CN204873403U CN201520527620.0U CN201520527620U CN204873403U CN 204873403 U CN204873403 U CN 204873403U CN 201520527620 U CN201520527620 U CN 201520527620U CN 204873403 U CN204873403 U CN 204873403U
Authority
CN
China
Prior art keywords
steel pipe
purlin
steel
ring
steel ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520527620.0U
Other languages
Chinese (zh)
Inventor
张定宏
张曰望
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ASIA DAIRY FAB Ltd
Original Assignee
ASIA DAIRY FAB Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ASIA DAIRY FAB Ltd filed Critical ASIA DAIRY FAB Ltd
Priority to CN201520527620.0U priority Critical patent/CN204873403U/en
Application granted granted Critical
Publication of CN204873403U publication Critical patent/CN204873403U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a supplementary steel pipe that is used for hoisting simultaneously room roof beam purlin, by steel pipe (1), steel ring (2), steel wire winding (3), rings (4), heave here (5) constitution, steel ring (2) welding is on steel pipe (1), and steel ring quantity is the same with the quantity of required installation purlin, and the distance between steel ring (2) is the same with the distance between the girder purlin holds in the palm, steel ring (2) cover is passed on steel pipe (1) in steel wire winding (3), cup joint in steel wire winding (3) below rings (4), heave here (5) are with the semi -circular structure of welded steel on steel pipe (1). The utility model provides a problem that the construction of traditional mounting process is slow, the quality is poor, the risk is high, the benefit is low has been solved to supplementary steel pipe, has shortened the time limit for a project, has promoted the quality, has increased the safety guarantee.

Description

A kind of auxiliary steel pipe for lifting room beam purlin simultaneously
Technical field
The present invention relates to the accessory appliances of a kind of pasture construction, be specifically related to a kind of auxiliary steel pipe for lifting room beam purlin when the pasture colony house of lightweight steel construction is built simultaneously.
Background technology
Although light steel construction cost is higher than general conventional concrete construction, because its construction is fast, the advantages such as energy-saving and emission-reduction, have obtained the accreditation of more and more building industry, entered fast-developing period, be used widely in all trades and professions in China.
Pasture colony house is applicable to using lightweight steel construction very much, but pasture, particularly cattle farm, and cowshed span is general all very large, due to wide coverage, so in the design of light steel cowshed and construction, just higher to the requirement of room beam and purlin.Installing particularly at purlin is all based on artificial construction at present, because cowshed span is large, highly high, and purlin use amount is large, and workman needs aloft work, one by one successively complete installation, speed of application is slow, personal safety has a big risk; And easily there is the situations such as purlin slants, downslide in installation process, last position of installing can be caused to offset by the purlin installation site designed, be not inconsistent with the slope of roof, very difficult during correction, but do not revise and cause roofing unbalance stress, the contingency question of easy generation roofing fracture, safeguards to cowshed and brings follow-up hidden danger.From cost aspect, present cost of labor, all higher than mechanization cost, uses artificial mounting purlines to become in cowshed construction to have to a bulk of cost paid completely.Therefore, no matter from the installation quality of purlin, or cost of installation is considered, pasture undertaking of construction is being sought to develop a kind of easy, efficient, economic purlin installation method all always.In a colony house, purlin has a lot of root, if crane can be used to lift many purlins simultaneously, will greatly save the purlin set-up time, but this requires that purlin can not be shifted in hoisting process at the same time, can not slide, and have certain slope due to cowshed roofing, in many purlin integral hoisting processes, purlin namely to be made overall identical with the slope of roof, the installation end of many purlins again can not be uneven, keep straight line.
Utility model content
For solving above-mentioned item problem, the utility model proposes a kind of auxiliary steel pipe for lifting room beam purlin simultaneously, object is to provide a kind of defect overcoming artificial mounting purlines method at present, utilizing machinery to replace the accessory appliances of manual efficient, easy, economic purlin installation method, significantly improve the installation quality of room beam purlin when saving the duration.
The auxiliary steel pipe for lifting room beam purlin simultaneously that the utility model provides, be made up of steel pipe 1, steel ring 2, bead coil 3, suspension ring 4, Heave Here 5, described steel ring 2 is welded on steel pipe 1, steel ring quantity is identical with the quantity of required mounting purlines, distance between steel ring 2 is identical with the distance between room beam purlin holder, described bead coil 3 is enclosed within steel pipe 1 through steel ring 2, and described suspension ring 4 are socketed in below bead coil 3, and described Heave Here 5 is with the semicircular structure of reinforcement welding on steel pipe 1.
Further, described steel pipe 1 arranges 2-4 Heave Here 5.
Further, described steel ring 2 is that the reinforcing bar that 6mm is thick is made.
Further, described bead coil 3 is that the reinforcing bar that 5mm is thick is made.
During installation, assemble needing the purlin of installation or purlin and room beam on the ground, according to site operation situation, adopt one or two auxiliary steel pipes as strut member, every root assists the suspension ring 4 of steel pipe to be connected by latch with the purlin hole of purlin 6 one end respectively, a crane rope 7 is installed in the Heave Here 5 of each auxiliary steel pipe, the other end of crane rope is summarized in crane hook, if lifting is purlin 6 and the unitized construction of room beam 8, then crane rope 7 is also installed at beam two ends in room, crane hook is summarized in the crane rope of auxiliary steel pipe, adjust each bar crane rope length and angle, make purlin or purlin identical with the slope of roof with the integral structure of room beam, start crane, when rising to beam relevant position, room, stablize crane hook, then purlin 6 on room beam 8 or an auxiliary steel pipe is first installed in order, the purlin 6 of opposite side is installed in order again, crane hook is unclamped again after installation terminates, then the latch of suspension ring 4 and purlin 6 is opened, remove auxiliary steel pipe.
the beneficial effects of the utility model are as follows:
1, make several purlin form an entirety, be convenient to utilize crane to install:existing purlin installation method by workman below purlin is hung up properly to be placed on relevant position by workman above after pulling on room beam again and to assemble, carrying out one by one, difficulty of construction is large, and security risk is high.The auxiliary steel pipe utilizing the utility model to provide, can assemble room beam, purlin and assembly thereof on ground, and with crane lifting, then only need carry out successively assembling with two workmans, construction technology is simple, and safety factor is high.
2, lift area and can reach more than 200m2, keep roof truss to stablize simultaneously:current hoisting, use two to four steel ropes, the object that area is little can only be lifted, but cowshed span is large, purlin wide coverage, use existing hoisting, the easy modification of purlin, and the auxiliary steel pipe that the utility model provides is as support, hanging integrated can use four to eight steel rope liftings simultaneously, auxiliary steel pipe can be kept in hoisting process consistent with the slope of roof and make the installation end of several purlin be straight line, thus ensure hanging integrated not modification, once lift area and can reach more than 200m2, the stability of roof truss can also be kept simultaneously.
3, purlin position stability can be ensured during lifting:assist the Position Design that steel pipe is connected with purlin steel ring, steel ring position of weld is identical with room beam purlin holder positional distance, bead coil hangs over this position of steel ring, hang purlin (bead coil one side joint steel pipe is while connect purlin) below, and the diameter of bead coil is less than steel ring diameter, when ensureing to lift, purlin position is stable, improves installation quality.
4, according to camp site situation flexible angle adjustment and Hoisting Program, can construct with civil engineering simultaneously, promote engineering progress:pasture colony house design is different, camp site situation also varies, in purlin construction in the past, because construction area span is large, large and the length consuming time of difficulty, can not carry out with civil engineering simultaneously, and often occur that installation question needs are done over again in construction, cause construction delay, and by using auxiliary steel pipe of the present utility model, can according to camp site situation, choice for use two auxiliary steel pipes, an auxiliary steel pipe and a room beam, the different schemes of an auxiliary steel pipe and two room beams lifts simultaneously, take only to need according to on-the-spot and the slope of roof situation during different schemes, Heave Here on auxiliary steel pipe is redefined position to carry out being welded and fixed, convenient and easy, the installation of purlin can be carried out with civil engineering simultaneously, promote engineering progress, ensure the duration.
