CN204753893U - Assembled shear wall structure - Google Patents
Assembled shear wall structure Download PDFInfo
- Publication number
- CN204753893U CN204753893U CN201520296470.7U CN201520296470U CN204753893U CN 204753893 U CN204753893 U CN 204753893U CN 201520296470 U CN201520296470 U CN 201520296470U CN 204753893 U CN204753893 U CN 204753893U
- Authority
- CN
- China
- Prior art keywords
- shear wall
- hole
- main body
- vertical
- wall structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
本实用新型公开了一种装配式剪力墙结构,包括剪力墙主体(1),在剪力墙主体(1)内部设置有至少一个竖向通孔(2),在剪力墙主体(1)上端设置有至少一个螺栓孔(3),在剪力墙主体(1)下端设置至少一个预留导向孔(4),预留导向孔(4)的位置与螺栓孔(3)的位置上下对应。本实用新型装配式剪力墙结构及其安装方法可精准快速水平定位,整体性好,安装快捷,无需斜撑进行支撑,节省了辅助材料成本。
The utility model discloses an assembled shear wall structure, which comprises a shear wall main body (1), at least one vertical through hole (2) is arranged inside the shear wall main body (1), and the shear wall main body ( 1) At least one bolt hole (3) is provided at the upper end, at least one reserved guide hole (4) is provided at the lower end of the shear wall main body (1), and the position of the reserved guide hole (4) and the position of the bolt hole (3) correspond up and down. The utility model's assembled shear wall structure and its installation method can be accurately and quickly positioned horizontally, have good integrity, and are quick to install, and do not need diagonal braces for support, which saves the cost of auxiliary materials.
Description
技术领域 technical field
本实用新型涉及建筑领域,尤其是装配式剪力墙结构。 The utility model relates to the construction field, in particular to an assembled shear wall structure.
背景技术 Background technique
装配式剪力墙结构作为装配式混凝土结构的一种,具有现场人工少、施工快捷、湿作业量少、材料用量少、施工现场扬尘及建筑垃圾少等优点在许多发达国家已有广泛应用,然而目前装配式剪力墙结构定位效果不好,容易存在错位的情况,为防止剪力墙在安装时出现倾斜倒塌的情况,还需要用人工用斜撑进行支撑,然而使用斜撑增加了工人劳动力,且不容易保证精度。 As a kind of prefabricated concrete structure, the prefabricated shear wall structure has the advantages of less on-site labor, quick construction, less wet work, less material consumption, less dust and construction waste on the construction site, and has been widely used in many developed countries. However, the positioning effect of the prefabricated shear wall structure is not good at present, and it is prone to misalignment. In order to prevent the shear wall from tilting and collapsing during installation, it is necessary to support it manually with diagonal braces. However, the use of diagonal braces increases Worker labor, and it is not easy to guarantee accuracy.
实用新型内容 Utility model content
本实用新型所要解决的技术问题是,针对上述现有技术的不足,提供一种装配式剪力墙结构,该装配式剪力墙结构可精准快速水平、竖直度定位,整体性好,安装快捷,无需斜撑进行支撑,节省了辅助材料成本。 The technical problem to be solved by the utility model is to provide a prefabricated shear wall structure for the deficiencies of the above-mentioned prior art. It is fast and does not require diagonal braces for support, saving the cost of auxiliary materials.
