CN204885963U - Prefabricated formula AT of modularization institute - Google Patents

Prefabricated formula AT of modularization institute Download PDF

Info

Publication number
CN204885963U
CN204885963U CN201520619521.5U CN201520619521U CN204885963U CN 204885963 U CN204885963 U CN 204885963U CN 201520619521 U CN201520619521 U CN 201520619521U CN 204885963 U CN204885963 U CN 204885963U
Authority
CN
China
Prior art keywords
linear quadratic
quadratic control
switch cubicle
prefabricated
precast box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520619521.5U
Other languages
Chinese (zh)
Inventor
高仕斌
高旻东
黄协平
吴志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHANGZHOU PACIFIC ELECTRIC POWER EQUIPMENT (GROUP) Co Ltd
Southwest Jiaotong University
China State Railway Group Co Ltd
Original Assignee
CHANGZHOU PACIFIC ELECTRIC POWER EQUIPMENT (GROUP) Co Ltd
Southwest Jiaotong University
China Railway Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHANGZHOU PACIFIC ELECTRIC POWER EQUIPMENT (GROUP) Co Ltd, Southwest Jiaotong University, China Railway Corp filed Critical CHANGZHOU PACIFIC ELECTRIC POWER EQUIPMENT (GROUP) Co Ltd
Priority to CN201520619521.5U priority Critical patent/CN204885963U/en
Application granted granted Critical
Publication of CN204885963U publication Critical patent/CN204885963U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a prefabricated formula AT of modularization institute, it is mainly assembled by high -pressure precast box and secondary control precast box and forms, is provided with high tension switchgear in the high -pressure precast box, and high tension switchgear includes house transformer and cubical switchboard, is provided with secondary control equipment in the secondary control precast box, is provided with the secondary control cable passage between high -pressure precast box and the secondary control precast box, and this secondary control cable passage is used for laying the connecting cable between high tension switchgear and the secondary control equipment. The utility model discloses can realize that the mill modularization is prefabricated, the installation of on -the -spot modularization, convenient and fast, reduced AT whole construction cost, shorten the construction cycle.

