CN205153510U - Building engineering vestibule colored steel installation hanging flower basket device - Google Patents

Building engineering vestibule colored steel installation hanging flower basket device Download PDF

Info

Publication number
CN205153510U
CN205153510U CN201520913695.2U CN201520913695U CN205153510U CN 205153510 U CN205153510 U CN 205153510U CN 201520913695 U CN201520913695 U CN 201520913695U CN 205153510 U CN205153510 U CN 205153510U
Authority
CN
China
Prior art keywords
flower basket
hanging flower
footstock
pulley
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520913695.2U
Other languages
Chinese (zh)
Inventor
杨锦博
任美红
李凤春
米华奇
王育炎
王艳军
陈哲
王继宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN201520913695.2U priority Critical patent/CN205153510U/en
Application granted granted Critical
Publication of CN205153510U publication Critical patent/CN205153510U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a building engineering vestibule colored steel installation hanging flower basket device, including footstock, track, hanging flower basket, characterized by: the footstock is groined type frame construction, installs the wheel in the lower part of two longerons, and the track is along vestibule length direction device in the top of vestibule, and the wheel of footstock is arranged in the track, is equipped with lug and hanging flower basket pulley at the both ends of footstock crossbeam, and the hanging flower basket is the rectangle basket, sets up a hanging flower basket respectively in four bight outsides of hanging flower basket and promotes electric block, and each hanging flower basket promotes electric block and is connected with the lug that corresponds through the hanging flower basket pulley that corresponds with wire rope respectively for promote the hanging flower basket, be equipped with on the crossbeam of footstock and hang the thing pulley, be equipped with on the hanging flower basket with hang that the thing pulley corresponds hang thing electric block, the wire rope who hangs thing electric block is through hanging the thing pulley. Its advantage is: it is convenient, nimble to use, safety, and convenient construction, work efficiency is high. Improve constructor's operation safety, also accelerated the construction progress simultaneously.

Description

Construction work vestibule colored steel installs nacelle device
Technical field
The utility model relates to a kind of construction work vestibule colored steel and installs nacelle device, belongs to building operations field of tool.
Background technology
Due to the particularity of industrial construction, in structural steelwork construction, usually meet the situation that the surrounding colored steels such as band conveyer corridor are installed.But because vestibule height is excessive, and sometimes require that four sides colored steel is installed, for construction causes great difficulty.Past often uses hanging ladder, not only dangerous large and installation difficulty is high, and construction speed also slows down thereupon simultaneously.
Summary of the invention
The purpose of this utility model is to provide a kind of convenient operation, it is flexible, convenient to use, and the construction work vestibule colored steel that safety, convenient construction, operating efficiency are high installs nacelle device.
The purpose of this utility model realizes with the following methods:
The utility model comprises footstock, track, hanging basket, it is characterized in that: footstock is the groined type frame construction that the longeron parallel with two, bottom by the crossbeam that two, top is parallel is formed, in the bottom of two parallel longerons, wheel is installed, track is installed on the top of vestibule along vestibule length direction, the wheel of footstock is arranged in track, hanger and hanging basket pulley is provided with at the two ends of footstock crossbeam, hanging basket pulley is positioned at the bottom of hanger, hanging basket is rectangle basket, outside four bights of hanging basket, a lifting of hanging basket electric block is set respectively, each lifting of hanging basket electric block is connected with corresponding hanger by corresponding hanging basket pulley with wire rope respectively, for promoting hanging basket, the crossbeam of footstock is provided with and hangs thing pulley, hanging basket being provided with and corresponding with hanging thing pulley hanging thing electric block, hanging the wire rope of thing electric block by hanging thing pulley.
The utility model has the advantages that: easy to use, flexible, safety, convenient construction, operating efficiency is high.Improve the job safety of constructor, also accelerate construction speed simultaneously.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is A-A direction view of Fig. 1;
Fig. 3 is the position relationship stereogram of footstock, hanging basket and vestibule.
Detailed description of the invention
With reference to accompanying drawing, the utility model comprises footstock 1, track 2, hanging basket 8, footstock is the groined type frame construction that the longeron parallel with two, bottom by the crossbeam that two, top is parallel is formed, crossbeam and longeron all adopt i iron to make, in the bottom of two parallel longerons, wheel 6 is installed, track adopts channel-section steel to make, track is installed on the top of vestibule along the length direction of vestibule 7, the wheel of footstock is arranged in track, hanger 4 and hanging basket pulley 5 is provided with at the two ends of footstock crossbeam, hanging basket pulley is positioned at the bottom of hanger, hanging basket 8 is rectangle basket, outside four bights of hanging basket, a lifting of hanging basket electric block 9 is set respectively, each lifting of hanging basket electric block 9 is connected with corresponding hanger by corresponding hanging basket pulley with wire rope respectively, for promoting hanging basket, the crossbeam of footstock is provided with and hangs thing pulley 3, hanging basket being provided with and corresponding with hanging thing pulley hanging thing electric block 10, hanging the wire rope of thing electric block by hanging thing pulley.Hanging basket is provided with switchbox 11, and all electric blocks all connect with switchbox, and switchbox connects with external power supply.
During application, constructor constructs in hanging basket, utilize lifting of hanging basket electric block to control the lifting of hanging basket, and footstock can drive hanging basket along rail moving, utilizes and hangs thing electric block lifting vestibule colored steel.
The utility model not only can be used on the construction of horizontal vestibule, also can be used on the construction of oblique vestibule.

