CN205591628U - A iron tower for high tension transmission line - Google Patents

A iron tower for high tension transmission line Download PDF

Info

Publication number
CN205591628U
CN205591628U CN201620401398.4U CN201620401398U CN205591628U CN 205591628 U CN205591628 U CN 205591628U CN 201620401398 U CN201620401398 U CN 201620401398U CN 205591628 U CN205591628 U CN 205591628U
Authority
CN
China
Prior art keywords
main tower
tower
main
steel wire
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620401398.4U
Other languages
Chinese (zh)
Inventor
马国锋
李志杰
刘冠军
吴晓燕
李善龙
张益明
刁建军
胡少波
吕会松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Longkou Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
Longkou Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Longkou Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical Longkou Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN201620401398.4U priority Critical patent/CN205591628U/en
Application granted granted Critical
Publication of CN205591628U publication Critical patent/CN205591628U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

本实用新型公开了一种用于高压输电线路的铁塔,包括底座及设置在所述的底座上方的第一主塔和第二主塔,在所述的第一主塔和第二主塔上分别设置有横梁,所述的横梁为沿所述的第一主塔和所述的第二主塔高度方向设置的至少2个,所述的横梁一端分别铰接在所述的第一主塔和第二主塔上,所述的横梁另一端悬空形成自由端,在所述的横梁上方的第一主塔和第二主塔上分别设置有转轴,在所述的转轴上设置有棘轮,在所述的第一主塔和所述的第二主塔上分别设置有与所述的棘轮相配合的棘爪,本实用新型通过采用将横梁铰接在第一主塔和第二主塔上,能够根据需要调整横梁自由端的位置,从而使横梁保持恒定角度,从而能够有效保证导线处于恒定位置。

The utility model discloses an iron tower used for high-voltage transmission lines, which comprises a base and a first main tower and a second main tower arranged above the base, and on the first main tower and the second main tower Crossbeams are respectively provided, and the crossbeams are at least 2 arranged along the height direction of the first main tower and the second main tower, and one end of the crossbeams is respectively hinged on the first main tower and the second main tower. On the second main tower, the other end of the crossbeam is suspended to form a free end, and a rotating shaft is respectively arranged on the first main tower and the second main tower above the crossbeam, and a ratchet is arranged on the rotating shaft. The first main tower and the second main tower are respectively provided with ratchets matched with the ratchet. The utility model adopts the method of hinged beams on the first main tower and the second main tower, The position of the free end of the crossbeam can be adjusted as required, so that the crossbeam maintains a constant angle, thereby effectively ensuring that the wire is at a constant position.

Description

一种用于高压输电线路的铁塔 An iron tower for high-voltage transmission lines

技术领域 technical field

本实用新型涉及一种用于高压输电线路的铁塔。 The utility model relates to an iron tower used for high-voltage transmission lines.

背景技术 Background technique

高压输电技术能够实现电能的远距离输送,具有可靠性高、灵活性强和经济性好的特点。现有的高压用铁塔结构单一,电气间隙不方便进行控制。 High-voltage transmission technology can realize long-distance transmission of electric energy, and has the characteristics of high reliability, strong flexibility and good economy. The existing high-voltage iron tower has a single structure, and the electrical clearance is inconvenient to control.

发明内容 Contents of the invention

本实用新型的目的在于提供一种用于高压输电线路的铁塔,能够改善现有技术存在的问题,通过采用将横梁铰接在第一主塔和第二主塔上,能够根据需要调整横梁自由端的位置,从而使横梁保持恒定角度,从而能够有效保证导线处于恒定位置。 The purpose of this utility model is to provide an iron tower for high-voltage transmission lines, which can improve the problems existing in the prior art, and can adjust the free end of the beam according to the needs by hinged beams on the first main tower and the second main tower. Position, so that the beam maintains a constant angle, which can effectively ensure that the wire is in a constant position.

