CN205228129U CN201521100564.9U CN201521100564U CN205228129U CN 205228129 U CN205228129 U CN 205228129U CN 201521100564 U CN201521100564 U CN 201521100564U CN 205228129 U CN205228129 U CN 205228129U
Authority
CN
China
Prior art keywords
kiln
dry kiln
sintering oven
dry
airduct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201521100564.9U
Other languages
Chinese (zh)
Inventor
曲宝华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201521100564.9U priority Critical patent/CN205228129U/en
Application granted granted Critical
Publication of CN205228129U publication Critical patent/CN205228129U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/60Production of ceramic materials or ceramic elements, e.g. substitution of clay or shale by alternative raw materials, e.g. ashes

Abstract

The utility model provides a modular assembly formula tunnel cave, it includes sintering kiln, dry kiln and waste heat recovery system, sintering kiln and dry kiln all include steel construction outer wall, thermal insulating layer and refractory material protective layer the inner chamber bottom surface of sintering kiln and dry kiln all is provided with the track that does benefit to fortune brickkiln car and remove, the waste heat recovery system is including the waste heat utilization connecting pipe of throwing the coal combustion area that passes the sintering kiln, sets up on sintering kiln upper portion, as the sintering kiln tuber pipe that branch pipe and waste heat utilization connecting pipe are linked together, sets up on dry kiln upper portion, crosses the dry kiln tuber pipe that fan and waste heat utilization connecting pipe are linked together as the lateral duct to reach and set up the exhaust tuber pipe of discharging fume of airing exhaust and holding at the dry kiln, sintering kiln tuber pipe and dry kiln tuber pipe extend to the length direction of sintering kiln and dry kiln respectively, and sintering kiln tuber pipe and dry kiln tuber pipe are linked together through inside branch pipe and sintering kiln and the dry kiln respectively.

Description

A kind of Modular assembled tunnel cave
Technical field
The utility model relates to brickkiln apparatus field, particularly relates to a kind of Modular assembled tunnel cave.
Background technology
Existing brick-baking kiln is mainly built by the mode of sun-dried mud brick operation at the scene, its outward appearance and integral heat insulation poor, precision is not high, and construction period is longer, and particularly kiln inside holding performance is very low; In adobe sintering and dry process, need a dead lift, efficiency is very low, so often cause down base and crowded bad, draw bad kiln wall phenomenon; And the hot blast of baking bricks of existing brickkiln is for directly discharge, has both been unfavorable for environmental air pollution, and has also result in a large amount of wastes of heat energy, when particularly the northern area of China is dry after brickmaking base in the winter time, lack heating owing to depositing base workshop, spy easily freezes base.
Utility model content
The purpose of this utility model is just to provide a kind of Modular assembled tunnel cave to above-mentioned the deficiencies in the prior art part.
The utility model realizes the technical scheme that above-mentioned purpose takes: a kind of Modular assembled tunnel cave, and it comprises sintering oven, dry kiln and residual neat recovering system; Described sintering oven and dry kiln include steel construction exterior wall, be arranged on the heat insulation layer of steel construction exterior wall interior surface, and be arranged on the refractory material protective layer of heat insulation layer interior surface, be provided with in the inner chamber bottom surface of described sintering oven and dry kiln the track being beneficial to the movement of fortune brick kiln car; Described residual neat recovering system comprises the UTILIZATION OF VESIDUAL HEAT IN tube connector in the throwing coal combustion district through sintering oven, the sintering oven airduct be arranged on sintering oven top, being connected as arm with UTILIZATION OF VESIDUAL HEAT IN tube connector, the dry kiln airduct be arranged on dry kiln top, being connected as arm by blower fan with UTILIZATION OF VESIDUAL HEAT IN tube connector, and the smoke evacuation exhaust airduct being arranged on dry kiln air outlet; Described sintering oven airduct and dry kiln airduct extend respectively to the length direction of sintering oven and dry kiln, and sintering oven airduct is connected with dry kiln inside with sintering oven respectively by arm with dry kiln airduct.
The utility model is provided with bent aerofoil at the inner space mouth place of described arm and sintering oven and dry kiln.
The air outlet of smoke evacuation exhaust airduct described in the utility model is connected with desulfurizing tower.
Principle of the present utility model and beneficial effect are: assembly type tunnel cave of the present utility model both can be once-setting firing tunnel kiln, also can be quadratic code fired tunnel kilns.The arrangement of tunnel drier and tunnel cave can be determined according to the actual conditions of production site, dry kiln and sintering oven " one " font can be adopted to arrange, also can adopt and be arranged in parallel, when tunnel drying kiln and sintering oven are arranged in parallel, the turnover of kiln car relies on kiln car connection.The arrangement of the assembled once-setting firing tunnel kiln that " one " font is arranged has two kinds, one is that sintering oven and dry kiln are separated by a distance, each own independently work system, another kind is exactly drying nest and sintering partial common tunnel, just separate with the section of burning till at suitable position air curtain or goalkeeper's dryer section, there is dry and sintering two cover work system, dry work system is responsible for wet base to be dried to hacking, burns till work system and raw brick can be burnt till the finished bricks meeting building requirements; Certainly also can adopt the mode be arranged in parallel, the adobe only needing workman drying kiln for drying to be crossed directly pushes sintering oven.The sintering oven of the utility model tunnel cave and the outermost layer of dry kiln are metal maintenance level, outermost baffle and heat insulation light heat insulation material are made component, be not damaged in order to protect light heat insulation material, kiln body, kiln top adopt assembled structure, kiln external molded dimension error is little, and outward appearance is neat, attractive in appearance, beautiful; When building package tunnel kiln, the various parts of the composition kiln only batch production need processed are transported to build on-site, then according to designing requirement, all parts forming kiln are assembled into tunnel cave.This is just as heavy mechanical equipment is installed, and by the various parts through processing, after installing according to the requirement of installation diagram, entire machine has just installed.
So just bring: 1. modularized production, Assembling.Can produce in batches in factory; For being inconvenient to transport or other reasons, also can make module at the construction field (site), assembling completes, reduce construction period; 2. kiln is equipped with bootstrap system to can be implemented in northern area winter dryness kiln for northern area and deposits base heating, and winter does not freeze base, ensures whole year production; 3. kiln inwall adopts hard refractory material as inner lining of kiln, thoroughly solve in drying, sintering process fall base squeeze bad, draw bad kiln wall phenomenon, adopt high-quality heat preserving and insulating material as filling between hard liner and steel construction exterior wall, ensure thermal source indiffusion.
Accompanying drawing explanation
Fig. 1 is plan structure schematic diagram of the present utility model.
Fig. 2 is section structure schematic diagram of the present utility model
In figure: 1, sintering oven; 2, dry kiln; 3, residual neat recovering system; 4, steel construction exterior wall; 5, heat insulation layer; 6, refractory material protective layer; 7, UTILIZATION OF VESIDUAL HEAT IN tube connector; 8, sintering oven airduct; 9, dry kiln airduct; 10, smoke evacuation exhaust airduct; 11, arm; 12, bent aerofoil; 13, desulfurizing tower; 14, track; 15, blower fan.
Detailed description of the invention
The utility model further describes below with reference to accompanying drawing.
As shown in Figure 1-2, a kind of Modular assembled tunnel cave of the present utility model, it comprises sintering oven 1, dry kiln 2 and residual neat recovering system 3; Described sintering oven 1 and dry kiln 2 include steel construction exterior wall 4, be arranged on the heat insulation layer 5 of steel construction exterior wall 4 interior surface, and be arranged on the refractory material protective layer 6 of heat insulation layer 5 interior surface, be provided with in the inner chamber bottom surface of described sintering oven 1 and dry kiln 2 track 14 being beneficial to the movement of fortune brick kiln car; Described residual neat recovering system 3 comprises the UTILIZATION OF VESIDUAL HEAT IN tube connector 7 in the throwing coal combustion district through sintering oven 1, the sintering oven airduct 8 be arranged on sintering oven top, being connected as arm with UTILIZATION OF VESIDUAL HEAT IN tube connector 7, the dry kiln airduct 9 be arranged on dry kiln top, being connected as arm by blower fan 15 with UTILIZATION OF VESIDUAL HEAT IN tube connector 7, and the smoke evacuation exhaust airduct 10 being arranged on dry kiln air outlet; Described sintering oven airduct 8 and dry kiln airduct 9 extend respectively to the length direction of sintering oven and dry kiln, and sintering oven airduct 8 is connected with dry kiln inside with sintering oven respectively by arm 11 with dry kiln airduct 9.
The utility model is provided with bent aerofoil 12 at described arm 11 with the inner space mouth place of sintering oven and dry kiln.
The air outlet of smoke evacuation exhaust airduct 10 described in the utility model is connected with desulfurizing tower 13.

Claims (3)

1. a Modular assembled tunnel cave, is characterized in that: it comprises sintering oven (1), dry kiln (2) and residual neat recovering system (3); Described sintering oven (1) and dry kiln (2) include steel construction exterior wall (4), be arranged on the heat insulation layer (5) of steel construction exterior wall (4) interior surface, and be arranged on the refractory material protective layer (6) of heat insulation layer (5) interior surface, be provided with in the inner chamber bottom surface of described sintering oven (1) and dry kiln (2) track (14) being beneficial to the movement of fortune brick kiln car; Described residual neat recovering system (3) comprises the UTILIZATION OF VESIDUAL HEAT IN tube connector (7) in the throwing coal combustion district through sintering oven (1), the sintering oven airduct (8) be arranged on sintering oven top, being connected as arm with UTILIZATION OF VESIDUAL HEAT IN tube connector (7), the dry kiln airduct (9) be arranged on dry kiln top, being connected as arm by blower fan (15) with UTILIZATION OF VESIDUAL HEAT IN tube connector (7), and smoke evacuation exhaust airduct (10) being arranged on dry kiln air outlet; Described sintering oven airduct (8) and dry kiln airduct (9) extend respectively to the length direction of sintering oven and dry kiln, and sintering oven airduct (8) is connected with dry kiln inside with sintering oven respectively by arm (11) with dry kiln airduct (9).
2. Modular assembled tunnel cave according to claim 1, is characterized in that: described arm (11) and the inner space mouth place of sintering oven and dry kiln are provided with bent aerofoil (12).
3. Modular assembled tunnel cave according to claim 1, is characterized in that: the air outlet of described smoke evacuation exhaust airduct (10) is connected with desulfurizing tower (13).
CN201521100564.9U 2015-12-21 2015-12-21 Modular assembly formula tunnel cave Expired - Fee Related CN205228129U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521100564.9U CN205228129U (en) 2015-12-21 2015-12-21 Modular assembly formula tunnel cave

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521100564.9U CN205228129U (en) 2015-12-21 2015-12-21 Modular assembly formula tunnel cave

Publications (1)

Publication Number Publication Date
CN205228129U true CN205228129U (en) 2016-05-11

Family

ID=55903186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521100564.9U Expired - Fee Related CN205228129U (en) 2015-12-21 2015-12-21 Modular assembly formula tunnel cave

Country Status (1)

Country Link
CN (1) CN205228129U (en)

Similar Documents

Publication Publication Date Title
US11193713B2 (en) Industrial kiln
CN103641345A (en) Material-distribution type cooling process of white cement clinker
CN201583131U (en) Afterheat utilization system of tunnel furnace
CN105757977A (en) Environment-friendly and energy-saving hot-blast furnace and use method thereof
CN102618681A (en) Grate-free double-preheating top combustion type hot blast stove
CN203518564U (en) Novel environment-friendly rotary energy-saving kiln
CN205228024U (en) Drying system of adobe
CN203163478U (en) Novel energy-saving kiln
CN102748926A (en) Building ceramic single-layer rapid dryer equipment
CN205228129U (en) Modular assembly formula tunnel cave
CN204255114U (en) A kind of wet green brick drying device
CN201637269U (en) Return air energy-saving annular kiln for shale brick production
CN104075572A (en) A novel environmental smoke processing system for a rotary energy-saving furnace
CN202770125U (en) Architectural ceramic monolayer rapid drying dryer
CN205245788U (en) Environmental protection and energy saving type semi -stiff extrusion process annular kiln
CN203116450U (en) Low-order coal drying upgrading equipment
CN202853354U (en) Modified direct burning bakeout tunnel kiln
CN204718354U (en) A kind of building materials material drying device
CN103925788A (en) Circulating adjustable ventilation system of large-section tunnel kiln of sintered brick production line
CN201764801U (en) Drying kiln
CN103134182A (en) Waste gas recovering all-steel air-cooled type energy-saving hot blast furnace
CN201355185Y (en) Energy-saving kiln
CN201021872Y (en) A tile stove
CN202204291U (en) Annular kiln with airtight-combined airbrakes and upper and lower annular air channels adopting semi-stiff extrusion process
CN205635387U (en) Industrial sludge preparation haydite device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160511

Termination date: 20171221

CF01 Termination of patent right due to non-payment of annual fee