本实用新型装配式剪力墙结构所采用的技术方案如下: The technical scheme adopted by the utility model assembled shear wall structure is as follows:
本实用新型装配式剪力墙结构,包括剪力墙主体,在剪力墙主体内部设置有至少一个竖向通孔,在剪力墙主体上端设置有至少一个螺栓孔,在剪力墙主体下端设置至少一个预留导向孔,预留导向孔的位置与螺栓孔的位置上下对应。竖向通孔在浇注前用于插入钢管,以便在竖直方向将上下两片装配式剪力墙结构进行临时定位连接,螺栓孔和预留导向孔用于容纳调平及定位装置,使上下两片装配式剪力墙结构在水平方向进行定位调整。 The utility model's assembled shear wall structure includes a shear wall main body, at least one vertical through hole is arranged inside the shear wall main body, at least one bolt hole is arranged at the upper end of the shear wall main body, and at least one bolt hole is arranged at the lower end of the shear wall main body. At least one reserved guide hole is provided, and the position of the reserved guide hole corresponds to the position of the bolt hole up and down. The vertical through holes are used to insert steel pipes before pouring, so as to temporarily connect the upper and lower assembled shear wall structures in the vertical direction. The bolt holes and reserved guide holes are used to accommodate the leveling and positioning devices, so that the upper and lower The two-piece prefabricated shear wall structure is positioned and adjusted in the horizontal direction.
作为本实用新型的优选方案,所述竖向通孔的数量为三个,三个竖向通孔均匀设置在剪力墙主体内部。通过将竖向通孔的数量设置为三个,可以加强上下两片装配式剪力墙结构连接的稳定性。 As a preferred solution of the present invention, the number of the vertical through holes is three, and the three vertical through holes are evenly arranged inside the main body of the shear wall. By setting the number of vertical through holes to three, the stability of the structural connection of the upper and lower prefabricated shear walls can be enhanced.
作为本实用新型的优选方案,所述螺栓孔的数量为两个,两个螺栓孔均匀分布在剪力墙主体上端,预留导向孔的数量与螺栓孔的数量相同,设置在剪力墙主体下端并与螺栓孔的位置上下对应。通过将螺栓孔的数量设置为两个,可以置入两个调平及定位装置,进一步提高上下两片装配式剪力墙结构之间水平方向定位的准确性。 As a preferred solution of the present utility model, the number of the bolt holes is two, and the two bolt holes are evenly distributed on the upper end of the main body of the shear wall. The lower end corresponds up and down with the positions of the bolt holes. By setting the number of bolt holes to two, two leveling and positioning devices can be placed to further improve the accuracy of positioning in the horizontal direction between the upper and lower assembled shear wall structures.
作为本实用新型的优选方案,在每个竖向通孔的上部均设置有方孔。通过在竖向通孔的上部设置方孔,,以便将楔子楔入钢管与竖向通孔之间的缝隙内,保证上下两片装配式剪力墙结构整体的垂直度。 As a preferred solution of the present invention, a square hole is arranged on the upper part of each vertical through hole. By setting a square hole on the upper part of the vertical through hole, the wedge is wedged into the gap between the steel pipe and the vertical through hole, so as to ensure the overall verticality of the upper and lower assembled shear wall structures.
作为本实用新型的优选方案,所述方孔的边长大于竖向通孔的直径7-15mm。 As a preferred solution of the present invention, the side length of the square hole is 7-15 mm longer than the diameter of the vertical through hole.
作为本实用新型的优选方案,所述方孔的边长大于竖向通孔的直径10mm。 As a preferred solution of the present utility model, the side length of the square hole is 10 mm longer than the diameter of the vertical through hole.
作为本实用新型的优选方案,在剪力墙主体上下两端分别设置有若干个均匀排列的环筋。 As a preferred solution of the present invention, several evenly arranged ring bars are respectively arranged at the upper and lower ends of the main body of the shear wall.
综上所述,本实用新型装配式剪力墙结构及其安装方法的优点是,该装配式剪力墙结构可精准快速水平定位,整体性好,安装快捷,无需斜撑进行支撑,节省了辅助材料成本。 To sum up, the advantages of the prefabricated shear wall structure and its installation method of the present invention are that the prefabricated shear wall structure can be accurately and quickly positioned horizontally, has good integrity, is quick to install, and does not need support by diagonal braces, saving Auxiliary material costs.
附图说明 Description of drawings
图1是本实用新型装配式剪力墙结构的正视图。 Fig. 1 is the front view of the assembled shear wall structure of the present invention.
图2是本实用新型装配式剪力墙结构的侧视图。 Fig. 2 is a side view of the assembled shear wall structure of the present invention.
图3是本实用新型装配式剪力墙结构的俯视图。 Fig. 3 is a top view of the assembled shear wall structure of the present invention.
图4是调平及定位装置的结构示意图。 Fig. 4 is a structural schematic diagram of the leveling and positioning device.
具体实施方式 Detailed ways
如图1至4所示,本实用新型装配式剪力墙结构,包括剪力墙主体1,在剪力墙主体1内部设置有至少一个竖向通孔2,所述竖向通孔2的数量优选为两个或三个,(图中以三个为例)三个竖向通孔2均匀设置在剪力墙主体1内部,三个竖向通孔2可以加强上下两片装配式剪力墙结构连接的稳定性。在每个竖向通孔2的上部均设置有方孔5,所述方孔5的边长大于竖向通孔的直径7-15mm,优选为10mm。 As shown in Figures 1 to 4, the utility model's assembled shear wall structure includes a shear wall main body 1, and at least one vertical through hole 2 is arranged inside the shear wall main body 1, and the vertical through hole 2 The number is preferably two or three, (three are taken as an example in the figure) three vertical through holes 2 are evenly arranged inside the main body of the shear wall 1, and the three vertical through holes 2 can strengthen the upper and lower two assembled shears. Stability of force-wall structural connections. A square hole 5 is arranged on the upper part of each vertical through hole 2, and the side length of the square hole 5 is 7-15 mm longer than the diameter of the vertical through hole, preferably 10 mm.
在剪力墙主体1上端设置有至少一个螺栓孔3,在剪力墙主体1下端设置至少一个预留导向孔4,预留导向孔4的位置与螺栓孔3的位置上下对应。所述螺栓孔3的数量为两个,两个螺栓孔3均匀分布在剪力墙主体1上端,预留导向孔4的数量与螺栓孔3的数量相同,设置在剪力墙主体1下端并与螺栓孔3的位置上下对应。螺栓孔3可以置入调平及定位装置,进一步提高上下两片装配式剪力墙结构之间水平方向定位的准确性。 At least one bolt hole 3 is provided at the upper end of the shear wall main body 1, and at least one reserved guide hole 4 is provided at the lower end of the shear wall main body 1, and the position of the reserved guide hole 4 corresponds to the position of the bolt hole 3 up and down. The number of the bolt holes 3 is two, and the two bolt holes 3 are evenly distributed on the upper end of the shear wall main body 1, and the number of the reserved guide holes 4 is the same as the number of the bolt holes 3, which are arranged at the lower end of the shear wall main body 1 and It corresponds up and down to the position of the bolt hole 3. The bolt hole 3 can be placed into a leveling and positioning device to further improve the accuracy of positioning in the horizontal direction between the upper and lower assembled shear wall structures.
在剪力墙主体1上下两端分别设置有若干个均匀排列的环筋6。竖向通孔2在浇注前用于插入钢管,以便在竖直方向将上下两片装配式剪力墙结构进行临时定位连接,螺栓孔3和预留导向孔4用于容纳调平及定位装置7,使上下两片装配式剪力墙结构在水平方向进行定位调整。环筋6的设置起到加强上下两片装配式剪力墙结构之间的连接作用。 A number of uniformly arranged ring bars 6 are respectively arranged at the upper and lower ends of the shear wall main body 1 . The vertical through hole 2 is used to insert steel pipes before pouring, so as to temporarily connect the upper and lower assembled shear wall structures in the vertical direction, and the bolt holes 3 and reserved guide holes 4 are used to accommodate leveling and positioning devices 7. Position and adjust the upper and lower assembled shear wall structures in the horizontal direction. The setting of the ring reinforcement 6 serves to strengthen the connection between the upper and lower assembled shear wall structures.
本实用新型装配式剪力墙结构的安装方法如下: The installation method of the prefabricated shear wall structure of the utility model is as follows:
a、在下部装配式剪力墙的竖向通孔2内放置钢管,在螺栓孔3内安装调平及定位装置7; a. Place a steel pipe in the vertical through hole 2 of the lower prefabricated shear wall, and install a leveling and positioning device 7 in the bolt hole 3;
b、将上部装配式剪力墙通孔沿钢管吊装至安装位置,调平及定位装置的上端插入到预留导向孔4内,实现上下两片装配式剪力墙的水平位置定位;钢管对上部剪力墙其临时支撑作用,使其不发生倾覆; b. Hoist the through hole of the upper prefabricated shear wall to the installation position along the steel pipe, and insert the upper end of the leveling and positioning device into the reserved guide hole 4 to realize the horizontal position positioning of the upper and lower prefabricated shear walls; The upper shear wall acts as a temporary support to keep it from overturning;
c、在钢管与竖向通孔2的缝隙之间楔入楔子,保证上下两片装配式剪力墙的垂直度; c. Insert a wedge between the gap between the steel pipe and the vertical through hole 2 to ensure the verticality of the upper and lower assembled shear walls;
d、在上下两片装配式剪力墙的接缝之间进行现浇层浇注; d. The cast-in-place layer is poured between the joints of the upper and lower prefabricated shear walls;
e、向上提升抽出钢管,在下部装配式剪力墙的竖向通孔2内浇注混凝土; e. Lift up and pull out the steel pipe, and pour concrete in the vertical through hole 2 of the lower prefabricated shear wall;
f、进行下一层剪力墙安装。 f. Proceed to the next layer of shear wall installation.
调平及定位装置7包括螺杆7-1、水平板7-2和连接支杆7-3,连接支杆7-3与螺杆7-1上下同轴固定设置,水平板7-2固定设置在连接支杆7-3与螺杆7-1之间。螺杆7-1的外螺纹与螺栓孔3的内螺纹相吻合,螺杆7-1置入螺栓孔3内,连接支杆7-3与预留导向孔4的大小相配合,连接支杆7-3置入预留导向孔4内。 The leveling and positioning device 7 includes a screw rod 7-1, a horizontal plate 7-2 and a connecting strut 7-3, the connecting strut 7-3 and the screw rod 7-1 are coaxially fixed up and down, and the horizontal plate 7-2 is fixedly set on Connect between the support rod 7-3 and the screw rod 7-1. The external thread of the screw rod 7-1 matches the internal thread of the bolt hole 3, the screw rod 7-1 is placed in the bolt hole 3, the connecting rod 7-3 matches the size of the reserved guide hole 4, and the connecting rod 7- 3 into the reserved guide hole 4.
钢管的长度等于上下两片装配式剪力墙的的高度,钢管的外径小于竖向通孔2的直径4-6mm。通过在竖向通孔2的上部设置方孔5以便将楔子楔入钢管与竖向通孔2之间的缝隙内,保证上下两片装配式剪力墙结构整体的垂直度。通过将钢管的长度设置为等于上下两片装配式剪力墙的的高度,钢管可以竖直插入上下两片装配式剪力墙结构的竖向通孔2内,对上下两片装配式剪力墙结构进行临时连接定位。通过将钢管的外径设置为小于竖向通孔2的直径4-6mm,可以使钢管与竖向通孔2之间留有一定的间隙,方便钢管的插入和提升取出。 The length of the steel pipe is equal to the height of the upper and lower prefabricated shear walls, and the outer diameter of the steel pipe is 4-6 mm smaller than the diameter of the vertical through hole 2 . By setting the square hole 5 on the upper part of the vertical through hole 2 so as to wedge the wedge into the gap between the steel pipe and the vertical through hole 2, the overall verticality of the upper and lower assembled shear wall structures is ensured. By setting the length of the steel pipe to be equal to the height of the upper and lower prefabricated shear walls, the steel pipe can be inserted vertically into the vertical through hole 2 of the upper and lower prefabricated shear wall structures. Wall structure for temporary connection positioning. By setting the outer diameter of the steel pipe to be 4-6mm smaller than the diameter of the vertical through hole 2, a certain gap can be left between the steel pipe and the vertical through hole 2, which facilitates the insertion and lifting of the steel pipe.
以上结合附图对本实用新型的优选实施方式做了详细说明,但本实用新型并不限于上述实施方式,在所属技术领域技术人员所具备的知识范围内,还可以在不脱离本实用新型宗旨的前提下作出各种变化。 The preferred embodiment of the utility model has been described in detail above in conjunction with the accompanying drawings, but the utility model is not limited to the above-mentioned embodiment. Various changes are made.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520296470.7U CN204753893U (en) | 2015-05-11 | 2015-05-11 | Assembled shear wall structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520296470.7U CN204753893U (en) | 2015-05-11 | 2015-05-11 | Assembled shear wall structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204753893U true CN204753893U (en) | 2015-11-11 |
Family
ID=54468616
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520296470.7U Expired - Fee Related CN204753893U (en) | 2015-05-11 | 2015-05-11 | Assembled shear wall structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204753893U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104831832A (en) * | 2015-05-11 | 2015-08-12 | 中国建筑第七工程局有限公司 | Assembly type shearing wall structure and mounting method thereof |
-
2015
- 2015-05-11 CN CN201520296470.7U patent/CN204753893U/en not_active Expired - Fee Related
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104831832A (en) * | 2015-05-11 | 2015-08-12 | 中国建筑第七工程局有限公司 | Assembly type shearing wall structure and mounting method thereof |
| CN104831832B (en) * | 2015-05-11 | 2017-12-08 | 中国建筑第七工程局有限公司 | Assembly of shear wall structure and its installation method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102493554B (en) | Abutting joint device of steel lattice column, and construction method of same | |
| CN207159789U (en) | A kind of beam prefabricated anti-collision wall structure of unit construction bridge | |
| CN108708394A (en) | A kind of tunneling boring exempts from the overlapping assembled comprehensive pipe gallery structure and construction method of support | |
| CN103321405B (en) | Large formwork lifting construction method for shear wall and cylinder concrete structure | |
| CN104831832B (en) | Assembly of shear wall structure and its installation method | |
| CN204753628U (en) | Guider that hangs down is transferred to contrary way of doing things steel -pipe column that can have enough to meet need | |
| CN106522282A (en) | Liftable post-cast strip template structure and system and construction method thereof | |
| CN109797969B (en) | Construction method of post-cast strip tool type advanced formwork lifting system | |
| CN106032704A (en) | A construction method for the structure on both sides of the post-cast belt with concrete columns supporting the roof | |
| CN217151150U (en) | Overhanging steel truss formwork supporting platform for aluminum mould-full concrete outer wall | |
| CN216195528U (en) | Assembled building element that can hoist fast | |
| CN204753893U (en) | Assembled shear wall structure | |
| CN103243910B (en) | Hydraulic pressure controlled reinforced concrete structure bed die vertical supporting system and construction method thereof | |
| CN203200664U (en) | Slip-form construction device for variable cross-section hollow high pier | |
| CN207436503U (en) | Efficient construction of precast floorslab hangs membrane module | |
| CN207314829U (en) | A kind of wooden model early tears support device open | |
| CN206941823U (en) | A kind of shock isolating pedestal | |
| CN206418523U (en) | A kind of liftable post-cast strip template structure and system | |
| CN106567538A (en) | Positioning mold for bathroom concrete flanges | |
| CN206397136U (en) | Assembled aluminum template masonry shearwalls reinforced concrete structural column | |
| CN104878775A (en) | Turnable top-down method steel pipe column verticality adjusting guide device and construction method thereof | |
| CN103669831B (en) | A kind of transformer station's cast-in-situ wall combined steel and construction method thereof | |
| CN103195079B (en) | Installing type template, installing type template group and complete installing type plate device | |
| CN206769416U (en) | A kind of concrete filled steel tube coupled column steel pipe temporary setting jig | |
| CN207109843U (en) | A kind of goaf transmission line foundation bracing means |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151111 Termination date: 20200511 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |