- CN204474067U CN204474067U CN201420853138.1U CN201420853138U CN204474067U CN 204474067 U CN204474067 U CN 204474067U CN 201420853138 U CN201420853138 U CN 201420853138U CN 204474067 U CN204474067 U CN 204474067U
- Authority
- CN
- China
- Prior art keywords
- cabinet
- frequency converter
- frequency conversion
- construction lifting
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 62
- 238000006243 chemical reaction Methods 0.000 title claims abstract description 57
- 238000009434 installation Methods 0.000 claims abstract description 26
- 230000017525 heat dissipation Effects 0.000 claims abstract description 8
- 238000012423 maintenance Methods 0.000 abstract description 11
- 238000009423 ventilation Methods 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 4
- 238000005192 partition Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 7
- 238000010586 diagram Methods 0.000 description 5
- 239000003990 capacitor Substances 0.000 description 4
- 239000000428 dust Substances 0.000 description 2
- 230000010354 integration Effects 0.000 description 2
- 238000002955 isolation Methods 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000001816 cooling Methods 0.000 description 1
- 235000008446 instant noodles Nutrition 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
Landscapes
- Patch Boards (AREA)
Abstract
本申请公开了一种施工升降变频一体机,包括:柜体和设置在柜体内一侧的变频器箱体,和设置在柜体内另一侧的电控部分,设置在柜体内并与变频器箱体属于同一侧的风道围板;设置在柜体内位于变频器箱体顶部的风扇;设置在柜体的侧板上与风扇位置相对应的通风孔;设置在柜体的底板上并与变频器箱体的底部相通的通风孔;风道围板和变频器箱体的面盖在柜体内形成一个封闭的、并贯通变频器箱体内部的散热风道。可见,本申请公开的施工升降变频一体机,用于安装变频器件的变频器箱体与用于安装电控器件的电控安装板分区设置,降低了维护难度,便于电气检修及变频器整体更换,提高了工作效率,并且设置了变频器部分的独立风道,增强了散热效果。
The application discloses a construction lifting and frequency conversion integrated machine, including: a cabinet body and a frequency converter box disposed on one side of the cabinet body, and an electric control part disposed on the other side of the cabinet body, which is disposed in the cabinet body and connected with the frequency converter The box belongs to the air duct coaming on the same side; the fan installed in the cabinet is located on the top of the inverter box; the ventilation hole corresponding to the position of the fan is installed on the side plate of the cabinet; The ventilation holes connected to the bottom of the inverter box; the air duct coaming plate and the cover of the inverter box form a closed heat dissipation air duct in the cabinet and penetrates the inside of the inverter box. It can be seen that in the all-in-one machine for construction, lifting and frequency conversion disclosed in this application, the frequency converter box used for installing frequency converter components and the electric control installation board for installing electronic control components are arranged in partitions, which reduces the difficulty of maintenance and facilitates electrical maintenance and overall replacement of the frequency converter. , improve the working efficiency, and set up the independent air duct of the inverter part, which enhances the heat dissipation effect.
Description
技术领域technical field
本申请涉及建筑施工设备技术领域,更具体地说,涉及一种施工升降变频一体机。The present application relates to the technical field of building construction equipment, and more specifically, relates to a construction lifting frequency conversion integrated machine.
背景技术Background technique
施工升降变频一体机是现代高层施工中与大型塔机相配合的必不可少的重要施工设备。特别是在高层、超高层建筑施工中担任了极其重要的任务,对于保证施工工期与施工人员的人身安全,降低施工成本,减轻施工人员劳动强度起着不可替代的作用。Construction lifting and frequency conversion integrated machine is an essential and important construction equipment that cooperates with large tower cranes in modern high-rise construction. Especially in the construction of high-rise and super high-rise buildings, it plays an extremely important task, and plays an irreplaceable role in ensuring the construction period and the personal safety of construction personnel, reducing construction costs, and reducing the labor intensity of construction personnel.
在施工时所述施工升降变频一体机一般安装在吊笼中,受限于吊笼内有限的安装空间,施工升降变频一体机内部安装集成度高、体积紧凑。现有施工升降变频一体机柜体内集成安装了断路器、主接触器、抱闸接触器、功率IGBT、制动IGBT、电容、散热器、驱动板、控制板等器件,且变频器部分例如包括所述功率IGBT、制动IGBT、电容、驱动板等一般都安装在柜体内的底层,对于变频器来说,这些是较容易损坏的,不方便维护更换。另外,这些电子器件发热量较大,施工升降变频器一体机内部由于集成度高结构紧凑,导致散热效果较差。During construction, the construction lifting and frequency conversion integrated machine is generally installed in the hanging cage, limited by the limited installation space in the hanging cage, the construction lifting and frequency converting integrated machine has a high degree of internal installation integration and a compact volume. Circuit breakers, main contactors, brake contactors, power IGBTs, brake IGBTs, capacitors, radiators, drive boards, control boards, etc. The power IGBT, brake IGBT, capacitor, driver board, etc. are generally installed on the bottom of the cabinet. For the inverter, these are easy to be damaged and inconvenient to maintain and replace. In addition, these electronic devices generate a lot of heat, and the interior of the all-in-one construction elevator inverter has a poor heat dissipation effect due to its high integration and compact structure.
实用新型内容Utility model content
有鉴于此,本申请提供一种施工升降变频一体机,用于解决现有技术中施工升降变频一体机出现运行故障时,维修时间长、难度大,因影响工作效率的问题。In view of this, the present application provides a construction elevator and frequency conversion integrated machine, which is used to solve the problem of long and difficult maintenance when the construction elevator and frequency conversion integrated machine in the prior art fails, which affects work efficiency.
为了实现上述目的,现提出的方案如下:In order to achieve the above purpose, the proposed scheme is as follows:
一种施工升降变频一体机,包括:A construction lifting frequency conversion integrated machine, including:
柜体,设置在柜体内一侧的变频器箱体,和设置在柜体内另一侧的电控部分;The cabinet, the frequency converter box set on one side of the cabinet, and the electric control part set on the other side of the cabinet;
设置在柜体内并与所述变频器箱体属于同一侧的风道围板;An air duct coaming plate arranged in the cabinet and belonging to the same side as the inverter cabinet;
设置在柜体内并位于所述变频器箱体顶部的风扇;a fan arranged in the cabinet and located on the top of the inverter cabinet;
设置在柜体的侧板上并与所述风扇位置相对应的通风孔;Ventilation holes arranged on the side panels of the cabinet and corresponding to the positions of the fans;
设置在柜体的底板上并与所述变频器箱体的底部相通的通风孔;Ventilation holes arranged on the bottom plate of the cabinet and communicating with the bottom of the inverter cabinet;
所述风道围板和变频器箱体的面盖在所述柜体内形成一个封闭的、并贯通变频器箱体内部的散热风道。The air duct coaming plate and the cover of the inverter box form a closed heat dissipation air duct in the cabinet and penetrates the inside of the inverter box.
优选的,上述施工升降变频一体机,包括:Preferably, the above-mentioned integrated frequency conversion machine for construction includes:
所述风道围板包括风道侧围板、风道上围板和设置在风道上围板上的风扇面板。The air duct coaming plate includes an air duct side coaming plate, an air duct upper coaming plate and a fan panel arranged on the air duct upper coaming plate.
优选的,上述施工升降变频一体机,包括:Preferably, the above-mentioned integrated frequency conversion machine for construction includes:
所述柜体的底板与变频器箱体的底部具有预设间距,所述风道围板还包括风道下围板,用于封闭包围所述柜体底部与变频器箱体底部之间的空腔。There is a preset distance between the bottom plate of the cabinet and the bottom of the inverter box, and the air duct coaming plate also includes an air duct lower coaming plate, which is used to seal and enclose the gap between the bottom of the cabinet body and the bottom of the inverter box body. cavity.
优选的,上述施工升降变频一体机中,所述风扇面板为L型结构,所述风扇面板的平行于变频器箱体面盖的一面上设有把手,所述风扇面板的垂直于所述变频器箱体面盖的一面上设有风扇安装位,所述变频器箱体顶部、所述风道上围板和所述风道侧围板之间形成有槽位,所述风扇面板通过抽拉式结构嵌入所述槽位,并使得所述风扇位于所述槽位内部。Preferably, in the above-mentioned all-in-one machine for construction lifting and frequency conversion, the fan panel has an L-shaped structure, a handle is provided on the side of the fan panel parallel to the surface cover of the inverter box, and a handle is provided on the side of the fan panel perpendicular to the frequency conversion There is a fan installation position on one side of the cover of the inverter box, and slots are formed between the top of the inverter box, the upper panel of the air duct and the side panel of the air duct, and the fan panel is The type structure is embedded in the slot, and the fan is located inside the slot.
优选的,上述施工升降变频一体机,还包括:Preferably, the above-mentioned all-in-one machine for construction lifting and frequency conversion also includes:
设置在所述柜体内背板上的变频器箱体安装梁和电控安装板安装梁,所述变频器箱体固定在所述变频器箱体安装梁上,所述电控部分设置在所述电控安装板上。The inverter box installation beam and the electric control installation board installation beam are arranged on the backboard of the cabinet, the inverter box is fixed on the inverter box installation beam, and the electric control part is arranged on the above electric control mounting plate.
优选的,上述施工升降变频一体机,还包括:Preferably, the above-mentioned all-in-one machine for construction lifting and frequency conversion also includes:
设置在所述变频器箱体的面盖上的控制板及键盘组件。A control panel and a keyboard assembly arranged on the surface cover of the inverter box.
优选的,上述施工升降变频一体机,还包括:Preferably, the above-mentioned all-in-one machine for construction lifting and frequency conversion also includes:
设置在所述柜体上用于封盖所述电控部分的面盖。A surface cover for covering the electric control part is arranged on the cabinet body.
优选的,上述施工升降变频一体机,包括:Preferably, the above-mentioned integrated frequency conversion machine for construction includes:
所述变频器箱体内部设置有散热器、变频IGBT、制动IGBT、电容和驱动板。A radiator, a frequency conversion IGBT, a braking IGBT, a capacitor and a drive board are arranged inside the inverter box.
优选的,上述施工升降变频一体机,包括:所述电控部分包括隔离变压器、控制接触器、主接触器和制动板。Preferably, the construction lifting frequency conversion integrated machine includes: the electric control part includes an isolation transformer, a control contactor, a main contactor and a braking plate.
从上述的技术方案可以看出,本申请公开的施工升降变频一体机,将用于安装变频器件的变频器箱体与用于安装电控器件的电控安装板分区设置,降低了维护难度,便于电气检修及变频器整体更换,提高了工作效率,并且设置了变频器部分的独立风道,增强了散热效果。It can be seen from the above technical solutions that the all-in-one machine for construction lifting and frequency conversion disclosed in this application divides the frequency converter box used for installing frequency converter components and the electronic control installation board for installing electronic control components, which reduces the difficulty of maintenance. It is convenient for electrical maintenance and overall replacement of the inverter, which improves work efficiency, and an independent air duct for the inverter part is set to enhance the heat dissipation effect.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据提供的附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description It is only an embodiment of the utility model, and those skilled in the art can also obtain other drawings according to the provided drawings without creative work.
图1为本申请实施例提供的一种施工升降变频一体机的结构图;Fig. 1 is a structural diagram of a construction lifting frequency conversion integrated machine provided by the embodiment of the present application;
图2为本申请实施例提供的一种施工升降变频一体机的结构图;Fig. 2 is a structural diagram of a construction lifting frequency conversion integrated machine provided by the embodiment of the present application;
图3为本申请实施例提供的一种施工升降变频一体机的结构图;Fig. 3 is a structural diagram of a construction lifting frequency conversion integrated machine provided by the embodiment of the present application;
图4为本申请实施例提供的一种施工升降变频一体机的结构图;Fig. 4 is a structural diagram of a construction lifting frequency conversion integrated machine provided by the embodiment of the present application;
图5为本申请实施例提供的一种施工升降变频一体机的结构图。Fig. 5 is a structural diagram of a construction lifting frequency conversion integrated machine provided by an embodiment of the present application.
具体实施方式Detailed ways
针对于现有技术中施工升降变频一体机一旦出现运行故障时,维修时间长、难度大,因影响工作效率的问题,本申请公开了一种施工升降变频一体机。Aiming at the problems in the prior art that once an operation failure occurs in the construction lifting and frequency conversion integrated machine, the maintenance time is long and difficult, and the work efficiency is affected, the present application discloses a construction lifting and frequency conversion integrated machine.
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.
参见图1-图5,本实施例公开的施工升降变频一体机包括:Referring to Fig. 1-Fig. 5, the all-in-one machine for construction lifting and frequency conversion disclosed in this embodiment includes:
柜体1、门板3和设置在柜体1内一侧的变频器箱体2,和设置在柜体内另一侧的电控部分;The cabinet body 1, the door panel 3, the frequency converter box body 2 arranged on one side of the cabinet body 1, and the electric control part arranged on the other side of the cabinet body;
设置在柜体1内并与所述变频器箱体2属于同一侧的风道围板;An air duct coaming plate arranged in the cabinet 1 and belonging to the same side as the inverter cabinet 2;
设置在柜体1内并位于所述变频器箱体2顶部的风扇9;A fan 9 arranged in the cabinet 1 and positioned at the top of the inverter cabinet 2;
设置在柜体1的侧板上并与所述风扇9位置相对应的通风孔(在图3中柜体1的右侧板上已示意出);Be arranged on the side plate of cabinet body 1 and the ventilation hole corresponding to the position of described fan 9 (shown schematically on the right side board of cabinet body 1 in Fig. 3);
设置在柜体1的底板上并与所述变频器箱体2的底部相通的通风孔(在图2中柜体1的底部上已示意出);Be arranged on the bottom plate of the cabinet 1 and communicate with the bottom of the inverter cabinet 2 (shown schematically on the bottom of the cabinet 1 in Fig. 2);
所述风道围板和变频器箱体2的面盖在所述柜体1内形成一个封闭的、并贯通变频器箱体2内部的散热风道。The air duct coaming plate and the cover of the inverter box 2 form a closed heat dissipation air duct in the cabinet 1 that penetrates the interior of the inverter box 2 .
参见申请上述实施例公开的施工升降变频一体机,其将用于安装变频器件的变频器箱体与用于安装电控器件的电控安装板分区设置,降低了维护难度,便于电气检修及变频器整体更换,提高了工作效率,并且设置了变频器部分的独立风道,增强了施工升降变频一体机的散热效果。Refer to the all-in-one machine for construction lifting and frequency conversion disclosed in the above-mentioned embodiment of the application, which divides the inverter box for installing the inverter components and the electric control installation board for installing the electronic control components, which reduces the difficulty of maintenance and facilitates electrical maintenance and frequency conversion. The inverter is replaced as a whole, which improves the work efficiency, and an independent air duct for the frequency converter is set up, which enhances the heat dissipation effect of the construction lifting frequency conversion integrated machine.
可以理解的是,本申请上述实施例中,所述柜体1和门板3之间可以通过铰链连接;所述柜体1内腔另一侧设置有用于安装电控部分的电控安装板7。It can be understood that, in the above embodiments of the present application, the cabinet body 1 and the door panel 3 can be connected by hinges; the other side of the inner cavity of the cabinet body 1 is provided with an electric control installation plate 7 for installing the electric control part .
其中,所述风道围板可以由风道侧围板4、风道上围板5和设置在风道上围板5上的风扇面板8组成。Wherein, the air duct coaming plate may be composed of the air duct side coaming plate 4 , the air duct upper coaming plate 5 and the fan panel 8 arranged on the air duct upper coaming plate 5 .
可以理解的是,为了方便维修所述施工升降变频一体机,所述柜体1的底板与变频器箱体2的底部具有预设间距,所述风道围板还包括风道下围板6,其用于封闭包围所述柜体1底部与变频器箱体2底部之间的空腔。It can be understood that, in order to facilitate the maintenance of the all-in-one construction lifting and frequency conversion machine, the bottom plate of the cabinet 1 has a preset distance from the bottom of the inverter box 2, and the air duct coaming also includes the air duct lower coaming 6 , which is used to seal and surround the cavity between the bottom of the cabinet body 1 and the bottom of the inverter cabinet body 2 .
可以理解的是,当所述施工升降变频一体机长期使用时,所述风扇面板8和设置在风扇面板8上的风扇会积累较多的灰尘,如果灰尘过多,则会影响所述风扇的工作效率,不利于对所述对施工升降变频一体机内的电器元件进行降温,因此,为了方便清洗或更换所述风扇面板8上的风扇,本申请所有的实施例中,所述风扇面板8可设置为前抽拉式结构,以便正面维护风扇面板8上的器件,其具体结构为:所述风扇面板8为L型结构,所述风扇面板8的平行于变频器箱体2面盖的一面上设有把手,所述风扇面板8的垂直于所述变频器箱体2面盖的一面上设有风扇安装位,所述变频器箱体2顶部、所述风道上围板5和所述风道侧围板4之间形成有槽位,所述风扇面板8通过抽拉式结构嵌入所述槽位,并使得所述风扇9位于所述槽位内部。It can be understood that when the all-in-one machine for construction, lifting and frequency conversion is used for a long time, the fan panel 8 and the fans arranged on the fan panel 8 will accumulate more dust. If there is too much dust, it will affect the performance of the fan. The work efficiency is not conducive to cooling the electrical components in the all-in-one machine for construction, lifting and frequency conversion. Therefore, in order to facilitate cleaning or replacement of the fan on the fan panel 8, in all embodiments of the present application, the fan panel 8 It can be set as a front pull-out structure so as to maintain the devices on the fan panel 8 from the front. The specific structure is: the fan panel 8 is an L-shaped structure, and the fan panel 8 is parallel to A handle is provided on one side, and a fan installation position is provided on the side of the fan panel 8 perpendicular to the surface cover of the inverter box 2, the top of the inverter box 2, the upper wall of the air duct 5 and the A slot is formed between the air duct side panels 4, and the fan panel 8 is inserted into the slot through a pull-out structure, so that the fan 9 is located inside the slot.
可以理解的是,为了保证所述变频器箱体2、电控安装板7与所述柜体1严格固定,且方便所述变频器箱体2和电控安装板7整体安装和拆卸更换,本申请上述实施例中的施工升降变频一体机内还包括:设置在所述柜体1的内背板上的变频器箱体安装梁15和电控安装板安装梁16,所述变频器箱体2固定在所述变频器箱体安装梁15上,所述电控安装板7设置在所述电控安装板安装梁16上。所述变频器箱体安装梁15和电控安装板安装梁16分别通过螺钉与变频器箱体2和电控安装板7一一对应相连。It can be understood that, in order to ensure that the inverter box 2 and the electric control mounting plate 7 are strictly fixed to the cabinet 1, and to facilitate the overall installation, disassembly and replacement of the inverter box 2 and the electric control mounting plate 7, The all-in-one machine for construction lifting and frequency conversion in the above-mentioned embodiments of the present application also includes: a frequency converter box mounting beam 15 and an electric control mounting plate mounting beam 16 arranged on the inner back plate of the cabinet body 1, and the frequency converter box The body 2 is fixed on the installation beam 15 of the inverter box body, and the electric control installation board 7 is arranged on the installation beam 16 of the electric control installation board. The inverter box installation beam 15 and the electric control installation board installation beam 16 are respectively connected to the inverter cabinet 2 and the electric control installation board 7 in one-to-one correspondence by screws.
可以理解的是,为了方便用户操作施工升降变频一体机,上述施工升降变频一体机还包括:设置在所述变频器箱体2的面盖上的控制板17及键盘组件,可以方便对控制板接线、以及方便查看键盘,所述键盘组件包括键盘支架18及设置在键盘支架上的键盘19。It can be understood that, in order to facilitate the user to operate the construction lifting frequency conversion integrated machine, the above construction lifting frequency conversion integrated machine also includes: a control board 17 and a keyboard assembly arranged on the surface cover of the frequency converter box 2, which can facilitate the control board Wiring, and convenient to check the keyboard, the keyboard assembly includes a keyboard bracket 18 and a keyboard 19 arranged on the keyboard bracket.
可以理解的是,为了使得所述施工升降变频一体机内的安装器件显的简单明了,减小各器件之间的连接线对用户操作带来的不便,本申请上述实施例中的施工升降变频一体机还包括:设置在所述柜体上的用于封盖所述电控部分的面盖的面盖26,所述面盖26通过两个侧支架(27和28)安装于所述柜体上,所述支架27设置于柜体左侧板上,另一侧支架28设置于变频器箱体2的左侧板上,且所述面盖26与变频器箱体2的面盖平齐,所述面盖26上设置有过线孔29,连接线通过所述过线孔29走到面盖26的下面,被所述面盖26覆盖,使得整体走线美观,同时方便了用户操作。It can be understood that, in order to make the installation devices in the construction lifting frequency conversion all-in-one machine simple and clear, and reduce the inconvenience caused by the connecting wires between various devices to the user's operation, the construction lifting frequency conversion in the above embodiments of the present application The all-in-one machine also includes: a cover 26 arranged on the cabinet body for covering the cover of the electric control part, and the cover 26 is installed on the cabinet through two side brackets (27 and 28). On the body, the bracket 27 is arranged on the left side panel of the cabinet, and the other side bracket 28 is arranged on the left side panel of the inverter box 2, and the cover 26 is flat with the cover of the inverter box 2. The surface cover 26 is provided with a wire hole 29, and the connecting wire goes to the bottom of the surface cover 26 through the wire hole 29, and is covered by the surface cover 26, so that the overall wiring is beautiful and convenient for users operate.
可以理解的是,为了方便用户安装和接线,本申请上述实施例中的施工升降变频一体机中还设置有一用于安装端子的端子安装板31,所述端子安装板31设置在风道下围板6上,所述端子安装板31上可以安装施工升降变频一体机的输入端子、输出端子、控制接线端子排。It can be understood that, in order to facilitate installation and wiring for users, the all-in-one machine for construction, lifting and frequency conversion in the above embodiments of the present application is also provided with a terminal mounting plate 31 for mounting terminals, and the terminal mounting plate 31 is arranged on the lower wall of the air duct On the board 6, the input terminal, output terminal, and control wiring terminal block of the construction lifting frequency conversion integrated machine can be installed on the terminal installation board 31.
可以理解的是,为了方便用户查看施工升降变频一体机的工作状态、对施工升降变频一体机进行操作,本申请上述实施例中的施工升降变频一体机还可以包括:设置在门板3上的指示灯板33、键盘观察窗34、GPRS模块35和与所述门板3铰接的操作窗36。所述指示灯板33与所述控制板17电连接,所述键盘观察窗34采用面膜透明显示键盘安装架上的键盘的显示区,操作者可以很直观的看到参数,可有效控制参数在安全工作范围内。It can be understood that, in order to facilitate the user to view the working status of the all-in-one construction lift and frequency conversion machine, and to operate the all-in-one construction lift and frequency conversion machine, the all-in-one construction lift and frequency conversion machine in the above embodiments of the present application may also include: an instruction set on the door panel 3 A lamp panel 33 , a keyboard observation window 34 , a GPRS module 35 and an operation window 36 hinged to the door panel 3 . The indicator light panel 33 is electrically connected with the control panel 17, and the keyboard observation window 34 adopts a mask to transparently display the display area of the keyboard on the keyboard mounting frame, so that the operator can see the parameters intuitively, and the parameters can be effectively controlled in within safe working range.
例如,参见图1-5,本申请公开的所述施工升降变频一体机的散热器10、变频IGBT11、制动IGBT12、电容13和驱动板14可以安装于所述变频器箱体2内部;For example, referring to Figs. 1-5, the radiator 10, frequency conversion IGBT11, brake IGBT12, capacitor 13 and drive board 14 of the all-in-one machine for construction lifting and frequency conversion disclosed in this application can be installed inside the frequency converter box 2;
所述施工升降变频一体机的隔离变压器22、控制接触器23、主接触器24和制动板25可以安装于电控安装板7上。控制板17与设置在端子安装板31上的控制接线端子排30之间的走线由所述过线孔29走到面盖26的覆盖面,因此,隐藏了控制接线端子排30的布线。使得整体走线美观。并且走线不影响面盖26的拆卸,方便面盖26下电器的维护。制动板25可以通过转接板安装在电控安装板7上,本申请还可以通过将制动板25的电气接线端子设置在可视范围内,使得其便于拆卸电气连线,方便制动板25的维修和替换。The isolation transformer 22 , the control contactor 23 , the main contactor 24 and the braking plate 25 of the construction lifting and frequency conversion integrated machine can be installed on the electric control mounting plate 7 . The wiring between the control board 17 and the control terminal block 30 arranged on the terminal mounting plate 31 goes from the wire passing hole 29 to the covering surface of the cover 26 , thus hiding the wiring of the control terminal block 30 . Makes the overall alignment beautiful. And the wiring does not affect the dismounting of the face cover 26, and the maintenance of the electrical appliances under the instant noodle cover 26. The brake plate 25 can be installed on the electric control mounting plate 7 through an adapter plate, and the application can also set the electrical connection terminals of the brake plate 25 within the visible range, so that it is convenient to disassemble the electrical connection and facilitate braking. Plate 25 repair and replacement.
在本实施例中,所述控制板17和驱动板14电连接,所述键盘支架18上除了安设有键盘19外还可以设置有加节电源20和坠落试验航插21。所述键盘19和坠落试验航插21与所述控制板17电连接,加节电源20与设置在端子安装排30上的输入端子电连接。键盘19、加节电源20及坠落试验航插21置于变频器箱体2的面盖的顶层,便于连接布线,操作维护。用户打开操作窗36,可以连接加节电源20接线和坠落试验航插21,方便加节电源20线缆连接和吊笼坠落试验航插21连接。In this embodiment, the control board 17 is electrically connected to the driving board 14 , and the keyboard bracket 18 may also be provided with a power supply 20 and a drop test aviation plug 21 in addition to the keyboard 19 . The keyboard 19 and the drop test aviation plug 21 are electrically connected to the control board 17 , and the power supply 20 is electrically connected to the input terminals provided on the terminal installation row 30 . The keyboard 19, the energy saving power supply 20 and the drop test aviation plug 21 are placed on the top layer of the cover of the inverter box body 2, which is convenient for connection and wiring, and operation and maintenance. The user opens the operation window 36 to connect the wiring of the power supply 20 and the aviation plug 21 for the drop test, so as to facilitate the cable connection of the power supply 20 and the aviation plug 21 for the drop test of the cage.
最后,还需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。Finally, it should also be noted that in this text, relational terms such as first and second etc. are only used to distinguish one entity or operation from another, and do not necessarily require or imply that these entities or operations, any such actual relationship or order exists. Furthermore, the term "comprises", "comprises" or any other variation thereof is intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus comprising a set of elements includes not only those elements, but also includes elements not expressly listed. other elements of or also include elements inherent in such a process, method, article, or device. Without further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article or apparatus comprising said element.
本说明书中各个实施例采用递进的方式描述,每个实施例重点说明的都是与其他实施例的不同之处,各个实施例之间相同相似部分互相参见即可。Each embodiment in this specification is described in a progressive manner, each embodiment focuses on the difference from other embodiments, and the same and similar parts of each embodiment can be referred to each other.
对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本实用新型。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本实用新型的精神或范围的情况下,在其它实施例中实现。因此,本实用新型将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。The above description of the disclosed embodiments enables those skilled in the art to realize or use the utility model. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Therefore, the present invention will not be limited to these embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420853138.1U CN204474067U (en) | 2014-12-26 | 2014-12-26 | A kind of construction lifting frequency conversion all-in-one |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420853138.1U CN204474067U (en) | 2014-12-26 | 2014-12-26 | A kind of construction lifting frequency conversion all-in-one |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204474067U true CN204474067U (en) | 2015-07-15 |
Family
ID=53629871
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420853138.1U Expired - Fee Related CN204474067U (en) | 2014-12-26 | 2014-12-26 | A kind of construction lifting frequency conversion all-in-one |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204474067U (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105429438A (en) * | 2015-12-29 | 2016-03-23 | 湖北江汉建筑工程机械有限公司 | Cabinet-type frequency converter for construction hoist and construction hoist |
| CN110606427A (en) * | 2019-08-12 | 2019-12-24 | 上海三菱电梯有限公司 | Elevator integrated driving device |
| CN110745659A (en) * | 2019-09-20 | 2020-02-04 | 浙江升航电子科技有限公司 | Internet of things system of construction elevator all-in-one machine |
| CN111453579A (en) * | 2020-03-24 | 2020-07-28 | 浙江华良建筑机械有限公司 | Frequency conversion lift all-in-one that construction was used |
| WO2021036410A1 (en) * | 2019-08-27 | 2021-03-04 | 苏州汇川技术有限公司 | Elevator control assembly and elevator control all-in-one machine having same |
| CN113133247A (en) * | 2021-04-19 | 2021-07-16 | 中国煤炭科工集团太原研究院有限公司 | Electric control device and shuttle car with same |
| CN116654729A (en) * | 2023-05-15 | 2023-08-29 | 菱王电梯有限公司 | Elevator control cabinet |
-
2014
- 2014-12-26 CN CN201420853138.1U patent/CN204474067U/en not_active Expired - Fee Related
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105429438A (en) * | 2015-12-29 | 2016-03-23 | 湖北江汉建筑工程机械有限公司 | Cabinet-type frequency converter for construction hoist and construction hoist |
| CN105429438B (en) * | 2015-12-29 | 2018-08-14 | 湖北江汉建筑工程机械有限公司 | A kind of building hoist case frequency converter and building hoist |
| CN110606427A (en) * | 2019-08-12 | 2019-12-24 | 上海三菱电梯有限公司 | Elevator integrated driving device |
| CN110606427B (en) * | 2019-08-12 | 2021-08-03 | 上海三菱电梯有限公司 | Elevator integrated driving device |
| WO2021036410A1 (en) * | 2019-08-27 | 2021-03-04 | 苏州汇川技术有限公司 | Elevator control assembly and elevator control all-in-one machine having same |
| CN110745659A (en) * | 2019-09-20 | 2020-02-04 | 浙江升航电子科技有限公司 | Internet of things system of construction elevator all-in-one machine |
| CN111453579A (en) * | 2020-03-24 | 2020-07-28 | 浙江华良建筑机械有限公司 | Frequency conversion lift all-in-one that construction was used |
| CN113133247A (en) * | 2021-04-19 | 2021-07-16 | 中国煤炭科工集团太原研究院有限公司 | Electric control device and shuttle car with same |
| CN113133247B (en) * | 2021-04-19 | 2023-08-25 | 中国煤炭科工集团太原研究院有限公司 | Electrical control device and shuttle car with same |
| CN116654729A (en) * | 2023-05-15 | 2023-08-29 | 菱王电梯有限公司 | Elevator control cabinet |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204474067U (en) | A kind of construction lifting frequency conversion all-in-one | |
| CN202785127U (en) | Elevator control cabinet shell | |
| CN204185040U (en) | Power frequency frequency conversion conversion all-in-one | |
| WO2018035992A1 (en) | External main control cabinet | |
| CN206640151U (en) | A kind of power distribution equipment and line arrangement structure | |
| CN204577918U (en) | A kind of novel multi-door power distribution cabinet with the solar energy LED illuminate function | |
| CN215525983U (en) | Aging cabinet for energy feedback type aging test of inverter | |
| CN216564103U (en) | An energy-saving and environmentally friendly outdoor power cabinet | |
| CN206894067U (en) | A kind of energy-saving lighting distribution box | |
| CN105514840B (en) | Multifunctional high-voltage switch cabinet | |
| CN206302067U (en) | A sound-proof sealed power distribution cabinet | |
| CN211090300U (en) | A new type of construction lifting and frequency conversion integrated machine | |
| CN220874849U (en) | Server convenient to dismantle | |
| CN208016194U (en) | A kind of household heat radiating type control cabinet | |
| CN207731263U (en) | A Comprehensive Test Bench for Computer Hardware Development | |
| CN205489084U (en) | Novel put cabinet in dustproof heat dissipation | |
| CN221885805U (en) | Variable frequency control cabinet of grocery elevator | |
| CN206099114U (en) | High heat dissipating's automatically controlled cabinet of security protection electric power | |
| CN204967032U (en) | Explosion -proof distribution box | |
| CN219394083U (en) | An integrated electric control cabinet used in fuel cell testing equipment | |
| CN206283750U (en) | A kind of ac fan fixed mount for being applied to rack | |
| CN205791026U (en) | Integrated centralized main electrical cabinet | |
| CN204651709U (en) | A kind of Novel distribution cabinet case | |
| CN204859801U (en) | A PLC control cabinet for skid-mounted pressurization points | |
| CN202119053U (en) | Electric control box of solar air conditioner |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150715 |