CN204626915U - A kind of large span heavy in section truss is across interior assembling rack platform - Google Patents

A kind of large span heavy in section truss is across interior assembling rack platform Download PDF

Info

Publication number
CN204626915U
CN204626915U CN201520335144.2U CN201520335144U CN204626915U CN 204626915 U CN204626915 U CN 204626915U CN 201520335144 U CN201520335144 U CN 201520335144U CN 204626915 U CN204626915 U CN 204626915U
Authority
CN
China
Prior art keywords
platform
beams
truss
horizontal
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201520335144.2U
Other languages
Chinese (zh)
Inventor
李明
邱文波
郭蕾
王安龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201520335144.2U priority Critical patent/CN204626915U/en
Application granted granted Critical
Publication of CN204626915U publication Critical patent/CN204626915U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Ladders (AREA)

Abstract

本实用新型公开了一种大跨度大截面桁架跨内组装支架平台,包括支架体和支座;所述支架体由两排立柱以及若干水平横梁构成,所有水平横梁将立柱横向连接为一体。立柱下端固定在支座上。支架体顶部设有两水平的顶部横梁,在两顶部横梁下设有对应的两平台横梁,两平台横梁与两排立柱对应连接;两平台横梁上铺设竹跳板形成操作平台,操作平台与顶部横梁之间形成作业空间。本支架平台高度根据不同基础位置标高设置,保证各个平台上端在同一标高上,很好的解决了支架平台对场地强度和平整度的问题。本支架平台上的操作平台位于顶部之下,与顶部之间设置有作业空间,方便作业人员操作,提高了施工效率。

The utility model discloses a large-span and large-section truss assembly bracket platform, which includes a bracket body and a support; the bracket body is composed of two rows of upright columns and a plurality of horizontal beams, and all the horizontal beams connect the upright columns horizontally into one body. The lower end of the column is fixed on the support. There are two horizontal top beams on the top of the support body, and two corresponding platform beams are arranged under the two top beams, and the two platform beams are connected with the two rows of columns correspondingly; bamboo springboards are laid on the two platform beams to form an operation platform, and the operation platform and the top beam work space between them. The height of the support platform is set according to the elevation of different foundation positions to ensure that the upper ends of each platform are on the same elevation, which solves the problem of the strength and flatness of the support platform to the site. The operating platform on the support platform is located under the top, and there is a working space between the top and the top, which is convenient for operators to operate and improves the construction efficiency.

Description

一种大跨度大截面桁架跨内组装支架平台A large-span and large-section truss assembly support platform in the span

技术领域 technical field

本实用新型涉及一种施工措施用平台,具体涉及一种用于大型场馆屋面大跨度大截面桁架跨内组装支架平台,属于建筑技术领域。 The utility model relates to a platform for construction measures, in particular to a platform for assembling a bracket within the span of a large-span and large-section truss on the roof of a large venue, and belongs to the field of building technology.

背景技术 Background technique

目前,大型表演场馆屋面往往涉及到大跨度桁架结构,对于桁架构件的安装常采用在外部搭设平台进行组装,该平台只能在基础条件好、平整开阔的场地使用。该组装平台即作为操作人员的站台,又作为放置施工工具的平台层。这种平台不能满足构件场馆内部组装的要求,施工效率低下,要求设置专门的吊装设备,转移、机械费用高,施工效率低下。因此如何对大跨度大截面桁架结构进行安全、高效的组装与安装是一个急待解决的问题。 At present, the roof of large-scale performance venues often involves long-span truss structures. The installation of truss members is often assembled on an external platform. This platform can only be used in a flat and open site with good foundation conditions. The assembly platform not only serves as a platform for operators, but also as a platform layer for placing construction tools. This kind of platform cannot meet the requirements for internal assembly of component venues, and the construction efficiency is low. It requires special hoisting equipment, high transfer and mechanical costs, and low construction efficiency. Therefore, how to safely and efficiently assemble and install large-span and large-section truss structures is an urgent problem to be solved.

发明内容 Contents of the invention

针对现有组装平台对施工场地基础及平整度要求高且效率低下等不足,本实用新型的目的是提供一种可以在跨内进行组装的支架平台,安装于场馆的内部,适用于任何内部不平整的情况,效率更加高效。 Aiming at the deficiencies of the existing assembly platform, such as high requirements on the foundation and flatness of the construction site, and low efficiency, the purpose of this utility model is to provide a support platform that can be assembled in the span, installed inside the stadium, and suitable for any internal The smoother the situation, the more efficient it is.

为实现上述目的,本实用新型的技术方案是这样来实现的: In order to achieve the above object, the technical solution of the utility model is achieved in this way:

一种大跨度大截面桁架跨内组装支架平台,包括支架体和支座;所述支架体由两排立柱以及若干水平横梁构成,每排立柱为2-4根,所有水平横梁将立柱横向连接为一体以形成连为一体的多个口字结构;支座固定安装在建筑结构上,立柱下端固定在支座上;支架体顶部设有两水平的顶部横梁,两顶部横梁与两排立柱上端对应连接,两顶部横梁形成支撑桁架的桁架平台;在两顶部横梁下设有对应的两水平的平台横梁,两平台横梁与两排立柱对应连接;顶部横梁和平台横梁两端相对支架体向外悬挑一定距离;两平台横梁上铺设竹跳板形成操作平台,操作平台与顶部横梁之间形成作业空间。 A large-span and large-section truss assembly bracket platform, including a bracket body and a support; the bracket body is composed of two rows of columns and a number of horizontal beams, each row of columns is 2-4, and all horizontal beams connect the columns horizontally Integrate to form a plurality of mouth structures connected as one; the support is fixedly installed on the building structure, and the lower end of the column is fixed on the support; the top of the support body is provided with two horizontal top beams, the two top beams and the upper ends of the two rows of columns Correspondingly connected, the two top beams form a truss platform supporting the truss; there are corresponding two horizontal platform beams under the two top beams, and the two platform beams are connected to the two rows of columns; the two ends of the top beam and the platform beam are facing outward relative to the bracket Cantilevered at a certain distance; bamboo springboards are laid on the beams of the two platforms to form an operating platform, and the operating space is formed between the operating platform and the top beams.

在每个口字结构内对角设置水平支撑;在横梁与立柱形成的竖向平面内设置斜撑。 Set horizontal supports diagonally in each word structure; set diagonal braces in the vertical plane formed by beams and columns.

所述水平横梁在不同高度上分层设置,每层上的水平横梁设置方式相同。 The horizontal beams are arranged in layers at different heights, and the horizontal beams on each floor are arranged in the same manner.

所述支座为与立柱数量一一对应的方形钢板构成,方形钢板通过螺栓与建筑结构固定,立柱下端焊接在方形钢板上表面。 The support is composed of square steel plates corresponding to the number of columns one by one, the square steel plates are fixed to the building structure by bolts, and the lower ends of the columns are welded to the upper surface of the square steel plates.

所述支架体上设有垂直爬梯,以作为连接地面与操作平台的通道。 The support body is provided with a vertical ladder as a channel connecting the ground and the operating platform.

所述操作平台周围设有一定高度的防护围挡。 A protective enclosure of a certain height is provided around the operating platform.

相比现有技术,本实用新型具有如下有益效果: Compared with the prior art, the utility model has the following beneficial effects:

1、本支架平台以场馆内部结构为基础,高度根据不同基础位置标高设置,保证各个平台上端在同一标高上,很好的解决了支架平台对场地强度和平整度的问题,可以适用于各种大跨度大截面的桁架的组装。 1. The support platform is based on the internal structure of the venue, and the height is set according to the elevation of different foundation positions to ensure that the upper ends of each platform are on the same elevation, which solves the problem of the strength and flatness of the support platform on the site, and can be applied to various Assembly of trusses with large spans and large sections.

2、本支架平台上的操作平台位于顶部之下,与顶部之间设置有作业空间,方便作业人员操作,避免了构件来回的翻面,节省了人力、物力,提高了施工效率。 2. The operating platform on the support platform is located under the top, and there is a working space between the top and the top, which is convenient for operators to operate, avoids the back and forth turning of components, saves manpower and material resources, and improves construction efficiency.

3、本平台搭设于场馆内部,桁架组装好后即可提升吊装,减少了桁架的多次转移,减少了变形,同时降低了桁架单次提升高度,提高效率的同时,更能保证施工安全。 3. The platform is built inside the stadium. After the trusses are assembled, they can be lifted and hoisted, which reduces the multiple transfers of the trusses, reduces deformation, and reduces the single lifting height of the trusses. It improves efficiency and ensures construction safety.

附图说明 Description of drawings

图1-本实用新型结构示意图。 Fig. 1 - structural representation of the utility model.

图2-支架平台与桁架拼装立面图。 Figure 2 - Elevation view of bracket platform and truss assembly.

图3-支架与桁架拼装平面图。 Figure 3 - Plane view of bracket and truss assembly.

具体实施方式 Detailed ways

下面结合附图对本实用新型作进一步说明。 Below in conjunction with accompanying drawing, the utility model is further described.

参见图1,从图上可以看出,本实用新型大跨度大截面桁架跨内组装支架平台,包括支架体和支座1;所述支架体由两排立柱2以及若干水平横梁3构成,每排立柱2为2-4根,实际设计为3根,所有水平横梁3将立柱2横向连接为一体以形成连为一体的多个口字结构。支座1固定安装在建筑结构(混凝土)上,立柱2下端固定在支座1上。支架体顶部设有两水平的顶部横梁4,两顶部横梁4与两排立柱2上端对应连接,两顶部横梁形成支撑桁架的桁架平台。在两顶部横梁4下设有对应的两水平的平台横梁5,两平台横梁5与两排立柱2对应连接;顶部横梁4和平台横梁5两端相对支架体向外悬挑一定距离。 Referring to Fig. 1, it can be seen from the figure that the large-span and large-section truss span assembly support platform of the present invention includes a support body and a support 1; the support body is composed of two rows of columns 2 and several horizontal beams 3, each Rows of columns 2 are 2-4, and the actual design is 3, and all horizontal beams 3 horizontally connect the columns 2 into one to form a plurality of word structures connected together. The support 1 is fixedly installed on the building structure (concrete), and the lower end of the column 2 is fixed on the support 1. Two horizontal top beams 4 are arranged on the top of the support body, and the two top beams 4 are correspondingly connected with the upper ends of the two rows of columns 2, and the two top beams form a truss platform supporting the truss. Two corresponding horizontal platform beams 5 are arranged under the two top beams 4, and the two platform beams 5 are correspondingly connected with two rows of columns 2; the two ends of the top beam 4 and the platform beam 5 cantilever a certain distance outward relative to the support body.

为了便于工人作业,在平台横梁及与立柱连接形成的平面内对角设置水平支撑,平台横梁和水平支撑形成的平台上满铺竹跳板以形成操作平台,操作平台四周设置一定高度的防护围挡,这样既便于施工,又能很好的保证操作人员的施工安全问题。操作平台与顶部横梁之间形成作业空间,工人对构件各个面的操作焊接均可进行,无需对大型构件进行翻面,方便有效。 In order to facilitate workers' work, horizontal supports are arranged diagonally in the plane formed by the platform beams and the connection with the columns. The platform formed by the platform beams and horizontal supports is covered with bamboo springboards to form an operation platform, and a certain height of protective fence is set around the operation platform. , which is not only convenient for construction, but also can ensure the construction safety of operators. A working space is formed between the operating platform and the top beam, and workers can perform welding operations on all sides of the components without turning over large components, which is convenient and effective.

在每个口字结构内对角设置水平支撑6;同时在水平横梁3与立柱2形成的竖向平面内设置斜撑7。其中,所述水平横梁3在不同高度上分层设置,每层上的水平横梁3设置方式相同。通过上述连接结构,可以进一步增强支架体的强度,使之连接成一个整体受力架体。 Horizontal supports 6 are arranged diagonally in each word-shaped structure; at the same time, diagonal braces 7 are arranged in the vertical plane formed by the horizontal beam 3 and the column 2 . Wherein, the horizontal beams 3 are arranged in layers at different heights, and the horizontal beams 3 on each layer are arranged in the same way. Through the above connection structure, the strength of the support body can be further enhanced, so that it can be connected into a whole stress-bearing frame body.

所述支座1为与立柱2数量一一对应的方形钢板构成,钢板上设置纵横向排列的连接孔,方形钢板通过螺栓、连接孔与建筑结构固定,立柱下端焊接在方形钢板上表面。 The support 1 is composed of square steel plates corresponding to the number of columns 2 one by one. Connection holes arranged vertically and horizontally are arranged on the steel plates. The square steel plates are fixed to the building structure through bolts and connection holes. The lower ends of the columns are welded to the upper surface of the square steel plates.

为方便上下,所述支架体上设有垂直爬梯8,爬梯8采用圆钢制作,以作为连接地面与操作平台的通道。 For the convenience of going up and down, the support body is provided with a vertical ladder 8, and the ladder 8 is made of round steel as a passage connecting the ground and the operating platform.

所述立柱为钢管,水平横梁与斜撑为角钢,平台横梁及顶部横梁为方钢。本平台为钢架结构,各部分之间采用焊接连接。 The columns are steel pipes, the horizontal beams and diagonal braces are angle steels, and the platform beams and top beams are square steels. The platform is a steel frame structure, and the parts are connected by welding.

在桁架组装时,可以根据桁架的分段数量确定本支架平台的个数,以桁架分段长短确定各支架平台间的距离,适用于各种类型分段桁架的组装,也适用于不同跨距场馆安装的需要。图2和图3为支架平台与桁架拼装效果图,图中桁架分为三段,所以需要的支架平台为四套。图2反映的是支架平台在建筑场馆内与桁架拼装效果。 When the truss is assembled, the number of the support platforms can be determined according to the number of truss segments, and the distance between each support platform can be determined by the length of the truss segments. It is suitable for the assembly of various types of segmented trusses, and is also suitable for different spans. Venue installation needs. Figure 2 and Figure 3 are the assembly effect diagrams of the support platform and the truss. In the figure, the truss is divided into three sections, so four sets of support platforms are required. Figure 2 reflects the assembly effect of the bracket platform and the truss in the building venue.

其中每个支架平台高度根据场馆内部安装位置的标高确定,这样既能保证各平台顶部标高一致,灵活的高度控制增加了平台的适用性。 The height of each support platform is determined according to the elevation of the installation location inside the venue, so as to ensure that the top elevation of each platform is consistent, and the flexible height control increases the applicability of the platform.

本实用新型借助于场馆内部结构进行安装,降低了桁架垂直吊装的高度,降低了安装的风险,提高了安装效率。 The utility model is installed by means of the internal structure of the stadium, which reduces the vertical hoisting height of the truss, reduces the risk of installation, and improves the installation efficiency.

以上实施例仅说明本实用新型的技术方案而非限制,尽管参照较佳实施例对实用新型方案进行了详细说明,本领域的普通技术人员应当理解,可以对本实用新型的技术方案进行修改或者等同替换,而不脱离本实用新型技术方案的宗旨和范围,其均应涵盖在本实用新型的权利要求范围内。 The above embodiments only illustrate the technical solution of the utility model without limitation, although the utility model solution has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical solution of the utility model can be modified or equivalent Replacement, without departing from the purpose and scope of the technical solution of the utility model, all of them should be covered by the scope of the claims of the utility model.

Claims (6)

1. large span heavy in section truss is across an interior assembling rack platform, it is characterized in that: comprise stake body and bearing; Described stake body by two row columns and some horizontal girds form, often arrange column be 2-4 root, all horizontal girds by upright horizontal to connecting as one to form the multiple mouthfuls of word structures be connected as a single entity; Bearing is fixedly mounted in building structure, and column lower end is fixed on bearing; Stake body top is provided with the top cross-bar of two levels, and two top cross-bar and two arrange that column upper end is corresponding to be connected, and two top cross-bar form the truss platform of sub-trusses; Have the platform beams of two corresponding levels in two top cross-bar, two platform beams and two arrange that column is corresponding to be connected; Top cross-bar and platform beams two ends opposite brackets body are outwards encorbelmented certain distance; Two platform beams are laid bamboo springboard and form operating platform, between operating platform and top cross-bar, form working space.
2. a kind of large span heavy in section according to claim 1 truss is across interior assembling rack platform, it is characterized in that: arrange horizontal support each mouthful of word structure inner opposite angle; In the vertical plane that crossbeam and column are formed, diagonal brace is set.
3. a kind of large span heavy in section according to claim 1 and 2 truss is across interior assembling rack platform, it is characterized in that: described horizontal gird is arranged at differing heights higher slice, and the horizontal gird set-up mode on every layer is identical.
4. a kind of large span heavy in section according to claim 1 truss is across interior assembling rack platform, it is characterized in that: described bearing for column quantity one to one square plate form, square plate is fixed by bolt and building structure, and column lower end is welded on square plate upper surface.
5. a kind of large span heavy in section according to claim 1 truss is across interior assembling rack platform, it is characterized in that: described stake body is provided with vertical cat ladder, using the passage as connection ground and operating platform.
6. a kind of large span heavy in section according to claim 1 truss is across interior assembling rack platform, it is characterized in that: the protection enclosing being provided with certain altitude around described operating platform.
CN201520335144.2U 2015-05-22 2015-05-22 A kind of large span heavy in section truss is across interior assembling rack platform Expired - Lifetime CN204626915U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520335144.2U CN204626915U (en) 2015-05-22 2015-05-22 A kind of large span heavy in section truss is across interior assembling rack platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520335144.2U CN204626915U (en) 2015-05-22 2015-05-22 A kind of large span heavy in section truss is across interior assembling rack platform

Publications (1)

Publication Number Publication Date
CN204626915U true CN204626915U (en) 2015-09-09

Family

ID=54045955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520335144.2U Expired - Lifetime CN204626915U (en) 2015-05-22 2015-05-22 A kind of large span heavy in section truss is across interior assembling rack platform

Country Status (1)

Country Link
CN (1) CN204626915U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111809849A (en) * 2020-08-18 2020-10-23 浙江中南建设集团钢结构有限公司 Auxiliary operation platform for installation of outer guard plate of ventilation building and its use method
CN112282330A (en) * 2020-10-19 2021-01-29 华能新能源股份有限公司河北分公司 Impeller assembling and hoisting platform for wind turbine generator in mountainous wind power plant
CN112482719A (en) * 2020-11-16 2021-03-12 北京市机械施工集团有限公司 Multifunctional operation platform for large-span truss and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111809849A (en) * 2020-08-18 2020-10-23 浙江中南建设集团钢结构有限公司 Auxiliary operation platform for installation of outer guard plate of ventilation building and its use method
CN111809849B (en) * 2020-08-18 2025-01-24 浙江中南绿建科技集团有限公司 Auxiliary belt counterweight operation platform for installing the outer protective plate of ventilation air building and use method thereof
CN112282330A (en) * 2020-10-19 2021-01-29 华能新能源股份有限公司河北分公司 Impeller assembling and hoisting platform for wind turbine generator in mountainous wind power plant
CN112482719A (en) * 2020-11-16 2021-03-12 北京市机械施工集团有限公司 Multifunctional operation platform for large-span truss and construction method thereof

Similar Documents

Publication Publication Date Title
CN106760529B (en) Roof steel truss sliding assembly construction platform and installation method
CN103132766B (en) Truss for lifting power transmission line tower connecting leg and erection method
CN204780560U (en) Steel suspension bridge assembly structure
CN212689520U (en) Quick docking operation platform
CN204626915U (en) A kind of large span heavy in section truss is across interior assembling rack platform
CN115288449A (en) Construction method of middle support installation of large-span grid frame
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN208845309U (en) The support platform and wind power generating set of tower
CN107119576A (en) Pier body construction safety protection platform
CN103967263B (en) Hydraulic automatic jumping discharging platform
CN207227957U (en) Pier body construction safety protection platform
CN113309008A (en) Steel case roof beam temporary support construction safety work platform
CN103397638A (en) Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support
CN103882882B (en) Integral jacking formula tower crane platform structure
CN102191866A (en) Device and method for removal construction of vertical posts positioned on lower part of large-span net rack
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
CN207526141U (en) Small-section tower-shaped steel structure assembled operating platform
CN211922969U (en) Umbrella-shaped elevated structure supporting frame for integrated module house
CN213204913U (en) Modular prefabricated staircase operation platform
CN211201112U (en) A prefabricated construction platform installed with segmented steel towers
CN204754150U (en) Disc type node scaffolding
CN210002826U (en) detachable welding platform for steel column construction
CN103388336B (en) Main purline part for inner support
CN211058275U (en) a stand
CN203175134U (en) Truss used for lifting electric transmission line tower connecting legs

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20150909