本实用新型通过以下技术方案实现: The utility model is realized through the following technical solutions:

一种用于高压输电线路的铁塔,包括底座及设置在所述的底座上方的第一主塔和第二主塔,在所述的第一主塔和第二主塔上分别设置有横梁,所述的横梁为沿所述的第一主塔和所述的第二主塔高度方向设置的至少2个,所述的横梁一端分别铰接在所述的第一主塔和第二主塔上,所述的横梁另一端悬空形成自由端,在所述的横梁上方的第一主塔和第二主塔上分别设置有转轴,在所述的转轴上设置有棘轮,在所述的第一主塔和所述的第二主塔上分别设置有与所述的棘轮相配合的棘爪,在所述的转轴上设置有绕线轮,在所述的绕线轮上设置有钢丝,所述的钢丝一端缠绕在所述的绕线轮上,所述的钢丝另一端固定连接在所述的横梁的自由端上,在所述的第一主塔和所述的第二主塔上分别设置有驱动电机,在所述的驱动电机上设置有驱动齿轮,所述的驱动齿轮与设置在所述的转轴上的从动齿轮相啮合,在所述的第一主塔和所述的第二主塔相向的端面上设置有高强弹簧,所述的高强弹簧一端固定连接在所述的第一主塔上,所述的高强弹簧另一端固定连接在所述的第二主塔上,在所述的第一主塔与其横梁的下端面之间设置有高强弹簧,在所述的第二主塔与其横梁下端面之间设置有高强弹簧。 An iron tower for high-voltage transmission lines, comprising a base and a first main tower and a second main tower arranged above the base, beams are respectively arranged on the first main tower and the second main tower, The crossbeams are at least 2 arranged along the height direction of the first main tower and the second main tower, and one end of the crossbeams is respectively hinged on the first main tower and the second main tower , the other end of the crossbeam is suspended to form a free end, a rotating shaft is respectively arranged on the first main tower and the second main tower above the crossbeam, a ratchet is arranged on the rotating shaft, and a ratchet is arranged on the first main tower above the crossbeam. The main tower and the second main tower are respectively provided with ratchets matched with the ratchet, a winding wheel is arranged on the rotating shaft, and a steel wire is arranged on the winding wheel, so One end of the steel wire is wound on the reel, and the other end of the steel wire is fixedly connected to the free end of the beam, respectively on the first main tower and the second main tower. A driving motor is provided, and a driving gear is arranged on the driving motor, and the driving gear meshes with the driven gear arranged on the rotating shaft. High-strength springs are arranged on the opposite end faces of the two main towers, one end of the high-strength spring is fixedly connected to the first main tower, and the other end of the high-strength spring is fixedly connected to the second main tower. A high-strength spring is arranged between the first main tower and the lower end surface of the beam, and a high-strength spring is arranged between the second main tower and the lower end surface of the beam.

进一步的,为更好地实现本实用新型,在所述的第一主塔和所述的第二主塔下端分别设置有支座,在所述的底座上端面上设置有2个定位槽,2个所述的定位槽之间设置有定位柱,两个所述的支座分别位于2个所述的定位槽内侧,在2个所述的定位槽之间设置有高强弹簧,所述的高强弹簧贯穿所述的定位柱,所述的高强弹簧两端分别固定连接在两个所述的支座相向的端面上。 Further, in order to better realize the utility model, supports are respectively provided at the lower ends of the first main tower and the second main tower, and two positioning grooves are provided on the upper end surface of the base, A positioning post is arranged between the two positioning slots, the two supports are respectively located inside the two positioning slots, a high-strength spring is arranged between the two positioning slots, and the The high-strength spring runs through the positioning column, and the two ends of the high-strength spring are respectively fixedly connected to the opposite end surfaces of the two supports.

进一步的,为更好地实现本实用新型,在所述的定位槽远离所述的定位柱一侧端面与所述的支座之间分别设置有高强弹簧。 Further, in order to better realize the utility model, high-strength springs are respectively arranged between the end surface of the positioning groove on the side away from the positioning column and the support.

进一步的,为更好地实现本实用新型,在所述的定位柱上方设置有端盖。 Further, in order to better realize the utility model, an end cover is arranged above the positioning column.

进一步的,为更好地实现本实用新型,在所述的底座上设置有2个对称设置的通孔,在所述的通孔内设置有钢丝绳,所述的钢丝绳远离所述的底座一端分别固定连接在所述的第一主塔和第二主塔远离横梁一侧端面上。 Further, in order to better realize the utility model, two symmetrically arranged through holes are arranged on the base, and steel wire ropes are arranged in the through holes, and the ends of the steel wire ropes away from the base are respectively It is fixedly connected to the end faces of the first main tower and the second main tower on the side away from the beam.

进一步的,为更好地实现本实用新型,在所述的第一主塔和所述的第二主塔远离所述的横梁一侧端面上端设置有外置横梁,在所述的外置横梁上设置有固定轴,在所述的固定轴上设置有滑轮,在所述的底座上设置有升降台,在所述的升降台上方设置有钢丝拉索,所述的钢丝拉索上端挂接在所述的滑轮上。 Further, in order to better realize the utility model, an external beam is arranged on the end face of the first main tower and the second main tower on the side away from the beam, and the external beam A fixed shaft is arranged on the fixed shaft, a pulley is arranged on the fixed shaft, a lifting platform is arranged on the base, a steel cable is arranged above the lifting platform, and the upper end of the steel cable is hooked on said pulley.

进一步的,为更好地实现本实用新型,在所述的底座上端面上设置有绕线轮,所述的钢丝拉索一端缠绕在该绕线轮上,在所述的底座的上端面上设置有用于驱动所述的绕线轮转动的电机。 Further, in order to better realize the utility model, a winding wheel is arranged on the upper end surface of the base, and one end of the steel wire cable is wound on the winding wheel, and on the upper end surface of the base A motor for driving the reel to rotate is provided.

进一步的,为更好地实现本实用新型,在所述的第一主塔和所述的第二主塔相向的端面上设置有连接梁。 Furthermore, in order to better realize the utility model, connecting beams are arranged on the opposite end faces of the first main tower and the second main tower.

进一步的,为更好地实现本实用新型,所述的连接梁中部向上方拱起,所述的连接梁两端分别固定连接在所述的第一主塔和所述的第二主塔上。 Further, in order to better realize the utility model, the middle part of the connecting beam is arched upwards, and the two ends of the connecting beam are respectively fixedly connected to the first main tower and the second main tower .

本实用新型与现有技术相比,具有以下有益效果: Compared with the prior art, the utility model has the following beneficial effects:

本实用新型通过采用将横梁铰接在第一主塔和第二主塔上,能够采用驱动电机调整横梁自由端的位置,同时,采用棘轮棘爪结构,能够方便实现对横梁位置的限定,避免其在高空架设线路时出现不稳定,由于在横梁与同侧的第一主塔或第二主塔之间设置有高强弹簧,使得横梁在安装固定之后,受到上方的钢丝的拉力和下方的高强弹簧的弹性力,能够有助于其保持稳定,将导线安装在横梁下方时,方便使导线之间的距离保持恒定。 The utility model can use the drive motor to adjust the position of the free end of the beam by hinged the beam on the first main tower and the second main tower. Instability occurs when the line is erected at high altitude. Since a high-strength spring is arranged between the beam and the first main tower or the second main tower on the same side, after the beam is installed and fixed, it is subjected to the tension of the steel wire above and the high-strength spring below. The elastic force helps to keep it stable and facilitates keeping the distance between the conductors constant when installing them under the beam.

附图说明 Description of drawings

为了更清楚地说明本实用新型实施例的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本实用新型的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。 In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following drawings will be briefly introduced in the embodiments. It should be understood that the following drawings only show some embodiments of the present invention. Therefore, it should not be regarded as a limitation on the scope. For those skilled in the art, other related drawings can also be obtained according to these drawings without creative work.

图1为本实用新型整体结构示意图。 Figure 1 is a schematic diagram of the overall structure of the utility model.

其中:1.第一主塔,2.第二主塔,3.底座,4.定位槽,5.定位柱,6.端盖,7.高强弹簧,8.钢丝绳,9.横梁,10.转轴,11.驱动齿轮,12.从动齿轮,13.驱动电机,14.升降台,15.外置横梁,16.滑轮,17.钢丝拉索,18.绕线轮,19.连接梁。 Among them: 1. The first main tower, 2. The second main tower, 3. Base, 4. Positioning groove, 5. Positioning column, 6. End cover, 7. High-strength spring, 8. Steel wire rope, 9. Beam, 10. Rotating shaft, 11. driving gear, 12. driven gear, 13. driving motor, 14. lifting table, 15. external beam, 16. pulley, 17. wire cable, 18. winding wheel, 19. connecting beam.

具体实施方式 detailed description

下面结合具体实施例对本实用新型进行进一步详细介绍,但本实用新型的实施方式不限于此。 The utility model will be further described in detail below in conjunction with specific examples, but the implementation of the utility model is not limited thereto.

实施例1: Example 1:

如图1所示,一种用于高压输电线路的铁塔,包括底座及设置在所述的底座上方的第一主塔1和第二主塔2,在所述的第一主塔和第二主塔上分别设置有横梁14,所述的横梁为沿所述的第一主塔和所述的第二主塔高度方向设置的至少2个,所述的横梁一端分别铰接在所述的第一主塔和第二主塔上,所述的横梁另一端悬空形成自由端,在所述的横梁上方的第一主塔和第二主塔上分别设置有转轴10,在所述的转轴上设置有棘轮,在所述的第一主塔和所述的第二主塔上分别设置有与所述的棘轮相配合的棘爪,在所述的转轴上设置有绕线轮18,在所述的绕线轮上设置有钢丝,所述的钢丝一端缠绕在所述的绕线轮上,所述的钢丝另一端固定连接在所述的横梁的自由端上,在所述的第一主塔和所述的第二主塔上分别设置有驱动电机13,在所述的驱动电机上设置有驱动齿轮11,所述的驱动齿轮与设置在所述的转轴上的从动齿轮12相啮合,在所述的第一主塔和所述的第二主塔相向的端面上设置有高强弹簧7,所述的高强弹簧一端固定连接在所述的第一主塔上,所述的高强弹簧另一端固定连接在所述的第二主塔上,在所述的第一主塔与其横梁的下端面之间设置有高强弹簧,在所述的第二主塔与其横梁下端面之间设置有高强弹簧。 As shown in Figure 1, a kind of iron tower for high-voltage transmission line, comprises base and the first main tower 1 and the second main tower 2 that are arranged on the base above, in the first main tower and the second main tower Crossbeams 14 are respectively arranged on the main tower, and the crossbeams are at least 2 arranged along the height direction of the first main tower and the second main tower, and one end of the crossbeams is respectively hinged on the first main tower. On the first main tower and the second main tower, the other end of the crossbeam is suspended to form a free end, and the first main tower and the second main tower above the crossbeam are respectively provided with a rotating shaft 10, and on the described rotating shaft A ratchet is provided, pawls matched with the ratchet are respectively provided on the first main tower and the second main tower, and a winding wheel 18 is provided on the rotating shaft. A steel wire is provided on the winding wheel, one end of the steel wire is wound on the winding wheel, and the other end of the steel wire is fixedly connected to the free end of the beam. The tower and the second main tower are respectively provided with a driving motor 13, and a driving gear 11 is arranged on the driving motor, and the driving gear meshes with the driven gear 12 arranged on the rotating shaft A high-strength spring 7 is arranged on the opposite end faces of the first main tower and the second main tower, and one end of the high-strength spring is fixedly connected to the first main tower, and the high-strength spring The other end is fixedly connected to the second main tower, a high-strength spring is arranged between the first main tower and the lower end surface of the beam, and a spring is arranged between the second main tower and the lower end surface of the beam. High strength spring.

本实施例中,将导线安装在横梁下方,启动驱动电机,使其带动驱动齿轮转动,驱动齿轮带动从动齿轮转动,从动齿轮带动转轴转动,与转轴过盈配合的绕线轮带动钢丝移动,将横梁的自由端拉伸到设定位置,在棘轮和棘爪的作用下,使得绕线轮不能倒转,在横梁下方的高强弹簧的作用下,使得横梁不能向上转动,使横梁下方的导线能够保持恒定位置。 In this embodiment, the wire is installed under the beam, and the driving motor is started to drive the driving gear to rotate, the driving gear drives the driven gear to rotate, the driven gear drives the rotating shaft to rotate, and the winding wheel with an interference fit with the rotating shaft drives the steel wire to move , Stretch the free end of the beam to the set position, under the action of the ratchet and the pawl, the winding wheel cannot be reversed, and under the action of the high-strength spring under the beam, the beam cannot be turned upward, so that the wire under the beam able to maintain a constant position.

实施例2: Example 2:

本实施例在实施例1的基础上,为了方便安装,优选地,在所述的第一主塔和所述的第二主塔下端分别设置有支座20,在所述的底座上端面上设置有2个定位槽4,2个所述的定位槽之间设置有定位柱5,两个所述的支座分别位于2个所述的定位槽内侧,在2个所述的定位槽之间设置有高强弹簧,所述的高强弹簧贯穿所述的定位柱,所述的高强弹簧两端分别固定连接在两个所述的支座相向的端面上。 In this embodiment, on the basis of Embodiment 1, in order to facilitate installation, preferably, supports 20 are respectively provided at the lower ends of the first main tower and the second main tower, and on the upper end surface of the base Two positioning slots 4 are provided, and a positioning column 5 is arranged between the two positioning slots. The two supports are respectively located inside the two positioning slots. A high-strength spring is arranged between them, the high-strength spring runs through the positioning column, and the two ends of the high-strength spring are respectively fixedly connected to the opposite end surfaces of the two supports.

通过在两个支座相向的端面之间设置高强弹簧,能够使第一主塔和第二主塔下方的支座保持相对稳定,在受到外力作用时,利用高强弹簧的弹性力作用,使两个支座保持稳定,避免由于地震等问题导致第一主塔或第二主塔产生损坏。 By arranging a high-strength spring between the opposite end faces of the two supports, the supports under the first main tower and the second main tower can be kept relatively stable. The first and second main towers are kept stable to avoid damage to the first main tower or the second main tower due to earthquakes and other problems.

本实施例中,为了进一步提高第一主塔和第二主塔的稳定性,优选地,在所述的定位槽远离所述的定位柱一侧端面与所述的支座之间分别设置有高强弹簧。 In this embodiment, in order to further improve the stability of the first main tower and the second main tower, preferably, between the end face of the positioning groove on the side away from the positioning column and the support, there are respectively High strength spring.

本实施例中,优选地,在所述的定位柱上方设置有端盖6。使端盖覆盖定位柱上方,使端盖两端与第一主塔和第二主塔相向的端面之间存在空间,从而能够避免第一主塔或第二主塔出现微小位移时碰撞端盖造成损坏。 In this embodiment, preferably, an end cover 6 is provided above the positioning column. Make the end cover cover the top of the positioning column, so that there is a space between the two ends of the end cover and the opposite end faces of the first main tower and the second main tower, so as to avoid collision with the end cover when the first main tower or the second main tower is slightly displaced cause damage.

为了使第一主塔和第二主塔保持稳定,本实施例中,优选地,在所述的底座上设置有2个对称设置的通孔,在所述的通孔内设置有钢丝绳8,所述的钢丝绳远离所述的底座一端分别固定连接在所述的第一主塔和第二主塔远离横梁一侧端面上。利用钢丝绳牵引第一主塔和第二主塔外侧,使其相对底座保持稳定。 In order to keep the first main tower and the second main tower stable, in this embodiment, preferably, two symmetrically arranged through holes are arranged on the base, and steel wire ropes 8 are arranged in the through holes, The ends of the steel wire ropes away from the base are respectively fixedly connected to the end faces of the first main tower and the second main tower on the side away from the beam. Use wire ropes to pull the outside of the first main tower and the second main tower to keep them stable relative to the base.

本实施例中,为了方便将维修人员输送到第一主塔和第二主塔上端进行维护操作,优选地,在所述的第一主塔和所述的第二主塔远离所述的横梁一侧端面上端设置有外置横梁15,在所述的外置横梁上设置有固定轴,在所述的固定轴上设置有滑轮16,在所述的底座上设置有升降台14,在所述的升降台上方设置有钢丝拉索17,所述的钢丝拉索上端挂接在所述的滑轮上。牵引钢丝拉索,使钢丝拉索带动升降台上升,从而能够方便将人员和设备提升到指定位置进行维护操作。 In this embodiment, in order to facilitate maintenance personnel to be transported to the upper ends of the first main tower and the second main tower for maintenance operations, preferably, when the first main tower and the second main tower are far away from the beam An external crossbeam 15 is arranged on the top of one end surface, a fixed shaft is arranged on the external crossbeam, a pulley 16 is arranged on the fixed shaft, and a lifting platform 14 is arranged on the base. A steel wire cable 17 is arranged above the lifting table, and the upper end of the steel wire cable is hooked on the pulley. Pull the steel wire cable, so that the steel wire cable drives the lifting platform to rise, so that the personnel and equipment can be easily lifted to the designated position for maintenance operations.

进一步优选地,本实施例中,为了方便提升升降台,在所述的底座上端面上设置有绕线轮18,所述的钢丝拉索一端缠绕在该绕线轮上,在所述的底座的上端面上设置有用于驱动所述的绕线轮转动的电机。通过电机带动绕线轮,使绕线轮缠绕钢丝拉索,使升降台移动。 Further preferably, in this embodiment, in order to facilitate the lifting of the lifting platform, a winding wheel 18 is arranged on the upper end surface of the base, and one end of the steel wire cable is wound on the winding wheel, and on the base A motor for driving the reel to rotate is arranged on the upper end surface. The winding wheel is driven by the motor, so that the winding wheel winds the steel wire cable to move the lifting platform.

为了提高整体结构的稳定性,本实施例中,优选地,在所述的第一主塔和所述的第二主塔相向的端面上设置有连接梁19。 In order to improve the stability of the overall structure, in this embodiment, preferably, a connecting beam 19 is provided on the opposite end faces of the first main tower and the second main tower.

为了提高第一主塔和第二主塔的抗震性能,本实施例中,优选地,所述的连接梁中部向上方拱起,所述的连接梁两端分别固定连接在所述的第一主塔和所述的第二主塔上。 In order to improve the seismic performance of the first main tower and the second main tower, in this embodiment, preferably, the middle part of the connecting beam is arched upwards, and the two ends of the connecting beam are fixedly connected to the first Main tower and said second main tower.

以上所述仅为本实用新型的优选实施例而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。 The above descriptions are only preferred embodiments of the utility model, and are not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present utility model shall be included in the protection scope of the present utility model.

Claims (9)

