CN204920249U - A simple and easy quick erector for installation of floor jib - Google Patents

A simple and easy quick erector for installation of floor jib Download PDF

Info

Publication number
CN204920249U
CN204920249U CN201520617753.7U CN201520617753U CN204920249U CN 204920249 U CN204920249 U CN 204920249U CN 201520617753 U CN201520617753 U CN 201520617753U CN 204920249 U CN204920249 U CN 204920249U
Authority
CN
China
Prior art keywords
pipe
nut
hand
mounting pipe
jib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520617753.7U
Other languages
Chinese (zh)
Inventor
郑彭元
陈银
张廷安
丁惠杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201520617753.7U priority Critical patent/CN204920249U/en
Application granted granted Critical
Publication of CN204920249U publication Critical patent/CN204920249U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a simple and easy quick erector for installation of floor jib, wherein expansion bolts is installed at the top of jib, and the bottom has a screw thread includes installation pipe and handheld pipe, the T venturi tube of handheld pipe for invering, the transverse part of T shape stands the fixed bottom of cup jointing at the installation pipe of body of portion as handle, T shape, the welding has the nut in the last mouth of pipe of installation pipe, and nut and installation union coupling are passed through to the bottom of jib, the axis parallel of each other of installation pipe, handheld pipe, nut and jib. The utility model discloses instrument simple structure, the preparation is convenient, and is with low costs, constructor only need stand on the structure floor alright carry out the jib installation, reduce the potential safety hazard for zero, easy operation has improved work prescription nature simultaneously, through setting up the different nut assembly of diameter, make the installation pipe be connected with the jib of various sizes, the cup jointing length and can adjust of installation pipe and handheld pipe, strong adaptability can be applied to the civil engineering furred ceiling and be under construction electromechanical professional jib construction etc..

Description

A kind of simple and fast erector installed for slab hanger rod
Technical field
The utility model technology relates to hanger erection technical field, is specifically related to a kind of simple and fast erector installed for slab hanger rod.
Background technology
Building site is in ceiling construction process, and installing suspension rod needs construction operation personnel to stand on man-like shelf to construct, and this method is very inadvisable, and first, construction operation personnel are without any security protection on man-like shelf, and safety belt is also fixed nowhere, and potential safety hazard is larger; The second, construction operation personnel are after installing place's suspension rod, and need to move the hanger construction that man-like shelf just can carry out next place, length consuming time, greatly reduces operating efficiency.In addition, the simple and fast suspension rod mounting tool suspension rod occurred in the recent period and the installation end size of instrument can not regulate, and can not adapt to the installation of multiple different model suspension rod; The whole height of erecting tools is non-adjustable, can not solve the various problems that personnel's height differences and ceiling height difference are brought, poor for applicability.
Utility model content
The purpose of this utility model is to provide a kind of simple and fast erector installed for slab hanger rod, to solve in current ceiling construction process, installs suspension rod and need construction operation personnel to stand on man-like shelf to construct, without any security protection, the ineffective technical problem of larger, the consuming time length of potential safety hazard; The installation end size of the suspension rod and instrument that also solve existing simple and easy suspension rod mounting tool can not regulate and the whole height of erecting tools is non-adjustable, can not adapt to the installation of multiple different model suspension rod, can not solve various problems, technical problem poor for applicability that personnel's height differences and ceiling height difference brings.
For achieving the above object, the utility model adopts following technical scheme:
A kind of simple and fast erector installed for slab hanger rod, the top of its middle hanger is provided with expansion bolt, bottom is threaded, it is characterized in that: comprise mounting pipe and hand-held pipe, comprise mounting pipe and hand-held pipe, described hand-held pipe is inverted T-shaped pipe, and the transverse part of T-shaped is as handle, and T-shaped stands the fixedly sleeved bottom in mounting pipe, body top in portion; Be welded with nut in the upper orifice of described mounting pipe, the bottom of described suspension rod is connected with mounting pipe by nut; The axis of described mounting pipe, hand-held pipe, nut and suspension rod is parallel to each other.
As preferred technical scheme, the latter half of described mounting pipe and the first half of hand-held pipe be corresponding perforate respectively on the both sides sidewall of differing heights, form the length-adjustment holes for regulating mounting pipe and the rear entire length of hand-held pipe socket, described mounting pipe and hand-held pipe are fixed connection by the rod shape connector of the length-adjustment holes overlapped through both.
Preferred further, described rod shape connector is pivot pin or bolt.
Preferred, described nut is a nut or the nut combinations body be welded into according to the mode that axis overlaps by the nut that some internal diameters are different, nut in described nut combinations body arranges according to the order that internal diameter reduces gradually from top to bottom, be welded and fixed between neighbouring nut, topmost the lateral wall of the nut that internal diameter is maximum is along being welded in the upper orifice of described mounting pipe.
Wherein, can be that mounting pipe is enclosed within outside described hand-held pipe during socket, the internal diameter of described mounting pipe and the external diameter of described hand-held pipe adapt.
Also can be hand-held pipe box outside described mounting pipe, the internal diameter of described hand-held pipe and the external diameter of described mounting pipe adapt.
Compared with prior art, the utility model has following characteristics and beneficial effect:
1, the utility model tool construction is simple, and easy to make, cost is low;
2, easy to use, safety is high: in operation process, constructor only need stand on structure floor just can carry out hanger erection, potential safety hazard is reduced to zero, simultaneously simple to operate, improve work limitation, prove that operating efficiency can improve more than three times through test, when overcoming traditional hanger erection, construction operation personnel on man-like shelf without any security protection, safety belt is also fixed nowhere, potential safety hazard is larger, and construction operation personnel need to move the hanger construction that man-like shelf just can carry out next place after installing place's suspension rod, this reduces the series of problems such as operating efficiency to a great extent, substantially increase operating efficiency and also ensure the safety of constructor simultaneously,
3, strong adaptability: by arranging the different nut combinations body of diameter, mounting pipe can be connected with the suspension rod of various sizes; By arranging length-adjustment holes, the socket length of mounting pipe and hand-held pipe can be regulated, and then according to the entire length of personnel's height and ceiling height regulation installer, expand the scope of application, strong adaptability.
The utility model can be applicable to civil engineering ceiling construction, electromechanical speciality hanger construction etc.
Accompanying drawing explanation
Fig. 1 is the overall structure schematic diagram of the simple and fast hanger erection device that the utility model relates to;
Fig. 2 is the structural representation of the mounting pipe 3 that the utility model relates to;
Fig. 3 is the structural representation of the hand-held pipe 4 that the utility model relates to;
Fig. 4 is the mounting pipe 3 that relates to of the utility model and the syndeton schematic diagram of hand-held pipe 4 socket part;
Fig. 5 is the installment state figure of simple and fast hanger erection device, suspension rod 1 and the floor 8 that the utility model relates to.
Reference numeral: 1-suspension rod, 2-nut, 3-mounting pipe, the hand-held pipe of 4-, 41-handle, 42-body, 5-rod shape connector, 6-length-adjustment holes, 7-expansion bolt, 8-floor.
Detailed description of the invention
Be described principle of the present utility model and feature below in conjunction with accompanying drawing, example, only for explaining the utility model, is not intended to limit scope of the present utility model.
As Fig. 1, a kind of simple and fast erector installed for slab hanger rod, the top of its middle hanger 1 is provided with expansion bolt 7, bottom is threaded, it is characterized in that: comprise mounting pipe 3 and hand-held pipe 4, as Fig. 2 and Fig. 3, described hand-held pipe 4 is inverted T-shaped pipe, the transverse part of T-shaped is as handle 41, and T-shaped stands the fixedly sleeved bottom in mounting pipe 3, top of the body 42 in portion; Be welded with nut 2 in the upper orifice of described mounting pipe 3, the bottom of described suspension rod 1 is connected with mounting pipe 3 by nut 2; The axis of described mounting pipe 3, hand-held pipe 4, nut 2 and suspension rod 1 four is parallel to each other.As shown in Figure 5, the latter half of described mounting pipe 3 and the first half of hand-held pipe 4 be corresponding perforate respectively on the both sides sidewall of differing heights, form the length-adjustment holes 6 for regulating mounting pipe 3 and hand-held pipe 4 to be socketed rear entire length, in the present embodiment mounting pipe 3 and hand-held pipe 4 adjacent lengths adjustment hole 6 between distance be all 100mm, described mounting pipe 3 and hand-held pipe 4 are fixed connection by the rod shape connector 5 of the length-adjustment holes 6 overlapped through both.As Fig. 4, described rod shape connector 5 is can be pivot pin or bolt.Wherein, for adapting to the suspension rod of different size, described nut 2 can be the nut combinations body be welded into according to the mode that axis overlaps by the nut that some internal diameters are different, nut in described nut combinations body arranges according to the order that internal diameter reduces gradually from top to bottom, be welded and fixed between neighbouring nut, topmost the lateral wall of the nut that internal diameter is maximum is along being welded in the upper orifice of described mounting pipe 3.During use, mate corresponding nut according to suspension rod size.The nut of totally three different-diameters in the embodiment related to, at 8 ~ 16mm not etc., the bottom of suspension rod 1 is connected with minimum nut and nethermost nut thread diameter.In addition, can be that described mounting pipe 3 is enclosed within outside described hand-held pipe 4 during socket, be this kind of mode in embodiment, the diameter of mounting pipe 3 be 20mm, and length is 1500mm, and hand-held pipe 4 diameter is 18mm, and length is 1900 ~ 2900mm.The internal diameter of described mounting pipe 3 and the external diameter of described hand-held pipe 4 adapt; Also can be that described hand-held pipe 4 is enclosed within outside described mounting pipe 3, the described internal diameter of hand-held pipe 4 and the external diameter of described mounting pipe 3 adapt.
Fig. 5 is the installment state figure of simple and fast hanger erection device, suspension rod 1 and the floor 8 that the utility model relates to, and main making and the constructing operation method of the utility model erector are:
1, connection pipe 3 and hand-held pipe 4: according to human height and the total length building floor height determination erector, according to the length needed, mounting pipe 3 and hand-held pipe 4 are socketed, corresponding length-adjustment holes 6 is aligned with each other, and is penetrated by rod shape connector 5 and connects in the air;
2, make nut combinations body: the mode that described nut combinations body is overlapped according to axis by the nut that some internal diameters are different is welded into, the nut in it arranges according to the order that internal diameter reduces gradually from top to bottom, is welded and fixed between neighbouring nut;
3, nut combinations body is fixed in mounting pipe 3: by the lateral wall of nut maximum for nut combinations body the top internal diameter along being welded in the upper orifice of described mounting pipe 3;
4, suspension rod 1 is threaded with nut 2: mate corresponding nut according to suspension rod size, the bottom of suspension rod 1 is threaded with nut 2;
5, install suspension rod 1: the handle holding hand-held pipe 4, the expansion bolt 7 at suspension rod 1 top is aimed at the hole place that floor 8 has been accomplished fluently, the bottom handle of the continuous hand-held pipe 4 of hammering, is fixed in floor 8 by the expansion bolt 7 of suspension rod 1 from top to bottom;
4, being separated of suspension rod 1 and erector: the hand-held pipe 4 of reverse turn spun along nut 2 and suspension rod 1, drives mounting pipe to rotate, the bottom of suspension rod 1 is separated with the nut 2 of nut combinations body, removes erector, carries out next place's hanger erection construction.
The foregoing is only preferred embodiment of the present utility model, not in order to limit the utility model, all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (6)

1. the simple and fast erector installed for slab hanger rod, the top of its middle hanger (1) is provided with expansion bolt (7), bottom is threaded, it is characterized in that: comprise mounting pipe (3) and hand-held pipe (4), described hand-held pipe (4) is inverted T-shaped pipe, the transverse part of T-shaped is as handle (41), and T-shaped stands the fixedly sleeved bottom in mounting pipe (3) of body (42) in portion; Be welded with nut (2) in the upper orifice of described mounting pipe (3), the bottom of described suspension rod (1) is connected with mounting pipe (3) by nut (2); The axis of described mounting pipe (3), hand-held pipe (4), nut (2) and suspension rod (1) four is parallel to each other.
2. a kind of simple and fast erector installed for slab hanger rod according to claim 1, it is characterized in that: the latter half of described mounting pipe (3) and the first half of hand-held pipe (4) be corresponding perforate respectively on the both sides sidewall of differing heights, form the length-adjustment holes (6) for regulating mounting pipe (3) and the rear entire length of hand-held pipe (4) socket, described mounting pipe (3) and hand-held pipe (4) are fixed connection by the rod shape connector (5) of the length-adjustment holes (6) overlapped through both.
3. a kind of simple and fast erector installed for slab hanger rod according to claim 2, is characterized in that: described rod shape connector (5) is pivot pin or bolt.
4. a kind of simple and fast erector installed for slab hanger rod according to claims 1 to 3 any one, it is characterized in that: described nut (2) is a nut or the nut combinations body be welded into according to the mode that axis overlaps by the nut that some internal diameters are different, nut in described nut combinations body arranges according to the order that internal diameter reduces gradually from top to bottom, be welded and fixed between neighbouring nut, topmost the lateral wall of the nut that internal diameter is maximum is along being welded in the upper orifice of described mounting pipe (3).
5. a kind of simple and fast erector installed for slab hanger rod according to claim 4, it is characterized in that: described mounting pipe (3) is enclosed within described hand-held pipe (4) outside, and the internal diameter of described mounting pipe (3) and the external diameter of described hand-held pipe (4) adapt.
6. a kind of simple and fast erector installed for slab hanger rod according to claims 1 to 3,5 any one, it is characterized in that: described hand-held pipe (4) is enclosed within described mounting pipe (3) outside, and the internal diameter of described hand-held pipe (4) and the external diameter of described mounting pipe (3) adapt.
CN201520617753.7U 2015-08-17 2015-08-17 A simple and easy quick erector for installation of floor jib Active CN204920249U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520617753.7U CN204920249U (en) 2015-08-17 2015-08-17 A simple and easy quick erector for installation of floor jib

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520617753.7U CN204920249U (en) 2015-08-17 2015-08-17 A simple and easy quick erector for installation of floor jib

Publications (1)

Publication Number Publication Date
CN204920249U true CN204920249U (en) 2015-12-30

Family

ID=54969387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520617753.7U Active CN204920249U (en) 2015-08-17 2015-08-17 A simple and easy quick erector for installation of floor jib

Country Status (1)

Country Link
CN (1) CN204920249U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836825A (en) * 2017-01-18 2017-06-13 浙江省建建设集团有限公司 A kind of hanger erection mechanism and its construction method
CN110536991A (en) * 2017-04-06 2019-12-03 乌尔玛Cyes公司 Vertical form

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836825A (en) * 2017-01-18 2017-06-13 浙江省建建设集团有限公司 A kind of hanger erection mechanism and its construction method
CN110536991A (en) * 2017-04-06 2019-12-03 乌尔玛Cyes公司 Vertical form

Similar Documents

Publication Publication Date Title
CN204920249U (en) A simple and easy quick erector for installation of floor jib
CN104372939A (en) Scaffold
CN204174911U (en) A kind of scaffold connecting device
CN102661031A (en) Simple and easy tool for mounting bracket hanging rod of roof and application method thereof
CN208518307U (en) A kind of fast pylon easy to install of adjustable platform width
CN204252496U (en) The convenient erecting device of construction work suspension rod
CN202936996U (en) Wall connecting piece for scaffold
CN205617778U (en) Outer wall scaffold frame is wall structure even
CN205009159U (en) Portable extra long formula expansion bolts installs sleeve
CN202645025U (en) Installation tool special for suspender
CN203003208U (en) Airduct hanger drilling and mounting tool
CN203569487U (en) Embedded part for installation of bridge pier hanging basket
CN206530078U (en) A kind of support meanss
CN206237081U (en) A kind of self-supporting cable tunnel frame with telescopic joint
CN202810162U (en) Simple tool for installing bracket hanging rod of top plate
CN105625749A (en) Steel pipe scaffold early-demounting component and device
CN205743047U (en) Twisting type dry wall installs vertical adjustment diagonal brace
CN203415908U (en) Heavy cable drawing machine
CN204163359U (en) Scaffold
CN203867182U (en) Steady tubular well shaftway blocking construction formwork
CN204237470U (en) A kind of tower crane attachment telescopic strut
CN215281729U (en) Top plate expansion bolt spanner
CN103590612B (en) Convenient purline correction device
CN203684644U (en) Scaffold installation element
CN202401755U (en) Curvature-adjustable concrete construction steel mould

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant