell body, inner housing, casing, the first dividing plate, second every
Plate, blow-off pipe, the first movable plate, the second movable plate, the first power unit, the second power unit, connection
Pipe;
Inner housing is placed in the inner side of shell body, and the inside of inner housing is provided with combustion chamber;
Casing is arranged on shell body, has cavity volume in casing, and the roof of casing is provided with charging aperture, casing
Diapire be provided with discharging opening, discharging opening connects with combustion chamber;Charging aperture projection position on the diapire of casing
Outside in discharging opening;
In first dividing plate, second partition are placed in cavity volume and cavity volume is divided into successively the first receiving chamber, the second appearance
Receive chamber, the 3rd accommodate chamber;First accommodates chamber is connected with the 3rd receiving chamber, and above-mentioned charging aperture, discharging opening are equal
Accommodate chamber with second to connect;
First dividing plate is provided with sewage draining exit;
First end of blow-off pipe is placed in outside casing, and the second end of blow-off pipe is connected through casing with sewage draining exit;
The upper surface of the diapire of casing tilts to sewage draining exit direction gradually downward from discharging opening;
The upper surface of the diapire of casing is provided with chute, and chute is arranged to sewage draining exit direction from discharging opening;
First movable plate, the second movable plate are placed in the second receiving intracavity, the first movable plate, the second movable plate
All may move with chute and be connected;The bottom of the first movable plate is provided with multiple breach, and multiple breach are sliding along being perpendicular to
The length direction of groove is arranged;
First power unit moves for driving the first movable plate;
Second power unit moves for driving the second movable plate;
First end of connecting tube connects with combustion chamber, and the second end of connecting tube and the 3rd accommodates chamber connection.
Preferably, rotor plate, the 3rd power unit are also included;
Rotor plate is placed in combustion chamber, and the first end of rotor plate is hinged with the roof of inner housing, the of rotor plate
Two ends are free end;
3rd power unit is used for driving rotor plate to rotate to drive rotor plate close or open discharging opening.
Preferably, also include that the first valve, the first valve are arranged in connecting tube.
Preferably, the first demarcation strip, ring baffle, exhaustor, air exhauster are also included;
First demarcation strip is placed in combustion chamber, and the edge of the first demarcation strip is connected with the sidewall of inner housing, and first
Demarcation strip is provided with the first through hole;
First end of baffle plate and the first through hole connect, and the second end of baffle plate downwardly extends;
The sidewall of inner housing is provided with steam vent, and steam vent is placed in the lower section of the first demarcation strip;
First end of exhaustor is connected with steam vent, and the second end of exhaustor is placed in the outside of shell body;
Air exhauster is arranged on exhaustor.
Preferably, water tank, the second demarcation strip, multiple water pipe are also included;
The sidewall of water tank is provided with venthole;
Second end of exhaustor is placed in water tank;
Second demarcation strip is placed in the lower section of the second end of exhaustor in being placed in water tank, the second demarcation strip is placed in out
The top of pore, the second demarcation strip is provided with multiple second through hole;
Multiple water pipes are placed in the lower section of the second demarcation strip in being placed in water tank, multiple water pipes lead to multiple second
Hole one_to_one corresponding is arranged, and the first end of water pipe and the second through hole connect, and the second end of water pipe downwardly extends, water
Second end of pipe is placed in the lower section of venthole.
Preferably, also including drain pipe, the first end of drain pipe is placed in the lower section of venthole in being placed in water tank,
First end of drain pipe is placed in the top of the second end of water pipe, and the second end of drain pipe is placed in the outside of water tank.
The sidewall of water tank is provided with impurity discharging port, and impurity discharging port is placed in the lower section of the second end of water pipe;
Also include that the second valve, the second valve are arranged on impurity discharging port.
Preferably, surrounding receiving space between shell body and inner housing, shell body is provided with water inlet, water outlet
Mouthful, water inlet, outlet all connect with receiving space.
Preferably, also including multiple connection post, be equipped with heat exchange chamber in each connection post, multiple connection posts are equal
Being placed in receiving space, the first end connecting post is connected with shell body, connects the second end of post through inner housing
Being connected with combustion chamber, each heat exchange chamber connected in post all connects with combustion chamber.
In this utility model, in combustion chamber, first lay material slag, then on material slag, place combustible, then
Rubbish is put into combustion chamber burn, owing to inner housing is the space of a relative closure, by temperature
And inner housing rubbish is divided into drying layer, dry distilling layer, reducing zone, oxide layer by the control of oxygen content.It is positioned at
The temperature in oxide layer region is up to 800-1000 degree Celsius, and rubbish can burn completely.
By combustible garbage within charging aperture adds casing, the first power unit is utilized to promote the first movable plate
Mobile, utilize the second power unit to promote the second movable plate to move, utilize the first movable plate, the second movable plate
Pressing waste, extrudes the sewage in rubbish, and owing to the diapire of casing is skewed setting, sewage is through the
Breach, sewage draining exit on one movable plate enter blow-off pipe and discharge.Repeatedly extrude several times, then, adjust first
Movable plate, the position of the second movable plate, allow rubbish in discharging opening enters combustion chamber.
By above-mentioned steps, effectively sewage in rubbish is discharged in advance, improve combustion efficiency, improve burning
Efficiency.
In combustion, the temperature in combustion chamber is relatively big, and high-temperature gas enters the first receiving through connecting tube
Chamber, the 3rd receiving intracavity, heat the second rubbish accommodating intracavity, be dried, remove the water in rubbish
Point, ready for next step burning, improve the efficiency of whole combustion process, improve combustion efficiency.
Utilize the 3rd power unit to drive rotor plate to rotate, constantly close, open discharging opening, it is to avoid rubbish
Blocking, improves discharging effect.
After rubbish enters combustion chamber, along the first demarcation strip through the first downward landing of through hole;It is in oxide layer position
The rubbish put can burn completely, produces the waste gas of the less pollutions such as carbon dioxide.Due to the first demarcation strip,
Surrounding a space between baffle plate and the sidewall of inner housing, these waste gas can be discharged through exhaustor;Steam vent
It is generally in the position of oxide layer.Increase by the first demarcation strip, baffle plate is easy to less pollution and incombustible
Gas separate with polluting the most serious and inflammable gas, it is simple to be respectively processed.
Waste gas, in exhaustor enters water tank, then, respectively enters multiple water pipe by multiple second through holes
In, then discharge, utilize the water in water tank that waste gas is entered cooling, dedusting, the wet clean, low of generation
Body is discharged from venthole, and impurity deposits in water tank.
Increase multiple water pipe, improve the contact area of waste gas and water, improve cooling, the effect of dedusting.
Increasing drain pipe, limit the water level in water tank, when the water yield is excessive, water can be discharged from drain pipe.Increase
Add drain pipe, the effective water yield limited in water tank, it is to avoid excessive or too small, in thus avoiding water pipe
The foreign material of deposition in gas impact water tank, it is to avoid water is stired and make muddy, improves purification, the effect of dedusting.Control water
The spacing between foreign material is deposited in second end of pipe and water tank.
When carrying out incineration firing, needing higher temperature, temperature reaches 800-1000 degree Celsius, therefore, needs
Shell body, inner housing are lowered the temperature.Add water within accommodating cavity space from water inlet, utilize water to shell
Body, inner housing are lowered the temperature, and increase the service life, and the hot water of generation can separately use it for anything else, and save resource,
Energy utilization rate is high.
Heat in combustion chamber also can enter in heat exchange chamber, utilizes water to lower the temperature to connecting post, expands fall
Temperature area, improves cooling-down effect.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
It should be noted that in the case of not conflicting, the embodiment in the application and the feature in embodiment
Combination that can be mutual;Below with reference to the accompanying drawings and in conjunction with the embodiments to this utility model elaborate.
With reference to Fig. 1:
A kind of garbage burning treatment installation that the utility model proposes, including shell body 1, inner housing 2, casing
3, the first dividing plate 4, second partition 5, blow-off pipe the 6, first movable plate the 7, second movable plate 8, first move
Power unit the 9, second power unit 10, connecting tube 11, rotor plate the 20, the 3rd power unit the 21, first valve
Door the 22, first demarcation strip 23, ring baffle 24, exhaustor 25, water tank the 28, second demarcation strip 29, many
Individual water pipe 30, drain pipe the 33, second valve 35, multiple connection post 39, air exhauster 41.
Inner housing 2 is placed in the inner side of shell body 1, and the inside of inner housing 2 is provided with combustion chamber 12.
Casing 3 is arranged on shell body 1, has cavity volume in casing 3, and the roof of casing 3 is provided with charging
Mouth 13, the diapire of casing 3 is provided with discharging opening 14, and discharging opening 14 connects with combustion chamber 12;Charging aperture 13
Projection on the diapire of casing 3 is positioned at the outside of discharging opening 14, it is to avoid rubbish is directly entered discharging opening 14
In.
First dividing plate 4, second partition 5 be placed in cavity volume and cavity volume be divided into successively the first receiving chamber 15,
Second accommodates chamber the 16, the 3rd accommodates chamber 17;First accommodates chamber 15 is connected with the 3rd receiving chamber 17, above-mentioned
Charging aperture 13, discharging opening 14 all accommodate chamber 16 with second and connect.
First dividing plate 4 is provided with sewage draining exit 18;First end of blow-off pipe 6 is placed in outside casing 3, blow-off pipe
Second end of 6 is connected through casing 3 with sewage draining exit 18.
The upper surface of the diapire of casing 3 tilts to sewage draining exit 18 direction gradually downward from discharging opening 14;It is easy to
Drainage flow, it is to avoid sewage enters discharging opening 14.
The upper surface of the diapire of casing 3 is provided with chute, and chute is arranged to sewage draining exit 18 direction from discharging opening 14.
First movable plate the 7, second movable plate 8 is placed in the second receiving chamber 16, the first movable plate 7,
Two movable plates 8 are all removable with chute to be connected;The bottom of the first movable plate 7 is provided with multiple breach 19, multiple
Breach 19 is arranged along the length direction being perpendicular to chute.
First power unit 9 moves for driving the first movable plate 7;Second power unit 10 is for driving the
Two movable plates 8 move.
First end of connecting tube 11 connects with combustion chamber 12, and the second end of connecting tube 11 and the 3rd accommodates chamber 17
Connection.
In the present embodiment, rotor plate 20 is placed in combustion chamber 12, the first end of rotor plate 20 and inner housing 2
Roof hinged, the second end of rotor plate 20 is free end;3rd power unit 21 is used for driving rotor plate
20 rotate to drive rotor plate 20 to close or open discharging opening 14;Avoid rubbish to block, improve rubbish and move
Efficiency.
In the present embodiment, the first valve 22 is arranged in connecting tube 11;It is right to choose whether as required
Rubbish in casing 3 preheats.
In the present embodiment, the first demarcation strip 23 is placed in combustion chamber 12, and the edge of the first demarcation strip 23 is with interior
The sidewall of housing 2 connects, and the first demarcation strip 23 is provided with the first through hole 26.
First end and first through hole 26 of baffle plate 24 connect, and the second end of baffle plate 24 downwardly extends.
The sidewall of inner housing 2 is provided with steam vent 27, and steam vent 27 is placed in the lower section of the first demarcation strip 23.
First end of exhaustor 25 is connected with steam vent 27;Air exhauster 41 is arranged on exhaustor 25.
In the present embodiment, water tank 28 is placed in the outside of shell body 1, and the sidewall of water tank 28 is provided with venthole
31;Second end of exhaustor 25 is placed in water tank 28.
Second demarcation strip 29 is placed in the lower section of the second end of exhaustor 25 in being placed in water tank 28, second separates
Plate 29 is placed in the top of venthole 31, and the second demarcation strip 29 is provided with multiple second through hole 32.
Multiple water pipes 30 are placed in the lower section of the second demarcation strip 29, multiple water pipes 30 in being placed in water tank 28
Arranging with multiple second through hole 32 one_to_one corresponding, the first end and second through hole 32 of water pipe 30 connect, water pipe
Second end of 30 downwardly extends, and the second end of water pipe 30 is placed in the lower section of venthole 31.
In the present embodiment, the first end of drain pipe 33 is placed in the lower section of venthole 31 in being placed in water tank 28,
First end of drain pipe 33 is placed in the top of the second end of water pipe 30, and the second end of drain pipe 33 is placed in water tank
The outside of 28.
In the present embodiment, the sidewall of water tank 28 is provided with impurity discharging port 34, and impurity discharging port 34 is placed in the of water pipe 30
The lower section of two ends;Second valve 35 is arranged on impurity discharging port 34;It is easy to discharge foreign material.
In the present embodiment, surrounding receiving space 36 between shell body 1 and inner housing 2, shell body 1 is provided with
Water inlet 37, outlet 38, water inlet 37, outlet 38 all connect with receiving space 36.
In the present embodiment, being equipped with heat exchange chamber 40 in each connection post 39, multiple connection posts 39 are placed in holding
Receiving in space 36, the first end connecting post 39 is connected with shell body 1, connects the second end of post 39 through interior
Housing 2 is connected with combustion chamber 12, and each heat exchange chamber 40 connected in post 39 all connects with combustion chamber 12.
First in combustion chamber 12, lay material slag, then place combustible on material slag, then rubbish is put into combustion
Burn in chamber 12 and burn, owing to inner housing 2 is the space of a relative closure, by temperature and oxygen-containing
Inner housing 2 rubbish is divided into drying layer, dry distilling layer, reducing zone, oxide layer by the control of amount.It is positioned at oxide layer
The temperature in region is up to 800-1000 degree Celsius, and rubbish can burn completely.
By combustible garbage within charging aperture 13 adds casing 3, the first power unit 9 is utilized to promote first
Movable plate 7 moves, and utilizes the second power unit 10 to promote the second movable plate 8 to move, utilizes the first movable plate
7, the second movable plate 8 pressing waste, extrudes the sewage in rubbish, owing to the diapire of casing 3 is skewed
Arranging, sewage breach 19 on the first movable plate 7, sewage draining exit 18 enter blow-off pipe 6 and discharge.Repeatedly
Extruding several times, then, adjusts the position of first movable plate the 7, second movable plate 8, allows rubbish through discharging opening
14 enter in combustion chamber 12.
By above-mentioned steps, effectively sewage in rubbish is discharged in advance, improve combustion efficiency, improve burning
Efficiency.
In combustion, the temperature in combustion chamber 12 is relatively big, and high-temperature gas enters the through connecting tube 11
One accommodates chamber the 15, the 3rd accommodates in chamber 17, accommodates the rubbish in chamber 16 to second and heats, is dried,
Remove the moisture in rubbish, ready for next step burning, improve the efficiency of whole combustion process, improve
Combustion efficiency.
Utilize the 3rd power unit 21 to drive rotor plate 20 to rotate, constantly close, open discharging opening 14,
Avoid rubbish to block, improve discharging effect.
After rubbish enters combustion chamber 12, along the first demarcation strip 23 through the first downward landing of through hole 26;It is in
The rubbish of oxide layer position can burn completely, produces the waste gas of the less pollutions such as carbon dioxide.Due to
Surrounding a space between the sidewall of one demarcation strip 23, baffle plate 24 and inner housing 2, these waste gas can be through row
Trachea 25 is discharged;Steam vent 27 is generally in the position of oxide layer.Increase the first demarcation strip 23, baffle plate 24
It is easy to separate less pollution and incombustible gas with polluting the most serious and inflammable gas, it is simple to
It is respectively processed.
Waste gas is in exhaustor 25 enters water tank 28, then, is respectively enterd by multiple second through holes 32
In multiple water pipes 30, then discharge, utilize the water in water tank 28 that waste gas is entered cooling, dedusting, produce
Clean, cryogenic gas discharge from venthole 31, impurity deposits in water tank 28.
Increase multiple water pipe 30, improve the contact area of waste gas and water, improve cooling, the effect of dedusting.
Increasing drain pipe 33, limit the water level in water tank 28, when the water yield is excessive, water can be from drain pipe 33
Discharge.Increase drain pipe 33, the effective water yield limited in water tank 28, it is to avoid excessive or too small, thus
The foreign material deposited in avoiding the gas impact water tank 28 in water pipe 30, it is to avoid water is stired and make muddy, raising purification,
The effect of dedusting.Control the spacing between the second end of water pipe 30 and water tank 28 interior deposition foreign material.
When carrying out incineration firing, needing higher temperature, temperature reaches 800-1000 degree Celsius, therefore, needs
Shell body 1, inner housing 2 are lowered the temperature.Add water within accommodating cavity space from water inlet 37, utilize water
Lowering the temperature shell body 1, inner housing 2, increase the service life, the hot water of generation can separately use it for anything else, joint
Resource-saving, energy utilization rate is high.
Heat in combustion chamber 12 also can enter in heat exchange chamber 40, utilizes water to lower the temperature to connecting post 39,
Expand cooling area, improve cooling-down effect.
The above, only this utility model preferably detailed description of the invention, but protection model of the present utility model
Enclose and be not limited thereto, the technology model that any those familiar with the art discloses at this utility model
In enclosing, conceive in addition equivalent or change according to the technical solution of the utility model and utility model thereof, all
Should contain within protection domain of the present utility model.
Claims (9)
1. a garbage burning treatment installation, it is characterised in that include shell body, inner housing, casing,
One dividing plate, second partition, blow-off pipe, the first movable plate, the second movable plate, the first power unit, second
Power unit, connecting tube;
Inner housing is placed in the inner side of shell body, and the inside of inner housing is provided with combustion chamber;
Casing is arranged on shell body, has cavity volume in casing, and the roof of casing is provided with charging aperture, casing
Diapire be provided with discharging opening, discharging opening connects with combustion chamber;Charging aperture projection position on the diapire of casing
Outside in discharging opening;
In first dividing plate, second partition are placed in cavity volume and cavity volume is divided into successively the first receiving chamber, the second appearance
Receive chamber, the 3rd accommodate chamber;First accommodates chamber is connected with the 3rd receiving chamber, and above-mentioned charging aperture, discharging opening are equal
Accommodate chamber with second to connect;
First dividing plate is provided with sewage draining exit;
First end of blow-off pipe is placed in outside casing, and the second end of blow-off pipe is connected through casing with sewage draining exit;
The upper surface of the diapire of casing tilts to sewage draining exit direction gradually downward from discharging opening;
The upper surface of the diapire of casing is provided with chute, and chute is arranged to sewage draining exit direction from discharging opening;
First movable plate, the second movable plate are placed in the second receiving intracavity, the first movable plate, the second movable plate
All may move with chute and be connected;The bottom of the first movable plate is provided with multiple breach, and multiple breach are sliding along being perpendicular to
The length direction of groove is arranged;
First power unit moves for driving the first movable plate;
Second power unit moves for driving the second movable plate;
First end of connecting tube connects with combustion chamber, and the second end of connecting tube and the 3rd accommodates chamber connection.
Garbage burning treatment installation the most according to claim 1, it is characterised in that also include rotor plate,
3rd power unit;
Rotor plate is placed in combustion chamber, and the first end of rotor plate is hinged with the roof of inner housing, the of rotor plate
Two ends are free end;
3rd power unit is used for driving rotor plate to rotate to drive rotor plate close or open discharging opening.
Garbage burning treatment installation the most according to claim 1, it is characterised in that also include the first valve
Door, the first valve is arranged in connecting tube.
Garbage burning treatment installation the most according to claim 1, it is characterised in that also include first point
Dividing plate, ring baffle, exhaustor, air exhauster;
First demarcation strip is placed in combustion chamber, and the edge of the first demarcation strip is connected with the sidewall of inner housing, and first
Demarcation strip is provided with the first through hole;
First end of baffle plate and the first through hole connect, and the second end of baffle plate downwardly extends;
The sidewall of inner housing is provided with steam vent, and steam vent is placed in the lower section of the first demarcation strip;
First end of exhaustor is connected with steam vent, and the second end of exhaustor is placed in the outside of shell body;
Air exhauster is arranged on exhaustor.
Garbage burning treatment installation the most according to claim 4, it is characterised in that also include water tank,
Second demarcation strip, multiple water pipe;
The sidewall of water tank is provided with venthole;
Second end of exhaustor is placed in water tank;
Second demarcation strip is placed in the lower section of the second end of exhaustor in being placed in water tank, the second demarcation strip is placed in out
The top of pore, the second demarcation strip is provided with multiple second through hole;
Multiple water pipes are placed in the lower section of the second demarcation strip in being placed in water tank, multiple water pipes lead to multiple second
Hole one_to_one corresponding is arranged, and the first end of water pipe and the second through hole connect, and the second end of water pipe downwardly extends, water
Second end of pipe is placed in the lower section of venthole.
Garbage burning treatment installation the most according to claim 5, it is characterised in that also include drain pipe,
First end of drain pipe is placed in the lower section of venthole in being placed in water tank, the first end of drain pipe is placed in water pipe
The top of the second end, the second end of drain pipe is placed in the outside of water tank.
Garbage burning treatment installation the most according to claim 6, it is characterised in that on the sidewall of water tank
Being provided with impurity discharging port, impurity discharging port is placed in the lower section of the second end of water pipe;
Also include that the second valve, the second valve are arranged on impurity discharging port.
Garbage burning treatment installation the most according to claim 1, it is characterised in that shell body and inner shell
Surround between body receiving space, shell body is provided with water inlet, outlet, water inlet, outlet all with appearance
Receive space connection.
Garbage burning treatment installation the most according to claim 8, it is characterised in that also include multiple company
Connecing post, be equipped with heat exchange chamber in each connection post, multiple connection posts are placed in accommodating in space, connect post
First end is connected with shell body, and the second end connecting post is connected through inner housing with combustion chamber, in each connection post
Heat exchange chamber all connect with combustion chamber.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620218719.7U CN205619323U (en) | 2016-03-21 | 2016-03-21 | Rubbish combustion processing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620218719.7U CN205619323U (en) | 2016-03-21 | 2016-03-21 | Rubbish combustion processing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205619323U true CN205619323U (en) | 2016-10-05 |
Family
ID=57031233
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620218719.7U Expired - Fee Related CN205619323U (en) | 2016-03-21 | 2016-03-21 | Rubbish combustion processing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205619323U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105698181A (en) * | 2016-03-21 | 2016-06-22 | 安徽未名生物环保有限公司 | Trash burning treatment device |
CN106338070A (en) * | 2016-11-18 | 2017-01-18 | 无锡市智锋金属科技有限公司 | Spiral refuse drying incinerator |
-
2016
- 2016-03-21 CN CN201620218719.7U patent/CN205619323U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105698181A (en) * | 2016-03-21 | 2016-06-22 | 安徽未名生物环保有限公司 | Trash burning treatment device |
CN105698181B (en) * | 2016-03-21 | 2018-07-20 | 安徽未名生物环保有限公司 | A kind of garbage burning treatment installation |
CN106338070A (en) * | 2016-11-18 | 2017-01-18 | 无锡市智锋金属科技有限公司 | Spiral refuse drying incinerator |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205619323U (en) | Rubbish combustion processing device | |
CN105716082A (en) | Device for treating household garbage | |
CN208019124U (en) | A kind of system of cement kiln cooperative disposal domestic waste | |
CN107477586A (en) | A kind of low temperature pyrolyzer autoreaction garbage disposal furnace | |
CN105698181B (en) | A kind of garbage burning treatment installation | |
CN207741115U (en) | A kind of intelligent environment protection melts bucket without discharge rubbish | |
CN205619321U (en) | A device for waste incineration | |
CN205619301U (en) | Device of rubbish burning can effectively carry out | |
CN205619328U (en) | A device for domestic waste handles | |
CN101435579A (en) | Medical rubbish vehicle-mounted gas smokeless furnace of cleaning environment protection burnable waste battery | |
KR101334880B1 (en) | Waste disposal system and exhaust gas to prevent the device used in the system | |
CN205606578U (en) | Garbage disposal furnace | |
CN205619302U (en) | Rubbish burner convenient to handle waste gas | |
CN205619303U (en) | A device for being directed at domestic waste handles | |
CN205619317U (en) | A device for rubbish burning | |
CN205606582U (en) | Garbage burning device | |
CN109882839B (en) | Biomass particle combustion furnace capable of using wet raw materials | |
CN205619298U (en) | Refuse treatment plant | |
CN109882835B (en) | Feeding mechanism in biomass particle combustion furnace | |
CN103436293B (en) | Multifunctional sludge gasification and combustion device | |
CN209857071U (en) | Novel garbage incinerator | |
CN105674291A (en) | Device for domestic waste treatment | |
CN205606558U (en) | Be convenient for carry out combustion processing equipment to rubbish | |
KR101509102B1 (en) | Explosion prevention measures are provided Pyrolysis system | |
CN211204032U (en) | Turn over and burn clean burning stove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161005 Termination date: 20200321 |