CN204940616U - The integrated prefabricated concrete folding wallboard of a kind of modular door and window - Google Patents

The integrated prefabricated concrete folding wallboard of a kind of modular door and window Download PDF

Info

Publication number
CN204940616U
CN204940616U CN201520576818.8U CN201520576818U CN204940616U CN 204940616 U CN204940616 U CN 204940616U CN 201520576818 U CN201520576818 U CN 201520576818U CN 204940616 U CN204940616 U CN 204940616U
Authority
CN
China
Prior art keywords
window
edge sealing
baffle plate
sealing baffle
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520576818.8U
Other languages
Chinese (zh)
Inventor
丁泓
汪力
恽燕春
樊骅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoye Group Co ltd
Shanghai Baoyue Residential Industry Co ltd
Original Assignee
Shanghai Zibao Housing Industrialization Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zibao Housing Industrialization Co Ltd filed Critical Shanghai Zibao Housing Industrialization Co Ltd
Priority to CN201520576818.8U priority Critical patent/CN204940616U/en
Application granted granted Critical
Publication of CN204940616U publication Critical patent/CN204940616U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Door And Window Frames Mounted To Openings (AREA)

Abstract

The utility model relates to the integrated prefabricated concrete folding wallboard of a kind of modular door and window, comprises inside and outside precoated plate layer, cast-in-situ concrete layer, reserved opening, auxiliary frame, edge sealing baffle plate, attaching nut, window frame; Cast-in-situ concrete layer between inside and outside precoated plate layer, be reserved opening in the middle of it, reserved opening surrounding arranges edge sealing baffle plate respectively, and edge sealing baffle plate is fixedly connected with inside and outside precoated plate layer by attaching nut, attaching nut has magnetic capping, and magnetic capping is adsorbed on the mould of steel limit; Auxiliary frame is located at inside edge sealing baffle plate, for window frame is fixed on edge sealing baffle plate.The capping of the utility model magnetic ensures that attaching nut can accurately locate; Window frame is installed in factory, namely ensures workmanship, enhances productivity again; The existence of edge sealing baffle plate, on-the-spot window hole place, without the need to formwork, decreases site work amount and quantity of refuse; The replacing of window frame is convenient in the existence of secondary frame, and flexibility improves greatly; Reinforcing bar improves the globality of edge sealing baffle plate and prefabricated panel.

Description

一种组装式的门窗一体化预制混凝土叠合墙板An assembled prefabricated concrete laminated wall panel with integrated doors and windows

技术领域 technical field

本实用新型涉及一种组装式的门窗一体化预制混凝土叠合墙板,属于建筑结构技术领域。 The utility model relates to an assembled door and window integrated prefabricated concrete laminated wall panel, which belongs to the technical field of building structures.

背景技术 Background technique

随着建筑业体制改革的不断深化和建筑规模的持续扩大,建筑业发展较快,其中建筑工业化不断受到政府和社会的关注,已然成为我国建筑业的发展方向。预制混凝土装配建筑作为建筑工业化的重点发展方向,越来越得到行业相关人员的重视和认可。而建筑工业化的一个重点发展方向是减少工地现场工作量,将大部分的工作搬到工厂完成,可有效提高工程质量、降低污染、保证进度。 With the continuous deepening of the reform of the construction industry system and the continuous expansion of the construction scale, the construction industry has developed rapidly. Among them, the construction industrialization has been continuously concerned by the government and society, and has become the development direction of my country's construction industry. As the key development direction of construction industrialization, prefabricated concrete assembly building has been more and more valued and recognized by relevant personnel in the industry. A key development direction of construction industrialization is to reduce the workload on the construction site and move most of the work to the factory to complete, which can effectively improve the quality of the project, reduce pollution, and ensure the progress.

预制混凝土叠合墙板作为预制混凝土的一种重要构件,现阶段还必须在现场进行窗框安装,无法充分体现预制混凝土装配建筑的优势。 As an important component of precast concrete, precast concrete laminated wall panels must be installed on site at this stage, which cannot fully reflect the advantages of precast concrete assembly buildings.

发明内容 Contents of the invention

本实用新型需要解决的技术问题是:现有的预制混凝土叠合墙板,需要在现场进行窗框安装,无法充分体现预制混凝土装配建筑的优势。 The technical problem to be solved by the utility model is: the existing prefabricated concrete laminated wall panels need to install window frames on site, which cannot fully reflect the advantages of prefabricated concrete assembly buildings.

本实用新型采取以下技术方案: The utility model takes the following technical solutions:

一种组装式的门窗一体化预制混凝土叠合墙板,包括内、外预制板层3、4、现浇混凝土层、预留洞口、副框9、封边挡板7、连接螺母2、窗框10;所述内外预制板层3、4之间是现浇混凝土层,其中间为预留洞口,预留洞口四周分别设置封边挡板7,所述封边挡板通过连接螺母2与内外预制板层3、4固定连接,所述连接螺母2具有磁性封盖2c,磁性封盖2c吸附在钢制边模上;所述副框9设于封边挡板7内侧,用于将窗框10固定在封边挡板7上。 An assembled door and window integrated prefabricated concrete laminated wall panel, including inner and outer prefabricated slab layers 3 and 4, cast-in-place concrete layers, reserved openings, sub-frames 9, edge baffles 7, connecting nuts 2, window Frame 10; between the inner and outer prefabricated slab layers 3 and 4 is a cast-in-situ concrete layer, in the middle of which is a reserved opening, and edge sealing baffles 7 are respectively arranged around the reserved openings, and the edge sealing baffles are connected to each other through connecting nuts 2 The inner and outer prefabricated board layers 3 and 4 are fixedly connected, the connecting nut 2 has a magnetic cover 2c, and the magnetic cover 2c is adsorbed on the steel side mold; The window frame 10 is fixed on the edge baffle 7 .

进一步的,所述现浇混凝土层内固定设置桁架筋5。 Further, truss bars 5 are fixedly arranged in the cast-in-situ concrete layer.

进一步的,所述内、外预制板层3、4内固定横向受力筋11、竖向受力筋12、设置补强钢筋1。 Further, the inner and outer prefabricated slabs 3 and 4 are internally fixed with transverse stress bars 11 and vertical stress bars 12, and reinforcing steel bars 1 are provided.

进一步的,所述连接螺母2上端具有T型杆2a、中部具有预埋螺母2b、底部具有磁性封盖2c。 Further, the connecting nut 2 has a T-shaped bar 2a at the upper end, a built-in nut 2b at the middle, and a magnetic cover 2c at the bottom.

进一步的,所述副框9为镀锌方管。 Further, the sub-frame 9 is a galvanized square tube.

本实用新型的有益效果在于: The beneficial effects of the utility model are:

1、磁性封盖的存在,保证连接螺母能够精确定位,提高了窗框安装的精确; 1. The existence of the magnetic cover ensures the precise positioning of the connecting nut and improves the accuracy of the window frame installation;

2、窗框在工厂安装,即保证工程质量,又提高生产效率; 2. The window frame is installed in the factory, which not only ensures the quality of the project, but also improves the production efficiency;

3、封边挡板的存在,现场窗洞口处无需支模,减少了现场工作量和垃圾量; 3. With the existence of edge-banding baffles, there is no need to support formwork at the window opening on site, which reduces the workload and amount of garbage on site;

4、不同于传统预制混凝土实心墙板窗框直接与混凝土接触,叠合墙板副框的存在便于窗框的更换,灵活性大大提高; 4. Different from the traditional prefabricated concrete solid wall panel window frame directly in contact with the concrete, the existence of the sub-frame of the laminated wall panel facilitates the replacement of the window frame, and the flexibility is greatly improved;

5、补强钢筋的存在,提高了封边挡板与预制墙板的整体性,预制墙板在生产、运输、施工等过程中出现开裂和破坏。 5. The existence of reinforcing steel bars improves the integrity of the edge baffle and prefabricated wall panels, and the prefabricated wall panels crack and damage during production, transportation, construction and other processes.

附图说明 Description of drawings

图1是带窗洞叠合墙板的侧面剖视图。 Figure 1 is a side sectional view of a laminated wall panel with a window hole.

图2是带窗洞叠合墙板的主视图。 Fig. 2 is a front view of a laminated wall panel with window holes.

图3是图2的局部放大图。 FIG. 3 is a partially enlarged view of FIG. 2 .

图4是图1上部的局部放大图。 Fig. 4 is a partial enlarged view of the upper part of Fig. 1 .

图5是图1下部的局部放大图。 Fig. 5 is a partially enlarged view of the lower part of Fig. 1 .

图6是安装封边挡板后的叠合墙板的侧面剖视图。 Fig. 6 is a side sectional view of the laminated wall panel after the edge sealing baffle is installed.

图7是安装封边挡板后的叠合墙板的主视图。 Fig. 7 is a front view of the laminated wall panel after the edge sealing baffle is installed.

图8是图7的局部放大图。 FIG. 8 is a partially enlarged view of FIG. 7 .

图9是图6上部的局部放大图。 Fig. 9 is a partially enlarged view of the upper part of Fig. 6 .

图10是图6下部的局部放大图。 Fig. 10 is a partially enlarged view of the lower part of Fig. 6 .

图11是窗户安装后的叠合墙板的侧面剖视图。 Figure 11 is a side cross-sectional view of a laminated wall panel with a window installed.

图12是窗户安装后的叠合墙板的主视图。 Figure 12 is a front view of the laminated wall panel after the window is installed.

图13是图11下部的局部放大图。 Fig. 13 is a partially enlarged view of the lower part of Fig. 11 .

图14是图11上部的局部放大图。 Fig. 14 is a partially enlarged view of the upper part of Fig. 11 .

图15是连接螺母的结构示意图。 Fig. 15 is a schematic structural view of a connecting nut.

图中,1.补强钢筋,2.连接螺母,2a.T型锚杆,2b.预埋螺母,2c.磁性封盖,3.内预制板层,4.外预制板层,5.桁架筋,6.连接螺母,7.封边挡板,8.密封条,9.副框,10.窗框,11.横向受力筋,12.竖向受力筋,13.钢制边模。 In the figure, 1. Reinforcing steel bar, 2. Connecting nut, 2a. T-shaped anchor rod, 2b. Embedded nut, 2c. Magnetic cover, 3. Inner prefabricated slab, 4. Outer prefabricated slab, 5. Truss Rib, 6. Connecting nut, 7. Edge baffle, 8. Sealing strip, 9. Sub-frame, 10. Window frame, 11. Horizontal stress rib, 12. Vertical stress rib, 13. Steel side formwork .

具体实施方式 detailed description

下面结合附图和具体实施例对本实用新型进一步说明。 Below in conjunction with accompanying drawing and specific embodiment the utility model is further described.

参见图1-图15,本实用新型一种组装式的门窗一体化叠合墙板,包括外预制层3、现浇钢筋混凝土层、内预制层4、预留洞口、副框9、封边挡板7、连接螺母2、窗框10。现浇钢筋混凝土层内设置有桁架筋5,外预制板层3和内预制板层4内均设置有纵横向受力钢筋,桁架筋5与外预制板层4、内预制板层3内的纵横向受力钢筋均进行固定。预留洞口四周用补强钢筋1进行加固。副框9通过自攻螺母与封边挡板7固定。封边挡板7通过固定螺钉穿过钢套管与预埋于内外预制混凝土中的连接螺母2固定,封边挡板7与内、外预制层接触面加设密封条8。窗框10通过自攻螺母穿过封边挡板7固定于副框9上。窗框10在工厂进行防水、保温处理。 Referring to Fig. 1-Fig. 15, an assembled door and window integrated laminated wall panel of the utility model includes an outer prefabricated layer 3, a cast-in-place reinforced concrete layer, an inner prefabricated layer 4, reserved openings, a sub-frame 9, and edge sealing Baffle plate 7, connecting nut 2, window frame 10. The cast-in-place reinforced concrete layer is provided with truss bars 5, the outer prefabricated slab 3 and the inner precast slab 4 are provided with longitudinal and transverse stress reinforcement, and the truss bars 5 and the outer precast slab 4 and the inner precast slab 3 The vertical and horizontal reinforced steel bars are all fixed. Reinforcing steel bars 1 are used around the reserved opening. The sub-frame 9 is fixed to the edge baffle 7 by self-tapping nuts. The edge sealing baffle 7 is fixed through the steel casing and the connecting nut 2 embedded in the inner and outer precast concrete by fixing screws, and the sealing strip 8 is added on the contact surface between the edge sealing baffle 7 and the inner and outer prefabricated layers. The window frame 10 is fixed on the sub-frame 9 through the edge sealing baffle 7 by self-tapping nuts. The window frame 10 is waterproofed and heat-insulated in the factory.

1)工厂生产步骤 1) Factory production steps

(a)内预制板层3制作:在绘制好定位线的底模上架设钢制边模,然后放样、绑扎纵横向受力钢筋、补强钢筋1、桁架筋5,固定连接螺母6,浇筑混凝土,送养护室; (a) Fabrication of inner prefabricated slab layer 3: set up steel side formwork on the bottom formwork with drawn positioning line, then stake out, tie longitudinal and transverse stress reinforcement, reinforcement reinforcement 1, truss reinforcement 5, fix connection nut 6, pour Concrete, sent to curing room;

(b)外预制板层4制作:在绘制好定位线的底模上架设钢制边模,然后在养护成型的内预制板层3上绑扎外预制层4纵横向受力钢筋、补强钢筋1,固定连接螺母6,最后在底模上浇筑混凝土,利用翻转装置将内预制板层3180度翻转后压入混凝土,送养护室; (b) Fabrication of the outer prefabricated slab 4: set up steel side forms on the bottom form with the drawn positioning line, and then bind the vertical and horizontal stress reinforcement and reinforcing steel bars of the outer prefabricated layer 4 on the cured and formed inner prefabricated slab 3 1. Fix the connecting nut 6, and finally pour concrete on the bottom mold, use the turning device to turn the inner prefabricated slab 3180 degrees, press it into the concrete, and send it to the curing room;

(c)将养护成型的内外预制板层拆除钢制边模,并拆除磁性封盖2c,在封边挡板7上通过自攻螺母固定副框9,在内外预制板层窗洞处预留密封条8,通过固定螺钉穿过钢套管将封边挡板与连接螺母固定。再用螺钉将窗框固定在副框9上,安装玻璃窗。 (c) Remove the steel side molds from the cured inner and outer prefabricated slabs, remove the magnetic cover 2c, fix the sub-frame 9 on the edge baffle 7 with self-tapping nuts, and reserve a seal at the window holes of the inner and outer prefabricated slabs Article 8, fix the edge banding baffle and the connecting nut through the steel sleeve through the fixing screw. The window frame is fixed on the secondary frame 9 with screws again, and the glass window is installed.

2)现场施工步骤 2) On-site construction steps

叠合墙板安装到位,现浇混凝土层浇筑混凝土即可。 The laminated wall panels are installed in place, and the cast-in-place concrete layer is poured with concrete.

本实用新型的窗框10采用塑钢窗框、铝合金窗框、木窗框、刚窗框中的任意一种,窗框10的防水、翻边保温处理均在工厂完成。 Window frame 10 of the present utility model adopts any one in plastic-steel window frame, aluminum alloy window frame, wooden window frame, just window frame, and the waterproofing of window frame 10, the heat preservation treatment of flanging is all finished in factory.

本实用新型磁性封盖的存在,保证连接螺母能够精确定位,提高了窗框安装的精确;窗框在工厂安装,即保证工程质量,又提高生产效率;封边挡板的存在,现场窗洞口处无需支模,减少了现场工作量和垃圾量;不同于传统预制混凝土实心墙板窗框直接与混凝土接触,叠合墙板副框的存在便于窗框的更换,灵活性大大提高;补强钢筋的存在,提高了封边挡板与预制墙板的整体性,预制墙板在生产、运输、施工等过程中出现开裂和破坏。 The existence of the magnetic cover of the utility model ensures that the connecting nuts can be positioned accurately, which improves the accuracy of the window frame installation; the window frame is installed in the factory, which not only ensures the quality of the project, but also improves the production efficiency; There is no need for formwork, which reduces the amount of on-site work and garbage; unlike traditional precast concrete solid wall panel window frames that are in direct contact with concrete, the existence of laminated wall panel sub-frames facilitates the replacement of window frames and greatly improves flexibility; Reinforcement The existence of steel bars improves the integrity of the edge banding baffle and prefabricated wall panels, and the prefabricated wall panels crack and damage during the production, transportation, construction and other processes.

Claims (5)

1. the integrated prefabricated concrete folding wallboard of modular door and window, is characterized in that:
Comprise inside and outside precoated plate layer (3,4), cast-in-situ concrete layer, reserved opening, secondary frame (9), edge sealing baffle plate (7), attaching nut (2), window frame (10);
Cast-in-situ concrete layer between described inside and outside precoated plate layer (3,4), be reserved opening in the middle of it, reserved opening surrounding arranges edge sealing baffle plate (7) respectively, described edge sealing baffle plate is fixedly connected with inside and outside precoated plate layer (3,4) by attaching nut (2), described attaching nut (2) has magnetic capping (2c), and magnetic capping (2c) is adsorbed on the mould of steel limit;
Described secondary frame (9) is located at edge sealing baffle plate (7) inner side, for window frame (10) is fixed on edge sealing baffle plate (7).
2. the integrated prefabricated concrete folding wallboard of modular door and window as claimed in claim 1, is characterized in that: described cast-in-situ concrete layer internal fixtion arranges girder rib (5).
3. the integrated prefabricated concrete folding wallboard of modular door and window as claimed in claim 1, is characterized in that: the described inside and outside precoated plate layer lateral stressed muscle of (3,4) internal fixtion (11), vertical applied force muscle (12), arrange reinforcing bar (1).
4. the integrated prefabricated concrete folding wallboard of modular door and window as claimed in claim 1, is characterized in that: described attaching nut (2) upper end has T-shaped bar (2a), middle part has embedded nut (2b), bottom has magnetic capping (2c).
5. the integrated prefabricated concrete folding wallboard of modular door and window as claimed in claim 1, is characterized in that: described secondary frame (9) is zinc-plated square tube.
CN201520576818.8U 2015-08-03 2015-08-03 The integrated prefabricated concrete folding wallboard of a kind of modular door and window Expired - Fee Related CN204940616U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520576818.8U CN204940616U (en) 2015-08-03 2015-08-03 The integrated prefabricated concrete folding wallboard of a kind of modular door and window

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520576818.8U CN204940616U (en) 2015-08-03 2015-08-03 The integrated prefabricated concrete folding wallboard of a kind of modular door and window

Publications (1)

Publication Number Publication Date
CN204940616U true CN204940616U (en) 2016-01-06

Family

ID=55008057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520576818.8U Expired - Fee Related CN204940616U (en) 2015-08-03 2015-08-03 The integrated prefabricated concrete folding wallboard of a kind of modular door and window

Country Status (1)

Country Link
CN (1) CN204940616U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499598A (en) * 2014-11-25 2015-04-08 张跃 Steel wire core modular heat insulation inner wall
CN110053128A (en) * 2019-03-19 2019-07-26 美好建筑装配科技有限公司 A kind of two-sided composite wallboard and its production technology with hole
CN111236500A (en) * 2020-03-19 2020-06-05 三一筑工科技有限公司 Laminated wall prefabricated member and production method thereof
CN111576683A (en) * 2020-03-10 2020-08-25 三一筑工科技有限公司 Laminated wall prefabricated member and production method thereof
CN114033099A (en) * 2021-11-30 2022-02-11 中建三局第二建设工程有限责任公司 Fixed structure for prefabricated laminated walls and prefabricated laminated wall components
CN115898199A (en) * 2022-11-15 2023-04-04 上海长三角宝业城市建设发展有限公司 A double-sided laminated wallboard sub-frame installation integrated structure
CN116696205A (en) * 2023-06-07 2023-09-05 中国十七冶集团有限公司 Wall-connecting window integrated plate and installation method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499598A (en) * 2014-11-25 2015-04-08 张跃 Steel wire core modular heat insulation inner wall
CN110053128A (en) * 2019-03-19 2019-07-26 美好建筑装配科技有限公司 A kind of two-sided composite wallboard and its production technology with hole
CN111576683A (en) * 2020-03-10 2020-08-25 三一筑工科技有限公司 Laminated wall prefabricated member and production method thereof
CN111236500A (en) * 2020-03-19 2020-06-05 三一筑工科技有限公司 Laminated wall prefabricated member and production method thereof
CN114033099A (en) * 2021-11-30 2022-02-11 中建三局第二建设工程有限责任公司 Fixed structure for prefabricated laminated walls and prefabricated laminated wall components
CN115898199A (en) * 2022-11-15 2023-04-04 上海长三角宝业城市建设发展有限公司 A double-sided laminated wallboard sub-frame installation integrated structure
CN116696205A (en) * 2023-06-07 2023-09-05 中国十七冶集团有限公司 Wall-connecting window integrated plate and installation method

Similar Documents

Publication Publication Date Title
CN102251607B (en) Reinforced concrete superposed wall joint connecting structure and construction method
CN102425265B (en) Composite wallboard manufacturing and installation methods
CN106013811A (en) Mounting method of prefabricated building
CN101649656A (en) Overlapped shear wall with prefabricated part and cast-in-situ part and manufacturing method thereof
CN101196069A (en) Combined disposal pouring steel reinforced concrete polyphenyl board thermal insulation board
CN201144480Y (en) Compound disposable cast reinforced concrete thermal insulation board
CN205604566U (en) Side fascia suitable for assembled concrete frame structure
CN205712716U (en) A kind of assembled architecture hollow precast concrete member
CN104746639A (en) Prefabricated bay window structure installed on laminated wall board and installing method
CN205955067U (en) Prefabricated coincide wallboard of outband moulding
CN104775555B (en) A kind of T-shaped composite plate shear wall edge member and attaching method thereof
CN104878836A (en) Prefabricated house and construction method thereof
CN204645253U (en) A kind of prefabricated house
CN204456428U (en) A kind of entirety being installed on composite wallboard is waftd window
CN107700697A (en) A kind of exterior wall prefabricated construction
CN110653918B (en) Construction method for synchronously pouring large-span corrugated steel inclined web precast beam with toothed block on top and bottom plates by post-tensioning method
CN113718984A (en) Vertical connecting structure of prefabricated wall panel and construction method thereof
CN205955003U (en) Take prefabricated coincide wallboard of vertical moulding
CN105756186A (en) Assembly type prefabricated truss balcony and installation method therefor
CN211622269U (en) An inner tube eccentrically placed hollow sandwich concrete-filled steel tube beam
CN205242729U (en) Fast assembly's precast concrete coincide wallboard
CN103255834A (en) Prefabricated heat-preservation balcony suitable for industrial production and construction method thereof
CN203462576U (en) Steel structure concrete building house
CN204475896U (en) A kind of novel full assembling steel house
CN218521951U (en) A fast-installed building structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20161219

Address after: 312030 Zhejiang province Shaoxing Keqiao Shanyin Road No. 501

Patentee after: BAOYE GROUP CO.,LTD.

Patentee after: SHANGHAI BAOYUE RESIDENTIAL INDUSTRY Co.,Ltd.

Address before: 201105 room D46, building, No. 277, Ping Qing Road, Shanghai, Minhang District, China

Patentee before: SHANGHAI ZIBAO HOUSING INDUSTRIALIZATION CO.,LTD.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160106