Accompanying drawing explanation
Fig. 1 is auxiliary steel-tube construction schematic diagram
Fig. 2 is the assembling schematic diagram that use two auxiliary steel pipes lift purlin simultaneously
Fig. 3 is the assembling schematic diagram that use auxiliary steel pipe lifts purlin and a room beam simultaneously
Fig. 4 position uses an auxiliary steel pipe to lift the assembling schematic diagram of purlin and two room beams simultaneously
In figure, each label lists as follows:
1-assists steel pipe, 2-steel ring, 3-bead coil, 4-suspension ring, 5-Heave Here, 6-purlin, 7-crane rope, 8-room beam.
Detailed description of the invention
Below in conjunction with accompanying drawing, embodiment of the present utility model is described in further details.
embodiment 1:
Use two auxiliary steel pipes to lift purlin simultaneously, auxiliary steel pipe is made up of steel pipe 1, steel ring 2, bead coil 3, suspension ring 4, Heave Here 5, described steel ring 2 is welded on steel pipe 1, steel ring quantity is identical with the quantity of required mounting purlines, distance between steel ring 2 is identical with the distance between room beam purlin holder, and described bead coil 3 is enclosed within steel pipe 1 through steel ring 2, and described suspension ring 4 are socketed in below bead coil 3, described Heave Here 5 is that quantity is 3 with the semicircular structure of reinforcement welding on steel pipe 1.Described steel ring 2 is that the reinforcing bar that 6mm is thick is made.Described bead coil 3 is that the reinforcing bar that 5mm is thick is made.
During mounting purlines, assemble needing the purlin installed according to cowshed general design on the ground, adopt two auxiliary steel pipes as strut member, every root assists the suspension ring 4 of steel pipe to be connected by latch with the purlin hole of purlin 6 one end respectively, a crane rope 7 is installed in the Heave Here 5 of each auxiliary steel pipe, the other end of crane rope 7 is summarized in crane hook, adjust each bar crane rope length and angle, make the integral inclined degree of purlin identical with the slope of roof, start crane to lift, when rising to beam relevant position, room, stablize crane hook, then purlin on an auxiliary steel pipe is first installed in order, another root is installed in order again and assists purlin on steel pipe, crane hook is unclamped again after installation terminates, then the latch of suspension ring and purlin is opened, remove auxiliary steel pipe.
embodiment 2:
Use an auxiliary steel pipe to lift purlin and a room beam simultaneously, auxiliary steel pipe is made up of steel pipe 1, steel ring 2, bead coil 3, suspension ring 4, Heave Here 5, described steel ring 2 is welded on steel pipe 1, steel ring quantity is identical with the quantity of required mounting purlines, distance between steel ring 2 is identical with the distance between room beam purlin holder, described bead coil 3 is enclosed within steel pipe 1 through steel ring 2, described suspension ring 4 are socketed in below bead coil 3, described Heave Here 5 is that quantity is 3 with the semicircular structure of reinforcement welding on steel pipe 1.Described steel ring 2 is that the reinforcing bar that 6mm is thick is made.Described bead coil 3 is that the reinforcing bar that 5mm is thick is made.
During installation, the purlin needing to install and room beam are assembled according to cowshed general design on the ground, adopt an auxiliary steel pipe as strut member, the suspension ring 4 of auxiliary steel pipe are connected by latch with the purlin hole of purlin 6 one end respectively, a crane rope 7 is installed in the Heave Here 5 of each auxiliary steel pipe, and then in the relevant position at beam two ends, a room, crane rope 7 is installed respectively, the other end of crane rope 7 is summarized in crane hook, adjust each bar crane rope length and angle, make purlin identical with the slope of roof with the integral inclined degree of room beam, start crane to lift, when rising to beam relevant position, room, stablize crane hook, then first room beam is installed, the purlin of opposite side is installed in order again, crane hook is unclamped again after installation terminates, then the latch of suspension ring and purlin is opened, remove auxiliary steel pipe.
embodiment 3:
Use an auxiliary steel pipe to lift purlin and two room beams simultaneously, auxiliary steel pipe is made up of steel pipe 1, steel ring 2, bead coil 3, suspension ring 4, Heave Here 5, described steel ring 2 is welded on steel pipe 1, steel ring quantity is identical with the quantity of required mounting purlines, distance between steel ring 2 is identical with the distance between room beam purlin holder, described bead coil 3 is enclosed within steel pipe 1 through steel ring 2, described suspension ring 4 are socketed in below bead coil 3, described Heave Here 5 is that quantity is 3 with the semicircular structure of reinforcement welding on steel pipe 1.Described steel ring 2 is that the reinforcing bar that 6mm is thick is made.Described bead coil 3 is that the reinforcing bar that 5mm is thick is made.
During installation, the purlin needing to install and two room beams are assembled according to cowshed general design on the ground, adopt an auxiliary steel pipe as strut member, the suspension ring 4 of auxiliary steel pipe are connected by latch with the purlin hole of purlin 6 one end respectively, a crane rope 7 is installed in the Heave Here 5 of each auxiliary steel pipe, and then in the relevant position at beam two ends, two rooms, crane rope 7 is installed respectively, the other end of crane rope 7 is summarized in crane hook, adjust each bar crane rope length and angle, make purlin identical with the slope of roof with the integral inclined degree of room beam, start crane to lift, when rising to beam relevant position, room, stablize crane hook, then first in order room beam is installed, the purlin of opposite side is installed in order again, crane hook is unclamped again after installation terminates, then the latch of suspension ring and purlin is opened, remove auxiliary steel pipe.
The auxiliary steel pipe of room beam purlin is lifted while the utility model provides, efficiently solve when room beam purlin is installed and can only lift by crane installation respectively successively, and the problem such as easy displacement in installation process, make several purlin and room beam can after ground is by designing requirement assembling, be lifted into relevant position again to install simultaneously, solve the problem that conventional mounting construction technology is slow, of poor quality, risk is high, benefit is low, shorten the duration, improve quality, add safety control.
Above the auxiliary steel pipe simultaneously lifting room beam purlin provided by the utility model is described in detail.Set forth principle of the present utility model and embodiment herein by detailed description of the invention, above explanation just understands method of the present utility model and core concept thereof for helping.Should be understood that; for those skilled in the art; under the prerequisite not departing from the utility model principle, can also carry out some improvement and modification to the utility model, these improve and modify and also fall in the protection domain of the utility model claim.