Description

Modularization prefabricated AT institute
Technical field
The utility model relates to a kind of modularization prefabricated AT institute, belongs to electric railway traction power supply technique field.
Background technology
At present, in China's electrified railway traction power supply system, AT (single-circuit transformer) supply power mode is widely used.Need arrange an AT institute every 15-20 kilometer along the railway, existing construction mode mostly is conventional house desigh, and outside railway line expropriation of land scope, be about 10m place apart from railway line, need take over the land for use in addition, the construction period is long, and floor space is large, cost is high.In hilly country, mountain area, the workload that on-the-spot civil engineering is installed is larger.Modularization prefabricated AT can be arranged under overpass between two adjacent viaduct piers, and without the need to extra expropriation of land, site installation test workload is little, has obvious advantage and wide application prospect.
Summary of the invention
Technical problem to be solved in the utility model is the defect overcoming prior art, a kind of modularization prefabricated AT institute is provided, it can realize that factory modularization is prefabricated, field moduleization is installed, convenient and swift, reduce AT integral constructing cost, shortening production cycle.
In order to solve the problems of the technologies described above, the technical solution of the utility model is: a kind of modularization prefabricated AT institute, it primarily of high-voltage prefabricated case and linear quadratic control precast box assembled, high voltage switchgear is provided with in high-voltage prefabricated case, and described high voltage switchgear comprises house transformer and switch cubicle, linear quadratic control equipment is provided with in linear quadratic control precast box, be provided with linear quadratic control cable passage between high-voltage prefabricated case and linear quadratic control precast box, this linear quadratic control cable passage is in order to lay the stube cable between high voltage switchgear and linear quadratic control equipment.
Further for the ease of field adjustable and maintenance work from now on, front portion and/or the left part of high voltage switchgear are provided with operating corridor.
Further for the ease of field adjustable and maintenance work from now on, front and/or rear and/or the right part of linear quadratic control equipment are provided with operating corridor.
Further, also air-conditioning is installed in high-voltage prefabricated case and/or linear quadratic control precast box.
Further, transformer is 27.5kV house transformer and 10kV house transformer, described switch cubicle comprises 27.5kV change used switch cubicle, 27.5kV downing switch cabinet, 27.5kV upstream switch cabinet, 10kV change switch cubicle used and two 27.5kV and becomes switch cubicle from lotus root, and 10kV house transformer is arranged in 10kV change switch cubicle used.
Further in order to make the high pressure stube cable consumption between house transformer and switch cubicle be down to minimum, and field basic is without the need to arranging cable trough, reduce the construction cost of its production cost and civil engineering, 27.5kV house transformer and the adjacent layout of 27.5kV change used switch cubicle, and be provided with through hole between 27.5kV house transformer and 27.5kV change switch cubicle used, this through hole is used for through high-tension cable to realize the connection of 27.5kV house transformer and 27.5kV change switch cubicle used.
Further, battery panel and/or ac panel are also installed in linear quadratic control precast box and/or protect observing and controlling screen and/or pulling equipment monitor screen and/or environmental safety monitor and control to shield and/or direct current cabinet.
After have employed technique scheme, the utility model by high-voltage prefabricated case and linear quadratic control precast box two modular tank assembled, all devices in two modular tank is all good at factory's installation testing, the separately transport of high-voltage prefabricated case and linear quadratic control precast box, to on-site consolidation together, stube cable between each modular tank, two casings all adopts standardized designs, shortens delivery cycle, decreases manufacturing cost.Reduce site installation test workload simultaneously, shorten construction period; In addition, linear quadratic control cable passage is provided with between high-voltage prefabricated case and linear quadratic control precast box, stube cable between high voltage switchgear and linear quadratic control equipment makes complete in advance in factory, two ends, with plug, are connected with the socket in high voltage switchgear and linear quadratic control equipment respectively, decrease field connection workload, can not make mistakes, reduce on-the-spot to line, debugging work load, field basic, without the need to arranging secondary cable ditch, reduces civil engineering cost; The utility model modularization prefabricated AT can be arranged under overpass between two adjacent viaduct piers, without the need to extra expropriation of land, reducings the construction costs, shortens the construction period.
Accompanying drawing explanation
Layout schematic diagram in Fig. 1 is modularization prefabricated AT of the present utility model;
Fig. 2 is the layout schematic diagram in high-voltage prefabricated case of the present utility model;
Fig. 3 is the layout schematic diagram in linear quadratic control precast box of the present utility model.
Embodiment
In order to make content of the present utility model more easily be clearly understood, below according to specific embodiment also by reference to the accompanying drawings, the utility model is described in further detail.
As shown in Figures 1 to 3, a kind of modularization prefabricated AT institute, it primarily of high-voltage prefabricated case 3 and linear quadratic control precast box 1 assembled, high voltage switchgear 6 is provided with in high-voltage prefabricated case 3, and described high voltage switchgear 6 comprises house transformer and switch cubicle, linear quadratic control equipment 2 is provided with in linear quadratic control precast box 1, be provided with linear quadratic control cable passage 5 between high-voltage prefabricated case 3 and linear quadratic control precast box 1, this linear quadratic control cable passage 5 is in order to lay the stube cable between high voltage switchgear 6 and linear quadratic control equipment 2.
As shown in Figure 1, the front portion of high voltage switchgear 6 and/or left part are provided with operating corridor 31.
As shown in Figure 1, the front and/or rear of linear quadratic control equipment 2 and/or right part are provided with operating corridor 31.
As shown in Figures 1 to 3, in high-voltage prefabricated case 3 and/or linear quadratic control precast box 1, air-conditioning 4 is also installed.
As shown in Figure 2, transformer is 27.5kV house transformer 61 and 10kV house transformer, described switch cubicle comprises 27.5kV change used switch cubicle 62,27.5kV downing switch cabinet 63,27.5kV upstream switch cabinet 64,10kV change used switch cubicle 65 and two 27.5kV and is arranged in 10kV change switch cubicle 65 used from lotus root change switch cubicle 66,10kV house transformer.
27.5kV house transformer 61 and the adjacent layout of 27.5kV change used switch cubicle 62, and be provided with through hole between 27.5kV house transformer 61 and 27.5kV change switch cubicle 62 used, this through hole is used for through high-tension cable to realize the connection of 27.5kV house transformer 61 and 27.5kV change switch cubicle 62 used.
As shown in Figure 3, battery panel 12 and/or ac panel 13 are also installed in linear quadratic control precast box 1 and/or protect observing and controlling screen 14 and/or pulling equipment monitor screen 15 and/or environmental safety monitor and control to shield 16 and/or direct current cabinet 17.
Operation principle of the present utility model is as follows:
The utility model by high-voltage prefabricated case 3 and linear quadratic control precast box 1 two modular tank assembled, all devices in two modular tank is all good at factory's installation testing, the separately transport of high-voltage prefabricated case 3 and linear quadratic control precast box 1, to on-site consolidation together, stube cable between each modular tank, two casings all adopts standardized designs, shorten delivery cycle, decrease manufacturing cost.Reduce site installation test workload simultaneously, shorten construction period; In addition, linear quadratic control cable passage 5 is provided with between high-voltage prefabricated case 3 and linear quadratic control precast box 1, stube cable between high voltage switchgear 6 and linear quadratic control equipment 2 makes complete in advance in factory, two ends, with plug, are connected with the socket in high voltage switchgear 6 and linear quadratic control equipment 2 respectively, decrease field connection workload, can not make mistakes, reduce on-the-spot to line, debugging work load, field basic, without the need to arranging secondary cable ditch, reduces civil engineering cost; The utility model modularization prefabricated AT can be arranged under overpass between two adjacent viaduct piers, without the need to extra expropriation of land, reducings the construction costs, shortens the construction period.
Above-described specific embodiment; technical problem, technical scheme and beneficial effect that the utility model solves are further described; be understood that; the foregoing is only specific embodiment of the utility model; be not limited to the utility model; all within spirit of the present utility model and principle, any amendment made, equivalent replacement, improvement etc., all should be included within protection range of the present utility model.

