CN204489872U - A kind of P/F trajectory device adapting to heavy-weight coil - Google Patents
A kind of P/F trajectory device adapting to heavy-weight coil Download PDFInfo
- Publication number
- CN204489872U CN204489872U CN201520147609.1U CN201520147609U CN204489872U CN 204489872 U CN204489872 U CN 204489872U CN 201520147609 U CN201520147609 U CN 201520147609U CN 204489872 U CN204489872 U CN 204489872U
- Authority
- CN
- China
- Prior art keywords
- shaped steel
- rail
- steel
- bearing
- bearing rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Winding, Rewinding, Material Storage Devices (AREA)
Abstract
Description
技术领域 technical field
本实用新型涉及一种轨道装置,具体是一种适应大卷重的P/F线轨道装置,应用于高速线材生产线中。 The utility model relates to a track device, in particular to a P/F line track device suitable for large coil weight, which is applied in a high-speed wire rod production line.
背景技术 Background technique
面对钢铁行业严峻形势,为提升盈利能力,国内各高速线材生产厂家纷纷调整产品结构,生产高附加值、大规格、大卷重线材产品,主要钢种为弹簧钢、冷镦钢、易切削钢、工具钢等高端产品,产品规格由φ5.5~φ16mm扩展为φ5.5~φ40mm,卷重由原来的1.7吨增加至2.1吨以上(卷重在原基础上提升20%以上)。 Facing the severe situation of the steel industry, in order to improve profitability, domestic high-speed wire rod manufacturers have adjusted their product structure to produce high value-added, large-scale, large-coil heavy wire products. The main steel types are spring steel, cold heading steel, and free-cutting steel. For high-end products such as steel and tool steel, the product specification has been expanded from φ5.5~φ16mm to φ5.5~φ40mm, and the coil weight has increased from 1.7 tons to more than 2.1 tons (the coil weight has increased by more than 20% on the original basis).
P/F线是高速线材生产线的重要组成部分,其重要功能是完成线材盘卷的积放、运输、冷却、打包、称重、卸卷等工艺。P/F线的本体是积式悬挂式输送机,而悬挂输送机及盘卷的重量主要是由P/F线轨道装置的承载轨承受,现有的承载轨为16#重载翻边槽钢,16Mn材质。随着高线卷重的增加,该轨道承载能力明显不足,使用过程中经常出现磨损、卡件等问题;尤其是拐弯处,因其具有较长的积放轨道、弯道多,经常出现过载,频繁出现牵引链、驱动链及减速机输出轴被拉断的设备故障,不仅影响输送过程,而且影响后续的处理速度及整条生产线的生产效率。 The P/F line is an important part of the high-speed wire rod production line, and its important functions are to complete the process of wire coil accumulation, transportation, cooling, packaging, weighing, and coil unloading. The body of the P/F line is an integral suspension conveyor, and the weight of the suspension conveyor and the coil is mainly borne by the bearing rail of the P/F line track device. The existing bearing rail is a 16# heavy-duty flanging groove Steel, 16Mn material. With the increase of the high wire coil weight, the bearing capacity of the track is obviously insufficient, and problems such as wear and clamping often occur during use; especially at corners, because of the long accumulation track and many bends, overload often occurs , Frequent equipment failures in which the traction chain, drive chain and output shaft of the reducer are pulled off, which not only affects the conveying process, but also affects the subsequent processing speed and the production efficiency of the entire production line.
因此,我们有必要设计一款新的P/F线轨道装置,以适应大卷重,解决现有轨道装置承载不足的问题。 Therefore, it is necessary for us to design a new P/F line track device to adapt to the large coil weight and solve the problem of insufficient load capacity of the existing track device.
实用新型内容 Utility model content
本实用新型的目的在于提供一种能适应大卷重,解决现有轨道装置承载不足的适应大卷重的P/F线轨道装置。 The purpose of the utility model is to provide a P/F line track device that can adapt to the heavy coil weight and solve the insufficient load capacity of the existing track device.