1.一种用于高压输电线路的铁塔,其特征在于:包括底座及设置在所述的底座上方的第一主塔和第二主塔,在所述的第一主塔和第二主塔上分别设置有横梁,所述的横梁为沿所述的第一主塔和所述的第二主塔高度方向设置的至少2个,所述的横梁一端分别铰接在所述的第一主塔和第二主塔上,所述的横梁另一端悬空形成自由端,在所述的横梁上方的第一主塔和第二主塔上分别设置有转轴,在所述的转轴上设置有棘轮,在所述的第一主塔和所述的第二主塔上分别设置有与所述的棘轮相配合的棘爪,在所述的转轴上设置有绕线轮,在所述的绕线轮上设置有钢丝,所述的钢丝一端缠绕在所述的绕线轮上,所述的钢丝另一端固定连接在所述的横梁的自由端上,在所述的第一主塔和所述的第二主塔上分别设置有驱动电机,在所述的驱动电机上设置有驱动齿轮,所述的驱动齿轮与设置在所述的转轴上的从动齿轮相啮合,在所述的第一主塔和所述的第二主塔相向的端面上设置有高强弹簧,所述的高强弹簧一端固定连接在所述的第一主塔上,所述的高强弹簧另一端固定连接在所述的第二主塔上,在所述的第一主塔与其横梁的下端面之间设置有高强弹簧,在所述的第二主塔与其横梁下端面之间设置有高强弹簧。 1. An iron tower for high-voltage transmission lines, characterized in that: it includes a base and a first main tower and a second main tower arranged above the base, and the first main tower and the second main tower Crossbeams are respectively arranged on the top, and the crossbeams are at least 2 arranged along the height direction of the first main tower and the second main tower, and one end of the crossbeams is respectively hinged on the first main tower and on the second main tower, the other end of the crossbeam is suspended to form a free end, a rotating shaft is respectively arranged on the first main tower and the second main tower above the crossbeam, and a ratchet is arranged on the rotating shaft, The first main tower and the second main tower are respectively provided with ratchet pawls matched with the ratchet, and a winding wheel is arranged on the rotating shaft. A steel wire is arranged on the top, one end of the steel wire is wound on the reel, and the other end of the steel wire is fixedly connected to the free end of the beam, between the first main tower and the The second main tower is respectively provided with driving motors, and a driving gear is arranged on the driving motors, and the driving gears are meshed with the driven gears arranged on the rotating shaft. A high-strength spring is arranged on the opposite end face of the tower and the second main tower, one end of the high-strength spring is fixedly connected to the first main tower, and the other end of the high-strength spring is fixedly connected to the second main tower. On the two main towers, a high-strength spring is arranged between the first main tower and the lower end surface of the beam, and a high-strength spring is arranged between the second main tower and the lower end surface of the beam. 2.根据权利要求1所述的一种用于高压输电线路的铁塔,其特征在于:在所述的第一主塔和所述的第二主塔下端分别设置有支座,在所述的底座上端面上设置有2个定位槽,2个所述的定位槽之间设置有定位柱,两个所述的支座分别位于2个所述的定位槽内侧,在2个所述的定位槽之间设置有高强弹簧,所述的高强弹簧贯穿所述的定位柱,所述的高强弹簧两端分别固定连接在两个所述的支座相向的端面上。 2. The iron tower for high-voltage transmission line according to claim 1, characterized in that: a support is respectively provided at the lower ends of the first main tower and the second main tower, and Two positioning grooves are arranged on the upper end surface of the base, and a positioning column is arranged between the two positioning grooves. A high-strength spring is arranged between the grooves, the high-strength spring runs through the positioning column, and the two ends of the high-strength spring are respectively fixedly connected to the opposite end surfaces of the two supports. 3.根据权利要求2所述的一种用于高压输电线路的铁塔,其特征在于:在所述的定位槽远离所述的定位柱一侧端面与所述的支座之间分别设置有高强弹簧。 3. The iron tower for high-voltage transmission lines according to claim 2, characterized in that: a high-strength bracket is respectively arranged between the end face of the positioning groove on the side away from the positioning column and the support. spring. 4.根据权利要求2或3所述的一种用于高压输电线路的铁塔,其特征在于:在所述的定位柱上方设置有端盖。 4. An iron tower for high-voltage transmission lines according to claim 2 or 3, characterized in that: an end cover is arranged above the positioning column. 5.根据权利要求1或2或3所述的一种用于高压输电线路的铁塔,其特征在于:在所述的底座上设置有2个对称设置的通孔,在所述的通孔内设置有钢丝绳,所述的钢丝绳远离所述的底座一端分别固定连接在所述的第一主塔和第二主塔远离横梁一侧端面上。 5. An iron tower for high-voltage transmission lines according to claim 1, 2 or 3, characterized in that: two symmetrically arranged through holes are arranged on the base, and in the through holes Steel wire ropes are provided, and the ends of the steel wire ropes away from the base are respectively fixedly connected to the end faces of the first main tower and the second main tower away from the beam. 6.根据权利要求1或2或3所述的一种用于高压输电线路的铁塔,其特征在于:在所述的第一主塔和所述的第二主塔远离所述的横梁一侧端面上端设置有外置横梁,在所述的外置横梁上设置有固定轴,在所述的固定轴上设置有滑轮,在所述的底座上设置有升降台,在所述的升降台上方设置有钢丝拉索,所述的钢丝拉索上端挂接在所述的滑轮上。 6. A steel tower for high-voltage transmission lines according to claim 1, 2 or 3, characterized in that: on the side of the first main tower and the second main tower away from the beam An external beam is arranged on the top of the end face, a fixed shaft is arranged on the external beam, a pulley is arranged on the fixed shaft, a lifting platform is arranged on the base, and a lifting platform is arranged above the lifting platform. A steel wire cable is provided, and the upper end of the steel wire cable is hung on the pulley. 7.根据权利要求6所述的一种用于高压输电线路的铁塔,其特征在于:在所述的底座上端面上设置有绕线轮,所述的钢丝拉索一端缠绕在该绕线轮上,在所述的底座的上端面上设置有用于驱动所述的绕线轮转动的电机。 7. The iron tower used for high-voltage transmission lines according to claim 6, characterized in that: a winding wheel is arranged on the upper end surface of the base, and one end of the steel wire cable is wound on the winding wheel On the upper end surface of the base, a motor for driving the reel to rotate is provided. 8.根据权利要求1或2或3所述的一种用于高压输电线路的铁塔,其特征在于:在所述的第一主塔和所述的第二主塔相向的端面上设置有连接梁。 8. An iron tower for high-voltage transmission lines according to claim 1, 2 or 3, characterized in that: on the opposite end faces of the first main tower and the second main tower, connecting beam. 9.根据权利要求8所述的一种用于高压输电线路的铁塔,其特征在于:所述的连接梁中部向上方拱起,所述的连接梁两端分别固定连接在所述的第一主塔和所述的第二主塔上。 9. An iron tower for high-voltage transmission lines according to claim 8, characterized in that: the middle part of the connecting beam is arched upwards, and the two ends of the connecting beam are respectively fixedly connected to the first Main tower and said second main tower.
CN201620401398.4U 2016-05-03 2016-05-03 A iron tower for high tension transmission line Withdrawn - After Issue CN205591628U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620401398.4U CN205591628U (en) 2016-05-03 2016-05-03 A iron tower for high tension transmission line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620401398.4U CN205591628U (en) 2016-05-03 2016-05-03 A iron tower for high tension transmission line

Publications (1)

Publication Number Publication Date
CN205591628U true CN205591628U (en) 2016-09-21

Family

ID=56934019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620401398.4U Withdrawn - After Issue CN205591628U (en) 2016-05-03 2016-05-03 A iron tower for high tension transmission line

Country Status (1)

Country Link
CN (1) CN205591628U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804475A (en) * 2016-05-03 2016-07-27 国网山东省电力公司龙口市供电公司 Iron tower for high-voltage transmission line
CN112012558A (en) * 2020-08-31 2020-12-01 合肥森印科技有限公司 A extension formula rural highway wire pole base for river pond is other

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804475A (en) * 2016-05-03 2016-07-27 国网山东省电力公司龙口市供电公司 Iron tower for high-voltage transmission line
CN105804475B (en) * 2016-05-03 2018-04-24 国网山东省电力公司龙口市供电公司 A kind of steel tower for ultra-high-tension power transmission line
CN112012558A (en) * 2020-08-31 2020-12-01 合肥森印科技有限公司 A extension formula rural highway wire pole base for river pond is other

Similar Documents

Publication Publication Date Title
EP2889251B1 (en) Load guiding arrangement
CN205489276U (en) Polling robot
CN214091279U (en) Electric pole correction device for electric power engineering
CN108862050B (en) More changing device
CN205591628U (en) A iron tower for high tension transmission line
CN110902566A (en) An anti-sway device for lifting equipment
CN114408756A (en) Gantry crane system for GIL installation
CN105804475B (en) A kind of steel tower for ultra-high-tension power transmission line
CN103723649A (en) Electric hoist
JP6378250B2 (en) Suspended load elevating apparatus and method for elevating suspended load for wind power generator
CN106882214A (en) A kind of novel electric power industry multi-functional operation car
CN110182698B (en) Climbing device and self-climbing crane
CN203850726U (en) Wire lifter on 10 kV power distribution telegraph pole
CN202245772U (en) Gantry crane and cable drum mechanism thereof
CN118100454B (en) Energy storage unit gravity block energy storage device and method
CN103795003A (en) Insulated wire lifting device for live working of 35kV power supply line
CN209411654U (en) Double rocking arm set tower pole lifting power-equipments
CN103274289A (en) Combined type multifunctional hanger
CN203242965U (en) Sag adjuster
CN207700795U (en) A kind of jacking system neutral body Garage lifting platform power drive unit
KR101317384B1 (en) The hoisting and installing method and apparatus of wind turbines by using the self tower
CN116374812A (en) Generator lifting device for offshore wind turbine
CN213537062U (en) Lifting device for power distribution network overhead line
CN212503855U (en) Lifting installation structure
CN103588131B (en) Eight-point synchronous automatic lifting maintenance platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20160921