Claims (7)

1. a modularization prefabricated AT institute, it is characterized in that, it primarily of high-voltage prefabricated case (3) and linear quadratic control precast box (1) assembled, high voltage switchgear (6) is provided with in high-voltage prefabricated case (3), and described high voltage switchgear (6) comprises house transformer and switch cubicle, linear quadratic control equipment (2) is provided with in linear quadratic control precast box (1), linear quadratic control cable passage (5) is provided with between high-voltage prefabricated case (3) and linear quadratic control precast box (1), this linear quadratic control cable passage (5) is in order to lay the stube cable between high voltage switchgear (6) and linear quadratic control equipment (2).
2. modularization prefabricated AT institute according to claim 1, is characterized in that: front portion and/or the left part of described high voltage switchgear (6) are provided with operating corridor (31).
3. modularization prefabricated AT institute according to claim 1, is characterized in that: front and/or rear and/or the right part of described linear quadratic control equipment (2) are provided with operating corridor (31).
4. modularization prefabricated AT institute according to claim 1, is characterized in that: be also provided with air-conditioning (4) in described high-voltage prefabricated case (3) and/or linear quadratic control precast box (1).
5. modularization prefabricated AT institute according to claim 1, it is characterized in that: described transformer is 27.5kV house transformer (61) and 10kV house transformer, described switch cubicle comprises 27.5kV change used switch cubicle (62), 27.5kV downing switch cabinet (63), 27.5kV upstream switch cabinet (64), 10kV change switch cubicle (65) used and two 27.5kV and becomes switch cubicle (66) from lotus root, and 10kV house transformer is arranged in 10kV change switch cubicle (65) used.
6. modularization prefabricated AT institute according to claim 5, it is characterized in that: described 27.5kV house transformer (61) and 27.5kV change used switch cubicle (62) adjacent layout, and be provided with through hole between 27.5kV house transformer (61) and 27.5kV change switch cubicle (62) used, this through hole is used for through high-tension cable to realize the connection of 27.5kV house transformer (61) and 27.5kV change switch cubicle (62) used.
7. modularization prefabricated AT institute according to claim 1, is characterized in that: be also provided with battery panel (12) and/or ac panel (13) in described linear quadratic control precast box (1) and/or protect observing and controlling screen (14) and/or pulling equipment monitor screen (15) and/or environmental safety monitor and control to shield (16) and/or direct current cabinet (17).
CN201520619521.5U 2015-08-17 2015-08-17 Prefabricated formula AT of modularization institute Expired - Fee Related CN204885963U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520619521.5U CN204885963U (en) 2015-08-17 2015-08-17 Prefabricated formula AT of modularization institute

