CN205371830U CN201620175629.4U CN201620175629U CN205371830U CN 205371830 U CN205371830 U CN 205371830U CN 201620175629 U CN201620175629 U CN 201620175629U CN 205371830 U CN205371830 U CN 205371830U
Authority
CN
China
Prior art keywords
support frame
concave station
main backstop
deck
burried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620175629.4U
Other languages
Chinese (zh)
Inventor
唐建文
段刚太
徐世国
孙永得
陈泽波
王伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DATANG QINGDAO HEAT Co Ltd
Original Assignee
DATANG QINGDAO HEAT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DATANG QINGDAO HEAT Co Ltd filed Critical DATANG QINGDAO HEAT Co Ltd
Priority to CN201620175629.4U priority Critical patent/CN205371830U/en
Application granted granted Critical
Publication of CN205371830U publication Critical patent/CN205371830U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pipeline Systems (AREA)

Abstract

The utility model discloses a heating power pipeline direct -burried fixed establishment, including direct -burried pipeline, concrete platform, put a tub concave station among the concrete platform, put tub concave station both sides and set up left and right sides supporting platform respectively, put the middle main tributary strut that is equipped with of tub concave station, a left side is put and is set up the left branch strut between tub concave station and the main tributary strut, and two terminal surfaces are fixed respectively and are set up on left supporting platform and main tributary strut about the left branch strut, and left branch strut endotheca has the direct -burried pipeline, and the right side is put and is set up the right branch strut between tub concave station and the main tributary strut, and two terminal surfaces are fixed respectively and are set up on right supporting platform and main tributary strut about the right branch strut, and right branch strut endotheca has the direct -burried pipeline, direct -burried pipeline top sets up the cassette. The utility model discloses an it is better to control the waterproof seal of support frame, and the safe operation of pipeline is guaranteed to the holding power that significantly reduces, increases life, the better fixed direct -burried pipeline of cassette ability, the utility model discloses simple structure, stability is good, and support nature is high.