Claims (4)

1. one kind for lifting the auxiliary steel pipe of room beam purlin simultaneously, it is characterized in that, by steel pipe (1), steel ring (2), bead coil (3), suspension ring (4), Heave Here (5) is formed, described steel ring (2) is welded on steel pipe (1), steel ring quantity is identical with the quantity of required mounting purlines, distance between steel ring (2) is identical with the distance between room beam purlin holder, described bead coil (3) is enclosed within steel pipe (1) through steel ring (2), described suspension ring (4) are socketed in bead coil (3) below, described Heave Here (5) is with the semicircular structure of reinforcement welding on steel pipe (1).
2. according to claim 1 for lifting the auxiliary steel pipe of room beam purlin simultaneously, it is characterized in that, described steel pipe (1) is arranged 2-4 Heave Here (5).
3. according to claim 1 for lifting the auxiliary steel pipe of room beam purlin simultaneously, it is characterized in that, described steel ring (2) is made for the reinforcing bar that 6mm is thick.
4. according to claim 1 for lifting the auxiliary steel pipe of room beam purlin simultaneously, it is characterized in that, described bead coil (3) is made for the reinforcing bar that 5mm is thick.
CN201520527620.0U 2015-07-20 2015-07-20 A supplementary steel pipe that is used for hoisting simultaneously room roof beam purlin Active CN204873403U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520527620.0U CN204873403U (en) 2015-07-20 2015-07-20 A supplementary steel pipe that is used for hoisting simultaneously room roof beam purlin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520527620.0U CN204873403U (en) 2015-07-20 2015-07-20 A supplementary steel pipe that is used for hoisting simultaneously room roof beam purlin

Publications (1)

Publication Number Publication Date
CN204873403U true CN204873403U (en) 2015-12-16

Family

ID=54817803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520527620.0U Active CN204873403U (en) 2015-07-20 2015-07-20 A supplementary steel pipe that is used for hoisting simultaneously room roof beam purlin

Country Status (1)

Country Link
CN (1) CN204873403U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760071A (en) * 2016-11-30 2017-05-31 盈创新材料(苏州)有限公司 A kind of 3D printing wall and preparation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760071A (en) * 2016-11-30 2017-05-31 盈创新材料(苏州)有限公司 A kind of 3D printing wall and preparation method thereof

Similar Documents

Publication Publication Date Title
CN104989109A (en) Method for lifting roof girders and purlines at the same time
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN203820287U (en) Composite steel carrying pole for hoisting roof tiles of steel structure workshops
CN205688642U (en) A kind of large space ceiling decoration supporting construction
CN204199686U (en) Without outrigger concrete parapet formwork system
CN202717501U (en) Pile foundation reinforcement cage lifting ring
CN204873403U (en) A supplementary steel pipe that is used for hoisting simultaneously room roof beam purlin
CN102061810B (en) Construction method of safe flat net positioned on periphery of building
CN102864935A (en) Novel purline mounting method
CN204416913U (en) A kind of shaped steel stone tongs
CN103791156A (en) Superaltitude quick installation method of large-diameter glass fiber reinforced plastic pipes
CN204663009U (en) Steel work pulley lifting bracket
CN204252082U (en) Arch dam bracket plate device
CN203066491U (en) Locator for installing round tube type connection member
CN203924484U (en) A kind of precast beam and there is the reinforced concrete structure of tenon anchor system
CN203806943U (en) Lifting device
CN202790959U (en) Steel pipe truss structure based on aloft lateral support
CN105648920B (en) A kind of construction method for hanging of bridge floor shoulder pole girder
CN111608319A (en) Optimized mounting structure and mounting method of dome-shaped suspended ceiling
CN104234316A (en) Steel-tube square reinforced concrete member and preparation method thereof
CN206156567U (en) Thin cylinder body hoist
CN202324658U (en) Device for installing large-span roof truss
CN205742743U (en) A kind of steel structure girder
CN205292077U (en) Tree is decorated to individual layer steel construction
CN103669720A (en) Precast beam and reinforced concrete structure with tenon anchor system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Auxiliary steel pipe for simultaneously hoisting roof beam purlin

Effective date of registration: 20211222

Granted publication date: 20151216

Pledgee: Bank of Nanjing Limited by Share Ltd. Beijing branch

Pledgor: ASIA DAIRY FAB. Ltd.

Registration number: Y2021110000105