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520619521.5U CN204885963U (en) 2015-08-17 2015-08-17 Prefabricated formula AT of modularization institute

Publications (1)

Publication Number Publication Date
CN204885963U true CN204885963U (en) 2015-12-16

Family

ID=54830295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520619521.5U Expired - Fee Related CN204885963U (en) 2015-08-17 2015-08-17 Prefabricated formula AT of modularization institute

Country Status (1)

Country Link
CN (1) CN204885963U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105024297A (en) * 2015-08-17 2015-11-04 常州太平洋电力设备(集团)有限公司 Modularized prefabricated AT station
CN106451168A (en) * 2016-10-26 2017-02-22 成都交大许继电气有限责任公司 Prefabricated intelligent traction substation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105024297A (en) * 2015-08-17 2015-11-04 常州太平洋电力设备(集团)有限公司 Modularized prefabricated AT station
CN105024297B (en) * 2015-08-17 2018-01-12 常州太平洋电力设备(集团)有限公司 Modularization prefabricated AT institutes
CN106451168A (en) * 2016-10-26 2017-02-22 成都交大许继电气有限责任公司 Prefabricated intelligent traction substation

Similar Documents

Publication Publication Date Title
CN205622124U (en) Prefabricated cabin formula transformer substation of 110kV
CN101299517A (en) Centralized remote electric power system
CN201398029Y (en) Main wiring structure capable of reducing scope of power failure of 220kVGIS substation
CN204885963U (en) Prefabricated formula AT of modularization institute
CN104821490A (en) 500 kV HGIS power distribution device arrangement structure
CN205583475U (en) Integrated transformer substation of 110kV prepackage type
CN205081386U (en) Track traffic is with intelligent prepackage type transformer substation
CN205092489U (en) Modern tram intelligence prepackage type transformer substation
CN106129991A (en) A kind of high-speed railway Special single-core cable grounding technical scheme
CN204706941U (en) High voltage input and low-voltage exports uninterrupted for distribution integrating device
CN105024297B (en) Modularization prefabricated AT institutes
CN203228694U (en) Movable 10kV van type switch station
CN201846015U (en) GIS (global information system) power distribution unit adopting one and half breaker connection
CN201985528U (en) Series compensation system adopting line iron towers
CN209375009U (en) A kind of 750kV GIS breaker double-row type arragement construction
CN108683082B (en) Power station at dam toe's outlet method for arranging
CN106451168A (en) Prefabricated intelligent traction substation
CN205790968U (en) A kind of wind farm substation T-shaped arrangement of 220kV power distribution equipment
CN202586129U (en) 110kV combination electric appliance GIS applied to integrated, prefabricated and box type substation
CN207282908U (en) The 500kV power distribution equipments arranged using half c-type
CN103166141A (en) Grounding grid of urban full-indoor transformer substation of 220kV
CN214176423U (en) Wind power plant
CN213980109U (en) Large-scale skid-mounted multifunctional combined prefabricated cabin
CN202678735U (en) Middle-arranged switch cabinet
CN208316035U (en) Power station at dam toe's outlet system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151216

Termination date: 20200817

CF01 Termination of patent right due to non-payment of annual fee