Prior art keywords
die
fixed support
gin pole
clamp
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520299754.1U
Other languages
Chinese (zh)
Inventor
张文志
陈玉宝
皮云生
张文渤
程林
刘泽强
陆长水
刘建东
杨志勇
王志刚
祝顺英
曹娜
王江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Harbour Fourthly Stevedoring Co., Ltd.
Original Assignee
TIANJIN HARBOUR FIFTH STEVEDORING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN HARBOUR FIFTH STEVEDORING CO Ltd filed Critical TIANJIN HARBOUR FIFTH STEVEDORING CO Ltd
Priority to CN201520299754.1U priority Critical patent/CN204638902U/en
Application granted granted Critical
Publication of CN204638902U publication Critical patent/CN204638902U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses the special tools of a kind of crane gin pole sheath clamp, it comprises base and top die, and described base and top die coordinate assembling to use; Described base is made up of base plate, fixed support and die; Described top die is made up of top board and punch; During use, by half-finished for clamp two ends from the circular hole of top die from bottom to top direction penetrate, be put in base, then entirety is put on press bench, and forcing press is suppressed top die, makes clamp be molded into the radian of needs.The utility model quality is little, can movement arbitrarily; The clamp one-shot forming that this tool making goes out, does not need reprocessing, can meet the making requirement of crane gin pole sheath clamp well, and easy and simple to handle, safe and reliable.

Description

Crane gin pole sheath clamp makes specific purpose tool
Technical field
The utility model belongs to moulded section technical field of tools, and particularly a kind of crane gin pole sheath clamp makes specific purpose tool.
Background technology
Crane is the main loading mechanization of PORT OF TIANJIN, machinery quantity is larger, and utilization rate is higher, crane eave tile often clashes into gin pole sheath when driving, causes the distortion of sheath turn-buckle, fracture, thread damage, because market does not have shaping clamp, so can only processing and fabricating voluntarily, like this, for addressing this problem, need the making requirement meeting clamp according to a kind of specific purpose tool of size characteristics development and design of clamp.
Utility model content
The purpose of this utility model is to overcome the deficiencies in the prior art, provides a kind of crane gin pole sheath clamp to make specific purpose tool.
The utility model realizes by the following technical solutions:
The special tools of a kind of crane gin pole sheath clamp comprise base and top die, and base and top die coordinate assembling to use;
Described base is made up of base plate, fixed support and die; Described fixed support comprises the first fixed support and the second fixed support, and described first fixed support is identical with the second fixed support shape, is rectangular shape, and the first fixed support and the second fixed support symmetry are fixedly installed on the upper surface of base plate; Described die comprises the first die and the second die, and the first die is identical with the second die shape, is semicircle, and its semicircular opening is upwards arranged; First die and the second die are fixed on base in parallel to each other, and bottom and the base plate of the first die and the second die are fixedly linked, and the two side ends of the first die and the second die is fixedly linked with the first fixed support and the second fixed support respectively; Gap is provided with between first die and the second die;
Described top die is made up of top board and punch, and described punch is semicircular structure, and the semicircular opening of punch is fixed on the intermediate symmetrical position of top board, and punch forms convex body shape; Top board is centrally symmetrically arranged with the first circular hole and the second circular hole, its aperture is identical.
In technique scheme, the length of described base plate is 200mm, and wide is 150mm, and thick is 15mm.
In technique scheme, described support bracket fastened length is 50mm, and wide is 30mm, and height is 100mm; Spacing between first fixed support and the second fixed support is 120mm.
In technique scheme, the external diameter of described first die and the second die is 120mm, and internal diameter is 80mm, and wide is 50mm.
In technique scheme, the external diameter of described punch is 100mm, and internal diameter is 80mm, and wide is 50mm.
In technique scheme, the diameter of described first circular hole and the second circular hole is 18mm.
In technique scheme, the length of described top board is 200mm, and wide is 50mm, and thick is 10mm.
Using method: clamp semi-finished product (two of long 50mm diameter 16mm processes the round steel of screw thread) are folded down the centre into " U " shape, make half-finished two ends from the circular hole of top die from bottom to top direction penetrate, be put in the gap between the first die of base and the second die, then entirety is put on press bench, the middle part of forcing press to top die is suppressed, make clamp be molded into the radian of needs, take off the manufacturing process that clamp completes whole clamp.
The utility model quality is little, can movement arbitrarily; The clamp one-shot forming that this tool making goes out, does not need reprocessing, can meet the making requirement of crane gin pole sheath clamp well, and easy and simple to handle, safe and reliable.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model,
Fig. 2 is the top view of Fig. 1,
Fig. 3 is the right view of Fig. 1,
Fig. 4 is the top view of the base in the utility model,
Fig. 5 is the structural representation of the top die in the utility model,
Fig. 6 is the top view of Fig. 5.
Detailed description of the invention
The technical solution of the utility model is further illustrated below in conjunction with specific embodiment.
As shown in accompanying drawing 1-4, the special tools of crane gin pole sheath clamp involved by the utility model comprise base and top die, and base and top die coordinate assembling to use;
Described base 1 is made up of base plate 1-1, fixed support and die; Described fixed support comprises the first fixed support 1-2 and the second fixed support 1-3, described first fixed support 1-2 is identical with the second fixed support 1-3 shape, be rectangular shape, the first fixed support 1-2 and the second fixed support 1-3 symmetry is fixedly installed on the upper surface of base plate 1-1; Described die comprises the first die 1-4 and the second die 1-5, and the first die 1-4 is identical with the second die 1-5 shape, and be semicircle, its semicircular opening is upwards arranged; First die 1-4 and the second die 1-5 is fixed on base in parallel to each other, bottom and the base plate 1-1 of the first die 1-4 and the second die 1-5 are fixedly linked, and the two side ends of the first die 1-4 and the second die 1-5 is fixedly linked with the first fixed support 1-2 and the second fixed support 1-3 respectively; Gap 1-6 is provided with between first die 1-4 and the second die 1-5;
As shown in accompanying drawing 5 and Fig. 6, described top die is made up of top board 2-1 and punch 2-2, and described punch 2-2 is semicircular structure, and the semicircular opening of punch 2-2 is fixed on the intermediate symmetrical position of top board 2-1, and punch 2-2 forms convex body shape; Top board 2-1 is centrally symmetrically arranged with the first circular hole 2-3 and the second circular hole 2-4, its aperture is identical.
The length of described base plate 1-1 is 200mm, and wide is 150mm, and thick is 15mm.
Described support bracket fastened length is 50mm, and wide is 30mm, and height is 100mm; Spacing between first fixed support 1-2 and the second fixed support 1-3 is 120mm.
The external diameter of described first die and the second die is 120mm, and internal diameter is 80mm, and wide is 50mm.
The external diameter of described punch 2-2 is 100mm, and internal diameter is 80mm, and wide is 50mm.
The diameter of described first circular hole 2-3 and the second circular hole 2-4 is 18mm.
The length of described top board 2-1 is 200mm, and wide is 50mm, and thick is 10mm.
Using method: clamp semi-finished product (two of long 50mm diameter 16mm processes the round steel of screw thread) are folded down the centre into " U " shape, make half-finished two ends from the circular hole of top die from bottom to top direction penetrate, be put in the gap between the first die of base and the second die, then entirety is put on press bench, the middle part of forcing press to top die is suppressed, make clamp be molded into the radian of needs, take off the manufacturing process that clamp completes whole clamp.
The utility model quality is little, can movement arbitrarily; The clamp one-shot forming that this tool making goes out, does not need reprocessing, can meet the making requirement of crane gin pole sheath clamp well, and easy and simple to handle, safe and reliable.
Above exemplary description is done to the utility model; should be noted that; when not departing from core of the present utility model, any simple distortion, amendment or other those skilled in the art can not spend the equivalent replacement of creative work all to fall into protection domain of the present utility model.

Claims (7)

1. the special tools of crane gin pole sheath clamp, comprise base and top die, it is characterized in that:
Described base is made up of base plate, fixed support and die; Described fixed support comprises the first fixed support and the second fixed support, and described first fixed support is identical with the second fixed support shape, is rectangular shape, and the first fixed support and the second fixed support symmetry are fixedly installed on the upper surface of base plate; Described die comprises the first die and the second die, and the first die is identical with the second die shape, is semicircle, and its semicircular opening is upwards arranged; First die and the second die are fixed on base in parallel to each other, and wherein, bottom and the base plate of the first die and the second die are fixedly linked, and the two side ends of the first die and the second die is fixedly linked with the first fixed support and the second fixed support respectively; Gap is provided with between first die and the second die;
Described top die is made up of top board and punch, and described punch is semicircular structure, and the semicircular opening of punch is fixed on the intermediate symmetrical position of top board; Described top board is centrally symmetrically arranged with the first circular hole and the second circular hole, its aperture is identical.
2. the special tools of crane gin pole sheath clamp according to claim 1, is characterized in that: the length of described base plate is 200mm, and wide is 150mm, and thick is 15mm.
3. the special tools of crane gin pole sheath clamp according to claim 1, it is characterized in that: described support bracket fastened length is 50mm, wide is 30mm, height is 100mm; Spacing between first fixed support and the second fixed support is 120mm.
4. the special tools of crane gin pole sheath clamp according to claim 1, is characterized in that: the external diameter of described first die and the second die is 120mm, and internal diameter is 80mm, and wide is 50mm.
5. the special tools of crane gin pole sheath clamp according to claim 1, is characterized in that: the external diameter of described punch is 100mm, and internal diameter is 80mm, and wide is 50mm.
6. the special tools of crane gin pole sheath clamp according to claim 1, is characterized in that: the diameter of described first circular hole and the second circular hole is 18mm.
7. the special tools of crane gin pole sheath clamp according to claim 1, is characterized in that: the length of described top board is 200mm, and wide is 50mm, and thick is 10mm.
CN201520299754.1U 2015-05-08 2015-05-08 Crane gin pole sheath clamp makes specific purpose tool Active CN204638902U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520299754.1U CN204638902U (en) 2015-05-08 2015-05-08 Crane gin pole sheath clamp makes specific purpose tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520299754.1U CN204638902U (en) 2015-05-08 2015-05-08 Crane gin pole sheath clamp makes specific purpose tool

Publications (1)

Publication Number Publication Date
CN204638902U true CN204638902U (en) 2015-09-16

Family

ID=54091678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520299754.1U Active CN204638902U (en) 2015-05-08 2015-05-08 Crane gin pole sheath clamp makes specific purpose tool

Country Status (1)

Country Link
CN (1) CN204638902U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104815909A (en) * 2015-05-08 2015-08-05 天津港第五港埠有限公司 Special tool for manufacturing crane derrick mast sheath fasteners

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104815909A (en) * 2015-05-08 2015-08-05 天津港第五港埠有限公司 Special tool for manufacturing crane derrick mast sheath fasteners

Similar Documents

Publication Publication Date Title
CN204638902U (en) Crane gin pole sheath clamp makes specific purpose tool
CN204320923U (en) A kind of punch die of processing thin-walled steel pipe symmetrical holes
CN104815909A (en) Special tool for manufacturing crane derrick mast sheath fasteners
CN203370885U (en) Lamp post bending machine
CN203803998U (en) Base for machining 520T type bends
CN203356230U (en) Elbow processing die base plate
CN204955063U (en) Make device of cylindrical concrete sample
CN202570939U (en) Dual-chamfering die for dowel screw
CN203221126U (en) Support compound die stamping device
CN204262599U (en) A kind of positioning fixture
CN203304398U (en) Bending die for support of automobile
CN204209023U (en) A kind of back-moving spring with fixing hole
CN203356375U (en) Sizing die for machining elbow
CN203171649U (en) Double-arm robot
CN208116995U (en) The super mould of burn-oning of ultrasonic, super weldering lower mold assemblies for auto lamp
CN201815721U (en) Clamping device for locking hole of web plate of rocker arm of straight-line machine
CN202239245U (en) Bend forming die
CN205732584U (en) A kind of frock bending molding for support roller hanger
CN202571135U (en) Baffle plate of nut mould
CN202606703U (en) Guiding rod of die for square U-shaped clamps
CN203356236U (en) Punch for machining three-way pipe
CN204470512U (en) Welding neck flange mould
CN202683798U (en) Bent pipe mould
CN203356446U (en) Improved elbow tool
CN203356374U (en) Die for machining three-way pipe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20181017

Address after: 300456 Tianjin Binhai New Area Tanggu Xingang two road 2750

Patentee after: Tianjin Harbour Fourthly Stevedoring Co., Ltd.

Address before: 300456 Tianjin Binhai New Area Tanggu Xingang two road 3653

Patentee before: Tianjin Harbour Fifth Stevedoring Co., Ltd.