Claims (1)

1. a construction work vestibule colored steel installs nacelle device, footstock, track, hanging basket, it is characterized in that: footstock is the groined type frame construction that the longeron parallel with two, bottom by the crossbeam that two, top is parallel is formed, in the bottom of two parallel longerons, wheel is installed, track is installed on the top of vestibule along vestibule length direction, the wheel of footstock is arranged in track, hanger and hanging basket pulley is provided with at the two ends of footstock crossbeam, hanging basket pulley is positioned at the bottom of hanger, hanging basket is rectangle basket, outside four bights of hanging basket, a lifting of hanging basket electric block is set respectively, each lifting of hanging basket electric block is connected with corresponding hanger by corresponding hanging basket pulley with wire rope respectively, for promoting hanging basket, the crossbeam of footstock is provided with and hangs thing pulley, hanging basket being provided with and corresponding with hanging thing pulley hanging thing electric block, hanging the wire rope of thing electric block by hanging thing pulley.
CN201520913695.2U 2015-11-17 2015-11-17 Building engineering vestibule colored steel installation hanging flower basket device Active CN205153510U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520913695.2U CN205153510U (en) 2015-11-17 2015-11-17 Building engineering vestibule colored steel installation hanging flower basket device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520913695.2U CN205153510U (en) 2015-11-17 2015-11-17 Building engineering vestibule colored steel installation hanging flower basket device

Publications (1)

Publication Number Publication Date
CN205153510U true CN205153510U (en) 2016-04-13

Family

ID=55689222

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520913695.2U Active CN205153510U (en) 2015-11-17 2015-11-17 Building engineering vestibule colored steel installation hanging flower basket device

Country Status (1)

Country Link
CN (1) CN205153510U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110644795A (en) * 2019-08-27 2020-01-03 中国二十冶集团有限公司 Construction method for high-altitude operation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110644795A (en) * 2019-08-27 2020-01-03 中国二十冶集团有限公司 Construction method for high-altitude operation

Similar Documents

Publication Publication Date Title
CN104192724B (en) Special purpose crane produced by a kind of aluminium section bar
CN204689550U (en) The support of the hanging suspension hook of scissor lift
CN205153510U (en) Building engineering vestibule colored steel installation hanging flower basket device
CN202346632U (en) Mine hydraulic type lifting crane
CN204510844U (en) A kind of large-span steel girder high-altitude mounting slip device
CN203159073U (en) Special multi-fulcrum overhang crane for maintaining hangar ceiling appliances
CN206051382U (en) A kind of electric power facility hanging apparatus
CN102556854B (en) Mine hydraulic hoisting traveling crane
CN202518943U (en) Creeper-traveler for coating bridge location
CN202186847U (en) Movable hanger frame
CN204162315U (en) A kind of dicycly hoisting crane
CN105712211B (en) A kind of equipment for being easy to steel structural overhead assembled
CN204038906U (en) Special purpose crane produced by a kind of aluminium section bar
CN202787930U (en) Hanging basket for high-place operations
CN203877754U (en) Mother-son trolley type bridge crane
CN204185124U (en) A kind of hoisting crane entablatrance
CN202864739U (en) Steaming bucket lifting device
CN203345921U (en) Device for hoisting electric locomotive
CN202529725U (en) Novel crane
CN204588497U (en) The vertical dolly of a kind of high elevator that hoists
CN202380754U (en) Floor-type steel transfer trolley
CN104401900A (en) Cover plate hoisting device
CN205472383U (en) Special loop wheel machine in novel workshop based on remote sensing control technique
CN203998703U (en) The large-scale thing air overturn hanging apparatus that hangs
CN204643682U (en) Traffic guideboard column hanging apparatus

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant