CN204826702U - Hard protector of folded cascade elevartor shaft - Google Patents
Hard protector of folded cascade elevartor shaft Download PDFInfo
- Publication number
- CN204826702U CN204826702U CN201520565679.9U CN201520565679U CN204826702U CN 204826702 U CN204826702 U CN 204826702U CN 201520565679 U CN201520565679 U CN 201520565679U CN 204826702 U CN204826702 U CN 204826702U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- horizontal rod
- rod steel
- elevator shaft
- horizontal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Elevator Door Apparatuses (AREA)
Abstract
本实用新型公开了一种可折叠式电梯井硬防护装置,包括电梯井墙体,还包括工字钢(1)、横向水平杆钢管(6)、纵向水平杆钢管(4)和模板(3),两根工字钢(1)作为主要支撑骨架一端插入电梯井墙体预留洞(2)里,横向水平杆钢管(6)跟纵向水平杆钢管(4)用十字扣件(10)连接作为次骨架搭设在主骨架工字钢(1)上;平台采用两块模板(3)搭设,两块模板(3)中间用合页(8)进行连接,以达到两个模板折叠用;预先在模板(3)跟工字钢(1)搭设出四个角预留长型空洞(7),并用弯钩式螺栓(9)对模板(3)跟工字钢(1)进行固定。本实用新型能消除过去在电梯井搭设防护时安全隐患,更好的满足施工安全及文明施工的需要。
The utility model discloses a foldable hard protection device for an elevator shaft, which comprises an elevator shaft wall, an I-beam (1), a horizontal horizontal rod steel pipe (6), a longitudinal horizontal rod steel pipe (4) and a template (3 ), two I-beams (1) are used as the main support frame and one end is inserted into the reserved hole (2) in the wall of the elevator shaft, and the horizontal horizontal rod steel pipe (6) and the vertical horizontal rod steel pipe (4) are used with cross fasteners (10) The connection is set up on the main frame I-beam (1) as a secondary frame; the platform is built with two templates (3), and the middle of the two templates (3) is connected with a hinge (8) to achieve the folding of the two templates; Set up the four corners of the formwork (3) and the I-beam (1) in advance to reserve long cavities (7), and use hook bolts (9) to fix the formwork (3) and the I-beam (1). The utility model can eliminate hidden safety hazards when erecting protection for elevator shafts in the past, and better meet the needs of construction safety and civilized construction.
Description
技术领域 technical field
本实用新型属于建筑设施,具体地涉及一种可折叠式电梯井硬防护装置。 The utility model belongs to building facilities, in particular to a foldable hard protection device for elevator shafts.
背景技术 Background technique
随着城市化的进程,建筑物的施工技术越来越高,但一些常见的安全隐患无法得到很好的根除。其中较为明显的临边防护、洞口防护问题。目前现场采用较多的方法是:在电梯井简易用几根钢管搭设,然后封闭电梯井门。但由于施工时的随意性和工人技术水平的差异或其他原因,此方法处理往往达不到安全的效果。 With the process of urbanization, the construction technology of buildings is getting higher and higher, but some common safety hazards cannot be well eradicated. Among them, the more obvious problems are edge protection and hole protection. The method that adopts more on the spot at present is: simply erect with several steel pipes in the elevator shaft, then close the elevator shaft door. However, due to the arbitrariness of construction and the difference in the technical level of workers or other reasons, this method often fails to achieve safe results.
发明内容 Contents of the invention
本实用新型的目的在于提供了安全、稳定的可折叠式电梯井硬防护装置,并且不用考虑对于空间的限制,简易的拆除、安装,更好的满足施工现场安全需要和文明施工要求。 The purpose of the utility model is to provide a safe and stable foldable elevator shaft hard protection device, which can be easily dismantled and installed without considering the limitation of space, and better meet the safety needs of the construction site and civilized construction requirements.
本发明的目的及解决其主要技术问题是采用以下技术方案来实现的:一种可折叠式电梯井硬防护装置,包括电梯井墙体,其特征在于:还包括工字钢、横向水平杆钢管、纵向水平杆钢管和模板,两根工字钢作为主要支撑骨架一端插入电梯井墙体预留洞里,横向水平杆钢管跟纵向水平杆钢管用十字扣件连接作为次骨架搭设在主骨架工字钢上;平台采用两块模板搭设,两块模板中间用合页进行连接,以达到两个模板折叠用;预先在模板跟工字钢搭设出四个角预留长型空洞,并用弯钩式螺栓对模板跟工字钢进行固定,使得平台模板跟骨架进行固定。 The purpose of the present invention and its main technical problems are achieved by adopting the following technical solutions: a foldable elevator shaft hard protection device, including the elevator shaft wall, which is characterized in that: it also includes I-beams, horizontal horizontal rod steel pipes 1. Longitudinal horizontal rod steel pipe and formwork. Two I-beams are used as the main support frame and one end is inserted into the reserved hole in the wall of the elevator shaft. The horizontal horizontal rod steel pipe and the longitudinal horizontal rod steel pipe are connected with cross fasteners as the secondary skeleton. On the beam; the platform is set up with two templates, and the middle of the two templates is connected by a hinge to achieve the folding of the two templates; the four corners of the template and the I-beam are set up in advance to reserve long holes, and use hooks Type bolts are used to fix the template and the I-beam, so that the platform template and the frame are fixed.
所述的可折叠式电梯井硬防护装置,其中:横向水平杆钢管跟纵向水平杆钢管两端均增设可调式顶撑顶住四周墙体,以达到整体骨架固定安全。 The foldable hard protection device for the elevator shaft, wherein: both ends of the horizontal horizontal rod steel pipe and the vertical horizontal rod steel pipe are provided with adjustable top braces to withstand the surrounding walls, so as to achieve the safety of the overall skeleton fixation.
所述的可折叠式电梯井硬防护装置,其中:横向水平杆钢管跟纵向水平杆钢管为Φ48mm钢管。 The foldable elevator shaft hard protection device, wherein: the horizontal horizontal bar steel pipe and the longitudinal horizontal bar steel pipe are Φ48mm steel pipes.
所述的可折叠式电梯井硬防护装置,其中:模板厚16mm。 The foldable elevator shaft hard protection device, wherein: the thickness of the template is 16mm.
本实用新型与现有技术相比具有明显的优点和有益效果。由以上技术方案可知,本实用新型现场安装,轻松拆除、安全稳定,具有以下特点: Compared with the prior art, the utility model has obvious advantages and beneficial effects. It can be seen from the above technical scheme that the utility model is installed on site, easy to dismantle, safe and stable, and has the following characteristics:
1、两块模板中间用合页进行连接,达到两个模板折叠用。 1. The middle of the two templates is connected by a hinge to achieve the folding of the two templates.
2、用弯钩式螺栓对模板跟工字钢进行固定,使得平台模板跟骨架进行固定。 2. Use hook bolts to fix the template and the I-beam, so that the platform template and the frame are fixed.
3、横向水平杆钢管跟纵向水平杆钢管两端均增设可调式顶撑顶住四周墙体,达到整体骨架固定安全。 3. Both ends of the horizontal horizontal rod steel pipe and the vertical horizontal rod steel pipe are equipped with adjustable top supports to withstand the surrounding walls, so as to achieve the safety of the overall skeleton fixation.
附图说明 Description of drawings
图1是本实用新型结构示意图, Fig. 1 is a structural representation of the utility model,
图2是图1的仰视图,即电梯井门示意图, Fig. 2 is the bottom view of Fig. 1, that is, the schematic diagram of the elevator shaft door,
图3是本实用新型折叠模板示意图, Fig. 3 is a schematic diagram of the folding template of the present invention,
图4是本实用新型折叠模板连接处的示意图。 Fig. 4 is a schematic diagram of the joint of the folded formwork of the present invention.
图中标记:1、工字钢,2、预留洞,3、模板,4、纵向水平杆钢管,5、顶撑,6、横向水平杆钢管7、长型空洞,8、合页,9、弯钩式螺栓,10、十字扣件。 Marks in the figure: 1. I-beam, 2. Reserved hole, 3. Template, 4. Longitudinal horizontal rod steel pipe, 5. Top support, 6. Horizontal horizontal rod steel pipe 7. Long hollow, 8. Hinge, 9 , Hook bolts, 10, cross fasteners.
具体实施方式 Detailed ways
以下结合附图和较佳实施例,对依据本实用新型提出的可折叠式电梯井硬防护装置具体实施方式、特征及其功效,详细说明如后。 Below in conjunction with the accompanying drawings and preferred embodiments, the specific implementation, features and effects of the foldable elevator shaft hard protection device proposed according to the utility model will be described in detail as follows.
参见图1-4,一种可折叠式电梯井硬防护装置,包括电梯井墙体,其特征在于:还包括工字钢1、横向水平杆钢管6、纵向水平杆钢管4和模板3,两根工字钢1作为主要支撑骨架一端插入电梯井墙体预留洞2里,横向水平杆钢管6跟纵向水平杆钢管4用十字扣件10连接作为次骨架搭设在主骨架工字钢1上;平台采用两块模板3搭设,两块模板3中间用合页8进行连接,以达到两个模板折叠用;预先在模板3跟工字钢1搭设出四个角预留长型空洞7,并用弯钩式螺栓9对模板3跟工字钢1进行固定,使得平台模板跟骨架进行固定。 Referring to Figures 1-4, a foldable elevator shaft hard protection device, including the elevator shaft wall, is characterized in that: it also includes I-beam 1, horizontal horizontal rod steel pipe 6, longitudinal horizontal rod steel pipe 4 and template 3, two One end of the root I-beam 1 is used as the main supporting frame and one end is inserted into the reserved hole 2 in the wall of the elevator shaft. The horizontal horizontal rod steel pipe 6 and the longitudinal horizontal rod steel pipe 4 are connected with cross fasteners 10 as a secondary frame and erected on the main frame I-beam 1. The platform is set up with two templates 3, and the middle of the two templates 3 is connected with a hinge 8 to achieve the folding of the two templates; the four corners of the template 3 and the I-beam 1 are set up in advance to reserve a long cavity 7, And the formwork 3 is fixed with the I-beam 1 with the hook type bolt 9, so that the platform formwork is fixed with the skeleton.
所述的可折叠式电梯井硬防护装置,其中:横向水平杆钢管6跟纵向水平杆钢管4两端均增设可调式顶撑5顶住四周墙体,以达到整体骨架固定安全。 The foldable hard protection device for the elevator shaft, wherein: both ends of the horizontal horizontal rod steel pipe 6 and the longitudinal horizontal rod steel pipe 4 are provided with adjustable top braces 5 to withstand the surrounding walls, so as to achieve the safety of the overall skeleton fixation.
所述的可折叠式电梯井硬防护装置,其中:横向水平杆钢管6跟纵向水平杆钢管4为Φ48mm钢管。 The foldable elevator shaft hard protection device, wherein: the horizontal horizontal rod steel pipe 6 and the longitudinal horizontal rod steel pipe 4 are Φ48mm steel pipes.
所述的可折叠式电梯井硬防护装置,其中:模板3厚16mm。 The foldable elevator shaft hard protection device, wherein: the template 3 is 16mm thick.
本实用新型现场安装,轻松拆除、安全稳定,采用防治结合的特点,改变了现有工序的现状,将建立起一种统一的安装标准和要求,保证了施工质量。 The utility model is installed on site, easy to dismantle, safe and stable, adopts the characteristics of combination of prevention and control, changes the status quo of the existing process, will establish a unified installation standard and requirements, and guarantees the construction quality.
以上所述,仅是本实用新型的较佳实施例而已,并非对本实用新型作任何形式上的限制,任何未脱离本实用新型技术方案内容,依据本实用新型的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本实用新型技术方案的范围内。 The above are only preferred embodiments of the present utility model, and are not intended to limit the present utility model in any form. Any modifications made to the above embodiments according to the technical essence of the present utility model do not deviate from the content of the technical solution of the present utility model. Any simple modifications, equivalent changes and modifications still belong to the scope of the technical solution of the present utility model.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520565679.9U CN204826702U (en) | 2015-07-31 | 2015-07-31 | Hard protector of folded cascade elevartor shaft |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520565679.9U CN204826702U (en) | 2015-07-31 | 2015-07-31 | Hard protector of folded cascade elevartor shaft |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204826702U true CN204826702U (en) | 2015-12-02 |
Family
ID=54684317
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520565679.9U Expired - Fee Related CN204826702U (en) | 2015-07-31 | 2015-07-31 | Hard protector of folded cascade elevartor shaft |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204826702U (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106049890A (en) * | 2016-08-08 | 2016-10-26 | 中建四局第三建筑工程有限公司 | Anti-falling hard protection block inside tower body and making method of hard protection block |
| TWI623483B (en) * | 2017-07-12 | 2018-05-11 | Wan Chang Yi | Elevator shaft working platform |
| CN112554579A (en) * | 2020-12-22 | 2021-03-26 | 中建四局第六建设有限公司 | Movable platform of unloading of assembled building utilization elevator well |
| CN112854787A (en) * | 2021-02-27 | 2021-05-28 | 安徽水利开发有限公司 | Self-locking horizontal sealing protective device for elevator shaft |
| CN116122549A (en) * | 2023-03-29 | 2023-05-16 | 上海星杰装饰有限公司 | Fitment is with safety device |
| CN117188800A (en) * | 2023-08-30 | 2023-12-08 | 中建五局第三建设有限公司 | Vertical entrance to a cave protector suitable for construction |
-
2015
- 2015-07-31 CN CN201520565679.9U patent/CN204826702U/en not_active Expired - Fee Related
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106049890A (en) * | 2016-08-08 | 2016-10-26 | 中建四局第三建筑工程有限公司 | Anti-falling hard protection block inside tower body and making method of hard protection block |
| CN106049890B (en) * | 2016-08-08 | 2018-06-05 | 中建四局第三建筑工程有限公司 | Preventing dropped material hard protection block and preparation method thereof inside a kind of tower body |
| TWI623483B (en) * | 2017-07-12 | 2018-05-11 | Wan Chang Yi | Elevator shaft working platform |
| CN112554579A (en) * | 2020-12-22 | 2021-03-26 | 中建四局第六建设有限公司 | Movable platform of unloading of assembled building utilization elevator well |
| CN112854787A (en) * | 2021-02-27 | 2021-05-28 | 安徽水利开发有限公司 | Self-locking horizontal sealing protective device for elevator shaft |
| CN116122549A (en) * | 2023-03-29 | 2023-05-16 | 上海星杰装饰有限公司 | Fitment is with safety device |
| CN117188800A (en) * | 2023-08-30 | 2023-12-08 | 中建五局第三建设有限公司 | Vertical entrance to a cave protector suitable for construction |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105201195A (en) | Liftable supporting leg type elevator shaft construction platform and method | |
| CN204126230U (en) | Assembly scaffold unit | |
| CN103556820A (en) | Suspension mold for enlarging and reinforcing concrete beam and construction method of suspension mold | |
| CN206352391U (en) | Socket joint type key slot type Quick Release support system | |
| CN102454292A (en) | Supporting steel frame of high altitude large-span cantilever structure mold frame | |
| CN205224288U (en) | Connection node of reinforced concrete superposed beam and steel pipe column | |
| CN201991226U (en) | Flange template support structure | |
| CN204343642U (en) | Builder's jack corner support frame | |
| CN203441069U (en) | Outer wall dangling working platform capable of overturning | |
| CN201943350U (en) | Supporting steel frame for die holder of high-altitude large span overhanging structure | |
| CN205577404U (en) | Template fixing tool is pour to shear force wall waist rail concrete | |
| CN219826024U (en) | Scaffold structure easy to build | |
| CN204001702U (en) | A kind of J-shaped wall plastic formwork | |
| CN105756067B (en) | A kind of method of horizontal temporary support support replacement in deep basal pit | |
| CN206376514U (en) | Tool climbing scaffold | |
| CN205822464U (en) | Floor type self-bearing prefabricated external wall panel | |
| CN204357020U (en) | Ancient building eaves structure | |
| CN205591507U (en) | Scaffold frame of easily dismantling | |
| CN211257760U (en) | A triangular support device for cantilevered scaffolding | |
| CN205153144U (en) | Joint construction of shear force corner portion and slant girder steel | |
| CN209243920U (en) | A kind of prefabricated components connecting node | |
| CN103276889B (en) | Full hall fastener type steel pipe scaffold anti-side shifting method | |
| CN205242981U (en) | Concrete construction operation platform | |
| CN219431314U (en) | Construction platform for outer flue of outer wall | |
| CN106703388A (en) | Construction scaffold platform erected in super-high-layer building elevator shaft |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151202 |