CN205046931U - Steel pipe shaft tower is cut -off to two sides in two return circuits that adopt triangle -shaped cross arm to arrange - Google Patents
Steel pipe shaft tower is cut -off to two sides in two return circuits that adopt triangle -shaped cross arm to arrange Download PDFInfo
- Publication number
- CN205046931U CN205046931U CN201520685697.0U CN201520685697U CN205046931U CN 205046931 U CN205046931 U CN 205046931U CN 201520685697 U CN201520685697 U CN 201520685697U CN 205046931 U CN205046931 U CN 205046931U
- Authority
- CN
- China
- Prior art keywords
- arm
- cross
- breaking
- tower body
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
一种采用三角形横担布置的双回路双侧开断钢管杆塔。它包括塔身、顶层地线横担、上层导线横担、下层导线横担,所述顶层地线横担自塔身背向开断侧布置一边垂直于目标开断线路的横担,面向开断侧布置一边三角形横担;所述上层导线横担分三层,每层自塔身平行目标开断线路布置两边横担,自塔身背向开断侧垂直目标开断线路布置一边横担;所述下层导线横担分三层,每层自塔身面向开断侧布置一边三角形横担。本实用新型仅采用一基杆塔实现双回路双侧开断,减少了杆塔数量;开断后形成四回路继续走线,避免四回路分支杆的使用,不改变相邻杆塔的导线布置方式,降低了邻塔改造的可能。
The utility model relates to a double-circuit double-side breaking steel pipe tower adopting a triangular cross-arm arrangement. It includes a tower body, a top-level ground wire cross-arm, an upper-level wire cross-arm, and a lower-layer wire cross-arm. One triangular cross arm is arranged on the broken side; the upper conductor cross arm is divided into three layers, each layer is arranged with two cross arms parallel to the target breaking line from the tower body, and one side cross arm is arranged perpendicular to the target breaking line from the back of the tower body to the breaking side ; The lower conductor cross-arm is divided into three layers, and each layer is arranged with a triangular cross-arm from the tower body to the breaking side. The utility model only adopts one base pole tower to realize double-circuit double-side disconnection, which reduces the number of pole towers; after disconnection, a four-circuit circuit is formed to continue routing, avoiding the use of four-circuit branch poles, and does not change the wire layout of adjacent pole towers, reducing the Possibility of renovation of adjacent tower.
Description
技术领域:Technical field:
本实用新型涉及高压输电线路技术领域,尤其涉及一种采用三角形横担布置的双回路双侧开断钢管杆塔。 The utility model relates to the technical field of high-voltage transmission lines, in particular to a steel pipe pole tower with double-circuit double-side breaking and adopting triangular cross-arm arrangement.
背景技术:Background technique:
在现有高压输电线路工程中,经常出现双回输电线路同时开断接入新建变电站的情况,通常采用在原双回线路下方新建两基双回路耐张杆塔,形成两条双回线路继续走线,随着城区高压走廊逐渐紧张,要求线路开断后通过四回路分支杆形成一条四回线路走线,该开断方式存在新建杆塔数量较多,占地面积较大,线路走廊较宽等问题,实施难度较大。 In existing high-voltage transmission line projects, double-circuit transmission lines are often disconnected and connected to new substations at the same time. Usually, two bases and double-circuit tension towers are built under the original double-circuit line to form two double-circuit lines and continue to run. , as the high-voltage corridor in the urban area is gradually tense, it is required to form a four-circuit line route through the four-circuit branch pole after the line is disconnected. This breaking method has problems such as a large number of new towers, a large footprint, and a wide line corridor. It is difficult to implement.
发明内容:Invention content:
本实用新型的目的是提供一种采用三角形横担布置的双回路双侧开断钢管杆塔,仅采用一基杆塔实现双回路双侧开断,减少了杆塔数量;开断后形成四回路继续走线,避免四回路分支杆的使用,不改变相邻杆塔的导线布置方式,降低了邻塔改造的可能。 The purpose of this utility model is to provide a double-circuit double-side breaking steel pipe pole tower with a triangular cross-arm arrangement. Only one base pole tower is used to realize double-circuit double-side breaking, which reduces the number of pole towers; after breaking, four circuits are formed to continue routing , avoid the use of four-circuit branch poles, do not change the wire arrangement of adjacent towers, and reduce the possibility of transformation of adjacent towers.
为了解决背景技术中存在的问题,本实用新型采用以下技术方案:它包括塔身、顶层地线横担、上层导线横担、下层导线横担,所述塔身顶端设置有顶层地线横担,顶层地线横担下方设置有上层导线横担,上层导线横担下方设置有下层导线横担; In order to solve the problems existing in the background technology, the utility model adopts the following technical scheme: it includes a tower body, a top ground wire cross arm, an upper layer wire cross arm, and a lower layer wire cross arm, and the top of the tower body is provided with a top ground wire cross arm , there is an upper-layer wire cross-arm under the top-layer ground wire cross-arm, and a lower-layer wire cross-arm is arranged under the upper-layer wire cross-arm;
所述顶层地线横担自塔身背向开断侧布置一边垂直于目标开断线路的横担,面向开断侧布置一边三角形横担; The ground wire cross arm on the top floor is arranged from the back of the tower body to the breaking side, and a cross arm perpendicular to the target breaking line is arranged, and a triangular cross arm is arranged facing the breaking side;
所述上层导线横担分三层,每层自塔身平行目标开断线路布置两边横担,自塔身背向开断侧垂直目标开断线路布置一边横担; The upper conductor crossarm is divided into three layers, each layer is arranged with two crossarms parallel to the target breaking line from the tower body, and one side crossarm is arranged perpendicular to the target breaking line from the back of the tower body to the breaking side;
所述下层导线横担分三层,每层自塔身面向开断侧布置一边三角形横担; The lower conductor cross-arm is divided into three layers, and each layer is arranged with a triangular cross-arm from the tower body to the breaking side;
所述三角形横担的三边横担呈等腰三角形布置,自塔身固定三角形横担的顶角,三角形横担的底边平行目标开断线路方向。 The three sides of the triangular cross arm are arranged in an isosceles triangle, the top angle of the triangular cross arm is fixed from the tower body, and the bottom edge of the triangular cross arm is parallel to the direction of the target breaking line.
本实用新型相比于现有技术方案具有以下优点: Compared with the prior art solutions, the utility model has the following advantages:
1)不改变目标开断线路导线布置,降低了目标开断线路相邻杆塔难以满足电气间隙要求的可能; 1) The wire layout of the target breaking line is not changed, which reduces the possibility that the adjacent towers of the target breaking line are difficult to meet the electrical clearance requirements;
2)仅利用一基本专利杆塔即可完成双回路双侧开断,新建杆塔数量较少,节约投资; 2) Only one basic patent tower can be used to complete double-circuit double-sided breaking, and the number of new towers is small, saving investment;
3)开断形成四回线路继续走线,原四回路分支塔可根据现场实际情况采用直线杆(或小角度转角杆)代替,降低了杆塔使用条件,缩减了线路走廊; 3) The four-circuit line is disconnected and continues to run. The original four-circuit branch tower can be replaced by a straight pole (or a small-angle corner pole) according to the actual situation on site, which reduces the use conditions of the pole tower and reduces the line corridor;
4)三角形横担有利于抵消目标开断线路与开断后形成线路对横担的受力,整体结构更稳定。 4) The triangular cross-arm is beneficial to offset the force on the cross-arm of the target breaking line and the formed line after breaking, and the overall structure is more stable.
附图说明:Description of drawings:
图1为本实用新型的结构示意图; Fig. 1 is the structural representation of the utility model;
图2为图1的右视图; Fig. 2 is the right view of Fig. 1;
图3为顶层地线横担的结构示意图; Fig. 3 is a structural schematic diagram of the cross arm of the ground wire on the top floor;
图4为上层导线横担的结构示意图; Fig. 4 is a structural schematic diagram of the upper-layer conductor cross-arm;
图5为下层导线横担的结构示意图; Fig. 5 is a structural schematic diagram of the lower conductor cross-arm;
图6为本实用新型接线示意图。 Fig. 6 is a schematic diagram of wiring of the utility model.
具体实施方式:detailed description:
参照图1-2,本实用新型它包括塔身1、顶层地线横担2、上层导线横担3、下层导线横担4,所述塔身1顶端设置有顶层地线横担2,顶层地线横担2下方设置有上层导线横担3,上层导线横担3下方设置有下层导线横担4; Referring to Fig. 1-2, the utility model comprises a tower body 1, a top ground wire cross arm 2, an upper layer wire cross arm 3, and a lower layer wire cross arm 4, the top of the tower body 1 is provided with a top ground wire cross arm 2, and An upper-layer wire cross-arm 3 is arranged below the ground wire cross-arm 2 , and a lower-layer wire cross-arm 4 is arranged below the upper-layer wire cross-arm 3 ;
参照图3,所述顶层地线横担2自塔身1背向开断侧布置一边垂直于目标开断线路的横担,面向开断侧布置一边三角形横担。 Referring to FIG. 3 , the top-floor ground wire crossarm 2 is arranged from the back of the tower body 1 to the breaking side with a crossarm perpendicular to the target breaking line, and a triangular crossarm is arranged facing the breaking side.
参照图4,所述上层导线横担3分三层,每层均呈T字型,每层自塔身1平行目标开断线路布置两边横担,自塔身1背向开断侧垂直目标开断线路布置一边横担。 Referring to Figure 4, the upper conductor cross arm 3 is divided into three layers, each layer is T-shaped, and each layer is arranged with cross arms on both sides from the tower body 1 parallel to the target breaking line, and from the tower body 1 back to the breaking side vertical target The breaking line is arranged on one side of the cross arm.
参照图5,所述下层导线横担4分三层,每层自塔身1面向开断侧布置一边三角形横担。 Referring to Fig. 5, the lower conductor cross-arm 4 is divided into three layers, and each layer is arranged with a triangular cross-arm from the tower body 1 to the breaking side.
参照图1-5,所述三角形横担的三边横担呈等腰三角形布置,自塔身固定三角形横担的顶角,三角形横担的底边平行目标开断线路方向。所述三角形横担顶点垂直于底边高的长度由原线路导地线布置决定;所述三角形横担底边的长度由开断形成四回线路导地线布置决定。 Referring to Figures 1-5, the three sides of the triangular cross arm are arranged in an isosceles triangle, the top angle of the triangular cross arm is fixed from the tower body, and the bottom edge of the triangular cross arm is parallel to the direction of the target breaking line. The length of the apex of the triangular cross-arm perpendicular to the height of the base is determined by the arrangement of the ground wires of the original line; the length of the bottom of the triangular cross-arm is determined by the arrangement of the ground wires of the disconnected and formed four-circuit line.
参照图6,于目标线路下方新建一基本实用新型杆塔,在上层导线横担中垂直于目标开断线路的横担上悬挂线路远离开断侧的导线,平行于目标开断线路的横担上悬挂开断后形成线路,利用上层导线横担中平行于线路方向的横担稍部悬挂跳线串,利用跳线串与跳线实现线路连通。在下层导线横担中三角形底边的两端处悬挂目标开断线路导线与开断后形成线路导线,顶层地线横担的垂直于目标开断线路地线的一边横担悬挂目标开断线路的地线,顶层地线横担的三角形横担的底边横担的两端处悬挂开断线路地线及开断后形成线路地线。 With reference to Fig. 6, build a new basic utility model pole tower below the target line, hang the wire on the cross arm perpendicular to the target breaking line on the cross arm of the upper layer conductor far away from the broken side, and parallel to the cross arm of the target breaking line The line is formed after the suspension is broken, and the jumper string is suspended from the cross-arm point parallel to the line direction in the upper-layer conductor cross-arm, and the line connection is realized by using the jumper string and the jumper wire. Suspend the target breaking line conductor at the two ends of the bottom edge of the triangle in the lower layer conductor cross arm and form the line conductor after breaking, and hang the target breaking line on the side of the top floor ground wire cross arm Ground wire, the two ends of the bottom side cross arm of the triangular cross arm of the ground wire cross arm of the top layer are suspended to break the line ground wire and form the line ground wire after breaking.
所述上层导线横担平行于目标开断线路方向的横担长度由开断后形成线路的导线布置方式决定,垂直于目标开断线路方向的横担长度由原线路的导线布置方式决定。 The length of the cross arm of the upper layer wire parallel to the direction of the target breaking line is determined by the arrangement of the wires forming the line after breaking, and the length of the cross arm perpendicular to the direction of the target breaking line is determined by the arrangement of the wires of the original line.
所述顶层地线横担、上层导线横担、下层导线横担长度及间距需考虑导线间和导地线间电气距离、导线与塔身的电气距离、上下层相邻导线间的最小水平偏移距离。 The length and spacing of the top-layer ground wire cross-arm, upper-layer wire cross-arm, and lower-layer wire cross-arm need to consider the electrical distance between the wires and the ground wires, the electrical distance between the wires and the tower body, and the minimum horizontal deviation between the upper and lower adjacent wires. Move distance.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520685697.0U CN205046931U (en) | 2015-09-07 | 2015-09-07 | Steel pipe shaft tower is cut -off to two sides in two return circuits that adopt triangle -shaped cross arm to arrange |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520685697.0U CN205046931U (en) | 2015-09-07 | 2015-09-07 | Steel pipe shaft tower is cut -off to two sides in two return circuits that adopt triangle -shaped cross arm to arrange |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205046931U true CN205046931U (en) | 2016-02-24 |
Family
ID=55340525
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520685697.0U Expired - Lifetime CN205046931U (en) | 2015-09-07 | 2015-09-07 | Steel pipe shaft tower is cut -off to two sides in two return circuits that adopt triangle -shaped cross arm to arrange |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205046931U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105155911A (en) * | 2015-09-07 | 2015-12-16 | 安徽华电工程咨询设计有限公司 | Double-loop double-side on-off steel tube role tower adopting triangular cross beam arrangement |
| CN109914897A (en) * | 2019-03-31 | 2019-06-21 | 中国电建集团福建省电力勘测设计院有限公司 | Double back overhead transmission line is cut-off with three-dimensional cross-arm steel pipe pole |
| CN110729692A (en) * | 2019-12-02 | 2020-01-24 | 上海神马电力工程有限公司 | Tensile transmission tower |
-
2015
- 2015-09-07 CN CN201520685697.0U patent/CN205046931U/en not_active Expired - Lifetime
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105155911A (en) * | 2015-09-07 | 2015-12-16 | 安徽华电工程咨询设计有限公司 | Double-loop double-side on-off steel tube role tower adopting triangular cross beam arrangement |
| CN109914897A (en) * | 2019-03-31 | 2019-06-21 | 中国电建集团福建省电力勘测设计院有限公司 | Double back overhead transmission line is cut-off with three-dimensional cross-arm steel pipe pole |
| CN109914897B (en) * | 2019-03-31 | 2024-02-23 | 中国电建集团福建省电力勘测设计院有限公司 | Three-way cross arm steel pipe pole for cutting off double-circuit overhead line |
| CN110729692A (en) * | 2019-12-02 | 2020-01-24 | 上海神马电力工程有限公司 | Tensile transmission tower |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105298201B (en) | Transmission line cable termination solid draws lower device | |
| CN205046931U (en) | Steel pipe shaft tower is cut -off to two sides in two return circuits that adopt triangle -shaped cross arm to arrange | |
| CN105155914A (en) | Cut-off angle steel tower for single-loop power transmission line | |
| CN103603536A (en) | Multi-loop crisscross-spanning steel pipe pole | |
| CN105257067A (en) | Double-circuit double-sided breaking steel-tube tower using V-shaped combined strings | |
| CN204920402U (en) | Transmission line single loop chamfer tower | |
| CN105257061A (en) | Single-circuit tower with variable nominal height | |
| CN205116866U (en) | Device is down drawn to transmission line cable termination solid | |
| CN203352105U (en) | A wire arrangement mode converting rod | |
| CN105155911B (en) | A kind of double loop bilateral using triangle cross-arm arrangement cut-offs steel pipe tower | |
| CN205046915U (en) | Adopt two sides in two return circuits of V style of calligraphy combination cluster to cut -off steel pipe shaft tower | |
| CN105155902B (en) | A kind of compact double circuit, which becomes, exhales high shaft tower | |
| CN105155910B (en) | A kind of single loop that string is combined using V-shape cut-offs steel pipe tower | |
| CN203846844U (en) | Double-circuit line joint use coordinated transposition post tower | |
| CN205046914U (en) | Single loop that adopts triangle -shaped cross arm cut -offs steel pipe shaft tower | |
| CN105155912B (en) | A kind of single loop using triangle cross-arm cut-offs steel pipe tower | |
| CN105155916A (en) | Single-loop angle steel tower with positive and negative phase-sequence transformation | |
| CN205046917U (en) | Two return circuits unilateral cut -offs cable and draws tangent tower down | |
| CN105155909A (en) | Steel tube pole tower for cutting single loop into different phase sequence arrangement | |
| CN204645804U (en) | Four times overhead wire divides pole | |
| CN205000712U (en) | Single loop cut -offs into steel pipe shaft tower that different phase sequences were arranged | |
| CN205046918U (en) | Single time transmission line cut -offs angle -steel tower | |
| CN205046930U (en) | Positive negative phase sequence of single loop transform angle -steel tower | |
| CN205046913U (en) | Single loop that adopts V style of calligraphy combination cluster cut -offs steel pipe shaft tower | |
| CN111827771A (en) | Branch tower for four-circuit overhead transmission line |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| AV01 | Patent right actively abandoned |
Granted publication date: 20160224 Effective date of abandoning: 20180313 |
|
| AV01 | Patent right actively abandoned |