本实用新型是这样实现的:一种适应大卷重的P/F线轨道装置,它包括牵引轨、承载轨和呈弧形结构的轨道支撑,所述牵引轨置于轨道支撑的内侧顶端,所述承载轨包括2个承载轨单元,每个承载轨单元包括第一T型钢和第二T型钢,第一T型钢的竖板与第二T型钢的横板焊接连接,第二T型钢的竖板与第一T型钢的横板焊接连接; The utility model is realized in the following way: a P/F line track device adaptable to large coil weight, which includes a traction rail, a bearing rail and a track support in an arc structure, the traction rail is placed on the inner top of the track support, The bearing rail includes 2 bearing rail units, each bearing rail unit includes a first T-shaped steel and a second T-shaped steel, the vertical plate of the first T-shaped steel is welded to the horizontal plate of the second T-shaped steel, and the second T-shaped steel The vertical plate is welded to the horizontal plate of the first T-shaped steel;
所述轨道支撑的一个底端置于第一个承载轨单元的第一T型钢的横板上,所述轨道支撑的另一个底端置于第二个承载轨单元的第一T型钢的横板上; One bottom end of the track support is placed on the horizontal plate of the first T-shaped steel of the first load-bearing rail unit, and the other bottom end of the track support is placed on the horizontal plate of the first T-shaped steel of the second load-bearing rail unit. board;
所述第一个承载轨单元的第一T型钢的竖板、第二个承载轨单元的第一T型钢的竖板与轨道支撑的内侧壁焊接连接;且第二T型钢6的横板的外侧与第一T型钢的竖板的外侧齐平。 The vertical plate of the first T-shaped steel of the first load-bearing rail unit, the vertical plate of the first T-shaped steel of the second load-bearing rail unit are welded to the inner sidewall of the track support; and the horizontal plate of the second T-shaped steel 6 The outer side is flush with the outer side of the riser of the first T-shaped steel.
按上述方案,所述第一T型钢的横板的厚度大于第二T型钢的横板的厚度;所述第一T型钢的竖板的厚度大于第二T型钢的竖板的厚度。 According to the above scheme, the thickness of the horizontal plate of the first T-shaped steel is greater than the thickness of the horizontal plate of the second T-shaped steel; the thickness of the vertical plate of the first T-shaped steel is greater than the thickness of the vertical plate of the second T-shaped steel.
按上述方案,所述第一T型钢和第二T型钢采用16Mn材质制成。 According to the above solution, the first T-shaped steel and the second T-shaped steel are made of 16Mn material.
按上述方案,承载轨与承载小车的导向轮的接触宽度为15-26mm。 According to the above scheme, the contact width between the bearing rail and the guide wheel of the bearing trolley is 15-26mm.
按上述方案,所述牵引轨为工字钢。 According to the above scheme, the traction rail is I-beam.
本实用新型为三轨制结构,包括牵引轨、承载轨和轨道支撑,其中,轨道支撑为拱形,轨道支撑内侧顶端和两底端分别设置有牵引轨和承载轨。牵引轨和承载轨可同时容纳牵引链条和车组在其中行进,完成物料输送功能,并且保持其稳定性和导向性。承载轨为双焊接T型钢,材质为16Mn,且重轨与承载小车的导向轮的接触宽度为15-26mm,增加了承载小车导向轮与承载轨的接触宽度,保证承载轨的结构强度,提高了其承载能力,适应大盘卷的输送;整个装置运行过程中,轨道变形小,无卡件现象发生,保证了导向轮工作效率;磨损小,使轨道装置的使用寿命为原来的3倍。 The utility model is a three-rail structure, including a traction rail, a load rail and a track support, wherein the track support is arched, and the top and bottom ends of the inner side of the track support are respectively provided with a traction rail and a load rail. The traction rail and the load rail can simultaneously accommodate the traction chain and the vehicle group to travel in it, complete the material conveying function, and maintain its stability and guidance. The carrying rail is double-welded T-shaped steel, the material is 16Mn, and the contact width between the heavy rail and the guide wheel of the carrying trolley is 15-26mm, which increases the contact width between the guiding wheel of the carrying trolley and the carrying rail to ensure the structural strength of the carrying rail and improve Its bearing capacity is improved, and it is suitable for the transportation of large coils; during the operation of the whole device, the track deformation is small, and there is no clamping phenomenon, which ensures the working efficiency of the guide wheel; the wear and tear is small, so that the service life of the track device is three times that of the original.
附图说明 Description of drawings
图1为本实用新型适应大卷重的P/F线轨道装置的结构示意图。 Fig. 1 is the structure schematic diagram of the utility model adapting to the P/F line track device of heavy volume.
图2为第一个承载轨单元的结构示意图。 Fig. 2 is a structural schematic diagram of the first load-carrying rail unit.
图中:1、牵引轨,2、承载轨和轨道支撑,3、车组,4、轨道支撑,5、第一T型钢,6、第二T型钢。 In the figure: 1, traction rail, 2, bearing rail and rail support, 3, car group, 4, rail support, 5, first T-shaped steel, 6, second T-shaped steel.
具体实施方式 Detailed ways
下面结合附图对本实用新型做进一步的说明。 Below in conjunction with accompanying drawing, the utility model is described further.
参见图1和图2,一种适应大卷重的P/F线轨道装置,它包括牵引轨1、承载轨2和呈弧形结构的轨道支撑4,所述牵引轨1置于轨道支撑4的内侧顶端,所述承载轨2包括2个承载轨单元,每个承载轨单元包括采用16Mn材质制成的第一T型钢5和第二T型钢6,第一T型钢5的竖板与第二T型钢6的横板焊接连接,第二T型钢6的竖板与第一T型钢5的横板焊接连接; Referring to Fig. 1 and Fig. 2, a P/F line track device adapting to large coil weight, it includes a traction rail 1, a load rail 2 and a rail support 4 in an arc structure, and the traction rail 1 is placed on the rail support 4 The inner top of the bearing rail 2 includes two bearing rail units, and each bearing rail unit includes the first T-shaped steel 5 and the second T-shaped steel 6 made of 16Mn material, the vertical plate of the first T-shaped steel 5 and the second T-shaped steel The horizontal plate of the second T-shaped steel 6 is welded and connected, and the vertical plate of the second T-shaped steel 6 is welded with the horizontal plate of the first T-shaped steel 5;
所述轨道支撑4的一个底端置于第一个承载轨单元的第一T型钢5的横板上(所述轨道支撑4的一个底端置于第一个承载轨单元的第一T型钢5的横板的右侧上方),所述轨道支撑4的另一个底端置于第二个承载轨单元的第一T型钢5的横板上(所述轨道支撑4的另一个底端置于第二个承载轨单元的第一T型钢5的横板的左侧上方),采用这种连接结构可以增加承载轨的强度,从而提高了承载能力,轨道变形小,无卡件现象,满足大卷重线材产品的输送要求; A bottom end of the track support 4 is placed on the horizontal plate of the first T-shaped steel 5 of the first load-bearing rail unit (a bottom end of the track support 4 is placed on the first T-shaped steel of the first load-bearing rail unit 5), the other bottom end of the track support 4 is placed on the transverse plate of the first T-shaped steel 5 of the second bearing rail unit (the other bottom end of the track support 4 is placed above the left side of the first T-shaped steel 5 of the second load-bearing rail unit), the strength of the load-bearing rail can be increased by using this connection structure, thereby improving the bearing capacity, the track deformation is small, and there is no clamping phenomenon, which meets the Conveying requirements for large coils and heavy wire products;
所述牵引轨1采用工字钢,导向性好。 The traction rail 1 adopts I-shaped steel, which has good guiding performance.
为了使承载轨2与轨道支撑4更好的连接,将第一个承载轨单元的第一T型钢5的竖板、第二个承载轨单元的第一T型钢5的竖板与轨道支撑4的内侧壁焊接连接,且第二T型钢6的横板的外侧与第一T型钢5的竖板的外侧齐平。 In order to better connect the bearing rail 2 to the rail support 4, the vertical plate of the first T-shaped steel 5 of the first bearing rail unit, the vertical plate of the first T-shaped steel 5 of the second bearing rail unit and the rail support 4 The inner side wall of the T-shaped steel is welded and connected, and the outer side of the horizontal plate of the second T-shaped steel 6 is flush with the outer side of the vertical plate of the first T-shaped steel 5 .
为了节约材质和增强承载轨2的强度,第一T型钢5的横板的厚度大于第二T型钢6的横板的厚度;所述第一T型钢5的竖板的厚度大于第二T型钢6的竖板的厚度。 In order to save material and enhance the strength of the bearing rail 2, the thickness of the horizontal plate of the first T-shaped steel 5 is greater than the thickness of the horizontal plate of the second T-shaped steel 6; the thickness of the vertical plate of the first T-shaped steel 5 is greater than that of the second T-shaped steel 6 The thickness of the risers.
为了增加车组3(承载小车)的导向轮与承载轨2的接触宽度,保证承载轨2的结构强度,提高其承载能力,可以将承载轨2与车组3(承载小车)的导向轮的接触宽度设计为15-26mm。 In order to increase the contact width between the guide wheels of the vehicle group 3 (carrying trolley) and the bearing rail 2, ensure the structural strength of the bearing rail 2, and improve its bearing capacity, the distance between the bearing rail 2 and the guide wheels of the vehicle group 3 (carrying trolley) can be The contact width is designed to be 15-26mm.
本实用新型为三轨制结构,包括牵引轨、承载轨和轨道支撑。轨道支撑内侧顶端轨道为工字型钢,轨道支撑内侧两底端轨道为两两相对的T型钢,T型钢材质为16Mn(Q345)。本实用新型的牵引轨可有效的控制车组和链条的速度,使经过轨道的材料速度可以控制,能够更好的与其他系统配合,完美的完成整个输送工作。本实用新型采用T型钢,使得运输小车的车轮与轨道接触面积加大,从而具有良好的导向性和高承载能力;使车组在弯道处的运行更加平稳,减少了轨道和导向轮的磨损,提高了轨道、车组的使用寿命。 The utility model is a three-rail structure, including a traction rail, a load rail and a rail support. The inner top track of the track support is I-shaped steel, and the inner two bottom tracks of the track support are two opposite T-shaped steels, and the material of the T-shaped steel is 16Mn (Q345). The traction rail of the utility model can effectively control the speed of the train group and the chain, so that the speed of the material passing through the track can be controlled, and it can better cooperate with other systems to perfectly complete the entire conveying work. The utility model adopts T-shaped steel, which increases the contact area between the wheel and the track of the transport trolley, thereby having good guiding and high load-bearing capacity; making the running of the vehicle group more stable at the curve, reducing the wear of the track and the guide wheel , Improve the service life of the track and train group.
