CN205077946U - 220kV overhead line and cable run connect cable of usefulness and step on tower - Google Patents
220kV overhead line and cable run connect cable of usefulness and step on tower Download PDFInfo
- Publication number
- CN205077946U CN205077946U CN201520576531.5U CN201520576531U CN205077946U CN 205077946 U CN205077946 U CN 205077946U CN 201520576531 U CN201520576531 U CN 201520576531U CN 205077946 U CN205077946 U CN 205077946U
- Authority
- CN
- China
- Prior art keywords
- cable
- platform
- climbing tower
- lines
- climbing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
- Fencing (AREA)
Abstract
本实用新型公开了一种220kV架空线路和电缆线路连接用的电缆登塔,登塔本体两侧设有相互对称的平台,登塔本体一侧的平台上从内向外依次设有避雷器、支柱绝缘子、电缆户外终端,平台两侧设有3付支架,电缆沟位于电缆户外终端正下方的平台上,登塔本体周围设有镂空铁质围栏,镂空铁质围栏上方设有电子围栏,平台下方还设有连接地面与平台的爬梯,本实用新型安装方便、节省占地面积、方便人员至平台工作、实用性强。
The utility model discloses a cable climbing tower for connecting 220kV overhead lines and cable lines. The two sides of the climbing tower body are provided with mutually symmetrical platforms, and the platform on one side of the climbing tower body is sequentially provided with lightning arresters and post insulators from inside to outside. , Cable outdoor terminal, there are 3 sets of brackets on both sides of the platform, the cable trench is located on the platform directly below the cable outdoor terminal, there is a hollow iron fence around the body of the climbing tower, an electronic fence is installed above the hollow iron fence, and there is an electric fence below the platform. There is a climbing ladder connecting the ground and the platform. The utility model is easy to install, saves floor space, facilitates personnel to work on the platform, and has strong practicability.
Description
技术领域technical field
本实用新型涉及电力工程安装领域,尤其涉及一种220kV架空线路和电缆线路连接用的电缆登塔。The utility model relates to the field of electric power engineering installation, in particular to a cable climbing tower for connecting 220kV overhead lines and cable lines.
背景技术Background technique
随着社会经济的发展,土地资源越来越昂贵,传统的架空线路下地方式为电缆终端场,该方式占地面积大,对人身和设备安全构成威胁,引下线过长容易导致风偏电气间隙不够,长期受风力作用摆动造成电缆终端头的线夹疲劳损坏。随着城市电网建设的不断推进,城市电网线路改造的不断深化,架空线、电缆混合线路在市区道路旁的使用的情况越来越多,如何解决征地和电缆登塔难题,加快割接工程的进度,这一状况目前有待急需解决。With the development of society and economy, land resources are becoming more and more expensive. The traditional way of undergrounding overhead lines is the cable terminal field. This method occupies a large area and poses a threat to personal and equipment safety. Too long down conductors may easily lead to wind deflection. The gap is not enough, and the long-term swing by the wind force causes fatigue damage to the clamp of the cable terminal head. With the continuous advancement of urban power grid construction and the continuous deepening of urban power grid line transformation, overhead lines and cable hybrid lines are used more and more beside urban roads. How to solve the problems of land acquisition and cable tower climbing and speed up the cutover project The progress of this situation needs to be resolved urgently.
为解决上述问题,本实用新型的目的在于提供安装方便、节省占地面积、方便人员至平台工作、实用性强的一种220kV架空线路和电缆线路连接用的电缆登塔。In order to solve the above problems, the purpose of this utility model is to provide a cable climbing tower for connecting 220kV overhead lines and cable lines, which is easy to install, saves floor space, facilitates personnel to work on the platform, and has strong practicability.
实用新型内容Utility model content
有鉴于现有技术的上述缺陷,本实用新型所要解决的技术问题是提供一种安装方便、节省占地面积、方便人员至平台工作、实用性强的一种220kV架空线路和电缆线路连接用的电缆登塔。In view of the above-mentioned defects of the prior art, the technical problem to be solved by the utility model is to provide a 220kV overhead line and cable line connection that is convenient for installation, saves floor space, facilitates personnel to work on the platform, and has strong practicability. Cable tower.
为实现上述目的,本实用新型提供了一种220kV架空线路和电缆线路连接用的电缆登塔,包括登塔本体,登塔本体两侧设有相互对称的平台,登塔本体一侧的平台上从内向外依次设有避雷器、支柱绝缘子、电缆户外终端,平台两侧设有3只支架,电缆沟位于电缆户外终端正下方的平台上,登塔本体周围设有围墙,围墙底部为镂空铁质围栏,镂空铁质围栏上方设有电子围栏,平台下方还设有连接地面与平台的爬梯。In order to achieve the above purpose, the utility model provides a cable climbing tower for connecting 220kV overhead lines and cable lines, including a climbing tower body, two sides of the climbing tower body are provided with mutually symmetrical platforms, and the platform on one side of the climbing tower body There are lightning arresters, post insulators, and cable outdoor terminals in order from the inside to the outside. There are 3 brackets on both sides of the platform. The cable trench is located on the platform directly below the cable outdoor terminals. There is a wall around the tower body, and the bottom of the wall is hollowed out. For the fence, there is an electronic fence above the hollow iron fence, and there is also a ladder connecting the ground and the platform below the platform.
进一步的,平台从地面以上12m处的登塔本体上向外引出。Further, the platform is drawn outward from the main body of the climbing tower 12m above the ground.
进一步的,平台长、宽、高为10m×7.75m×2m。Further, the length, width and height of the platform are 10m×7.75m×2m.
进一步的,避雷器高度为2.4m,爬距为7812mm,标称放电电流10kA。Furthermore, the height of the arrester is 2.4m, the creepage distance is 7812mm, and the nominal discharge current is 10kA.
进一步的,电缆户外终端爬距不小于7850mm。Furthermore, the creepage distance of the cable outdoor terminal is not less than 7850mm.
进一步的,支柱绝缘子额定弯曲负荷不小于8kN。Further, the rated bending load of the post insulator is not less than 8kN.
进一步的,电缆沟长、宽为2m×8m,镂空铁质围栏高度为3m,电子围栏高度为1.5m。Furthermore, the length and width of the cable trench are 2m×8m, the height of the hollow iron fence is 3m, and the height of the electronic fence is 1.5m.
进一步的,登塔平台至地面上有3付支架,且支架之间通过横担连接固定,保证支架的强度。Further, there are 3 pairs of supports from the tower climbing platform to the ground, and the supports are connected and fixed by cross arms to ensure the strength of the supports.
本实用新型的有益效果:The beneficial effects of the utility model:
本实用新型的登塔本体两侧设有相互对称的平台,登塔本体一侧的平台上从内向外依次设有避雷器、支柱绝缘子、电缆户外终端,平台两侧设有3付支架,电缆沟位于电缆户外终端正下方的平台上,登塔本体周围设有镂空铁质围栏,镂空铁质围栏上方设有电子围栏,平台下方还设有连接地面与平台的爬梯,具有安装方便、节省占地面积、方便人员至平台工作、实用性强的优点。Both sides of the climbing tower body of the utility model are provided with mutually symmetrical platforms, and the platform on one side of the climbing tower body is provided with lightning arresters, pillar insulators, and cable outdoor terminals in sequence from the inside to the outside. Located on the platform directly below the outdoor cable terminal, there is a hollow iron fence around the climbing tower body, an electronic fence above the hollow iron fence, and a ladder connecting the ground and the platform below the platform, which is easy to install and saves space. Small size, convenient for people to work on the platform, and strong practicability.
以下将结合附图对本实用新型的构思、具体结构及产生的技术效果作进一步说明,以充分地了解本实用新型的目的、特征和效果。The conception, specific structure and technical effects of the present utility model will be further described below in conjunction with the accompanying drawings, so as to fully understand the purpose, characteristics and effects of the present utility model.
附图说明Description of drawings
图1是本实用新型的平台结构俯视图。Fig. 1 is a top view of the platform structure of the present invention.
图2是本实用新型结构示意图。Fig. 2 is a structural schematic diagram of the utility model.
图3是本实用新型结构示意图。Fig. 3 is a structural schematic diagram of the utility model.
具体实施方式detailed description
如图1-图3所示,一种220kV架空线路和电缆线路连接用的电缆登塔,包括登塔本体1,所述登塔本体1两侧设有相互对称的平台2,所述登塔本体1一侧的平台2上从内向外依次设有避雷器3、支柱绝缘子4、电缆户外终端5,所述平台2两侧设有3只支架6,电缆沟7位于所述电缆户外终端5正下方的平台2上,所述登塔本体1周围设有围墙8,围墙8底部为镂空铁质围栏81,所述镂空铁质围栏81上方设有电子围栏82,所述平台2下方还设有连接地面与平台的爬梯9。As shown in Figures 1-3, a cable climbing tower for connecting 220kV overhead lines and cable lines includes a climbing tower body 1, and mutually symmetrical platforms 2 are arranged on both sides of the climbing tower body 1, and the climbing tower The platform 2 on one side of the main body 1 is provided with a lightning arrester 3, a post insulator 4, and an outdoor cable terminal 5 in order from the inside to the outside. There are three brackets 6 on both sides of the platform 2, and the cable trench 7 is located at the front of the cable outdoor terminal 5. On the platform 2 below, a wall 8 is provided around the tower body 1, and the bottom of the wall 8 is a hollow iron fence 81, an electronic fence 82 is arranged above the hollow iron fence 81, and an electronic fence 82 is arranged below the platform 2. The climbing ladder 9 that connects ground and platform.
本实用新型进一步优化的技术方案,所述平台2从地面以上12m处的登塔本体1上向外引,所述平台2长、宽、高为10m×7.75m×2m。本实施例中,所述避雷器3高度为2.4m,爬距为7812mm,标称放电电流10kA。In the further optimized technical solution of the utility model, the platform 2 is drawn outward from the climbing tower body 1 at 12m above the ground, and the length, width and height of the platform 2 are 10m×7.75m×2m. In this embodiment, the arrester 3 has a height of 2.4m, a creepage distance of 7812mm, and a nominal discharge current of 10kA.
此外,所述电缆户外终端5爬距不小于7850mm,支柱绝缘子4额定弯曲负荷不小于8kN。In addition, the creepage distance of the cable outdoor terminal 5 is not less than 7850mm, and the rated bending load of the post insulator 4 is not less than 8kN.
本实施例采用的电缆沟7长、宽为2m×8m,镂空铁质围栏高度为3m,电子围栏高度为1.5m。The length and width of the cable trench 7 used in this embodiment are 2m×8m, the height of the hollow iron fence is 3m, and the height of the electronic fence is 1.5m.
进一步的,登塔平台至地面上有3付支架,且支架之间通过横担连接固定,保证支架的强度。Further, there are 3 pairs of supports from the tower climbing platform to the ground, and the supports are connected and fixed by cross arms to ensure the strength of the supports.
本实用新型登塔本体两侧设有相互对称的平台,登塔本体一侧的平台上从内向外依次设有避雷器、支柱绝缘子、电缆户外终端,平台两侧设有3付支架,电缆沟位于电缆户外终端正下方的平台上,登塔本体周围设有镂空铁质围栏,镂空铁质围栏上方设有电子围栏,平台下方还设有连接地面与平台的爬梯,从而使其安装方便、节省占地面积、方便人员至平台工作、实用性强的优点。Both sides of the climbing tower body of the utility model are provided with mutually symmetrical platforms, and the platform on one side of the climbing tower body is provided with lightning arresters, pillar insulators, and outdoor cable terminals in sequence from the inside to the outside. On the platform directly below the outdoor cable terminal, there is a hollow iron fence around the climbing tower body, an electronic fence above the hollow iron fence, and a ladder connecting the ground and the platform below the platform, which makes it easy to install and saves space. It has the advantages of large floor area, convenience for personnel to work on the platform, and strong practicability.
以上详细描述了本实用新型的较佳具体实施例。应当理解,本领域的普通技术人员无需创造性劳动就可以根据本实用新型的构思做出诸多修改和变化。因此,凡本技术领域中技术人员依本实用新型的构思在现有技术的基础上通过逻辑分析、推理或者有限的实验可以得到的技术方案,皆应在由权利要求书所确定的保护范围内。The preferred specific embodiments of the present utility model have been described in detail above. It should be understood that those skilled in the art can make many modifications and changes according to the concept of the present utility model without creative efforts. Therefore, all technical solutions that can be obtained by those skilled in the art based on the concept of the utility model through logical analysis, reasoning or limited experiments on the basis of the prior art should be within the scope of protection defined by the claims .
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520576531.5U CN205077946U8 (en) | 2015-08-03 | 2015-08-03 | Tower stepped on by the cable that 220kV overhead transmission line and cable run connect |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520576531.5U CN205077946U8 (en) | 2015-08-03 | 2015-08-03 | Tower stepped on by the cable that 220kV overhead transmission line and cable run connect |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN205077946U true CN205077946U (en) | 2016-03-09 |
| CN205077946U8 CN205077946U8 (en) | 2016-08-10 |
Family
ID=55430360
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520576531.5U Expired - Lifetime CN205077946U8 (en) | 2015-08-03 | 2015-08-03 | Tower stepped on by the cable that 220kV overhead transmission line and cable run connect |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205077946U8 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667277A (en) * | 2018-12-25 | 2019-04-23 | 中国能源建设集团广东省电力设计研究院有限公司 | Cantilevered coupling beam cable termination field |
| CN115749418A (en) * | 2022-11-23 | 2023-03-07 | 国网河南省电力公司经济技术研究院 | Cable platform for double-loop steel pipe tower of power transmission line |
-
2015
- 2015-08-03 CN CN201520576531.5U patent/CN205077946U8/en not_active Expired - Lifetime
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667277A (en) * | 2018-12-25 | 2019-04-23 | 中国能源建设集团广东省电力设计研究院有限公司 | Cantilevered coupling beam cable termination field |
| CN115749418A (en) * | 2022-11-23 | 2023-03-07 | 国网河南省电力公司经济技术研究院 | Cable platform for double-loop steel pipe tower of power transmission line |
Also Published As
| Publication number | Publication date |
|---|---|
| CN205077946U8 (en) | 2016-08-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203654846U (en) | Steel pipe pole used for cable terminal of electric transmission line | |
| CN101202431B (en) | Insulation tower head for overhead lines of distribution network | |
| CN104295147B (en) | A kind of framework being applicable to transformer station's outlet | |
| CN205077946U (en) | 220kV overhead line and cable run connect cable of usefulness and step on tower | |
| CN206128808U (en) | Novel single loop cable dead end tower | |
| CN205502701U (en) | 750kV and 330kV thoughtlessly press 0~20 angle tower in four return circuits | |
| CN204391660U (en) | A kind of ultra-high-tension power transmission line list returns strain rod tower lead wire and earth wire arrangement system | |
| CN207260730U (en) | A kind of double loop cable termination tower | |
| CN202042864U (en) | Unbalance insulation earthing device for half-composite pole tower | |
| CN202042865U (en) | Earthing device of power transmission line of composite pole tower | |
| CN204174995U (en) | A kind of framework being applicable to transformer station's outlet | |
| CN206091522U (en) | Existing single loop strain insulator iron tower cable draws lower beam | |
| CN105098694A (en) | Overhead lightning line erection method based on typical design of power distribution network | |
| CN204899380U (en) | A tower is striden to straight lines height in two return circuits for 330kV alternating current transmission line | |
| CN203826907U (en) | Full-coverage overhead transmission line lightning protection apparatus | |
| CN108005458A (en) | Singly cut-off π sections towers in double loop | |
| CN203166445U (en) | Device using coupling ground line to reduce lightning trip-out rate of transmission line | |
| CN206422254U (en) | A kind of simple earthing or grounding means in base station | |
| CN207069293U (en) | One kind uses distribution framework made of composite insulating material | |
| CN202190040U (en) | Grounding bus connector of supporting insulator | |
| CN213869188U (en) | Double-circuit 110kV/220kV mixed-voltage transmission line tower on the same tower | |
| CN208335889U (en) | Composite insulation cross arm | |
| CN202550447U (en) | Lightning arrester for 10kv distribution line | |
| CN204040587U (en) | A kind of independent tower double back cable shoe platform | |
| CN205123211U (en) | Transmission of electricity corridor is with multi -functional shaft tower of lightning protection |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CGPU | Change to patent or to utility model | ||
| CU01 | Correction of utility model |
Correction item: Inventor Correct: Du Zhihang|Xu Zhenzhong|Wang Jiangbo|Zhu Jinglin|Lu Chenjian False: Du Zhihang|Zhu Jinglin|Lu Chenjian Number: 10 Page: The title page Volume: 32 |
|
| CU03 | Publication of corrected utility model |
Correction item: Inventor Correct: Du Zhihang|Xu Zhenzhong|Wang Jiangbo|Zhu Jinglin|Lu Chenjian False: Du Zhihang|Zhu Jinglin|Lu Chenjian Number: 10 Volume: 32 |
|
| ERR | Gazette correction | ||
| DD01 | Delivery of document by public notice |
Addressee: Li Haiyan Document name: Notice of amendment |
|
| CX01 | Expiry of patent term |
Granted publication date: 20160309 |
|
| CX01 | Expiry of patent term |