CN205252513U - Erect and put log bridge - Google Patents

Erect and put log bridge Download PDF

Info

Publication number
CN205252513U
CN205252513U CN201520922665.8U CN201520922665U CN205252513U CN 205252513 U CN205252513 U CN 205252513U CN 201520922665 U CN201520922665 U CN 201520922665U CN 205252513 U CN205252513 U CN 205252513U
Authority
CN
China
Prior art keywords
log
pile
column
utility
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520922665.8U
Other languages
Chinese (zh)
Inventor
孙金富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201520922665.8U priority Critical patent/CN205252513U/en
Application granted granted Critical
Publication of CN205252513U publication Critical patent/CN205252513U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an erect and put log bridge, including the stand, and be fixed in the platform on the stand, and set up the security steel rope cable between the stand, still be fixed with two parallel ropes between the stand, the interval is provided with the log pile between the parallel rope, every movable lock latch is installed to the log pile both sides. The utility model discloses an erect and put log bridge, the project organization is reasonable, and the log pile interval is adjustable, the optional security of diameter is good, and interesting high, the challenge is strong, and can temper participant's four limbs, tests participant's health balancing capability.

Description

A kind of perpendicular log bridge of putting
Technical field
The utility model relates to a kind of erecting and puts log bridge, belongs to the entertainment selection field of expanding.
Background technology
Current expansion entertainment selection is using amusement as main purpose, general be all arranged on ground or a little more than the position on ground, its challenge is not high, less for participant's psychological pressure, mainly test participant's stability of standing, cannot reach the object of whole body exercise; Due to the restriction in place, it is in the majority that existing expansion entertainment selection equipment is fixedly installed in addition, and total degree of difficulty is lower.
Utility model content
(1) technical problem that will solve
For addressing the above problem, the utility model proposes a kind of erecting and put log bridge, security is good, and interesting high, challenge is strong, and can temper participant's four limbs, test participant's balance ability.
(2) technical scheme
Of the present utility model erecting put log bridge, comprises column, and is fixed on the platform on column, and be arranged at the safety lanyard rope between column, and participant is played a protective role; Between described column, be also fixed with two parallel ropes; Between described parallel rope, be arranged at intervals with log pile; Each described log pile both sides are provided with movable snap close.
As preferred embodiment, the diameter of section 0.1 ~ 0.5m of each described log pile; By regulating movable snap close, regulating the spacing between adjacent described log pile is 0.5 ~ 1m.
(3) beneficial effect
Compared with prior art, of the present utility model erecting put log bridge, and project organization is reasonable, and log pile spacing is adjustable, and its diameter also can be selected as required; Security is good, and interesting high, challenge is strong, and can temper participant's four limbs, test participant's balance ability.
Brief description of the drawings
Fig. 1 is overall structure schematic diagram of the present utility model.
Parts in accompanying drawing are labeled as: 1-column, 2-platform, 3-safety lanyard rope, 4-parallel rope, 5-log pile, the movable snap close of 6-.
Detailed description of the invention
Embodiment 1:
The perpendicular log bridge of putting as shown in Figure 1, comprises column 1, and is fixed on the platform 2 on column 1, and is arranged at the safety lanyard rope 3 between column 1, and participant is played a protective role; Between described column 1, be also fixed with two parallel ropes 4; Between described parallel rope 4, be arranged at intervals with log pile 5; Each described log pile 5 both sides are provided with movable snap close 6.
Wherein, the diameter of section 0.2m of each described log pile 5; By regulating movable snap close 6, regulating the spacing between adjacent described log pile 5 is 0.5m.
Embodiment 2:
Of the present utility model erecting put log bridge, comprises column 1, and is fixed on the platform 2 on column 1, and be arranged at the safety lanyard rope 3 between column 1, and participant is played a protective role; Between described column 1, be also fixed with two parallel ropes 4; Between described parallel rope 4, be arranged at intervals with log pile 5; Each described log pile 5 both sides are provided with movable snap close 6.
Wherein, the diameter of section 0.5m of each described log pile 5; By regulating movable snap close 6, regulating the spacing between adjacent described log pile 5 is 1m.
Participant's pin is trampled on log pile, passes by from log pile, completes whole expansion entertainment selection; Thereby whole equipment can regulate the distance between adjacent log pile by the movable snap close on the horizontal steel wire cable of adjusting, in addition, can also regulate log pile diameter, thereby adjust the complexity of expanding entertainment selection, and by highly participant being produced to psychological pressure.
Embodiment recited above is described preferred embodiment of the present utility model, not design of the present utility model and scope is limited. Do not departing under the prerequisite of the utility model design concept; various modification and improvement that this area ordinary person makes the technical solution of the utility model; all should drop into protection domain of the present utility model; the technology contents of the utility model request protection, has all been documented in claims.

Claims (2)

1. erect and put a log bridge, comprise column, and be fixed on the platform on column, and be arranged at the safety lanyard rope between column; It is characterized in that: between described column, be also fixed with two parallel ropes; Between described parallel rope, be arranged at intervals with log pile; Each described log pile both sides are provided with movable snap close.
2. according to claim 1 erecting put log bridge, it is characterized in that: the diameter of section 0.1 ~ 0.5m of each described log pile; Spacing between adjacent described log pile is 0.5 ~ 1m.
CN201520922665.8U 2015-11-18 2015-11-18 Erect and put log bridge Expired - Fee Related CN205252513U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520922665.8U CN205252513U (en) 2015-11-18 2015-11-18 Erect and put log bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520922665.8U CN205252513U (en) 2015-11-18 2015-11-18 Erect and put log bridge

Publications (1)

Publication Number Publication Date
CN205252513U true CN205252513U (en) 2016-05-25

Family

ID=55994064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520922665.8U Expired - Fee Related CN205252513U (en) 2015-11-18 2015-11-18 Erect and put log bridge

Country Status (1)

Country Link
CN (1) CN205252513U (en)

Similar Documents

Publication Publication Date Title
CN207115792U (en) A kind of safe construction experiences equipment
CN205252513U (en) Erect and put log bridge
CN206815163U (en) A kind of suspension cable construction bridge
CN205235253U (en) High altitude rings bridge
CN206388436U (en) A kind of transmission tower high-altitude trainer
CN205323082U (en) Monospar sky bridge type high ladder with safety belt
CN203971275U (en) Outward bound facility unit, four-way self protection type high-altitude
CN205252389U (en) Stake bridge is suspended in midair in high altitude
CN205252388U (en) Rectangular wood of cross that falls suspends bridge in midair
CN203494151U (en) Amusement park equipment for rope adventure
CN205252390U (en) High altitude triangle rings bridge
CN206621673U (en) Regularization escape device for temporary building
CN205252512U (en) Cake suspends bridge in midair
CN203280963U (en) High-altitude psychological behavior training facility
CN205252402U (en) Single foot of lurch suspends bridge in midair
CN205460566U (en) Transformer that stability is high overhauls uses safety belt lift kits
CN204103309U (en) A kind of composite type inspection platform
CN206267512U (en) A kind of movable operating platform
CN203213951U (en) Parallel three-upright post climb-proof device
CN205252434U (en) Side direction rock climbing wall
CN206282466U (en) A kind of work high above the ground body-sensing system
CN205307777U (en) Thick bolt bridge of drop shot rope
CN103638630B (en) Multiple altitude combination formula high ladders
CN205252514U (en) Single track skidding steel wire bridge with lumps of wood
CN104064984A (en) Double split wire line maintenance pulley

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160525

Termination date: 20171118

CF01 Termination of patent right due to non-payment of annual fee