CN205077116U - Steel billet heating furnace walking beam who can local dismantlement changes - Google Patents

Steel billet heating furnace walking beam who can local dismantlement changes Download PDF

Info

Publication number
CN205077116U
CN205077116U CN201520844488.6U CN201520844488U CN205077116U CN 205077116 U CN205077116 U CN 205077116U CN 201520844488 U CN201520844488 U CN 201520844488U CN 205077116 U CN205077116 U CN 205077116U
Authority
CN
China
Prior art keywords
crossbeam
water
condenser tube
cooled tube
connecting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520844488.6U
Other languages
Chinese (zh)
Inventor
张洪雷
徐国涛
王悦
刘黎
周旺枝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Co Ltd
Original Assignee
Wuhan Iron and Steel Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Corp filed Critical Wuhan Iron and Steel Group Corp
Priority to CN201520844488.6U priority Critical patent/CN205077116U/en
Application granted granted Critical
Publication of CN205077116U publication Critical patent/CN205077116U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a steel billet heating furnace walking beam who can local dismantlement changes which by the crossbeam, with the stand that the crossbeam is connected, establish condenser tube, the component of the refractory castable layer condenser tube outside in crossbeam and stand, its condenser tube is divided into the condenser tube no. 1 of crossbeam and the condenser tube no. 2 of stand, be connected with the connecting plate no. 1 of taking the screw at condenser tube both ends of crossbeam, be connected with the connecting plate no. 2 of screw at the condenser tube's no. 2 of stand both ends corresponding to connecting plate no. 1, be connected with Y shape anchor assembly in the condenser tube outward appearance, be equipped with the layers of insulating fabric between condenser tube and refractory castable layer, be equipped with antiseized sediment coating on refractory castable layer surface, the bolt is equipped with in the screw of connecting plate no. 1 and connecting plate no. 2. The utility model discloses can carry out the part and change, and change swift convenience, improve the life cycle to can practice thrift raw and other materials, improve work efficiency, can prefabricate outside the stove, in order to guarantee its preparation quality.

Description

A kind of can partial disassembly change billet heating furnace walking beam
Technical field
The utility model relates to a kind of billet heating furnace, specifically belong to a kind of can partial disassembly change billet heating furnace walking beam.
Background technology
Existing process furnace walking beam, its structure is made up of crossbeam, column and water-cooled tube, and it is the monolithic be welded into, and can not break each other.Its installation method first crossbeam and column and water-cooled tube is installed in stove, then carry out pouring into a mould or ramming and being wrapped by water beam at water pipe surrounding refractory materials by mold sections, to reduce hot steel billet and furnace high-temperature to the destruction of water-cooled tube.In actual production, because the structure of its walking beam exists irrationality, as being mono-layer refractory, refractory masses easily peels off and easy dry slag, causes walking beam to move difficulty, impact is produced, also due between its crossbeam and column, both water-cooled tubes are monolithic, therefore when the water-cooled tube on crossbeam or the impaired generation of the water-cooled tube on column such as to be leaked at the fault, when needing to change in time, then need to carry out integral replacing.This causes not only wasting raw material, and causes repair and maintenance workload large, with duration, affects unit operation rate, and mainly in stove, prepares this walking beam, affect preparation efficiency even preparation quality.
Utility model content
The deficiency that the utility model exists for prior art, provides one to carry out local replacing, and changes efficient and convenient, improve life cycle, and can save material, increase work efficiency, can carry out outside stove prefabricated can the billet heating furnace walking beam changed of partial disassembly.
Realize the technical measures of above-mentioned purpose:
A kind of can partial disassembly change billet heating furnace walking beam, it is by crossbeam, the column that is connected with crossbeam, be located at the water-cooled tube in crossbeam and column, the refractory casting bed of material outside water-cooled tube forms, it is: water-cooled tube is divided into the water-cooled tube one of crossbeam and the water-cooled tube two of column; Be connected with the web plate one of band screw at water-cooled tube one two ends of crossbeam, correspond to the web plate two that web plate one is connected with screw at the two ends of the water-cooled tube two of column; Be connected with Y shape anchoring piece in water-cooled tube appearance, between water-cooled tube and the refractory casting bed of material, be provided with layers of insulating fabric; Slag adhesion coating is provided with on refractory casting bed of material surface; At the screw of web plate one and web plate two built with bolt.
Feature of the present utility model: can carry out local replacing, and change efficient and convenient, improves life cycle, and can save material, increase work efficiency, can carry out prefabricated outside stove, to ensure its preparation quality.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
In figure: 1-crossbeam, 2-column, 3-water-cooled tube, 4-refractory casting bed of material, 5-water-cooled tube one, 6-screw, 7-web plate one, 8-water-cooled tube two, 9-web plate two, 10-Y shape anchoring piece, 11-layers of insulating fabric, 12-slag adhesion coating, 13-bolt.
Embodiment
Be described further below in conjunction with accompanying drawing:
A kind of can partial disassembly change billet heating furnace walking beam, it is by crossbeam 1, the column 2 that is connected with crossbeam 1, be located at crossbeam 1 and the water-cooled tube 3 in column 2, the refractory casting bed of material 4 outside water-cooled tube forms, its water-cooled tube 3 is divided into the water-cooled tube 1 of crossbeam 1 and the water-cooled tube 28 of column 2; Adopt at water-cooled tube 1 two ends of crossbeam 1 welding process to be connected with the web plate 1 of band screw 6, correspond to web plate 1 at the two ends of the water-cooled tube 28 of column 2 and adopt welding process to be connected with the web plate 29 of screw 6; Be welded with Y shape anchoring piece 10 at water-cooled tube 1 and water-cooled tube 28 appearance, between water-cooled tube 1 and the water-cooled tube 28 refractory casting bed of material 4 corresponding with it, be provided with layers of insulating fabric 11; Slag adhesion coating 12 is provided with on the refractory casting bed of material 4 surface; At the screw 6 of web plate 1 and web plate 29 built with bolt 13.
Principle of work is same as prior art.
This embodiment is only the best and exemplifies, the restricted enforcement not to technical solutions of the utility model.

Claims (1)

1. one kind can partial disassembly change billet heating furnace walking beam, it is by crossbeam, the column that is connected with crossbeam, be located at the water-cooled tube in crossbeam and column, the refractory casting bed of material outside water-cooled tube forms, it is characterized in that: water-cooled tube is divided into the water-cooled tube one of crossbeam and the water-cooled tube two of column; Be connected with the web plate one of band screw at water-cooled tube one two ends of crossbeam, correspond to the web plate two that web plate one is connected with screw at the two ends of the water-cooled tube two of column; Be connected with Y shape anchoring piece in water-cooled tube appearance, between water-cooled tube and the refractory casting bed of material, be provided with layers of insulating fabric; Slag adhesion coating is provided with on refractory casting bed of material surface; At the screw of web plate one and web plate two built with bolt.
CN201520844488.6U 2015-10-28 2015-10-28 Steel billet heating furnace walking beam who can local dismantlement changes Expired - Fee Related CN205077116U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520844488.6U CN205077116U (en) 2015-10-28 2015-10-28 Steel billet heating furnace walking beam who can local dismantlement changes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520844488.6U CN205077116U (en) 2015-10-28 2015-10-28 Steel billet heating furnace walking beam who can local dismantlement changes

Publications (1)

Publication Number Publication Date
CN205077116U true CN205077116U (en) 2016-03-09

Family

ID=55429534

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520844488.6U Expired - Fee Related CN205077116U (en) 2015-10-28 2015-10-28 Steel billet heating furnace walking beam who can local dismantlement changes

Country Status (1)

Country Link
CN (1) CN205077116U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109114975A (en) * 2018-09-18 2019-01-01 安徽马钢设备检修有限公司 A kind of walking beam furnace water cooling beam column installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109114975A (en) * 2018-09-18 2019-01-01 安徽马钢设备检修有限公司 A kind of walking beam furnace water cooling beam column installation method

Similar Documents

Publication Publication Date Title
CN102443685B (en) Method for constructing middle trough lining of vacuum chamber of vacuum circulating degasification furnace
CN205077116U (en) Steel billet heating furnace walking beam who can local dismantlement changes
CN203610633U (en) Cored crystallization system for up-drawing continuous casting of copper tubes and copper alloy tubes
CN203947123U (en) A kind of converter tap hole tube of being convenient to carry out guide-localization
CN201497368U (en) Composite roller for roller hearth furnace
CN103471396A (en) Masonry construction structure of heating furnace bottom
CN202655584U (en) Crystallizer of hollow pipe billet
CN207395482U (en) A kind of air-cooled hanging moving partition wall of annular furnace
CN203382784U (en) Desulfurization spray gun
CN204830854U (en) Online lower cone with alloy heating furnace
CN203489692U (en) Stepped heating furnace bottom brick seat structure
CN203212593U (en) Swing chute of composite material
CN203489691U (en) Hearth masonry construction of heating furnace
CN203586816U (en) Building structure for lower opening of hot air returning pipe
CN207512211U (en) A kind of molding alloy chute of refining furnace gravity flow
CN204286120U (en) A kind of cement kiln preheaters inner core wall built-up
CN202555333U (en) Roller sleeve resetting device
CN204678908U (en) Dumpage type electric arc furnaces
CN102699291B (en) Crystallizer device for continuously casting hollow tube blanks
CN201210011Y (en) Anchor device used in fire resistant pouring material
CN204043402U (en) A kind of fluidized bed furnace wall reinforcement drag hook
CN201527185U (en) Heating furnace skirt hem brick
CN202382574U (en) H-steel large-span heating furnace
CN202973907U (en) Prefabricated brick convenient to install
CN202041076U (en) Crucible

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170713

Address after: 430083 Qingshan District, Hubei, Wuhan factory before the door No. 2

Patentee after: Wuhan iron and Steel Company Limited

Address before: 430080 Wuhan, Hubei Friendship Road, No. 999, Wuchang

Patentee before: Wuhan Iron & Steel (Group) Corp.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160309

Termination date: 20201028

CF01 Termination of patent right due to non-payment of annual fee