With the waste recovery streamline of dust arrester
Technical field
The utility model relates to waste recovery equipment, particularly a kind of waste recovery streamline with dust arrester.
Background technology
Certain waste material can be produced unavoidably in process of production, for the process of waste material, directly throw away and just cause the wasting of resources, there is no too much space to deposit pending waste material simultaneously yet. waste material performance is to a certain extent close to being even better than raw material in fact, if utilize together with raw material so waste material can reclaim, saving resource to a great extent, improve the performance of product is also a facilitation simultaneously.At present, it is broken with manually being cracked by waste product that general waste recovery utilizes, then mix with sand material to be together involved in inside grinding machine through conveyer belt and use, although this serves the effect of waste reclamation to a certain extent, but there is Railway Project: 1, together with sand material through weighing balance, because there be being mixed into of waste material, the initial data of sand material cannot be added up accurately; 2, cobbing efficiency is not high; 3, the injury to environment and human body of dust that process and feeding process produce is broken into pieces; 3, the usage quantity of uncontrollable waste material.
Summary of the invention
The purpose of this utility model is improved for above shortcoming exactly, and provide simply reasonable in design, production efficiency is high, a kind of waste recovery streamline with dust arrester of no dust pollution.
The waste recovery streamline of the utility model band dust arrester, it is characterized in that: there is hopper, disintegrating machine, feed bin, conveyer belt and cage, the side of hopper is furnished with disintegrating machine and feed bin respectively, below the discharging opening of hopper and between disintegrating machine feeding port, below the discharging opening of disintegrating machine and be all furnished with conveyer belt between the feeding port of feed bin, the discharging opening arranged beneath of feed bin has cage to form waste recovery streamline; The top of described hopper and feed bin is equipped with dust cap, the top of disintegrating machine and cage feed opening is equipped with dust shield, dust shield on the dust cap of hopper, on disintegrating machine and cage feed opening is equipped with centrifugal blower, centrifuge is all connected with a water tank by airduct, and described water tank is provided with water inlet pipe, drainpipe and blast pipe.
The waste recovery streamline of described band dust arrester, is characterized in that: be provided with spray equipment in described water tank.
The utility model is simply reasonable in design, and production efficiency is high, no dust pollution, and effectively control the utilization of waste material, staffing is few, share and utilizes equipment and human resources.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure: 1-hopper, 2-disintegrating machine, 3-feed bin, 4-conveyer belt, 5-cage, 6-dust cap, 7-dust shield, 8-centrifugal blower, 9-airduct, 10-water tank, 11-water inlet pipe, 12-drainpipe, 13-blast pipe, 14-spray equipment.
Detailed description of the invention
See Fig. 1, the waste recovery streamline of the utility model band dust arrester, there is hopper 1, disintegrating machine 2, feed bin 3, conveyer belt 4 and cage 5, the side of hopper 1 is furnished with disintegrating machine 2 and feed bin 3 respectively, below the discharging opening of hopper 1 and between disintegrating machine 2 feeding port, below the discharging opening of disintegrating machine 2 and be all furnished with conveyer belt 4 between the feeding port of feed bin 3, the discharging opening arranged beneath of feed bin 3 has cage 5 to form waste recovery streamline; The top of described hopper 1 and feed bin 3 is equipped with dust cap 6, the top of disintegrating machine 2 and cage 5 feed opening is equipped with dust shield 7, dust shield 7 on the dust cap of hopper 1, on disintegrating machine 2 and cage 5 feed opening is equipped with centrifugal blower 8, centrifuge is all connected with a water tank 10 by airduct 9, and described water tank 10 is provided with water inlet pipe 11, drainpipe 12 and blast pipe 13; Spray equipment 14 is provided with in described water tank 10.Operation principle: waste material loading machine is poured in hopper, at the uniform velocity delivered in disintegrating machine by first-level transport band, the even broken rear conveying belt with sides second-pumping that passes through of disintegrating machine is to feed bin, on the feeding cage three grades conveying sand material conveyer belt of bin bottom, be involved in grinding machine and use together with the sand material transported out after metering; Dust process: can dust be produced when can produce dust, cage blowing to sand material band when loading machine can produce dust, crusher in crushing in batch turning process, so very big pollution is caused to production environment, potential injury is also caused to human body simultaneously, so install dust cap and dust shield and centrifugal blower in the relevant position of hopper, disintegrating machine, cage feed opening, and utilize water law dust collecting system effectively to address this problem, create one clean without dust production space; The utilization of effective control waste material: according to the actual conditions of production and the performance requirement of product, carry out fragmentation at regular time and quantity, reasonable employment waste material, do not affect metering and the use of raw material; Staffing situation: in original staffing situation, do not increase anyone, only utilizes the free time handling waste material of loading machine, Appropriate application equipment and human resources.