Description

A kind of heat distribution pipeline direct-burried fixed mechanism
Technical field
This utility model relates to a kind of fixed mechanism, is specifically related to a kind of heat distribution pipeline direct-burried fixed mechanism.
Background technology
At present, heat distribution pipeline is laid, and for saving the energy, beautifies the environment, mostly adopts direct-buried mode.But the fixing intensity of the heat distribution pipeline of outdoor of the prior art is not high, and support strength is low so that the less stable of heat distribution pipeline.
Utility model content
The purpose of this utility model is for overcoming above-mentioned the deficiencies in the prior art, it is provided that a kind of heat distribution pipeline direct-burried fixed mechanism.
For achieving the above object, this utility model adopts following technical proposals, a kind of heat distribution pipeline direct-burried fixed mechanism, including concrete platform, described concrete platform is put pipe concave station, described pipe concave station both sides of putting are respectively provided with left support platform and right support platform, described left support platform and right support platform is fixed below arranges buried bar;The described centre putting pipe concave station is provided with main backstop, and described main backstop is fixed below arranges buried bar, and described buried bar and concrete platform match fastening;
Described main backstop will be put pipe concave station and be divided into a left side to put pipe concave station and pipe concave station is put on the right side;Described main backstop and a left side are put pipe concave station and are enclosed a left side and put tube space, and described main backstop and the right side are put pipe concave station and enclosed a right side and put tube space;
A described left side is put and is arranged left support frame between pipe concave station and main backstop, described left support frame is concave structure, the groove of described left support frame concave structure is arranged at a left side and puts in tube space, the groove of described left support frame concave structure and a described left side are put tube space and are matched, two, the left and right of described left support frame concave structure end face is fixedly installed on left support platform and main backstop respectively, it is cased with the first directly buried pipeline in the groove of described left support frame concave structure, described first directly buried pipeline is provided above the first deck, the left end of described first deck is hinged with the left side of left support frame, the described right-hand member of the first deck and the right side of left support frame are bolted to connection;
The described right side is put and is arranged right support frame between pipe concave station and main backstop, described right support frame is concave structure, the groove of described right support frame concave structure is arranged at the right side and puts in tube space, the groove of described right support frame concave structure and the described right side are put tube space and are matched, two, the left and right of described right support frame concave structure end face is fixedly installed on right support platform and main backstop respectively, it is cased with the second directly buried pipeline in the groove of described right support frame concave structure, described second directly buried pipeline is provided above the second deck, the right-hand member of described second deck is hinged with the right side of right support frame, the described left end of the second deck and the left side of right support frame are bolted to connection.
Preferably, described first deck and the second deck are arcuate structure.
Preferably, some buried bars it are uniformly distributed below described left support frame, right support frame and main backstop.
The beneficial effects of the utility model are, left and right sidesing supporting frame structure of the present utility model, and because its groove structure is complete, water-proof sealing is better, greatly reduce support force, it is possible to ensure the safe operation of pipeline, increase its service life, deck is adopted can better to fix directly buried pipeline, the heat distribution pipeline direct-burried fixed mechanism that this utility model provides, simple in construction, good stability, supportive is high, and the laying for Urban Buried Pipeline Network provides reliable technological means.
Accompanying drawing explanation
Fig. 1 is this utility model structural representation;
Wherein 1. first directly buried pipeline, 2. concrete platform, 3. left support platform, 4. right support platform, 5. buried bar, 6. main backstop, 7. tube space is put on a left side, and 8. tube space is put on the right side, 9. left support frame, 10. right support frame, 11. the second directly buried pipeline, 12. first decks, 13. first bolts, 14. the second deck, 15. second bolts.
Detailed description of the invention
Below in conjunction with drawings and Examples, this utility model is further illustrated.
A kind of heat distribution pipeline direct-burried fixed mechanism, including concrete platform 2, described concrete platform 2 puts pipe concave station, described in put pipe concave station both sides and be respectively provided with that left support platform 3 and right support platform 4, described left support platform 3 and right support platform 4 are fixed below arranges buried bar 5;The described centre putting pipe concave station is provided with main backstop 6, and described main backstop 6 is fixed below arranges buried bar 5, and described buried bar 5 and concrete platform 2 match fastening;
Described main backstop 6 will be put pipe concave station and be divided into a left side to put pipe concave station and pipe concave station is put on the right side;Described main backstop 6 and a left side are put pipe concave station and are enclosed a left side and put tube space 7, and described main backstop 6 and the right side are put pipe concave station and enclosed a right side and put tube space 8;
A described left side is put and is arranged left support frame 9 between pipe concave station and main backstop 6, described left support frame 9 is concave structure, the groove of described left support frame 9 concave structure is arranged at a left side and puts in tube space 7, the groove of described left support frame 9 concave structure and a described left side are put tube space 7 and are matched, two, the left and right end face of described left support frame 9 concave structure is fixedly installed on left support platform 3 and main backstop 6 respectively, it is cased with the first directly buried pipeline 1 in the groove of described left support frame 9 concave structure, described first directly buried pipeline 1 is provided above the first deck 12, the left end of described first deck 12 is hinged with the left side of left support frame 9, the right-hand member of described first deck 12 is connected by the first bolt 13 is fixing with the right side of left support frame 9;
The described right side is put and is arranged right support frame 10 between pipe concave station and main backstop 6, described right support frame 10 is concave structure, the groove of described right support frame 10 concave structure is arranged at the right side and puts in tube space 8, the groove of described right support frame 10 concave structure and the described right side are put tube space 8 and are matched, two, the left and right end face of described right support frame 10 concave structure is fixedly installed on right support platform 4 and main backstop 6 respectively, it is cased with the second directly buried pipeline 11 in the groove of described right support frame 10 concave structure, described second directly buried pipeline 11 is provided above the second deck 14, the right-hand member of described second deck 14 is hinged with the right side of right support frame 10, the left end of described second deck 14 is connected by the second bolt 15 is fixing with the left side of right support frame 10.
Described first deck 12 and the second deck 14 are arcuate structure.
Some buried bars 5 it are uniformly distributed below described left support frame 9, right support frame 10 and main backstop 6.
Left and right sidesing supporting frame structure of the present utility model, and because its groove structure is complete, water-proof sealing is better, greatly reduces support force, ensure that the safe operation of pipeline, increase its service life, adopt deck can better fix directly buried pipeline, the heat distribution pipeline direct-burried fixed mechanism that this utility model provides, simple in construction, good stability, supportive is high, and the laying for Urban Buried Pipeline Network provides reliable technological means.
Detailed description of the invention of the present utility model is described in conjunction with accompanying drawing although above-mentioned; but the not restriction to this utility model protection domain; one of ordinary skill in the art should be understood that; on the basis of the technical solution of the utility model, those skilled in the art need not pay various amendments or deformation that creative work can make still within protection domain of the present utility model.

Claims (3)

1. a heat distribution pipeline direct-burried fixed mechanism, it is characterized in that, including concrete platform, described concrete platform is put pipe concave station, described pipe concave station both sides of putting are respectively provided with left support platform and right support platform, described left support platform and right support platform is fixed below arranges buried bar;The described centre putting pipe concave station is provided with main backstop, and described main backstop is fixed below arranges buried bar, and described buried bar and concrete platform match fastening;
Described main backstop will be put pipe concave station and be divided into a left side to put pipe concave station and pipe concave station is put on the right side;Described main backstop and a left side are put pipe concave station and are enclosed a left side and put tube space, and described main backstop and the right side are put pipe concave station and enclosed a right side and put tube space;
A described left side is put and is arranged left support frame between pipe concave station and main backstop, described left support frame is concave structure, the groove of described left support frame concave structure is arranged at a left side and puts in tube space, the groove of described left support frame concave structure and a described left side are put tube space and are matched, two, the left and right of described left support frame concave structure end face is fixedly installed on left support platform and main backstop respectively, it is cased with the first directly buried pipeline in the groove of described left support frame concave structure, described first directly buried pipeline is provided above the first deck, the left end of described first deck is hinged with the left side of left support frame, the described right-hand member of the first deck and the right side of left support frame are bolted to connection;
The described right side is put and is arranged right support frame between pipe concave station and main backstop, described right support frame is concave structure, the groove of described right support frame concave structure is arranged at the right side and puts in tube space, the groove of described right support frame concave structure and the described right side are put tube space and are matched, two, the left and right of described right support frame concave structure end face is fixedly installed on right support platform and main backstop respectively, it is cased with the second directly buried pipeline in the groove of described right support frame concave structure, described second directly buried pipeline is provided above the second deck, the right-hand member of described second deck is hinged with the right side of right support frame, the described left end of the second deck and the left side of right support frame are bolted to connection.
2. a kind of heat distribution pipeline direct-burried fixed mechanism as claimed in claim 1, is characterized in that, described first deck and the second deck are arcuate structure.
3. a kind of heat distribution pipeline direct-burried fixed mechanism as claimed in claim 1, is characterized in that, be uniformly distributed some buried bars below described left support frame, right support frame and main backstop.
CN201620175629.4U 2016-03-08 2016-03-08 Heating power pipeline direct -burried fixed establishment Expired - Fee Related CN205371830U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620175629.4U CN205371830U (en) 2016-03-08 2016-03-08 Heating power pipeline direct -burried fixed establishment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620175629.4U CN205371830U (en) 2016-03-08 2016-03-08 Heating power pipeline direct -burried fixed establishment

Publications (1)

Publication Number Publication Date
CN205371830U true CN205371830U (en) 2016-07-06

Family

ID=56265216

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620175629.4U Expired - Fee Related CN205371830U (en) 2016-03-08 2016-03-08 Heating power pipeline direct -burried fixed establishment

Country Status (1)

Country Link
CN (1) CN205371830U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107300091A (en) * 2017-08-25 2017-10-27 绵阳飞远科技有限公司 Direct-Buried Heating Pipeline system with corrosion-resistant thermal insulation function
CN109488005A (en) * 2018-09-12 2019-03-19 深圳市建艺装饰集团股份有限公司 Horizontal pipe mounting structure and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107300091A (en) * 2017-08-25 2017-10-27 绵阳飞远科技有限公司 Direct-Buried Heating Pipeline system with corrosion-resistant thermal insulation function
CN109488005A (en) * 2018-09-12 2019-03-19 深圳市建艺装饰集团股份有限公司 Horizontal pipe mounting structure and construction method
CN109488005B (en) * 2018-09-12 2020-09-15 深圳市建艺装饰集团股份有限公司 Horizontal pipeline installation structure and construction method

Similar Documents

Publication Publication Date Title
CN204031047U (en) A kind of color steel tile roof photovoltaic plant installation system
CN106301160A (en) A kind of Overwater floating carrier
CN204216820U (en) Water float bowl photovoltaic generating system
CN104124913B (en) The installation method of newly-built solar energy roof integrated power generation system
CN104746812A (en) Multi-function and multi-purpose tile/plate
CN204733114U (en) A kind of Overwater floating carrier
CN204761370U (en) Unsteady carrier on water
CN204408247U (en) A kind of water solar power supply system
CN105155870A (en) New-energy portable house
CN204993195U (en) Device for connecting installation photovoltaic support on various steel tile roof
CN210423992U (en) Building pipe for building water supply and drainage pipeline
CN205063379U (en) New forms of energy activity board house
CN207142629U (en) A kind of overlength super thin metal roof boarding lifts aid
CN206099849U (en) A penetrating continuous connector for fixing photovoltaic modules and flexible supports
CN203036534U (en) Anti-theft and energy-saving solar streetlamp
CN204959684U (en) Flood prevention device
CN203522065U (en) Vertical-section phase-isolated bus conductor temporary supporting structure
CN202361256U (en) Solar street lamp
CN202674762U (en) Support frame of intelligent solar lighting monitoring device
CN204947527U (en) A kind of iron tower of power transmission line cable bearer
CN216344490U (en) Water conservancy pipeline convenient to install for drainage engineering
CN202544473U (en) Erecting and supporting device for herringbone rods
CN204886802U (en) Roof photovoltaic power generation photovoltaic mounting system
CN204417996U (en) A kind of steel bridge heat-insulation system
CN219372331U (en) Assembled photovoltaic board connection structure suitable for steel construction roofing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160706