CN204876567U - Building templates's adjusting device - Google Patents

Building templates's adjusting device Download PDF

Info

Publication number
CN204876567U
CN204876567U CN201520600612.4U CN201520600612U CN204876567U CN 204876567 U CN204876567 U CN 204876567U CN 201520600612 U CN201520600612 U CN 201520600612U CN 204876567 U CN204876567 U CN 204876567U
Authority
CN
China
Prior art keywords
hole
construction formwork
base
nut
building templates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520600612.4U
Other languages
Chinese (zh)
Inventor
杨翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Jiachen New Material Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201520600612.4U priority Critical patent/CN204876567U/en
Application granted granted Critical
Publication of CN204876567U publication Critical patent/CN204876567U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides a building templates's adjusting device, that adjusts building templates when the device is used for the concatenation to build highly keeps unanimous, the device is including base, bolt and atress tray, the base is spliced by a plurality of angle steel in proper order to be constituteed, a base side with building templates's working face is in the coplanar, and the another side is supported and is established arbitrary minor face connection box below of building templates just is equipped with a plurality of the 2nd connect the via hole, the 2nd connect the via hole below corresponds the welding has first nut, the atress tray is arranged in the base below just the up end of atress tray is equipped with the screw hole, the bolt passes in proper order a connect the via hole and the 2nd connect the via hole reach with first nut the screw hole threaded connection of atress tray. The utility model has the advantages that wall form's levelness is guaranteed to height that can effective leveling building templates, and convenient operation has prolonged building templates's life.

Description

A kind of adjusting device of construction formwork
[technical field]
The utility model relates to construction formwork assembling field, more particularly, relates to a kind of adjusting device of construction formwork.
[background technology]
When existing building template carries out assembled building, be first the construction formwork of lower one deck has been built and joints cement, after theing cement solidifies, carry out the assembled of last layer construction formwork again build.And when lower floor's cement surface water smash out-of-flatness (the general deviation 1-5cm of planeness) time, with regard to needing, the height of superstructure template self is regulated, superstructure template just can be made smooth and easyly assembledly to complete, the problem such as there will not be connecting hole position to align.At present, processing mode when traditional architecture template runs into lower floor's cement surface out-of-flatness is: low place adds with other construction formwork padded, high place is by existing building template brachymemma polishing, like this whenever running into lower one deck cement surface and being uneven, all obtain and again adjust the size of construction formwork, not only process is loaded down with trivial details, expends man-hour, and accelerate the loss of construction formwork, shorten the application life of construction formwork.
[summary of the invention]
The technical problems to be solved in the utility model, be the adjusting device that a kind of construction formwork is provided, by the common cooperation of bolt, base and stressed pallet, the height of effective leveling construction formwork, even if superstructure template also can be carried out assembled under sustained height in the irregular situation of lower floor's cement surface, thus ensure the levelness of wall form, and easy to operate, extend the application life of construction formwork.
The utility model is achieved in that a kind of adjusting device of construction formwork, described construction formwork surrounding is coated with connection box, described connection box is distributed with a plurality of first connecting through hole, the height of construction formwork is regulated to be consistent when described device is built for splicing, described device comprises base, bolt and stressed pallet, described base is spliced successively by a plurality of angle steel and forms, the work plane of described base one side and described construction formwork is in same plane, another side is below the arbitrary minor face connection box being located at described construction formwork and be provided with a plurality of second connecting through hole, below described second connecting through hole, correspondence is welded with the first nut, described stressed pallet is placed in below described base and the upper surface of described stressed pallet is provided with screwed hole, first connecting through hole described in described screw bolt passes and the second connecting through hole are also threaded with the screwed hole of the first nut and described stressed pallet.
Preferably, described device also comprises pad and the second nut, described second nut lock to be paid on described bolt and is fitted with described pad upper surface, described pad center is provided with circular hole, described pad is placed in above described first connecting through hole and described circular hole is overlapping with described first connecting through hole, and described bolt is arranged in described circular hole.
The utility model has the advantage of:
1, by the common cooperation of bolt, base and stressed pallet, can the height of leveling construction formwork effectively, even if superstructure template also can be carried out assembled under sustained height in the irregular situation of lower floor's cement surface, thus ensure the levelness of wall form, simple to operation, save man-hour, extend the application life of construction formwork;
2, the second nut lock to be paid on bolt and is fitted with pad, is both increased the lifting surface area of bolt by pad, the connection box of construction formwork can be made to be connected with base again tightr.
[accompanying drawing explanation]
The utility model is further described with reference to the accompanying drawings in conjunction with the embodiments.
Fig. 1 is overall structure schematic diagram of the present utility model.
Fig. 2 is front view of the present utility model.
Fig. 3 is the utility model one embodiment base structural representation.
Accompanying drawing marks
100-construction formwork 1-connection box 11-minor face connection box
12-long limit connection box 13-first connecting through hole 2-base
21-angle steel 22-second connecting through hole 23-first nut
3-bolt 4-stressed pallet 41-screwed hole
5-pad 6-second nut
[detailed description of the invention]
Refer to Fig. 1, shown in Fig. 2 and Fig. 3, the adjusting device of a kind of construction formwork of the utility model, described construction formwork 100 surrounding is coated with connection box 1 and (comprises minor face connection box 11 and long limit connection box 12, lower same), described connection box 1 is distributed with a plurality of first connecting through hole 13, the height of construction formwork 100 is regulated to be consistent when described device is built for splicing, described device comprises base 2, bolt 3 and stressed pallet 4, described base 2 is spliced successively by a plurality of angle steel 21 and forms, the work plane of described base 2 one side and described construction formwork 100 is in same plane, another side is below the arbitrary minor face connection box 11 being located at described construction formwork 100 and be provided with a plurality of second connecting through hole 22, below described second connecting through hole 22, correspondence is welded with the first nut 23, described stressed pallet 4 is placed in below described base 2 and the upper surface of described stressed pallet 4 is provided with screwed hole 41, described bolt 3 is threaded with the screwed hole 41 of the first nut 23 and described stressed pallet 4 through described first connecting through hole 13 and the second connecting through hole 22 successively.
Described device also comprises pad 5 and the second nut 6, described second nut 6 is locked to pay and to be fitted with described pad 5 upper surface on described bolt 3, it is (not shown that described pad 5 center is provided with circular hole, lower same), described pad 5 is placed in above described first connecting through hole 13 and described circular hole is overlapping with described first connecting through hole 13, and described bolt 3 is arranged in described circular hole.
The utility model, when lower floor's cement surface builds out-of-flatness, first place stressed pallet 4 in out-of-flatness place, secondly (now base 2 another side will keep same plane with construction formwork 100 work plane to the first connecting through hole 13 being aimed at by the second connecting through hole 22 of base 2 side on the arbitrary minor face connection box 11 of construction formwork 100, the height adjusting construction formwork 100 like this carries out cement when building, base 2 is equivalent to a part for construction formwork 100, ensure that the wall leveling after building), on the first connecting through hole 13, place pad 5 again and the circular hole on pad 5 is alignd with the first connecting through hole 13, finally bolt 3 is passed circular hole successively, first connecting through hole 13, second connecting through hole 22 is threaded with the screwed hole 41 of the first nut 23 with stressed pallet 4, when lower floor's cement surface is lower slightly, then bolt 3 is rotated down, now will withstand stressed pallet 4 because bolt 3 is threaded with the first nut 23 and stressed pallet 4 construction formwork 100 is risen, when lower floor's cement surface is lower slightly, then bolt 3 is rotated up, withstanding stressed pallet 4 equally makes construction formwork 100 decline, thus realize the object regulating construction formwork 100 height, make construction formwork 100 can continue combination assembling, ensure the levelness of wall form.
The above, be only the utility model preferred embodiment, therefore the scope that the utility model implements can not be limited according to this, the equivalence namely done according to the utility model the scope of the claims and description change with modify, all should still belong in scope that the utility model contains.

Claims (2)

1. the adjusting device of a construction formwork, described construction formwork surrounding is coated with connection box, described connection box is distributed with a plurality of first connecting through hole, it is characterized in that: when described device is built for splicing, regulate the height of construction formwork to be consistent, described device comprises base, bolt and stressed pallet, described base is spliced successively by a plurality of angle steel and forms, the work plane of described base one side and described construction formwork is in same plane, another side is below the arbitrary minor face connection box being located at described construction formwork and be provided with a plurality of second connecting through hole, below described second connecting through hole, correspondence is welded with the first nut, described stressed pallet is placed in below described base and the upper surface of described stressed pallet is provided with screwed hole, first connecting through hole described in described screw bolt passes and the second connecting through hole are also threaded with the screwed hole of the first nut and described stressed pallet.
2. the adjusting device of a kind of construction formwork according to claim 1, it is characterized in that: described device also comprises pad and the second nut, described second nut lock to be paid on described bolt and is fitted with described pad upper surface, described pad center is provided with circular hole, described pad is placed in above described first connecting through hole and described circular hole is overlapping with described first connecting through hole, and described bolt is arranged in described circular hole.
CN201520600612.4U 2015-08-11 2015-08-11 Building templates's adjusting device Expired - Fee Related CN204876567U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520600612.4U CN204876567U (en) 2015-08-11 2015-08-11 Building templates's adjusting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520600612.4U CN204876567U (en) 2015-08-11 2015-08-11 Building templates's adjusting device

Publications (1)

Publication Number Publication Date
CN204876567U true CN204876567U (en) 2015-12-16

Family

ID=54820958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520600612.4U Expired - Fee Related CN204876567U (en) 2015-08-11 2015-08-11 Building templates's adjusting device

Country Status (1)

Country Link
CN (1) CN204876567U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268993A (en) * 2017-06-26 2017-10-20 中建铝新材料广东有限公司 building template system
CN110485707A (en) * 2019-07-26 2019-11-22 中国华冶科工集团有限公司 Wall column formwork blocks levelling device and its construction method
CN112267580A (en) * 2020-10-26 2021-01-26 中国建筑第七工程局有限公司 Connecting part for assembly type building

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268993A (en) * 2017-06-26 2017-10-20 中建铝新材料广东有限公司 building template system
CN110485707A (en) * 2019-07-26 2019-11-22 中国华冶科工集团有限公司 Wall column formwork blocks levelling device and its construction method
CN110485707B (en) * 2019-07-26 2021-11-23 中国华冶科工集团有限公司 Wall column formwork plugging leveling device and construction method thereof
CN112267580A (en) * 2020-10-26 2021-01-26 中国建筑第七工程局有限公司 Connecting part for assembly type building

Similar Documents

Publication Publication Date Title
CN105888236B (en) frame template system
CN208668817U (en) A kind of light-duty armored concrete formula precast stair
CN204876567U (en) Building templates's adjusting device
WO2019233193A1 (en) Integrally-formed aluminum alloy construction template
CN104358410B (en) Anti-arc wall form space orientation control method
CN203939225U (en) Floor concrete casting operation platform is built in room
CN203403674U (en) Adjustable stair steel form of instrument formula
CN202500323U (en) Novel splicing structure
CN211341907U (en) Civil engineering construction support
CN208649894U (en) A steel anchor beam and steel corbel unit group tire frame
CN103255929A (en) Assembly technology of adjustable supporting columns and eight type modularized steel floor slab moulds
CN211967899U (en) An automatic spraying and maintenance device for the prefabricated beam field of highway bridges
CN207620365U (en) Temporary support structure
CN205654082U (en) Half tunnel formwork
CN215168019U (en) Civil engineering concrete building template
CN206844673U (en) Pedal for quadric-plastering before floor concrete final set
CN206319628U (en) One kind building assembled wallboard fitting machine
CN107119931B (en) Concrete stepped formwork device for theatre multi-section curve auditorium and construction method thereof
CN213836316U (en) Movable type pedestal
CN212773578U (en) A kind of prefabricated building quick dismantling independent support system
CN213858951U (en) Hydraulic engineering's water conservancy pipeline supports connection structure
CN219137703U (en) Height-adjustable crown beam steel support Z-shaped hanging device
CN205558256U (en) Two concrete construction die carrier systems that prop separation
CN206957226U (en) A kind of model sheetinstallat workbench
CN112211110A (en) Movable type pedestal

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200117

Address after: 350000 Fujian Province Fuzhou Taijiang District Aofeng Road 20 Hongxing Court Phase III Aofeng Square Building 10 stories 03A

Patentee after: FUZHOU JIACHEN NEW MATERIAL Co.,Ltd.

Address before: 1, 803, 350000, Tong Xin Village, drum West Road, 306 Drum Tower Road, Gulou District, Fujian, Fuzhou

Patentee before: Yang Xiang

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151216