适应大卷重的P/F线轨道装置于2015年1月在武钢高线设备实施,实施效果良好。预计创效200万元以上。其中:①按贡献率10%计算,生产大规格、大卷重产品产生利润:60000吨/年×40元/吨×10%=24万元;②降低PF线设备故障时间以及节约备件成本产生效益:40+148=188万元。 The P/F line track device adapted to the heavy coil weight was implemented in Wuhan Iron and Steel's high-line equipment in January 2015, and the implementation effect was good. It is estimated that the profit will be more than 2 million yuan. Among them: ①Based on the contribution rate of 10%, the profit generated by the production of large-scale and large-volume heavy products: 60,000 tons/year×40 yuan/ton×10%=240,000 yuan; ②Reduce the failure time of PF line equipment and save the cost of spare parts Benefit: 40+148=1.88 million yuan.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520147609.1U CN204489872U (en) | 2015-03-16 | 2015-03-16 | A kind of P/F trajectory device adapting to heavy-weight coil |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520147609.1U CN204489872U (en) | 2015-03-16 | 2015-03-16 | A kind of P/F trajectory device adapting to heavy-weight coil |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204489872U true CN204489872U (en) | 2015-07-22 |
Family
ID=53569155
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520147609.1U Expired - Fee Related CN204489872U (en) | 2015-03-16 | 2015-03-16 | A kind of P/F trajectory device adapting to heavy-weight coil |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204489872U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114803343A (en) * | 2022-04-25 | 2022-07-29 | 青岛雷霆重工股份有限公司 | Double-guide heavy-load special-shaped bearing track |
-
2015
- 2015-03-16 CN CN201520147609.1U patent/CN204489872U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114803343A (en) * | 2022-04-25 | 2022-07-29 | 青岛雷霆重工股份有限公司 | Double-guide heavy-load special-shaped bearing track |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN201801183U (en) | Steel coil transporting trolley | |
| CN107262999A (en) | A kind of lift car plate weld positioning tool | |
| CN208827822U (en) | A kind of Novel lightweight heavy duty mine car | |
| CN204489872U (en) | A kind of P/F trajectory device adapting to heavy-weight coil | |
| CN203512574U (en) | Suspended type ground power & free chain | |
| CN102530505B (en) | Ground heavy-duty horizontal-drive turning friction type transport line | |
| CN204137005U (en) | A kind of vehicle body of railway vehicle edge beam of underframe and end pieces connection structure | |
| CN102398773A (en) | Lifting transfer device | |
| CN102320521B (en) | Continuous circular shoreside container loading bridge of port | |
| CN207016054U (en) | One kind friction conveyor line rail | |
| CN203431022U (en) | Integral type bearing seat of plate type feeding machine | |
| CN202369275U (en) | Improved structure of suspended double-track crane | |
| CN204507063U (en) | A kind of railway goods train bogie and car body overhead hoist | |
| CN210824474U (en) | Steel plate stacking device | |
| CN203319142U (en) | Online weighing device of suspension conveying system | |
| CN202400749U (en) | Multi-end beam double beam crane structure | |
| CN202201451U (en) | Conveying trolley | |
| CN208037380U (en) | A kind of wire rod PF line delivery system rail sets | |
| CN204296865U (en) | Dumper subframe | |
| CN206129287U (en) | Horizontal translation device of tunnel secondary lining platform truck superstructure | |
| CN203143573U (en) | Antidumping friction convey trolley | |
| CN205076677U (en) | Bank bridge monkey track and bank bridge hoist | |
| CN203143567U (en) | Belt-type lifting and suspending variable-track vehicle | |
| CN103523459A (en) | Suspension type ground power and free chain | |
| CN202896623U (en) | Novel workpiece conveying vehicle |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20170720 Address after: 430083, Gate No. 2, Qingshan District, Hubei, Wuhan Patentee after: WUHAN IRON AND STEEL Co.,Ltd. Address before: 430080 Wuhan, Hubei Friendship Road, No. 999, Wuchang Patentee before: WUHAN IRON AND STEEL (GROUP) Corp. |
|
| TR01 | Transfer of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150722 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |